Construction method for high-altitude conversion of building machine for overhanging building
By using temporary supports and beams in the construction of cantilevered buildings, the problem of dismantling and reinstalling the building machine was solved, which improved construction efficiency and safety and reduced costs.
Patent Information
- Application Number
- CN202410409213.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-07
- Publication Date
- 2026-11-20
- Estimated Expiration
- 2044-04-07
AI Technical Summary
In existing construction technologies, building machines need to be dismantled and reinstalled during the construction of cantilevered buildings, which leads to problems such as extended construction period and increased costs.
Temporary supports and beams are used to provide hoisting space, ensuring the stability of the building machine during cantilever construction, avoiding large-scale adjustments, and achieving construction compatibility between the building machine and the cantilever structure.
It improved the efficiency of cantilever building construction, reduced the number of times building machines need to be dismantled and installed, ensured the safety and stability of construction, and reduced construction costs.
Smart Images

Figure CN118167033B_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of building construction machine technology, and specifically relates to a high-altitude conversion construction method for building construction machines used in cantilevered buildings. Background Technology
[0002] The "Sky Building Machine," a new industrialized intelligent construction technology, is an equipment platform and supporting construction technology independently developed in my country. The Sky Building Machine and its construction technology utilize mechanized operations and intelligent control to achieve industrialized intelligent construction of high-rise residential buildings using cast-in-place reinforced concrete. A key feature is that the entire process is completed centrally and layer by layer in the air. This equipment platform simulates a mobile building factory, bringing the factory to the construction site. It employs mechanical operation and intelligent control methods in conjunction with the existing commercial concrete supply chain and high-altitude concrete pumping technology to simultaneously construct the above-ground structural main body and integrated insulation and finishing panels layer by layer. This technology replaces manual labor, enabling the overall cast-in-place construction of high-rise and super high-rise reinforced concrete buildings.
[0003] When a super high-rise building incorporates a cantilever structure, a truss layer needs to be installed within the core tube to correspond to the cantilever structure. The steel trusses of the truss layer pass through the core tube, which can improve the stability of the cantilever structure. During the construction of the truss layer of a cantilever building, the steel trusses may interfere with and collide with the building construction machine. Therefore, in current construction techniques, the building construction machine needs to be dismantled during the construction of the truss layer, and then reassembled after the steel trusses are hoisted for subsequent building construction. The installation and dismantling of the building construction machine involves a huge amount of work, prolongs the construction period, and increases construction costs. Summary of the Invention
[0004] The purpose of this invention is to provide a high-altitude conversion construction method for building machines used in cantilevered buildings, in order to solve the problem in the above-mentioned background art that building machines need to be dismantled and reinstalled in the construction of cantilevered buildings, which prolongs the construction period and increases costs.
[0005] To achieve the above objectives, the present invention provides the following technical solution: A high-altitude conversion construction method for a building-building machine used in cantilevered buildings, wherein the cantilevered building includes a cantilever structure and a core tube, the cantilever structure is located on the nth floor, and an installation truss is installed within the nth floor of the core tube; the building-building machine includes an inner frame, an outer frame, and a top platform, the top platform including a top horizontal beam and a top longitudinal beam, the top horizontal beam being aligned with the length direction of the installation truss; the installation trusses are arranged parallel and spaced inside the core tube, comprising the following steps: S1. Install the building construction machine and carry out core tube construction; S2. Raise the top platform of the building machine to the n+1 floor, tie the wall steel bars of the n-2 floor, then designate the top beam that is located on the same vertical plane as the installation truss as the top beam to be demolished, and set the embedded parts on the top of the n-2 floor wall at the adjacent side position of the top beam to be demolished, and then pour the concrete of the n-2 floor wall. After the walls of S3 and n-2 are formed, temporary supports are set on the embedded parts of the n-2 layer, and then temporary crossbeams are installed on the top of the temporary supports. The temporary crossbeams are connected to the inner frame and outer frame of the building machine. S4. Remove the top beam to be removed from the top platform; S5. Hoisting and installing the truss; according to the design position of the truss, remove the walkway panels and protective nets that interfere with it in advance; hoist the truss in sections, first lift each section of the truss to directly above the installation position, and then hoist it to the designated position; S6. Reinstall the top beam to be removed, and then remove the temporary beam and temporary support. S7. Tie the n-1 layers and n layers of steel bars, and then pour the n-1 layer of wall concrete. S8, the overall lifting building machine, is used for subsequent concrete pouring of the core tube wall.
[0006] Furthermore, in step S8, if the external bracket interferes with the bracket of the installation truss when the building machine is lifted upward, the walkway plate is removed, and the walkway plate is reinstalled after the interference position has passed the bracket.
[0007] Furthermore, the temporary crossbeam is set parallel to the side of the top crossbeam to be removed, and is located on the same horizontal plane as the top crossbeam.
[0008] Furthermore, in steps S4 and S5, the top beams to be removed are dismantled in batches, and the trusses are installed in corresponding batches.
[0009] Furthermore, in steps S7 and S8, the templates used for pouring the n-1 layer wall and the n layer wall have notches at the corbel positions where the trusses are installed.
[0010] Furthermore, in step S5, if the length of the corbel extending beyond the outer side of the wall is less than 1.5m, only the walkway slab needs to be removed; if the length of the corbel extending beyond the outer side of the wall is not less than 1.5m, both the walkway slab and the protective net need to be removed at the same time, and a horizontal pipe connection should be installed at the break point, along with a dense mesh net.
[0011] Furthermore, when the installation truss is also set on the outer wall of the core tube, and the length of the installation truss is approximately the length of the corresponding outer wall of the core tube, step S4 further includes: disassembling all the outer brackets on one side corresponding to the outer installation truss; step S5 further includes: lifting the outer installation truss to the outside of the installation position, then moving it to the designated position and installing and fixing it; step S6 further includes: resetting the installation brackets.
[0012] Furthermore, when the installation truss is also located on the outer wall of the core tube, and the length of the installation truss is significantly less than the length of the corresponding outer wall of the core tube, step S4 further includes: removing part of the external bracket corresponding to the outer installation truss; step S5 further includes: lifting the outer installation truss to the outside of the installation position, then moving it to the designated position and installing and fixing it; step S6 further includes: resetting the installation bracket.
[0013] The present invention has the following beneficial effects: 1. The present invention provides a high-altitude conversion construction method for building construction machines used in cantilevered buildings. The building construction machine is used in the construction of the cantilever layer to realize the high-altitude conversion and deformation of the building construction machine. Temporary columns and temporary beams are used to ensure the stability of the building construction machine during the conversion process, and hoisting space is provided for the installation of trusses. No large-scale adjustments are required, so as to achieve construction compatibility between the building construction machine and the cantilever structure and improve the overall construction efficiency.
[0014] 2. The present invention provides a high-altitude conversion construction method for building construction machines used in cantilevered buildings. When the outer wall of the core tube is equipped with an installation truss, the external hanging frame is removed to provide hoisting space for the installation truss, making the construction convenient and quick.
[0015] 3. The present invention provides a high-altitude conversion construction method for building construction machines used in cantilever buildings, which provides a new approach to the rapid dismantling and modification of building construction machines at the truss level, solving the problem of time-consuming and labor-intensive dismantling and reinstallation of building construction machines. At the same time, it provides protection for the construction process of truss installation and ensures construction safety. In addition, by adding temporary measures, the safety and stability of building construction machine dismantling and modification process are effectively guaranteed, which has good value for promotion and use. Attached Figure Description
[0016] Figure 1 This is a top view of the cantilevered building and the roof platform of the building construction machine involved in the present invention; Figure 2 This invention relates to the process after the n-2 layers of wall are formed. Figure 1 Cross-sectional view of AA in the middle; Figure 3 The present invention is for the hoisting of the installation truss. Figure 1 Cross-sectional view of AA in the middle; Figure 4 For the present invention, during construction of layer n-1 Figure 1 Cross-sectional view of AA in the middle; Figure 5 This invention relates to the process after the n-2 layers of wall are formed. Figure 1 Cross-sectional view of BB in the middle; Figure 6 The present invention is for the installation and hoisting of trusses. Figure 1 Cross-sectional view of BB in the middle; Figure 7 For the present invention during construction of layer n-1 Figure 1 Cross-sectional view of BB in the middle.
[0017] In the diagram: 1-Inner frame, 2-Outer hanging frame, 3-Top platform, 4-Temporary support column, 5-Temporary crossbeam, 6-Installation truss. Detailed Implementation
[0018] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.
[0019] A high-altitude conversion construction method for a building machine used in cantilevered buildings, wherein the cantilevered building includes a core tube and a cantilever structure, the cantilever structure is set on the nth floor, and an installation truss 6 is set inside the nth floor of the core tube. The end of the installation truss 6 extends out of the core tube and is equipped with a corbel for the installation connection of the cantilever structure; the building machine includes an inner frame 1, an outer hanging frame 2 and a top platform 3, the top platform 3 includes a top horizontal beam and a top longitudinal beam, the top horizontal beam being aligned with the length direction of the installation truss 6.
[0020] Example 1: The installation truss 6 is set in parallel intervals inside the core tube.
[0021] like Figure 1 As shown in Example 1, a high-altitude conversion construction method for cantilever buildings using a building-building machine includes the following steps: S1. Install the building construction machine and carry out core tube construction; S2. Raise the top platform 3 of the building machine to the n+1 floor, tie the wall reinforcement of the n-2 floor, then designate the top beam located on the same vertical plane as the installation truss 6 as the top beam to be demolished, and set the embedded parts on the top of the n-2 floor wall at the adjacent side position of the top beam to be demolished, then install the formwork on both sides of the n-2 floor wall, and pour the n-2 floor wall concrete. S3, such as Figure 2As shown, after the wall of the n-2th floor is formed, temporary support columns 4 are set on the embedded parts of the n-2th floor, and then temporary crossbeams 5 are installed on the top of the temporary support columns 4. The temporary crossbeams 5 are connected to the inner frame 1 and the outer hanging frame 2 of the building machine. The temporary crossbeams 5 are set parallel to the side of the top crossbeam to be removed and are located on the same horizontal plane as the top crossbeam. The temporary crossbeams 5 are used to achieve the temporary connection between the inner frame 1 and the outer hanging frame 2. S4. Remove the top beam to be removed from the top platform 3; S5, such as Figure 3 As shown, hoist and install truss 6; according to the design position of truss 6, remove the walkway panels and protective nets that interfere with it in advance; hoist truss 6 in sections, first lift each section of truss 6 to directly above the installation position, then hoist it to the designated position and connect it to the core tube or the previously installed section of truss 6; S6, such as Figure 4 As shown, reinstall the top beam to be removed, and then remove the temporary beam 5 and the temporary support 4; S7. Tie the n-1 layers and n layers of steel bars, and then pour the n-1 layer of wall concrete. S8, the overall lifting building machine, is used for subsequent concrete pouring of the core tube wall.
[0022] In step S2, after the n-2 layer wall is cast and formed, the template is removed and suspended at the n-2 layer position. When the template interferes with the suspension shoe, the template is lifted and placed at the n-1 layer position.
[0023] In step S3, the temporary support 4 and the embedded parts are connected by welding.
[0024] In step S5, if the length of the corbel extending beyond the outer side of the wall of the truss 6 is less than 1.5m, only the walkway slab needs to be removed; if the length of the corbel extending beyond the outer side of the wall of the truss 6 is not less than 1.5m, the walkway slab and the protective net need to be removed at the same time, and a horizontal pipe connection is set at the break point, and a dense mesh net is set for temporary protection. The horizontal pipe and the corbel do not interfere with each other.
[0025] Before step S5, the placing boom and other equipment on the top platform 3 can be hoisted back to the ground. After all the trusses 6 are installed, the placing boom can be hoisted back to the top platform 3.
[0026] In steps S4 and S5, when there are a large number of trusses 6 to be installed, the top beams to be removed need to be dismantled in batches to ensure the overall stability of the building machine. The trusses 6 are installed in batches accordingly.
[0027] In steps S7 and S8, the formwork used for pouring the n-1 layer wall and the n layer wall is loose formwork, which makes it easy to set notches at the corbel positions where the truss 6 is installed.
[0028] In step S8, the subsequent core tube construction continues. When the building machine is lifted up to the nth floor where the suspension shoe is located, it is necessary to ensure that the suspension shoe and the installation truss 6 are misaligned. When the building machine is lifted up, if the external bracket 2 interferes with the corbel of the installation truss 6, the walkway plate needs to be removed. After the interference position passes through the corbel, the walkway plate is restored to ensure that the external bracket 2 is not completely disconnected.
[0029] The outer side of the template is reinforced with walers.
[0030] Example 2: The installation truss 6 is installed on the outer wall of the core tube, and the length of the installation truss 6 is approximately the length of the corresponding outer wall of the core tube.
[0031] Example 2 provides a high-altitude conversion construction method for building construction machines used in cantilevered buildings, comprising the following steps: S1. Install the building construction machine and carry out core tube construction; S2. When the top platform 3 of the building machine is raised to the n+1 floor, the steel bars of the n-2 floor wall are tied, and then the formwork is installed on both sides of the n-2 floor wall and the n-2 floor wall concrete is poured. S3, such as Figure 5 , 6 As shown, all the outer brackets 2 on one side corresponding to the outer mounting truss 6 are disassembled; S4. Hoist the outer installation truss 6; lift the outer installation truss 6 to the outside of the installation position, then move it to the designated position and install and fix it. S5, such as Figure 7 As shown, after the installation of truss 6 is completed, the external bracket 2 is repositioned and installed. S6. Tie the n-1 layers and n layers of steel bars, and then pour the n-1 layer of wall concrete. S7. The building-building machine is lifted as a whole to carry out the subsequent concrete pouring of the core tube wall.
[0032] Example 3: The installation truss 6 is installed on the outer wall of the core tube, and the length of the installation truss 6 is significantly less than the length of the corresponding outer wall of the core tube.
[0033] Example 3 provides a high-altitude conversion construction method for cantilever buildings using a building-building machine. The difference between Example 2 and Example 3 is the following steps: S3, dismantle the portion of the external hanging frame 2 corresponding to the outer installation truss 6. The remaining steps are the same as in Example 2.
[0034] Finally, it should be noted that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the foregoing embodiments, those skilled in the art can still modify the technical solutions described in the foregoing embodiments or make equivalent substitutions for some of the technical features. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the protection scope of the present invention.
Claims
1. A high-altitude conversion construction method for building construction machines used in cantilevered buildings, wherein, The cantilevered building includes a cantilever structure and a core tube. The cantilever structure is located on the nth floor, and the core tube is equipped with an installation truss (6) on the nth floor. The building machine includes an inner frame (1), an outer frame (2), and a top platform (3). The top platform (3) includes a top horizontal beam and a top longitudinal beam. The top horizontal beam is aligned with the length direction of the installation truss (6). The installation trusses (6) are arranged parallel to each other inside the core tube. The building is characterized by the following steps: S1. Install the building construction machine and carry out core tube construction; S2. Raise the top platform (3) of the building machine to the n+1 floor, tie the wall reinforcement of the n-2 floor, then designate the top beam that is located on the same vertical plane as the installation truss (6) as the top beam to be demolished, and set the embedded parts on the top of the n-2 floor wall at the adjacent side position of the top beam to be demolished, and then pour the concrete of the n-2 floor wall. After the walls of S3 and n-2 are formed, temporary support columns (4) are set on the embedded parts of the n-2 layer, and then temporary crossbeams (5) are installed on the top of the temporary support columns (4). The temporary crossbeams (5) are connected to the inner frame (1) and the outer frame (2) of the building machine. S4. Remove the top beam to be removed from the top platform (3); S5. Hoisting and installing the truss (6); According to the design position of the truss (6), remove the walkway and protective net that interfere with it in advance; hoist the truss (6) in sections. First, lift each section of the truss (6) to the top of the installation position, and then hoist it to the designated position. S6. Reinstall the top beam to be removed, and then remove the temporary beam (5) and temporary support (4). S7. Tie the n-1 layers and n layers of steel bars, and then pour the n-1 layer of wall concrete. S8, the overall lifting building machine, is used for subsequent concrete pouring of the core tube wall.
2. The high-altitude conversion construction method for building construction machines used in cantilevered buildings according to claim 1, characterized in that, In step S8, when the building machine is lifted upwards, if the external bracket (2) interferes with the corbel of the installation truss (6), the walkway plate is removed, and the walkway plate is restored after the interference position passes the corbel.
3. The high-altitude conversion construction method for building construction machines used in cantilevered buildings according to claim 1, characterized in that, The temporary crossbeam (5) is set parallel to the side of the top crossbeam to be removed and is on the same horizontal plane as the top crossbeam.
4. The high-altitude conversion construction method for building construction machines used in cantilevered buildings according to claim 1, characterized in that, In steps S4 and S5, the top beam to be removed is dismantled in batches, and the truss (6) is installed in corresponding batches.
5. A high-altitude conversion construction method for building construction machines used in cantilevered buildings according to claim 1, characterized in that, In steps S7 and S8, the templates used for pouring the n-1 layer wall and the n layer wall have notches set at the corbel positions of the truss (6).
6. A high-altitude conversion construction method for building construction machines used in cantilevered buildings according to claim 1, characterized in that, In step S5, if the length of the corbel extending beyond the outer side of the wall of the truss (6) is less than 1.5m, only the walkway slab needs to be removed; if the length of the corbel extending beyond the outer side of the wall of the truss (6) is not less than 1.5m, the walkway slab and the protective net need to be removed at the same time, and a horizontal pipe connection is set at the break point, and a dense mesh net is set.
7. The high-altitude conversion construction method for a building construction machine for cantilevered buildings according to claim 1, wherein the installation truss (6) is also set on the outer wall of the core tube, and the length of the installation truss (6) is approximately the length of the corresponding outer wall of the core tube, characterized in that, Step S4 also includes: disassembling all the outer brackets (2) on one side corresponding to the outer mounting truss (6); Step S5 also includes: lifting the outer mounting truss (6) to the outside of the installation position, then moving it to the designated position and installing it; Step S6 also includes: resetting the outer brackets (2).
8. The high-altitude conversion construction method for a building construction machine for cantilevered buildings according to claim 1, wherein the installation truss (6) is also set on the outer wall of the core tube, and the length of the installation truss (6) is significantly less than the corresponding length of the outer wall of the core tube, characterized in that, Step S4 also includes: removing part of the outer bracket (2) corresponding to the outer mounting truss (6); Step S5 also includes: lifting the outer mounting truss (6) to the outside of the installation position, then moving it to the designated position and installing it; Step S6 also includes: resetting the outer bracket (2).
Citation Information
Patent Citations
Installation method of special-shaped and curved-surface suspension type steel structure system
CN111364615A
High-altitude conversion construction method for building machine of variable-cross-section shear wall
CN117661846A