A hot blast stove backflow cooling system and process
By introducing exhaust pipes and ejectors into the hot blast stove system, combined with purging gas regulation and analysis instruments, the problems of large footprint and safety hazards of the hot blast stove backflow shutdown system have been solved, achieving the effects of investment savings and operational safety.
Patent Information
- Application Number
- CN202410334687.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-22
- Publication Date
- 2026-11-20
- Estimated Expiration
- 2044-03-22
AI Technical Summary
The existing hot blast stove backflow shutdown system occupies a large area, increases investment costs, and has a low chimney, making it easy for gas to disperse and posing a hazard to the safety and health of operators.
The system employs a combined design of exhaust pipes, ejectors, and purge gas supply pipes. The ejector provides high-pressure injection gas to guide the blast furnace gas into the flue gas pipe and safely discharge it through the hot blast stove chimney. Combined with CO and O₂ analyzers for monitoring and purge gas regulation, it ensures safe discharge and pressure control.
It saves investment in hot blast stove systems, reduces the risk of gas hazards to operators, prevents gas diffusion, and enables safe and efficient shutdown operations.
Smart Images

Figure CN118222777B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of blast furnace ironmaking technology, specifically to a hot blast stove backflow shutdown system and process. Background Technology
[0002] During normal operation, a blast furnace contains a large amount of ore and coke. The hot blast stove heats the cold air and sends it through hot blast pipes into the blast furnace to burn with the coke, producing gas to reduce the ore. When the blast furnace needs temporary maintenance or when external conditions change and production needs to be temporarily halted, the cold blast supply must be stopped, i.e., a shutdown operation is performed. At the start of the shutdown, the combustion of coke inside the blast furnace results in a large amount of residual gas. If equipment such as the tuyeres needs to be replaced, a large amount of gas will escape from the tuyeres, affecting operation and personnel safety. Therefore, a reverse-flow shutdown operation is used to prevent gas leakage.
[0003] Currently, the mainstream reverse-flow shutdown process involves drawing a separate reverse-flow shutdown duct from the highest point of the hot blast duct, with a reverse-flow shutdown valve installed on it. A dedicated reverse-flow shutdown chimney is then constructed around the valve, with the chimney's interior either painted or bricked. The highest point of the reverse-flow shutdown chimney is at least 4 meters higher than the hot blast stove frame. When reverse-flow shutdown is required, the reverse-flow shutdown valve is opened, utilizing the "chimney effect" to vent the residual gas in the blast furnace into the upper atmosphere.
[0004] This process typically involves placing the backflow ventilation duct, valves, and backflow ventilation chimney on the hot blast stove platform. When these facilities are placed on the hot blast stove platform, the hot blast stove frame needs to be extended. This method, on the one hand, requires a large footprint, increasing the investment in the hot blast stove system and negatively impacting its maintenance. On the other hand, the hot blast stove's backflow ventilation chimney is relatively low compared to surrounding structures, potentially allowing gas to drift into nearby buildings, posing a risk to the safety and health of operators. Summary of the Invention
[0005] In order to reduce the investment in hot blast stoves while reducing the risk of blast gas hazard to the safety and health of operators, this invention proposes a novel hot blast stove backflow blast shutdown system and process.
[0006] The hot blast stove backflow shutdown system according to the present invention includes: an exhaust pipe, one end of which is connected to the connection between the hot blast pipe and the mixing blast pipe of the hot blast stove, and the other end of which is connected to the flue gas pipe of the hot blast stove; an ejector, which is disposed on the exhaust pipe; and an ejector gas source pipe, which is connected to the ejector. During blast furnace shutdown, the ejector gas source pipe provides injection gas to the ejector, so that the ejector transports the gas in the hot blast pipe to the flue gas pipe via the exhaust pipe.
[0007] Furthermore, the hot blast stove backflow shutdown system also includes a purge gas source pipe, which connects to the area between the ejector and the flue gas pipe on the exhaust pipe.
[0008] Furthermore, the exhaust pipe is equipped with a first shut-off valve and a first blind flange valve located at the front end of the ejector, and a second shut-off valve and a second blind flange valve located at the rear end of the ejector. The purge gas source pipe is connected to the area on the exhaust pipe between the second blind flange valve and the flue gas pipe.
[0009] Furthermore, the ejector gas source pipeline is equipped with an ejector gas shut-off valve and an ejector gas flow regulating valve.
[0010] Furthermore, the purge gas supply pipeline is equipped with a purge gas shut-off valve and a purge gas flow regulating valve.
[0011] Furthermore, CO and O2 analyzers are installed on the flue gas duct.
[0012] Furthermore, the inner wall of the exhaust pipe is lined with a lining, which is formed by bricklaying or spraying.
[0013] Furthermore, the ejector gas in the ejector gas source pipeline is nitrogen or other inert gas; the purge gas in the purge gas source pipeline is nitrogen or other inert gas or water vapor.
[0014] The hot blast stove reverse flow shutdown process according to the present invention includes: conveying the gas in the hot blast duct of the hot blast stove to the flue gas duct of the blast furnace through an ejector that provides high-pressure injection gas.
[0015] Furthermore, the hot blast stove backflow shutdown process also includes: monitoring the CO and O2 content in the flue gas duct; when the CO and O2 content exceeds the preset safety value, blowing purge gas into the flue gas duct to reduce the CO and O2 content.
[0016] Compared with the prior art, the hot blast stove backflow shutdown system and process of the present invention have the following advantages:
[0017] 1) The backflow ventilation duct and chimney were eliminated, and the length of the hot blast stove frame was shortened, saving investment in the hot blast stove system. For renovation or expansion projects, eliminating the backflow ventilation duct and chimney allows the saved one-span hot blast stove frame to be used to build a new hot blast stove nearby, reducing the increased investment costs for various pipes, cables, etc., caused by building hot blast stoves over long distances, and avoiding unreasonable system layout.
[0018] 2) The original, collapsed chimney was relatively low compared to the surrounding buildings, and the emitted gas posed a hazard to the safety and health of the operators. Hot blast stove chimneys are typically higher than surrounding structures, and the gas emitted through them does not pose a hazard to the safety and health of the operators.
[0019] 3) It can adjust the pressure inside the blast furnace to a slightly negative pressure to prevent blast furnace gas from spreading from the tuyeres and other sources, thus protecting the safety and health of operators and maintenance personnel. Attached Figure Description
[0020] Figure 1 This is a schematic diagram of the structure of a hot blast stove backflow shutdown system according to an embodiment of the present invention. Detailed Implementation
[0021] To better understand the purpose, structure, and function of this invention, the invention will be described in further detail below with reference to the accompanying drawings.
[0022] Figure 1 The structure of a hot blast stove backflow shutdown system 100 according to an embodiment of the present invention is shown. For example... Figure 1 As shown, the hot blast stove backflow shutdown system 100 may include: an exhaust pipe 1, one end of which is connected to the connection point O between the hot blast pipe 16 and the mixing pipe 12 of the hot blast stove 24, and the other end of which is connected to the flue gas pipe 19 of the hot blast stove 24; an ejector 4, which is mounted on the exhaust pipe 1; and an ejector gas source pipe 20, which is connected to the ejector 4. During blast furnace shutdown, the ejector gas source pipe 20 provides injection gas to the ejector 4, so that the ejector 4 transports the gas in the hot blast pipe 16 to the flue gas pipe 19 via the exhaust pipe 1.
[0023] like Figure 1 As shown, the mixing duct 12 connects the cold blast duct 7 and the hot blast duct 16. When the blast furnace 23 is in normal production, the cold air in the cold blast duct 7 passes through the mixing regulating valve 31 and the mixing valve 30 on the mixing duct 12 and then enters the hot blast duct 16 to regulate the temperature of the hot blast. When the blast furnace is shut down, the mixing regulating valve 31 and the mixing valve 30 are closed, allowing the high-pressure injection gas to enter the ejector 4 through the ejector gas source duct 20. Under the action of the high-pressure injection gas, the residual gas in the hot blast duct 16 is continuously drawn into the ejector 4, thereby carrying the shut-down gas into the flue gas duct 19 of the hot blast stove 24, and finally discharged through the hot blast stove chimney 25, achieving the effect of safely discharging the residual gas in the blast furnace 23. During the shutdown process, the flow rate of the high-pressure injection gas can be adjusted according to the shutdown time, thereby adjusting the discharge rate of the shutdown gas.
[0024] The hot blast stove backflow shutdown system 100 of this embodiment of the invention provides an exhaust pipe 1, one end of which is connected to the connection point O between the hot blast pipe 16 and the mixing pipe 12 of the hot blast stove 24, and the other end is connected to the flue gas pipe 19 of the hot blast stove 24. Through the "chimney effect," the gas in the blast furnace 23 is drawn to the hot blast stove chimney 25 for discharge. In existing hot blast stove systems, the hot blast pipe 16 is usually located above the hot blast stove 24, while the flue gas pipe 19 is located at the ground. Because the flue gas pipe 19 is lower than the hot blast pipe 24, due to the "chimney effect," the gas cannot automatically enter the flue gas pipe 19 from the hot blast pipe 16 and then be discharged from the hot blast stove chimney 25 during shutdown. Therefore, the hot blast stove backflow shutdown system 100 of this embodiment of the invention provides an ejector 4 on the exhaust pipe. The ejector 4 generates initial suction force to guide the gas to the hot blast stove chimney 25. Ejector 4 has a jetting function. When the high-pressure gas enters the ejector inside ejector 4, it ejects a supersonic gas flow from the nozzle. Due to Bernoulli's principle and the viscosity of the gas, the high-pressure jet gas will entrain the gas in the pipeline, thus creating a negative pressure in the ejector's suction chamber. This continuously draws the gas through ejector 4 into the flue gas duct 19, and finally discharges it into the atmosphere through the hot blast stove chimney 25. When sufficient suction is generated, ejector 4 can be closed, and the gas will be discharged into the atmosphere by the chimney's suction.
[0025] Compared with the prior art, the hot blast stove backflow shutdown system 100 of the present invention eliminates the need for Figure 1 The backflow shut-off valve 28, backflow shut-off duct 26, and backflow shut-off chimney 27, shown by the dashed lines, simultaneously shorten the hot blast stove frame length, saving on hot blast stove system investment. For renovation or expansion projects, these components are omitted. Figure 1 The backflow shutdown valve 28, backflow shutdown pipe 26, and backflow shutdown chimney 27, shown by the dashed lines, allow the saved span of the hot blast stove frame to be used to build a new hot blast stove nearby. This reduces the increased investment costs for various pipes and cables caused by building a hot blast stove over a long distance, and avoids unreasonable system layout. Furthermore, because the existing backflow shutdown chimney 27 is relatively low compared to surrounding buildings, the emitted gas poses a hazard to the safety and health of operators. In contrast, the hot blast stove chimney 25 is typically higher than surrounding structures, and the gas emitted through the hot blast stove chimney 25 will not pose a hazard to the safety and health of operators. This significantly reduces the investment in the hot blast stove while also reducing the risk of shutdown gas hazard to the safety and health of operators. Furthermore, the ejector 4 in the hot blast stove backflow shutdown system 100 of this embodiment of the invention has a strong suction force when working, which can be used to adjust the pressure inside the blast furnace 23 and adjust the internal pressure of the blast furnace 23 to a slightly negative pressure. This can further prevent the gas from the blast furnace 23 from diffusing from the tuyeres 29 and other parts, which could cause harm to the safety and health of the operators and maintenance personnel.
[0026] In such Figure 1In the preferred embodiment shown, the hot blast stove backflow shutdown system 100 further includes a purge gas source pipe 14, which connects to the area on the exhaust pipe 1 located between the ejector 4 and the flue gas pipe 19. With this configuration, during shutdown, when the gas content in the flue gas pipe 19 exceeds a set value, such as excessive CO and O2 content, the purge gas in the purge gas source pipe 14 can purge the flue gas pipe 19 to reduce the CO and O2 content, thereby preventing gas explosions.
[0027] According to the present invention, in such Figure 1 In the preferred embodiment shown, the exhaust pipe 1 may be equipped with a first shut-off valve 2 and a first blind flange valve 3 located at the front end of the ejector 4, and a second shut-off valve 5 and a second blind flange valve 6 located at the rear end of the ejector 4. The purge gas source pipe 14 connects to the area on the exhaust pipe 1 located between the second blind flange valve 6 and the flue gas pipe 19. In this embodiment, the first shut-off valve 2 and the first blind flange valve 3 at the front end of the ejector 4 are used to cut off the high-temperature hot air during normal production of the blast furnace 23, and the second shut-off valve 5 and the second blind flange valve 6 at the rear end of the ejector 4 are used to cut off the high-temperature flue gas during normal production of the blast furnace 23. The coordinated use of the first shut-off valve 2 and the first blind flange valve 3, as well as the second shut-off valve 5 and the second blind flange valve 6, can prevent mutual leakage between the various medium pipes, thereby achieving effective cut-off of the gas and preventing gas leakage and safety accidents.
[0028] Preferably, the first shut-off valve 2 can be a high-temperature resistant valve, preferably a water-cooled gate valve, which can shut off the hot air and can be used under high-temperature gas conditions. The first blind valve 3 has zero leakage, which can prevent gas that may leak from the shut-off valve 2 from entering the flue gas duct 19.
[0029] According to the present invention, in such Figure 1 In the preferred embodiment shown, the ejector gas source pipeline 20 may be equipped with an ejector gas shut-off valve 8 and an ejector gas flow regulating valve 9. The ejector gas shut-off valve 8 is used to shut off the high-pressure ejector gas when the ejector 4 or other valves are under maintenance. The ejector gas flow regulating valve 9 can regulate the flow rate of the high-pressure ejector gas. The flow rate of the high-pressure ejector gas can be determined according to the amount of shut-off gas produced by the blast furnace. The opening degree of the ejector gas flow regulating valve 9 can be adjusted according to the shut-off time, or according to the amount of gas in the furnace, to save the amount of high-pressure ejector gas.
[0030] Preferably, such as Figure 1 As shown, located Figure 1 The jet gas shut-off valve 8 on the left side shown can preferably be a manual shut-off valve, which can be used to shut off the ejector gas when other valves are under maintenance. The jet gas shut-off valve 8 on the right side can preferably be an electric shut-off valve, which can be used to open the valve to operate the system when the system is shut down.
[0031] More preferably, such as Figure 1 As shown, a check valve 11 can also be installed on the ejector gas source pipeline 20 to prevent other gases, such as cold air or hot air, from flowing back into the ejector gas source pipeline.
[0032] Furthermore, the ejector gas source pipeline 20 may also be equipped with an ejector gas flow meter 10 and a gas pressure gauge 13. The ejector gas flow meter 10 is used to record the amount of ejector gas used and can be used for feedback from the flow regulating valve. The gas pressure gauge 13 is used to record the pressure of the ejector gas.
[0033] According to the present invention, in such Figure 1 In the preferred embodiment shown, a purge gas shut-off valve 15 and a purge gas flow regulating valve 18 may be installed on the purge gas source pipeline 14. The purge gas shut-off valve 15 is used to shut off the purge gas when other valves are under maintenance, and the purge gas flow regulating valve 18 can regulate the flow rate of the purge gas. The flow rate of the purge gas can be determined according to the CO and O2 content in the flue gas pipeline 19 to avoid gas explosion.
[0034] Preferably, such as Figure 1 As shown, located Figure 1 The purge gas shut-off valve 15 on the left side is preferably an electrically operated shut-off valve, which is used to open the valve to operate the system during purging. The purge gas shut-off valve 15 on the right side is preferably a manually operated shut-off valve, which can be used to cut off the purge gas when other valves are under maintenance.
[0035] More preferably, such as Figure 1 As shown, a check valve 11 can also be installed on the purge gas source pipeline 14 to prevent other gases such as cold air, hot air, and coal gas from flowing back into the purge gas source pipeline.
[0036] Furthermore, a purge gas flow meter 17 and a gas pressure gauge 13 may also be installed on the purge gas source pipeline 14. The purge gas flow meter 17 is used to record the amount of purge gas used and can be used for feedback from the flow regulating valve. The gas pressure gauge 13 is used to record the pressure of the purge gas.
[0037] According to the present invention, in such Figure 1 In the preferred embodiment shown, a CO analyzer 21 and an O2 analyzer 22 may also be installed on the flue gas duct 19. The CO analyzer 21 and the O2 analyzer 22 are used to detect the CO and O2 content in the gas when the ventilation is stopped. When the gas exceeds the standard, the flue gas duct 19 is kept in a safe state by opening the purge gas shut-off valve 15 and the purge gas flow regulating valve 18.
[0038] Furthermore, the inner wall of the exhaust pipe 1 may be lined with a refractory material, preferably formed by bricklaying or spraying. This feature is designed to prevent high-temperature gas from damaging the pipe and causing gas leakage, thus ensuring the safety of operators.
[0039] According to the present invention, the ejector gas in the ejector gas source pipe 20 can be high-pressure nitrogen or other inert gas; the purge gas in the purge gas source pipe 14 can be low-pressure nitrogen or other inert gas or water vapor.
[0040] In the hot blast stove backflow shutdown system of this embodiment of the invention, when the blast furnace is shut down, the first shut-off valve 2 and the first blind flange valve 3 at the front end of the ejector 4, and the second shut-off valve 5 and the second blind flange valve 6 at the rear end of the ejector 4 are first opened. Then, the injection gas shut-off valve 8 and the injection gas flow regulating valve 9 are opened, allowing high-pressure injection gas to enter the ejector 4 through the ejector gas source pipe 20. Under the injection action of the high-pressure injection gas, the residual gas in the hot blast pipe 16 is continuously drawn into the ejector 4, thereby carrying the shutdown gas into the flue gas pipe 19, and finally discharged from the hot blast stove chimney 25, achieving the effect of safely discharging the residual gas in the blast furnace. When the CO and O2 gas content in the flue gas duct 19 exceeds the set value, the CO analyzer 21 and O2 analyzer 22 will issue an alarm. At this time, the purge gas shut-off valve 15 and the purge gas flow regulating valve 18 can be opened to purge gas into the flue gas duct 19. The opening degree of the purge gas flow regulating valve 18 can be adjusted according to the values of the CO analyzer 21 and O2 analyzer 22, thereby adjusting the flow rate of the purge gas, so as to achieve a more economical reduction of CO and O2 content and prevent gas explosion.
[0041] Furthermore, the hot blast stove backflow shutdown process according to an embodiment of the present invention may include: conveying the gas in the hot air duct 16 and the mixing air duct 12 of the hot blast stove 24 to the flue gas duct 19 of the hot blast stove 24 through an ejector 4 that provides high-pressure injection gas.
[0042] When shutting down a blast furnace using the hot blast stove reverse-flow shutdown process of this embodiment of the invention, high-pressure injection gas is provided to the ejector 4. Under the action of the high-pressure injection gas, the residual gas in the hot blast duct 16 and the mixing channel 12 is continuously drawn into the ejector 4, thereby carrying the shutdown gas into the flue gas duct 19 of the hot blast stove 24, and finally discharged through the hot blast stove chimney 25, achieving the effect of safely discharging the residual gas in the blast furnace 23. The hot blast stove reverse-flow shutdown process of this embodiment of the invention eliminates the reverse-flow shutdown valve 28, reverse-flow shutdown duct 26, and reverse-flow shutdown chimney 27 used in the existing process, while shortening the length of the hot blast stove frame and saving investment in the hot blast stove system. For renovation or expansion projects, eliminating the reverse-flow shutdown valve 28, reverse-flow shutdown duct 26, and reverse-flow shutdown chimney 27 allows the saved one-span hot blast stove frame to be used to build a new hot blast stove nearby, reducing the increased investment costs for various pipelines, cables, etc., caused by building a hot blast stove over a long distance, and avoiding unreasonable system layout. Furthermore, since the existing backflow shutdown chimney 27 is relatively low compared to the surrounding buildings, the emitted gas poses a hazard to the safety and health of operators. In contrast, the hot blast stove chimney 25 is typically higher than the surrounding structures, and the gas emitted through it does not pose a hazard to the safety and health of operators. This significantly reduces the investment in the hot blast stove while also reducing the risk of shutdown gas hazard to operators' safety and health. In addition, the ejector 4 in the hot blast stove backflow shutdown process of this embodiment of the invention has a strong suction force during operation, which can be used to regulate the pressure inside the blast furnace 23, adjusting the internal pressure of the blast furnace 23 to a slightly negative pressure. This further prevents the gas from the blast furnace 23 from diffusing through the tuyeres 29 and other openings, thus preventing hazards to the safety and health of operators and maintenance personnel.
[0043] Preferably, the pressure of the gas ejected by the ejector 4 can be greater than or equal to 0.2 MPa.
[0044] Furthermore, the hot blast stove backflow shutdown process may also include: monitoring the CO and O2 content in the flue gas duct 19, and when the CO and O2 content exceeds the preset safety value, blowing purge gas into the flue gas duct 19 to reduce the CO and O2 content, thereby preventing gas explosion.
[0045] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, and not to limit them. Although the present invention has been described in detail with reference to the foregoing embodiments, those skilled in the art should understand that modifications can still be made to the technical solutions described in the foregoing embodiments, or equivalent substitutions can be made to some or all of the technical features therein. These modifications or substitutions do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present invention, and they should all be covered within the scope of the claims and specification of the present invention. In particular, as long as there is no structural conflict, the various technical features mentioned in the embodiments can be combined in any way. The present invention is not limited to the specific embodiments disclosed herein, but includes all technical solutions falling within the scope of the claims.
Claims
1. A hot blast stove backflow shutdown system, characterized in that, include: An exhaust pipe, one end of which is connected to the connection point between the hot air pipe and the mixing air pipe of the hot blast stove, and the other end of which is connected to the flue gas pipe of the hot blast stove. An ejector, wherein the ejector is disposed on the exhaust pipe, and An ejector gas source pipeline, which is connected to the ejector. During blast furnace shutdown, the ejector gas source pipeline provides injection gas to the ejector, so that the ejector can transport the gas in the hot blast pipeline to the flue gas pipeline via the exhaust pipeline.
2. The hot blast stove backflow shutdown system according to claim 1, characterized in that, The hot blast stove backflow shutdown system also includes a purge gas source pipe, which is connected to the area on the exhaust pipe located between the ejector and the flue gas pipe.
3. The hot blast stove backflow shutdown system according to claim 2, characterized in that, The exhaust pipe is provided with a first shut-off valve and a first blind flange valve located at the front end of the ejector, and a second shut-off valve and a second blind flange valve located at the rear end of the ejector. The purge gas source pipe is connected to the area on the exhaust pipe between the second blind flange valve and the flue gas pipe.
4. The hot blast stove backflow shutdown system according to claim 3, characterized in that, The ejector gas source pipeline is equipped with an ejector gas shut-off valve and an ejector gas flow regulating valve.
5. The hot blast stove backflow shutdown system according to claim 2, characterized in that, The purging gas source pipeline is equipped with a purging gas shut-off valve and a purging gas flow regulating valve.
6. The hot blast stove backflow shutdown system according to claim 5, characterized in that, The flue gas duct is equipped with a CO analyzer and an O2 analyzer.
7. The hot blast stove backflow shutdown system according to any one of claims 1 to 6, characterized in that, The inner wall of the exhaust pipe is lined, which is formed by bricklaying or spraying.
8. The hot blast stove backflow shutdown system according to any one of claims 2 to 6, characterized in that, The ejector gas in the ejector gas source pipeline is nitrogen or other inert gas; the purge gas in the purge gas source pipeline is nitrogen or other inert gas or water vapor.
9. A hot blast stove reverse flow shutdown process, characterized in that, include: The gas in the hot air duct of the hot air furnace is delivered to the flue gas duct of the hot air furnace through an ejector that provides high-pressure jet gas.
10. The hot blast stove reverse flow shutdown process according to claim 9, characterized in that, Also includes: The CO and O2 content in the flue gas duct is monitored. When the CO and O2 content exceeds the preset safety value, purge gas is blown into the flue gas duct to reduce the CO and O2 content.