Engineering vehicle bucket rear jaw processing method and secondary tool setting boring tooling
By combining the first and second boring tools, along with multiple tool setting and positioning blocks, the machining problem of the rear jaw parts of the engineering vehicle's bucket was solved. This achieved high-precision hole coaxiality and parallelism, ensuring control over boring depth and machine tool rotation error, and improving machining efficiency and quality.
Patent Information
- Application Number
- CN202410476365.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-19
- Publication Date
- 2026-11-20
- Estimated Expiration
- 2044-04-19
AI Technical Summary
Due to their large size, complex structure, and poor welding dimensional stability, the rear jaw parts of engineering vehicle buckets lack a unified reference during boring. It is difficult to guarantee the coaxiality and parallelism of the five sets of holes, and the boring depth is too deep, resulting in large machine tool rotation errors and making it difficult to achieve high-precision machining.
The machining method adopts a combination of a first boring tool and a second boring tool. The first boring tool is used for welding parts and boring the holes in group A. The second boring tool is used to clamp the parts and work with a special tool holder to machine the holes in groups B, C, D, and E. By repeatedly adjusting the tool setting and using the positioning tool adjustment block, the relative positional relationship of the holes and the machining accuracy are ensured.
It achieved high-precision machining of the rear jaw of the engineering vehicle bucket, ensuring the coaxiality and parallelism of each group of holes, solving the problems of excessive boring depth and machine tool rotation error, and improving machining efficiency and quality.
Smart Images

Figure CN118180899B_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of automotive parts processing technology, specifically relating to a method for machining the rear jaw of an engineering vehicle bed and a secondary tooling tool for boring. Background Technology
[0002] Reference Figures 1-3 The rear jaw of the engineering vehicle bucket is characterized by its large size, complex structure, high degree of fit between multiple sets of holes, and the fact that the main frame is welded from thin blank plates, resulting in poor dimensional stability. Therefore, the main difficulties in processing this part are as follows: (1) The dimensions and relative positions of the five sets of holes are required to be high, but due to the structure, they cannot be completed in one clamping and boring operation; (2) The boring depth is too deep; (3) The poor dimensional stability of the weld results in a lack of a unified and stable reference during boring; (4) The machine tool must rotate 180° during boring, resulting in a large rotation error.
[0003] As can be seen from the figure, the part is a welded structure. From the technical requirements analysis, the part has five groups of holes: A, B, C, D, and E. Technically, it is necessary to ensure that the holes in group B and group C are coaxial, and that the holes in group D and group E are coaxial. In addition, it is necessary to ensure that the line connecting the centers of the holes in group A is parallel to the line connecting the centers of the holes in groups B and C, and must also be parallel to the line connecting the centers of the holes in groups D and E. Furthermore, the positional accuracy of each group of holes must be ensured, and the distance S1 must be symmetrical along the center line. The technical requirements are high.
[0004] From a structural and material analysis perspective: because the welded plates are all thin plates and are all raw materials, the dimensional uniformity after welding is poor, resulting in a lack of a unified benchmark for subsequent processing; the four groups of holes, B, C, D, and E, are distributed on both sides of the workpiece and are the farthest apart, so it is difficult to ensure the coaxiality and parallelism between the four groups of holes; the holes in group A are blocked by the side plates on both sides, and if only the holes in groups B and C are processed, the relationship between the holes in group A and the four groups of holes B, C, D, and E cannot be guaranteed, further increasing the processing difficulty; furthermore, the depths of S3 and S4 during boring are relatively deep, and ordinary tool holders cannot meet the boring requirements, and the diameters of groups B and C are equal, the diameters of groups D and E are equal, and the whole is symmetrical about the center line.
[0005] Therefore, it is necessary to design reasonable machining steps and boring tools based on the structural characteristics of the part, solve the above difficulties, ensure the machining accuracy and quality requirements of the part, and at the same time ensure the economic efficiency of machining.
[0006] Chinese utility model patent CN217859678U discloses a welding fixture for a front subframe of an automobile chassis. The fixture includes a base plate, and further comprises two sets of positioning and clamping mechanisms for the front suspension bracket, front longitudinal beam, front control arm bracket, stabilizer bar bracket, rear longitudinal beam, and rear crossbeam. Each of these mechanisms is symmetrically arranged on both sides of the base plate. It also includes two sets of front longitudinal beam positioning and clamping mechanisms, respectively located on both sides of the front end of the base plate; and two positioning and clamping mechanisms for the rear suspension sleeve and rear suspension bracket, located in the middle of the rear end of the base plate. This design is simple, reasonable, easy to operate, and provides accurate positioning. The fixture has a short manufacturing cycle, allowing for rapid response to prototype production needs and meeting vehicle assembly schedules. It also has a short change cycle, enabling it to adapt to product design changes at any time. Chinese invention patent CN117620570A discloses a welding fixture for a rear subframe of an automobile chassis, including a tooling frame, a limiting crank, a corner limiting mechanism, and a transverse and longitudinal straightening mechanism. In this invention, the output end of cylinder two drives a lifting plate to move, which in turn drives the longitudinal clamping top seat to abut against the rear subframe body of the automobile chassis. Through a sliding rod and two triangular guide frames, the opening guide component one and the opening guide component two move downwards synchronously, causing the slider to slide on the inclined end faces of the fixed frame on both sides. This, in turn, causes the upper end faces of the transverse clamping top plates on both sides to abut against the middle section of one side of the rear subframe, achieving bidirectional positioning and straightening in both the transverse and longitudinal directions. This avoids thermal deformation of the relatively long transverse and longitudinal beams of the rear subframe during welding, ensuring the quality of the workpiece. It also allows for rapid cooling and shaping of the central reinforcing ribs of the rear subframe while straightening them, preventing weld cracking at the welding end due to later straightening. While the above two devices are designed for different problems with the chassis, they cannot solve the problem proposed in this solution. Summary of the Invention
[0007] To address the aforementioned problems, this invention aims to provide a method for machining the rear jaw of an engineering vehicle bucket and a secondary tooling for boring.
[0008] To achieve the above objectives, the present invention adopts the following technical solution: a secondary boring tool for the rear jaw of an engineering vehicle bucket, comprising a first boring tool and a second boring tool, wherein the first boring tool is used for the assembly and welding of parts, and the second boring tool is used for boring holes in parts.
[0009] Preferably, the first boring tool includes a main support frame, on which several positioning support plates are provided. The positioning support plates fix the bottom plate of the part from all sides and fix the upright plate of the part through a pin assembly.
[0010] Preferably, the second boring tool includes a main support, a grid-shaped connecting rod set on the main support and parallel to the main support, a mandrel fixed on the grid-shaped connecting rod, and two pairs of positioning structures aligned at both ends of the main support;
[0011] The positioning structure includes a positioning and calibrating block at the top, a positioning pin on the positioning and calibrating block, and a diamond-shaped positioning pin and a positioning pin fixed to the base. A wear-resistant sleeve is embedded in the positioning and calibrating block, and a hinged clamping mechanism is also provided to clamp it.
[0012] Preferably, the main support is in the shape of a grid, with several tightening screws and pressure plates on its outer frame, and correction reference blocks as correction reference surfaces are integrally welded on both sides of the support.
[0013] Preferably, the positioning and calibrating block is convex in shape, with a positioning pin connected to its upper end, and U-shaped grooves opened on the upper surfaces of both sides of its lower end. A diamond-shaped positioning pin and a positioning pin are vertically connected on the two sides of the lower end, and the hinged clamping mechanism is fixed to the positioning and calibrating block through the U-shaped grooves.
[0014] The hinged clamping mechanism includes a T-shaped positioning post, as well as a matching nut and washer.
[0015] A method for auxiliary machining of the rear jaw of an engineering vehicle bucket using a secondary tool-calibrating boring fixture includes the following steps:
[0016] Step 1: Using the first boring tool, weld the two vertical plates where the A group holes in the middle of the part are located to the base plate, and use a special tool bar to bore the A group holes;
[0017] Step 2: Use the first boring tool to assemble and weld the remaining parts, and then perform a second precision boring;
[0018] Step 3: Use the second boring tool to clamp the parts to ensure the relative positional relationship between the holes in group A and the holes in the other groups;
[0019] Step 4: Use the second boring tool to clamp the part and use a special tool holder to machine the holes in groups B, C, D, and E;
[0020] The second boring tool requires multiple tool setting adjustments during operation, including tool setting using the calibration reference surface and positioning calibration block.
[0021] Preferably, the specific operation of step 1 is as follows:
[0022] Step 11: Use the welding pin assembly as the positioning element, take the round hole on the middle vertical plate of part A as the positioning rough reference, flatten the large surface of the bottom plate of the part, and tighten the part from the top of the four sides. Use the first boring tool to weld the bottom plate and the two vertical plates to ensure the S2 distance on the part and the parallelism between them.
[0023] Step 12: After assembly welding, arrange tie rods and install accompanying fixtures for welding to ensure the opening dimensions of the two vertical plates are parallel to each other;
[0024] Step 13: After welding, allow the vessel to stand naturally for the specified time to allow the welding deformation stress to be released;
[0025] Step 14: Use a special tool holder to bore the holes in group A.
[0026] Preferably, the welding pin assembly is used as the positioning element, with the bored round hole on the upper part of the vertical plate in the middle of part A as the positioning precision reference, the large surface of the bottom plate of the part is leveled, and the part is tightened. The other parts except the bottom plate and the vertical plate are assembled and welded using the first boring tool.
[0027] Preferably, the special tool holder includes a roughing tool holder and a finishing tool holder, both of which have a longer effective length than conventional tool holders.
[0028] Preferably, the specific process of step 3 is as follows: using the bored round hole on the middle upright plate of group A as the positioning precision reference, leveling the large surface of the bottom plate of the part, distributing multiple pressure points, ensuring uniform pressure, and setting multiple apex points around the part to tighten it.
[0029] Preferably, the specific process of step 4 is as follows:
[0030] Step 41: Before clamping the part, use the calibration datum surface to calibrate the second boring tool;
[0031] Step 42: Use the second boring tool to clamp the part, and use the cross-shaped connecting rod and mandrel to position the part by using the A group holes and the machined S1 two sides;
[0032] Step 43: Use the positioning pin to fix the holes B, C, D, and E of the part through the positioning and locating tool block, and the positioning pin and the four holes B, C, D, and E are clearance fit.
[0033] Step 44: Use the tightening screw and pressure plate to tighten and prevent loosening. The clamping is now complete.
[0034] Step 45: Roughly bore holes B and D using a rough boring bar, leaving an appropriate allowance for finishing. Then, use a finish boring bar for finishing. Once holes B and D are finished, a positioning and alignment block is needed to set the tool on the second boring fixture.
[0035] Step 46: After the holes in groups B and D are machined, the machine tool platform rotates 180°. After the rotation, the calibration reference face is used to set the tool on the second boring tool to compensate for the machine tool rotation error and ensure the machining accuracy of the holes in groups C and E. The boring of the holes in groups C and E can be completed by following the same steps as boring the holes in groups B and D.
[0036] Preferably, in step 4, the second boring tool needs to be calibrated and tool-set multiple times. The first time, the tool is calibrated using the calibration reference surface; the second time, after clamping, the tool is calibrated using the positioning calibration block to ensure the correct position of the machining hole; the third time, after the machine tool rotates 180°, the tool is recalibrated using the calibration reference surface to compensate for machine tool errors.
[0037] Compared with the prior art, the present invention has the following advantages:
[0038] 1. The first boring tooling structure is specifically designed to complete the assembly and welding of the base plate, the vertical plate, and the remaining parts, ensuring the S2 distance and mutual parallelism. It is easy to operate and improves efficiency. A special tool holder is designed to solve the problem of excessive boring distance.
[0039] 2. The positioning and calibrating tool of the second boring fixture is a detachable structure, which is equipped with clamping and other structures to ensure the convenience of the boring process and the relative positional relationship between the holes in group A and the other groups of holes. This ensures the machining strength, accuracy and quality requirements, and the positioning datum ensures uniform pressure during the clamping process. It is not easy to deform after the clamping device is removed. The quick-release and quick-installation structure is adopted to improve the machining efficiency. The second boring fixture performs multiple tool settings, using the positioning and calibrating tool block and the calibration datum surface to calibrate the tool. This ensures both the machining position and the machine tool rotation error.
[0040] 3. The processing method of the present invention, in conjunction with the boring tool, ensures that the positions of each group of holes are within the design technical requirements, and the parallelism between the connecting lines of each hole center is also guaranteed. On this basis, other problems are also reasonably solved, so the technical requirements of the rear jaw of the bucket are fully realized. Attached Figure Description
[0041] To more clearly illustrate the technical solutions in the specific embodiments of the present invention, the drawings used in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.
[0042] Figure 1 This is a top view of the rear jaw of the engineering vehicle bed in this invention;
[0043] Figure 2 This is a side view of the rear jaw of the engineering vehicle bed in this invention;
[0044] Figure 3 This is a three-dimensional structural schematic diagram of the rear jaw of the engineering vehicle bed in this invention;
[0045] Figure 4 This is a front view of the part clamped by the first boring tool in this invention;
[0046] Figure 5This is a side view of the part clamped by the first boring tool in this invention;
[0047] Figure 6 This is a top view of the part clamped by the first boring tool in this invention;
[0048] Figure 7 This is a three-dimensional schematic diagram of the first boring tool clamping the part in this invention;
[0049] Figure 8 This is a schematic diagram of the rough boring bar structure in this invention;
[0050] Figure 9 This is a schematic diagram of the precision boring bar structure in this invention;
[0051] Figure 10 This is a three-dimensional schematic diagram of the welding of the remaining parts using the first boring tool in this invention;
[0052] Figure 11 This is a top view of the welding of the remaining parts using the first boring tool in this invention;
[0053] Figure 12 This is a front view of the second boring tool in this invention;
[0054] Figure 13 This is a top view of the second boring tool in this invention;
[0055] Figure 14 This is a side view of the second boring tool in this invention;
[0056] Figure 15 This is a top view of the second boring tool in this invention positioning the holes in group A of the part and the two sides of the machined S1.
[0057] Figure 16 This is a three-dimensional view of the positioning of the second boring tool on the holes of part A and the two sides of the machined S1 in this invention.
[0058] Figure 17 This is a top view of the part being fixed by inserting a positioning pin in this invention;
[0059] Figure 18 This is a three-dimensional schematic diagram of fixing the part by inserting a positioning pin in this invention;
[0060] In the figure, 1-main support, 2-grid connecting rod, 3-mandrel, 4-diamond positioning pin, 5-positioning and calibrating block, 6-wear-resistant sleeve, 7-positioning pin, 8-positioning pin, 9-tightening screw, 10-pressure plate, 11-hinged clamping mechanism, 12-correction reference surface, 13-pin assembly, 14-support, 15-positioning support plate, a-first boring tool, b-second boring tool; c-rough boring tool holder; d-fine boring tool holder. Detailed Implementation
[0061] The present invention will be further described below with reference to the accompanying drawings and specific embodiments. However, it should not be construed that the scope of the subject matter of the present invention is limited to the following embodiments. All modifications, substitutions and alterations made based on ordinary technical knowledge and common practices in the art without departing from the above-described technical concept of the present invention are included within the scope of the present invention.
[0062] Reference Figure 1-3 The schematic diagram of the parts shows that the rear jaw of the bucket blocks the boring of the A group hole in the middle of the rear jaw. Therefore, the machining method is designed to weld the two vertical plates where the A group hole is located to the base plate using the first boring tool a, then to bore the A group hole, then to weld the remaining parts together, and then to perform a second precision boring.
[0063] The processing method is as follows:
[0064] 1.Reference Figure 4-6 The first boring tool a includes a bracket 14, on which a plurality of positioning support plates 15 are provided. The positioning support plates 15 fix the bottom plate of the rear jaw from all sides and fix the upright plate of the part by means of the pin assembly 13.
[0065] Reference Figure 7 During assembly welding, the pin assembly 13 pin is used as the positioning element. The round hole on the middle vertical plate of the rear jaw A group is used as the positioning rough reference. The bottom plate of the rear jaw is leveled and a total of 8 vertices are set around the large surface to tighten the rear jaw. The first boring tool a is used to assemble and weld the base plate and the two vertical plates to ensure that the S2 distance on the rear jaw is parallel to each other.
[0066] 2. After assembly welding, arrange tie rods and install accompanying fixtures for welding to ensure the opening size of the two side plates of the rear jaw of the bucket and their parallelism;
[0067] 3. After welding, allow the vessel to stand naturally for the specified time to allow the welding deformation stress to be released;
[0068] 4. The boring of the A group holes on the rear jaw is performed to establish a unified benchmark for boring other groups of holes subsequently. To this end, a special tool holder is designed to solve the problem of excessive boring depth. (Refer to...) Figure 8 and Figure 9 To ensure that the machining technical requirements and performance are met, a roughing boring bar (c) and a finishing boring bar (d) are designed respectively. Compared with conventional boring bars, the effective machining length and rigidity are significantly improved.
[0069] 5.Reference Figure 10 and Figure 11 Continue using the first boring tool a to assemble and weld the remaining parts. Use the pin assembly 13 as the positioning element and the round hole after boring on the upper part of the middle vertical plate of group A as the positioning precision reference. Set up 8 vertices around the large surface of the part base plate to tighten the parts. Use the first boring tool a to assemble and weld the other parts except the base plate and the vertical plate.
[0070] 6. Using the second boring fixture b, the relative positional relationship between the holes in group A and the other groups of holes is ensured to guarantee the machining strength, accuracy, and quality requirements. The boring fixture is placed on the boring machine table, and the fixture is calibrated to maintain a unified reference. The bucket rear jaw is then moved, still using the round hole after boring on the upper part of the vertical plate in the middle of group A of the bucket rear jaw as the positioning reference. The large surface of the bottom plate of the part is leveled, and five pressure points are distributed to ensure uniform pressure. A total of eight apex points are set around the part to tighten it, making it less prone to deformation after the clamping device is removed. The boring sleeve adopts a quick-release and quick-install structure, which helps to improve machining efficiency.
[0071] Reference Figures 12-14 The second boring tool b includes a main support 1, a grid-shaped connecting rod 2 mounted on and parallel to the main support 1, a mandrel 3 fixed on the grid-shaped connecting rod 2, and two pairs of positioning structures aligned at both ends of the main support 1. The positioning structure includes a positioning and calibrating block 5 at the uppermost end, with a positioning pin 7 on the positioning and calibrating block 5. The positioning and calibrating block 5 is fixed to the base by diamond-shaped positioning pins 4 and 8. A wear-resistant sleeve 6 is embedded in the positioning and calibrating block 5, and a hinged clamping mechanism 11 is also provided to clamp it. The main support 1 is grid-shaped, with several tightening screws 9 and pressure plates 10 on its outer frame, and calibration reference blocks as calibration reference surfaces 12 are integrally welded to its two ends. The positioning and calibrating block 5 is convex in shape, with a positioning pin 7 connected to its upper end. U-shaped grooves are formed on the upper surfaces of both sides of its lower end, and diamond-shaped positioning pins 4 and 8 are vertically connected to the two sides of its lower end. The hinged clamping mechanism 11 is fixed to the positioning and calibrating block 5 through the U-shaped grooves. The hinged clamping mechanism 11 includes a T-shaped positioning post, and matching nuts and washers.
[0072] The positioning and calibrating block 5 is a detachable structure with a wear-resistant sleeve 6 embedded inside. During clamping, the positioning and calibrating block 5, in conjunction with the locating pin 7, achieves the positioning function, ensuring that the position of the hole to be machined is determined and correct. During boring, it can serve as a tool calibration reference for the machine tool spindle, ensuring the correct machining infeed position; that is, the positioning reference and the tool calibration reference are unified. During boring, it can be removed to facilitate the machine tool spindle infeed and manual measurement. The positioning and calibrating block 5 is positioned by the diamond-shaped locating pin 4 and the locating pin 8, and is clamped by the hinged clamping mechanism 11. Through the cooperation of these three, the positioning and calibrating block 5 can be accurately positioned and quickly disassembled, ensuring the accuracy of the positioning of the four sets of holes B, C, D, and E, and saving clamping time. During machining, the positioning and calibrating blocks 5 at the left and right symmetrical positions are coaxial and the lines connecting the hole centers are parallel. The calibration reference surface 12 is designed on both sides of the boring fixture and is completed by welding it to the main support 1 and then machining it as a whole, which can effectively ensure the calibration accuracy. When using it, the machined plane of this structure can be calibrated.
[0073] The specific machining steps for groups B, C, D, and E are as follows:
[0074] 1. First, hoist the second boring tool b onto the machine tool, and then use the calibration reference surface 12 to calibrate the second boring tool b;
[0075] 2.Reference Figure 15 and Figure 16 The rear jaw of the bucket is hoisted onto the boring fixture. During clamping, the cross-shaped connecting rod 2 and the mandrel 3 are used to position the A group holes in the second boring fixture b and the two sides of the machined S1. This positioning mainly ensures that the machined rear jaw is parallel as a whole, and that the left and right sides of the rear jaw are symmetrical along the center, and S1 is symmetrical along the center line, so that the A group holes and other groups of holes are connected, which is the basis for ensuring that the connecting lines of the hole centers are parallel.
[0076] 3.Reference Figure 17 and Figure 18 The positioning pin 7 is inserted through the positioning adjustment block 5 until it is inserted into the holes of groups B, C, D, and E of the part. The positioning pin 7 is fitted with the four holes of groups B, C, D, and E with an appropriate clearance to ensure smooth insertion. In this way, the theoretical center positions of the four holes of groups B, C, D, and E can be found, which can ensure the positional accuracy of the four holes and the coaxiality of the holes of groups B and C, and the holes of groups D and E, and that the lines connecting the holes are parallel.
[0077] 4. Use the tightening screw 9 and pressure plate 10 to tighten and prevent loosening. The clamping is now complete.
[0078] 5. Install the special rough boring bar c on the machine tool spindle; pull out the positioning pins 7 that are inserted into the holes of group B and group D, and at the same time install the holes on the spindle calibration positioning and calibration block 5 of the special rough boring bar c. After calibration, remove the positioning and calibration block 5, rough bore the holes of group B, and leave an appropriate allowance for finishing.
[0079] 6. After rough boring of group B holes is completed, the spindle is withdrawn along the axial direction and replaced with a special precision boring tool holder d for precision machining. After machining of group B holes is completed, the spindle is withdrawn.
[0080] 7. Replace the spindle with a special rough boring bar c, move the spindle to calibrate the upper hole of the positioning and calibrating block 5, remove the positioning and calibrating block 5 and the rough boring D group of holes after calibration, and leave an appropriate allowance for finishing.
[0081] 8. After rough boring of group D holes is completed, the spindle is withdrawn along the axial direction and replaced with a special precision boring tool holder d for precision machining. Group D holes are now machined.
[0082] 9. After the holes in groups B and D are machined, the machine tool platform is rotated 180°. After the rotation is completed, the datum surface 12 is corrected to compensate for the machine tool rotation error and ensure the machining accuracy of the holes in groups D and E.
[0083] 10. When boring holes C and E, the machining process can be completed by following the same steps as boring holes B and D.
[0084] This method, combined with the boring tool, ensures that the positions of each group of holes are within the design technical requirements, and the parallelism between the connecting lines of each hole center is also guaranteed. On this basis, other problems are also reasonably solved, so the technical requirements of the rear jaw of the bucket are fully realized.
[0085] The foregoing has provided a detailed description of a method for machining the rear jaw of an engineering vehicle bucket and a secondary tooling boring fixture. Specific examples have been used to illustrate the structure and working principle of the invention. The descriptions of these embodiments are merely for the purpose of helping to understand the method and core ideas of the invention. It should be noted that those skilled in the art can make various improvements and modifications to the invention without departing from its principles, and these improvements and modifications also fall within the scope of protection of the claims of this invention.
Claims
1. A secondary tooling tool for boring the rear jaw of an engineering vehicle bucket, characterized in that: It includes a first boring fixture (a) and a second boring fixture (b). The first boring fixture (a) is used for welding the parts together, and the second boring fixture (b) is used for boring the parts. The first boring tool (a) includes a bracket (14), on which a plurality of positioning support plates (15) are provided. The positioning support plates (15) fix the bottom plate of the part from all sides and fix the upright plate of the part through the pin assembly (13). The second boring tool (b) includes a main support (1), a grid-shaped connecting rod (2) set on the main support (1) and parallel to the main support (1), a mandrel (3) fixed on the grid-shaped connecting rod (2), and two pairs of positioning structures aligned at both ends of the main support (1); The positioning structure includes a positioning and calibrating block (5) at the top, a positioning pin (7) on the positioning and calibrating block (5), and the positioning and calibrating block (5) is fixed to the base by a diamond-shaped positioning pin (4) and a positioning pin (8). A wear-resistant sleeve (6) is embedded in the positioning and calibrating block (5), and a hinged clamping mechanism (11) is also provided to clamp it.
2. The secondary tooling boring fixture for the rear jaw of the engineering vehicle bucket according to claim 1, characterized in that: The main support (1) is shaped like a grid, with several tightening screws (9) and pressure plates (10) on its outer frame, and correction reference blocks (12) are provided on its two ends by integral welding.
3. The secondary tooling boring fixture for the rear jaw of the engineering vehicle bucket according to claim 1, characterized in that: The positioning and calibrating block (5) is convex in shape, with a positioning pin (7) connected to its upper end. U-shaped grooves are provided on the upper surfaces of both sides of its lower end, and diamond-shaped positioning pins (4) and positioning pins (8) are vertically connected on the upper surfaces of both sides of its lower end. The hinged clamping mechanism (11) is fixed on the positioning and calibrating block (5) through the U-shaped groove.
4. The secondary tooling boring fixture for the rear jaw of the engineering vehicle bucket according to claim 1, characterized in that: The articulated clamping mechanism (11) includes a T-shaped positioning post, and a matching nut and washer.
5. A method for auxiliary machining of the rear jaw of an engineering vehicle bucket using the secondary tool-calibrating boring fixture described in any one of claims 1-4: comprising the following steps, Step 1: Using the first boring tool (a), weld the two vertical plates where the A group holes in the middle of the part are located to the base plate and use a special tool bar to bore the A group holes; Step 2: Use the first boring tool (a) to assemble and weld the remaining parts, and then perform a second precision boring; Step 3: Use the second boring tool (b) to clamp the parts to ensure the relative positional relationship between the holes in group A and the holes in the other groups; Step 4: Use the second boring tool (b) to clamp the part and use a special tool holder to machine the holes in groups B, C, D, and E; The second boring tool (b) requires multiple tool adjustments during operation, including tool adjustment using the calibration reference surface (12) and the positioning calibration block (5).
6. The method for assisting in the processing of the rear jaw of an engineering vehicle bucket according to claim 5, characterized in that: The specific steps of step 1 are as follows: Step 11: Use the welding pin assembly (13) as the positioning element, take the round hole on the middle vertical plate of part A as the positioning rough reference, flatten the bottom plate of the part, and tighten the part from the top of the four sides. Use the first boring tool (a) to weld the bottom plate and the two vertical plates to ensure that the S2 distance on the part is parallel to each other. Step 12: After assembly welding, arrange tie rods and install accompanying fixtures for welding to ensure the opening dimensions of the two vertical plates are parallel to each other; Step 13: After welding, allow the vessel to stand naturally for the specified time to allow the welding deformation stress to be released; Step 14: Use a special tool holder to bore the holes in group A.
7. The method for assisting in the processing of the rear jaw of an engineering vehicle bucket according to claim 5, characterized in that: The specific steps of step 2 are as follows: the welding pin assembly (13) is used as the positioning element, the round hole after boring on the upper part of the middle vertical plate of part A is used as the positioning precision reference, the bottom plate of the part is leveled and the part is tightened, and the other parts except the bottom plate and the vertical plate are welded using the first boring tool (a).
8. The method for assisting in the processing of the rear jaw of an engineering vehicle bucket according to claim 5, characterized in that: The special tool holder includes a roughing tool holder (c) and a finishing tool holder (d), both of which have a longer effective length than conventional tool holders.
9. The method for assisting in the processing of the rear jaw of an engineering vehicle bucket according to claim 5, characterized in that: The specific process of step 3 is as follows: using the bored round hole on the middle upright plate of group A as the positioning precision reference, level the large surface of the bottom plate of the part, disperse multiple pressure points, and ensure uniform pressure. Set multiple apex points around the part to tighten it.
10. The method for assisting in the processing of the rear jaw of an engineering vehicle bucket according to claim 5, characterized in that: The specific process of step 4 is as follows: Step 41: Before clamping the part, use the calibration reference surface (12) to calibrate the second boring tool (b); Step 42: Use the second boring tool (b) to clamp the part, and use the cross-shaped connecting rod (2) and the mandrel (3) to position the part in conjunction with the A group holes and the machined S1 sides; Step 43: Use the positioning pin (7) to pass through the positioning and positioning tool block (5) to fix the holes of groups B, C, D and E of the part, and the positioning pin (7) and the four groups of holes B, C, D and E are clearance fit; Step 44: Use the tightening screw (9) and pressure plate (10) to tighten and prevent loosening, and the clamping is completed; Step 45: Use the rough boring bar (c) to rough bore the holes in groups B and D, and leave an appropriate allowance for finishing. Then use the finish boring bar (d) to finish the holes in groups B and D. The holes in groups B and D are finished. The positioning and alignment block (5) is used to set the tool of the second boring fixture (b). Step 46: After the holes in groups B and D are machined, the machine tool platform rotates 180°. After the rotation, the second boring tool (b) is set using the calibration reference surface (12) to compensate for the machine tool rotation error and ensure the machining accuracy of the holes in groups C and E. The boring of the holes in groups C and E can be completed by imitating the boring of the holes in groups B and D.
11. The method for assisting in the processing of the rear jaw of an engineering vehicle bucket according to claim 5, characterized in that: In step 4, the second boring tool (b) needs to be corrected and the tool set multiple times. The first time, the tool is corrected using the correction reference surface (12). The second time, after clamping, the tool is corrected using the positioning correction block (5) to ensure that the position of the machining hole is correct. The third time, after the machine tool rotates 180°, the tool is corrected again using the correction reference surface (12) to make up for the machine tool error.
Citation Information
Patent Citations
Welding fixture for rear auxiliary frame of automobile chassis
CN117620570A
Welding fixture for front auxiliary frame of automobile chassis
CN217859678U
Secondary tool correcting and boring tool for rear jaw of engineering truck bucket
CN222831179U