Composite curtain wall of metal plate and tempered glass for same building and construction method

CN118273470BActive Publication Date: 2026-10-23CHINA CONSTR SECOND BUREAU DECORATION ENG CO
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202410202623.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-02-23
Publication Date
2026-10-23
Estimated Expiration
2044-02-23

AI Technical Summary

Technical Problem

[0005]本发明旨在解决上述问题,从而提供一种应用同一建筑的金属板及钢化玻璃复合式幕墙及施工方法,通过衔接部将金属板幕墙和钢化玻璃幕墙连接为整体,进而使GTC主楼外观协调、美观,更加简洁,同时衔接部的设置降低了金属板幕墙和钢化玻璃幕墙衔接的难度,满足了设计施工要求,也实现了钢化玻璃幕墙倾斜设置,也解决了钢化玻璃幕墙受自重及倾斜设置的双重影响使得钢化玻璃幕墙整体的稳定性较差,抗风能力差的缺陷,同时,也降低了倾斜钢化玻璃幕墙的施工难度,保证了施工质量

Benefits of technology

[0016]采用上述技术方案的本发明,与现有技术相比,其突出的特点是:

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118273470B_ABST
    Figure CN118273470B_ABST
Patent Text Reader

Abstract

The application discloses a composite curtain wall of metal plate and tempered glass applied to the same building and a construction method. The composite curtain wall of metal plate and tempered glass is arranged on a main body structure of a GTC main building, and comprises a metal plate curtain wall and a tempered glass curtain wall. The main body structure comprises a foundation raft and a floor slab. The floor slab separates a first floor and a second floor of the main body structure. A wall body is arranged between the foundation raft and the floor slab. A roof truss structure is arranged on the floor slab. The metal plate curtain wall is arranged on an outer side of the wall body. The tempered glass curtain wall is arranged between the floor slab and the roof truss structure. The tempered glass curtain wall is arranged in a downward and outward inclined mode from bottom to top. A connecting part is arranged between the metal plate curtain wall and the tempered glass curtain wall. The metal plate curtain wall and the tempered glass curtain wall are connected as a whole through the connecting part, the connecting difficulty is reduced, and the design and construction requirements are met. On the basis of realizing the inclined arrangement of the tempered glass curtain wall, the defects of poor stability and poor wind resistance of the tempered glass curtain wall are solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of glass curtain walls, and more particularly to a composite curtain wall using metal panels and tempered glass in the same building and a construction method thereof. Background Technology

[0002] In one of the airport GTC transportation hub projects undertaken by our company, the GTC main building has two floors including the roof. The first floor has a metal panel curtain wall, while the second floor has a tempered glass curtain wall. The curtain wall height is 27.38 meters, the roof eaves perimeter is 340.5 meters, and the curtain wall perimeter is 277 meters.

[0003] To highlight the design concept and make the overall shape of the GTC main building more aesthetically pleasing, the metal panel curtain wall is installed on the main structure of the first floor of the GTC main building, while the tempered glass curtain wall is installed on the main structure of the second floor of the GTC main building, tilting from the inside of the main building to the outside from the bottom up. This design makes it difficult to connect the metal panel curtain wall and the tempered glass curtain wall. Improper handling of the connection will result in an uncoordinated appearance of the GTC main building, which not only makes it difficult to meet the design and construction requirements, but also makes the construction of the tempered glass curtain wall more difficult due to the outward tilt design, making it difficult to guarantee the construction quality. At the same time, the tempered glass curtain wall is affected by its own weight and the tilt design, resulting in poor overall stability and poor wind resistance, and has many defects.

[0004] Therefore, there is an urgent need for a composite curtain wall system using metal panels and tempered glass in the same building, as well as a construction method, to solve the aforementioned technical problems. Summary of the Invention

[0005] This invention aims to solve the above-mentioned problems, thereby providing a composite curtain wall of metal panels and tempered glass used in the same building and its construction method. The metal panel curtain wall and the tempered glass curtain wall are connected into a whole through the joint, thereby making the appearance of the GTC main building more harmonious, beautiful and simple. At the same time, the setting of the joint reduces the difficulty of connecting the metal panel curtain wall and the tempered glass curtain wall, meets the design and construction requirements, and also realizes the tilting setting of the tempered glass curtain wall. It also solves the defects of poor overall stability and poor wind resistance of the tempered glass curtain wall due to the dual effects of its own weight and tilting setting. In addition, it reduces the construction difficulty of the tilted tempered glass curtain wall and ensures the construction quality.

[0006] The technical solution adopted by the present invention to solve the aforementioned problem is as follows: A composite curtain wall of metal panels and tempered glass is used in the same building. The composite curtain wall is installed on the main structure of the GTC main building. The composite curtain wall includes a metal panel curtain wall and a tempered glass curtain wall. The main structure includes a foundation raft slab and floor slabs. The floor slabs are located above the foundation raft slab and separate the first and second floors of the main structure. A wall is provided between the foundation raft slab and the floor slabs. A roof truss structure is provided on the floor slabs. The metal panel curtain wall is installed on the outer side of the wall, and the tempered glass curtain wall is installed between the floor slabs and the roof truss structure. The tempered glass curtain wall is inclined from bottom to top and from the inside to the outside. A [missing information - likely a design element] is provided between the metal panel curtain wall and the tempered glass curtain wall. The tempered glass curtain wall includes several wind-resistant columns arranged sequentially along the outline of the floor slab, with adjacent columns spaced apart. The lower ends of the wind-resistant columns are inclinedly fixed to the edge of the upper surface of the floor slab, and the upper ends are connected to the roof truss structure. A cantilever section is formed on the outer side of the upper ends of the wind-resistant columns, enclosing the outline of the floor slab. The cantilever section is connected to the roof truss structure. Sunshade steel trusses are fixed at intervals along the height direction on the outer side of adjacent wind-resistant columns. Sunshade steel trusses at the same height are arranged enclosing the outline of the floor slab, positioned between the cantilever section and the floor slab. A support is fixed between the floor slab and the cantilever section. The steel cables passing through the sunshade steel truss are connected to the truss and are spaced apart along its length. The truss is covered with decorative panels. An aluminum crossbeam is fixed to the inner side of each truss, positioned between adjacent wind-resistant columns. Tempered glass is installed between adjacent upper and lower aluminum crossbeams. An upper edge joint is provided between the tempered glass and the cantilever section, and a lower edge joint is provided between the tempered glass and the floor slab, connecting to a connecting section. The connecting section is located on the floor slab and includes a connecting steel frame fixed to the outer edge of the floor slab. A honeycomb panel is installed on the outer surface of the connecting steel frame, connecting to the lower edge of the floor slab. The edge joints are connected; the metal panel curtain wall includes a wall frame located on the outer side of the wall. The upper part of the wall frame is connected to the connecting steel frame, and the lower part of the wall frame is fixed to the foundation raft. Several aluminum alloy adapters are fixedly connected to the wall frame. The several aluminum alloy adapters are spaced apart along the length of the wall frame. Each aluminum alloy adapter is vertically continuous along the height of the wall frame. Several aluminum alloy grilles are installed on the several aluminum alloy adapters. The several aluminum alloy grilles are spaced apart along the height of the wall frame. The several aluminum alloy adapters and several aluminum alloy grilles together form a grid structure, and an aluminum alloy rodent-proof mesh is installed in each grid block.

[0007] Furthermore, a first embedded part is pre-embedded in the floor slab. Three first steel ear plates are vertically fixed on the upper surface of the first embedded part. Two adjacent first steel ear plates are spaced apart from each other, and the three first steel ear plates together form two slots. A second steel ear plate perpendicular to the first embedded part is inserted into each of the two slots. A through hole is provided on the three first steel ear plates and the two second steel ear plates. A set of fastening bolts is installed in the through hole. The upper side of the two second steel ear plates is inclined from the inner side close to the main structure to the outer side away from the main structure. The wind-resistant column has a rectangular cross section. A connecting plate is fixed on the lower end face of the wind-resistant column. The two second steel ear plates are fixedly connected to the connecting plate. The wind-resistant column is inclined according to the slope of the upper side of the two second steel ear plates. Several reinforcing plates are fixed on the outer side of the left first steel ear plate and the right first steel ear plate. The several reinforcing plates are spaced apart along the length direction of the first steel ear plate. The several reinforcing plates are fixed on the upper surface of the first embedded part.

[0008] Furthermore, a reinforcing steel beam is fixedly connected between the upper parts of two adjacent wind-resistant columns, a first base is fixed on the inner side of the reinforcing steel beam, a steel tie rod is connected to the first base, a second base is fixed on the bottom surface of the roof truss structure, and the other end of the steel tie rod is connected to the second base.

[0009] Furthermore, the cantilever section includes a cantilever steel frame fixed to a reinforcing steel beam. A honeycomb panel is installed on the bottom surface of the cantilever steel frame. The upper surface of the cantilever steel frame gradually slopes from the side closest to the tempered glass to the side furthest from the tempered glass. A sealing steel frame is installed between the cantilever steel frame and the roof truss structure. An aluminum plate is installed on the sealing steel frame, the upper surface of the cantilever steel frame, and the outer surface furthest from the tempered glass. An insulation board is installed between the cantilever steel frame and the reinforcing steel beam, and between the sealing steel frame and the roof truss structure. An upper edge finishing node is located between the cantilever steel frame and the insulation board. The upper edge finishing node includes a positioning steel frame fixed to the cantilever steel frame and located between the cantilever steel frame and the insulation board. An edge finishing piece is connected to the bottom surface of the positioning steel frame. The tempered glass connected to the cantilever section is installed on the edge finishing piece. An edge sealing plate fixed between the edge finishing piece and the reinforcing steel beam is installed at the bottom of the insulation board.

[0010] Furthermore, an upper anchor plate is fixed to the cantilevered steel frame, one end of the steel cable is connected to the upper anchor plate, a second embedded part is pre-embedded in the floor slab, a lower anchor plate is fixed on the upper surface of the second embedded part, and the other end of the steel cable passes through the sunshade steel truss from top to bottom and is connected to the lower anchor plate.

[0011] Furthermore, several connecting columns are vertically fixed to the outer surface of each wind-resistant column, with these connecting columns spaced apart along the height direction. The sunshade steel truss is fixed between two connecting columns at the same height between two adjacent wind-resistant columns. Two inserts are vertically fixed to the side of one of the connecting columns, and one end of the sunshade steel truss is inserted into these two inserts, both of which are bolted to the sunshade steel truss. The other end of the sunshade steel truss is fixed to the side of another connecting column. The sunshade steel truss includes an upper chord and a lower chord, which are connected to each other. The structure is designed with several inclined web members arranged sequentially from left to right between the upper and lower chords. These inclined web members form a continuous zigzag shape. A vertical web member is installed between the beginning and end of two adjacent inclined web members, and the vertical web member is fixed vertically between the upper and lower chords. A steel cable is installed on each vertical web member located in the middle of the sunshade steel truss. A through-hole is provided in the middle of each vertical web member, and a cable clamp is installed in each through-hole. The steel cable passes through the through-hole and connects to the cable clamp.

[0012] Furthermore, the decorative panel includes a first decorative aluminum panel, a second decorative aluminum panel, and a honeycomb panel. The first decorative aluminum panel is installed on the upper surface of the sunshade steel truss, the honeycomb panel is installed on the lower surface of the sunshade steel truss, and the second decorative aluminum panel has a U-shaped cross section and is fixed on the outer side of the sunshade steel truss away from the tempered glass. The first decorative aluminum panel, the second decorative aluminum panel, and the honeycomb panel together cover the sunshade steel truss.

[0013] Furthermore, the aluminum beam is fixed to the inner sides of two adjacent wind-resistant columns facing each other, and a connecting assembly is provided between the aluminum beam and the tempered glass. The connecting assembly includes an inclined positioning member, a connecting part is provided on the left side of the positioning member, the connecting part and the aluminum beam are connected by bolts, a limiting part is provided in the middle of the right side of the positioning member, and tempered glass is provided above and below the limiting part. One side of each of the two tempered glass pieces abuts against the right side of the positioning member, and a fastening member abuts against the other side of the two tempered glass pieces. The fastening member and the limiting part are connected, and the fastening member and the positioning member together clamp the two tempered glass pieces. A decorative buckle is fastened and installed on the other side of the fastening member.

[0014] Furthermore, the lower edge node includes a supporting steel pipe, which is fixed to the floor slab and connected to the connecting steel frame. A clamping assembly is connected to the supporting steel pipe, including a first clamping member. An inclined protrusion is provided on the lower left side of the first clamping member. Tempered glass abuts against the inclined protrusion, and one side of the tempered glass abuts against the left side of the first clamping member. A second clamping member abuts against the other side of the tempered glass. The second clamping member is connected to the first clamping member, and the first and second clamping members together clamp the tempered glass. The second clamping member is connected to the honeycomb panel located on the upper surface of the connecting steel frame. A flashing plate is connected to the right side of the first clamping member and is fixed to the floor slab.

[0015] A construction method for a composite curtain wall using metal panels and tempered glass in the same building includes the following steps: A. Model according to the construction drawings, install the wall grid on the outer side of the wall according to the model, and install the connecting steel frame on the floor slab; B. Model according to the construction drawings, and mark the positioning points of each wind-resistant column on the floor slab based on the model and with the help of a total station; C. Install each wind-resistant column in sequence according to the construction drawings and the model. The wind-resistant columns are installed between the floor slab and the roof truss structure. Reinforcing steel beams are installed on the upper part between two adjacent wind-resistant columns. Steel tie rods connected to the roof truss structure are installed on the reinforcing steel beams. D. Install steel trusses layer by layer from bottom to top on the wind-resistant columns according to the construction drawings and the modeling model; E. Based on the construction drawings and the modeling model, install the cantilevered steel frame connected to the reinforcing steel beam on the outer side of the wind-resistant column; F. Based on the construction drawings and the modeling model, install each steel cable passing through the sunshade steel truss of each floor between the cantilevered steel frame and the floor slab. G. Install aluminum crossbeams one by one between adjacent wind-resistant columns according to the construction drawings and the modeling model; H. Install the tempered glass one by one according to the construction drawings and the modeling model. The tempered glass located at the upper edge node and the lower edge node will be installed later. I. Based on the construction drawings and the modeling model, install insulation boards between the cantilevered steel frame and the reinforcing steel beam and on the outer side of the roof truss structure, and install sealing steel frames between the roof truss structure and the cantilevered steel frame, and then install the tempered glass at the edge finishing nodes. J. Install aluminum plates on the sealing steel frame, aluminum plates and honeycomb panels on the cantilever steel frame, and decorative panels on the sunshade steel truss, based on the construction drawings and modeling. K. Install the tempered glass at the lower edge joint on the floor slab according to the construction drawings and the modeling model; L. Install the honeycomb panels on the connecting steel frame according to the construction drawings and the modeling model, and connect the honeycomb panels to the lower edge node. M. According to the construction drawings and the model, install aluminum alloy adapters on the wall frame, install aluminum alloy grilles on the aluminum alloy adapters, and install aluminum alloy rodent-proof mesh.

[0016] The present invention, which adopts the above technical solution, has the following prominent features compared with the prior art: This invention installs a metal panel curtain wall on the outer side of the first-floor wall of the main structure, and a tempered glass curtain wall between the floor slabs and the roof truss structure of the main structure. A connecting part is installed on the floor slab to connect the metal panel curtain wall and the tempered glass curtain wall into a whole, thus making the GTC main building's appearance more harmonious, beautiful, and simpler. At the same time, the connection part reduces the difficulty of connecting the metal panel curtain wall and the tempered glass curtain wall, meeting design and construction requirements. Several wind-resistant columns are installed obliquely along the contour of the floor slab between the floor slab and the roof truss structure to achieve initial fixation of the wind-resistant columns. A cantilevered section connected to the roof truss structure is installed on the outer side of these wind-resistant columns, and a sunshade steel truss is installed between adjacent wind-resistant columns. The sunshade steel trusses at the same height are enclosed together, thus providing a unified appearance for the GTC main building. Several layers of sunshade steel trusses are installed from bottom to top on the wind-resistant columns. The wind-resistant columns are connected into a whole through the cantilevered sections and the sunshade steel trusses to strengthen the wind-resistant columns. Several steel cables are installed sequentially along the outline of the floor slab between the cantilevered sections and the floor slab, and each steel cable passes through each layer of sunshade steel trusses from top to bottom. The connection between the steel cables and the sunshade steel trusses strengthens the stability of the sunshade steel trusses. The wind-resistant columns, cantilevered sections, and sunshade steel trusses together form the overall load-bearing structure of the tempered glass curtain wall. While achieving the tilted setting of the tempered glass curtain wall, it also solves the defects of poor overall stability and poor wind resistance of the tempered glass curtain wall caused by the dual effects of its own weight and tilted setting. At the same time, it also reduces the construction difficulty of the tilted tempered glass curtain wall and ensures the construction quality. Attached Figure Description

[0017] Figure 1 This is a schematic diagram of the main view structure of the present invention; Figure 2 This is a schematic diagram of the connection structure between the wind-resistant column and the first embedded part of the present invention; Figure 3 This is a schematic diagram of the cantilever section of the present invention; Figure 4 This is a schematic diagram of the structure of the edge-receiving node of the present invention; Figure 5 This is a schematic diagram of the externally projecting steel frame of the present invention; Figure 6 This is a schematic diagram of the structure of the lower edge node of the present invention; Figure 7 This is a schematic diagram of the installation structure of the sunshade steel truss of the present invention; Figure 8 This is a schematic diagram of the main view structure of the sunshade steel truss of the present invention; Figure 9 This is a schematic diagram of the metal panel curtain wall structure of the present invention; In the diagram: 1. Floor slab; 2. Roof truss structure; 3. Wind-resistant column; 4. Cantilever section; 5. Sunshade steel truss; 6. Steel cable; 7. Decorative panel; 8. Aluminum beam; 9. Tempered glass; 10. Upper edge finishing node; 11. Lower edge finishing node; 12. First embedded part; 13. First steel ear plate; 14. Second steel ear plate; 15. Fastening bolt assembly; 16. Connecting plate; 17. Ribbed plate; 18. Reinforcing steel beam; 19. First base; 20. Steel tie rod; 21. Second base; 22. Cantilever steel frame; 23. Honeycomb panel; 24. Sealing steel frame; 25. Aluminum plate; 26. Insulation board; 27. Positioning steel frame; 28. Edge finishing piece; 29. ​​Edge sealing plate; 30. 31. Upper anchor plate; 32. Second embedded part; 33. Lower anchor plate; 34. Connecting column; 35. Insert core; 36. Upper chord; 37. Lower chord; 38. Inclined web member; 39. Vertical web member; 40. Cable clamp; 41. First decorative aluminum plate; 42. Second decorative aluminum plate; 43. Positioning part; 44. Fastening part; 45. Decorative buckle plate; 46. Connecting steel frame; 47. First clamping part; 48. Second clamping part; 49. Flashing; 50. Wall frame; 51. Aluminum alloy adapter; 52. Aluminum alloy grille; 53. Aluminum alloy rodent-proof mesh; 54. Connecting part; 55. Metal panel curtain wall; 56. Tempered glass curtain wall; 57. Foundation raft slab; 58. Wall. Detailed Implementation

[0018] The following description of the embodiments will help the public to better understand the present invention. However, the specific embodiments provided by the applicant should not and should not be regarded as a limitation on the technical solution of the present invention. Any changes to the definition of components or technical features and / or formal but not substantive changes to the overall structure should be regarded as the scope of protection defined by the technical solution of the present invention.

[0019] See Figures 1 to 9 As shown, the technical solution of the present invention is as follows: A composite curtain wall of metal panels and tempered glass is used in the same building. The composite curtain wall is installed on the main structure of the GTC main building. It includes a metal panel curtain wall 54 and a tempered glass curtain wall 55. The main structure includes a foundation raft slab 56 and floor slabs 1. The floor slabs 1 are located above the foundation raft slab 56 and separate the first and second floors of the main structure. A wall 57 is provided between the foundation raft slab 56 and the floor slabs 1. A roof truss structure 2 is provided on the floor slabs 1. The metal panel curtain wall 54 is located on the outer side of the wall 57, and the tempered glass curtain wall 55 is located between the floor slabs 1 and the roof truss structure 2. The tempered glass curtain wall 55 extends from bottom to top and from the inside out. The structure is inclined outwards, with a connecting part 53 between the metal panel curtain wall 54 and the tempered glass curtain wall 55. The tempered glass curtain wall 55 includes several wind-resistant columns 3, the number of which is determined according to the construction drawings. Each wind-resistant column 3 is a 750x300x30x25 rectangular steel bar. The wind-resistant columns 3 are arranged sequentially along the outline of the floor slab 1, with adjacent wind-resistant columns 3 spaced apart. The lower end of the wind-resistant column 3 is inclined and fixed to the edge of the upper surface of the floor slab 1, and the upper end of the wind-resistant column 3 is connected to the roof truss structure 2, thereby achieving the initial fixation of the wind-resistant column 3. A cantilever part 4 is provided on the outer side of the upper end of the several wind-resistant columns 3 along the outline of the floor slab 1, which together encloses the cantilever part 4. The roof truss structure 2 is connected, and the cantilever section 4 strengthens the stability of the upper part of the enclosed wind-resistant columns 3. Sunshade steel trusses 5 are fixed at intervals along the height direction on the outer surfaces of adjacent wind-resistant columns 3. Sunshade steel trusses 5 at the same height are arranged in a single layer along the outline of the floor slab 1. Several layers of enclosed sunshade steel trusses 5 are arranged at intervals from bottom to top between the cantilever section 4 and the floor slab 1. The sunshade steel trusses 5 strengthen the stability of the enclosed wind-resistant columns 3. The wind-resistant columns 3, the cantilever section 4, and the sunshade steel trusses 5 together form the overall load-bearing structure of the tempered glass curtain wall 55. Steel tension rods are fixed between the floor slab 1 and the cantilever section 4, passing sequentially through the sunshade steel trusses 5. Cable 6, steel cable 6 is connected to the sunshade steel truss 5 and the steel cable 6 is spaced apart along the length of the sunshade steel truss. The steel cable 6 strengthens the stability of the sunshade steel truss 5. Decorative panel 7 is covered on the sunshade steel truss 5. The decorative panel 7 plays a protective and decorative role for the steel truss. Aluminum crossbeam 8 is fixed on the inner side of each sunshade steel truss 5. The aluminum crossbeam 8 is set between two adjacent wind-resistant columns 3. Tempered glass 9 is installed between two adjacent aluminum crossbeams 8. An upper edge node 10 is set between the tempered glass 9 and the cantilever 4. A lower edge node 11 is set between the tempered glass 9 and the floor slab 1. The lower edge node 11 is connected to the connecting part 53.The connecting part 53 is installed on the floor slab 1. The connecting part 53 includes a connecting steel frame 45, which is made of square tubes spliced ​​together. The connecting steel frame 45 is fixed to the outer edge of the floor slab 1. A third embedded part is pre-embedded in the floor slab 1, and the connecting steel frame 45 is fixed to the third embedded part. A honeycomb panel 23 is installed on the outer surface of the connecting steel frame 45, and the honeycomb panel 23 is connected to the lower edge node 11. The metal panel curtain wall 54 includes a wall grid 49 located on the outer surface of the wall 57. The wall grid 49 is a grid structure made of square tubes spliced ​​together. The upper part of the wall grid 49 is connected to the connecting steel frame 45, and the lower part of the wall grid 49 is fixed to the foundation raft slab 56, thereby realizing the fixation of the wall grid 49. Several aluminum alloy adapters 50 are fixedly connected to the wall grid 49. The number and spacing of the aluminum alloy adapters 50 are determined according to the construction requirements. Each aluminum alloy adapter 50 is connected to the wall grid 49 by screws. Several aluminum alloy adapters 50 are spaced apart along the length of the wall grid 49, and each aluminum alloy adapter 50 is vertically continuous along the height of the wall grid 49. Several aluminum alloy grilles 51 are installed on the several aluminum alloy adapters 50. The number and spacing of the aluminum alloy grilles 51 are determined according to construction requirements. Each aluminum alloy grille 51 is connected to the aluminum alloy adapter 50 by screws. The several aluminum alloy grilles 51 are spaced apart along the height of the wall grid 49. The several aluminum alloy adapters 50 and the several aluminum alloy grilles 51 together form a mesh structure, and an aluminum alloy rodent-proof mesh 52 is installed in each mesh block. The aluminum alloy rodent-proof mesh 52 is connected to the aluminum alloy adapter 50 and the aluminum alloy grille 51 by screws.

[0020] A first embedded part 12 is pre-embedded in the floor slab 1. The first embedded part 12 consists of an embedded steel plate and four anchor bolts. The first embedded part 12 and the floor slab 1 are cast together. Three first steel ear plates 13 are vertically welded to the upper surface of the first embedded part 12. The three first steel ear plates 13 are all 600*290*30mm steel plates. Two adjacent first steel ear plates 13 are spaced apart from each other, and the three first steel ear plates 13 together form two slots. A second steel ear plate 14 perpendicular to the first embedded part 12 is inserted into each of the two slots. A through hole is provided on the three first steel ear plates 13 and the two second steel ear plates 14. A fastening bolt group 15 is installed in the through hole. The three first steel ear plates 13 and the two second steel ear plates 14 are fastened together by the fastening bolt group 15. The upper side of the two second steel ear plates 14 extends from the inner side near the main structure to the outer side. Inclined to the outside of the main structure, the wind-resistant column 3 has a rectangular cross-section. A connecting plate 16 is welded to the lower end face of the wind-resistant column 3. Two second steel ear plates 14 are fixedly connected to the connecting plate 16. The wind-resistant column 3 is inclined according to the slope of the upper side of the two second steel ear plates 14, thereby achieving the inclined fixation of the wind-resistant column 3. Four reinforcing plates 17 are welded to the outer side of the left first steel ear plate 13 and the right first steel ear plate 13. The four reinforcing plates 17 are spaced apart along the length direction of the first steel ear plate 13. The four reinforcing plates 17 are welded to the upper surface of the first embedded part 12, and the two first steel ear plates 13 are reinforced by the reinforcing plates 17. The wind-resistant column 3 is fixed on the floor slab 1 through the above structural settings, ensuring the firmness of the connection structure between the wind-resistant column 3 and the floor slab 1. At the same time, the wind-resistant column 3 is installed on the two second steel ear plates 14 to achieve the inclined setting of the wind-resistant column 3.

[0021] A reinforcing steel beam 18 is welded between the upper parts of two adjacent wind-resistant columns 3. The reinforcing steel beam 18 connects the upper parts of several wind-resistant columns 3 into a whole, improving the load-bearing capacity and stability of the upper parts of several wind-resistant columns 3. A first base 19 is welded on the inner side of the reinforcing steel beam 18, and a steel tie rod 20 is connected to the first base 19. A second base 21 is welded on the bottom surface of the roof truss structure 2, and the other end of the steel tie rod 20 is connected to the second base 21. The reinforcing steel beam 18 is connected to the roof truss structure 2 through the steel tie rod 20. The reinforcing steel beam 18 and the wind-resistant columns 3 are connected by the steel tie rod 20, which improves the load-bearing capacity and stability of the wind-resistant columns 3 and prevents the roots of the wind-resistant columns 3 from breaking due to stress.

[0022] The cantilever section 4 includes a cantilever steel frame 22, which is made of square tubing and welded to the reinforcing steel beam 18. A honeycomb panel 23 is installed on the bottom surface of the cantilever steel frame 22. The upper surface of the cantilever steel frame 22 is gradually inclined from the side closer to the tempered glass 9 to the side farther away from the tempered glass 9, thereby improving the water drainage capacity of the cantilever section 4 and preventing water accumulation, leakage, and corrosion of the cantilever steel frame 22. A sealing steel frame 2 is welded between the cantilever steel frame 22 and the roof truss structure 2. 4. The sealing steel frame 24 connects the cantilever steel frame 22 and the roof truss structure 2, reinforcing the cantilever steel frame 22 and fixing the insulation board 26. Aluminum plates 25 are installed on the upper surfaces of the sealing steel frame 24 and the cantilever steel frame 22, as well as on the outer surfaces away from the tempered glass 9. The aluminum plates 25 and honeycomb panels 23 provide protection and decoration for the cantilever steel frame 22 and the sealing steel frame 24. Between the cantilever steel frame 22 and the reinforcing steel beam 18, and... An insulation board 26 is installed between the sealing steel frame 24 and the roof truss structure 2, thereby improving the insulation performance of the GTC main building. The upper edge node 10 is set between the cantilever steel frame 22 and the insulation board 26. The upper edge node 10 includes a positioning steel frame 27, which is made of spliced ​​steel pipes. The positioning steel frame 27 is welded to the cantilever steel frame 22 and is located between the cantilever steel frame 22 and the insulation board 26. An edge trim 28 is connected to the bottom surface of the positioning steel frame 27 and is connected to the cantilever section 4. The tempered glass 9 is installed on the edge trim 28 and fixed by the edge trim 28. At the bottom of the insulation board 26, there is an edge sealing plate 29 fixed between the edge trim 28 and the reinforcing steel beam 18. The edge sealing plate 29 plays a protective and decorative role for the insulation board 26. The above-mentioned cantilever part 4 connects several wind-resistant columns 3 to the roof truss, which improves the stability and load-bearing capacity of the upper part of several wind-resistant columns 3. The upper edge trim node 10 fixes the tempered glass 9 connected to the cantilever part 4.

[0023] An upper anchor plate 30 is welded to the cantilever steel frame 22. One end of the steel cable 6 is connected to the upper anchor plate 30. A second embedded part 31 is pre-embedded in the floor slab 1. The second embedded part 31 is composed of an embedded steel plate and four anchor bolts. The second embedded part 31 is cast together with the floor slab 1. A lower anchor plate 32 is welded to the upper surface of the second embedded part 31. The other end of the steel cable 6 passes through the sunshade steel truss 5 from top to bottom and is connected to the lower anchor plate 32. Both the upper anchor plate 30 and the lower anchor plate 32 are made of spliced ​​steel plates. The above structural arrangement achieves a stable connection between the steel cable 6 and the cantilever part 4 and the floor slab 1, and the steel cable 6 strengthens the stability of the sunshade steel truss 5.

[0024] Several connecting columns 33 are vertically welded to the outer surface of each wind-resistant column 3. These connecting columns 33 are spaced apart along the height direction. The number and specifications of the connecting columns 33 are determined according to construction requirements. A sunshade steel truss 5 is fixed between two connecting columns 33 at the same height of two adjacent wind-resistant columns 3. Two inserts 34, both square tubes, are vertically welded to the side of one of the connecting columns 33. One end of the sunshade steel truss 5 is inserted into the two inserts 34, and both inserts 34 are bolted to the sunshade steel truss 5. The other end of the sunshade steel truss 5 is welded to the side of another connecting column 33. Thus, the sunshade steel truss 5 connects several wind-resistant columns 3 into a whole. The arrangement of the sunshade steel truss 5 helps to distribute and transfer the force borne by the wind-resistant columns 3, improving their load-bearing capacity and stability. The sunshade steel truss 5 is composed of spliced ​​round steel tubes and includes an upper chord 35 and a lower chord 36. The upper chord 35 and lower chord 36 are spaced apart from each other. Between the upper chord 35 and lower chord 36, from left to right, are several inclined web members 37 arranged in a continuous zigzag pattern. One end of each inclined web member 37 is welded to the upper chord 35, and the other end is welded to the lower chord 36. A vertical web member 38 is arranged between the beginning and end of two adjacent inclined web members 37, and the vertical web member 38 is welded perpendicularly to the upper chord 36. Between the chord 35 and the lower chord 36; a steel cable 6 is correspondingly installed on each vertical web member 38 located in the middle of the sunshade steel truss 5. A vertically penetrating connecting hole is provided in the middle of each vertical web member 38, and a cable clamp 39 is installed in each connecting hole. The steel cable 6 passes through the connecting hole and connects with the cable clamp 39; thus, the sunshade steel truss 5 is connected to the steel cable 6, and the steel cable 6 improves the stability of the sunshade steel truss 5.

[0025] Decorative panel 7 includes a first decorative aluminum panel 40, a second decorative aluminum panel 41, and a honeycomb panel 23. The first decorative panel 7 is installed on the upper surface of the sunshade steel truss 5, and the honeycomb panel 23 is installed on the lower surface of the sunshade steel truss 5. The second decorative aluminum panel 41 has a U-shaped cross-section and is fixed on the outer side of the sunshade steel truss 5 away from the tempered glass 9. The first decorative aluminum panel 40, the second decorative aluminum panel 41, and the honeycomb panel 23 together cover the sunshade steel truss 5. A supporting corner piece is fixed on the upper surface of the sunshade steel truss 5 near the tempered glass 9, and a connecting corner piece is fixed on the supporting corner piece. A first connecting piece is fixed on the upper surface of the sunshade steel truss 5 away from the tempered glass 9. A second connecting piece is provided between the first connecting piece and the connecting corner piece and fixed on the upper surface of the sunshade steel truss 5. The first decorative aluminum panel 40 is installed on the connecting corner piece, the first connecting piece, and the second connecting piece. The first decorative aluminum panel 40 extends from the side near the tempered glass 9 towards the side away from the tempered glass 9. The tempered glass 9 gradually tilts to the other side; the second decorative aluminum plate 41 has a U-shaped cross section and covers the outer side of the sunshade steel truss 5 away from the tempered glass 9. The second decorative aluminum plate 41 includes an upper horizontal part, a middle vertical part and a lower horizontal part. The upper horizontal part is connected to the first connecting member. A third connecting member is fixed on the lower surface of the sunshade steel truss 5. A first auxiliary corner piece is connected to the lower horizontal part. The first auxiliary corner piece is connected to the third connecting member. A fourth connecting corner piece is fixed on the lower surface of the sunshade steel truss 5 near the tempered glass 9. Second auxiliary corner pieces are provided on the left and right sides of the honeycomb panel 23. The second auxiliary corner piece on the left side is connected to the third connecting member, and the second auxiliary corner piece on the right side is connected to the fourth connecting member. The above-mentioned decorative panel 7 covers the sunshade steel truss 5 together with the first decorative aluminum plate 40, the second decorative aluminum plate 41 and the honeycomb panel 23, which plays a protective and decorative role for the sunshade steel truss 5, and also prevents water from accumulating on the sunshade steel truss 5.

[0026] An aluminum beam 8 is fixed to the inner sides of two adjacent wind-resistant columns 3 facing each other. A connecting assembly connects the aluminum beam 8 and the tempered glass 9. The connecting assembly includes an inclined positioning member 42. A connecting part is provided on the left side of the positioning member 42. The connecting part and the aluminum beam 8 are connected by bolts. A limiting part is provided in the middle of the right side of the positioning member 42. Tempered glass 9 is provided above and below the limiting part. One side of each of the two tempered glass 9 abuts against the right side of the positioning member 42. A fastening member 43 abuts against the other side of the two tempered glass 9. The fastening member 43 is connected to the limiting part, and the fastening member 43 and the positioning member 42 together clamp the two tempered glass 9. A decorative buckle plate 44 is fastened and installed on the other side of the fastening member 43. The aluminum beam 8 is fixed to the tempered glass 9 by the connecting assembly, ensuring the firmness of the installation of the tempered glass 9.

[0027] The lower edge node 11 includes a supporting steel pipe, which is fixed to the floor slab 1 and connected to the connecting steel frame 45. A clamping assembly is connected to the supporting steel pipe. The clamping assembly includes a first clamping member 46. An inclined protrusion is provided on the lower left side of the first clamping member 46. The tempered glass 9 abuts against the inclined protrusion, and one side of the tempered glass 9 abuts against the left side of the first clamping member 46. A second clamping member 47 abuts against the other side of the tempered glass 9. The second clamping member 47 is connected to the first clamping member 46. The first clamping member 46 and the second clamping member 47 together clamp the tempered glass 9. The second clamping member 47 is connected to the honeycomb plate 23 located on the upper surface of the connecting steel frame 45. A flashing plate 48 is connected to the right side of the first clamping member 46 and is fixed to the floor slab 1.

[0028] A construction method for a composite curtain wall using metal panels and tempered glass in the same building includes the following steps: A. Model according to the construction drawings, install the wall grid 49 on the outer side of the wall 57 according to the model, and install the connecting steel frame on the floor slab 1. B. Model according to the construction drawings, and mark the positioning points of each wind-resistant column 3 on the floor slab 1 based on the model and with the help of a total station; C. Install each wind-resistant column 3 in sequence according to the construction drawings and the model. The wind-resistant column 3 is installed between the floor slab 1 and the roof truss structure 2. Reinforcing steel beams 18 are installed on the upper part between two adjacent wind-resistant columns 3 in sequence. Steel tie rods 20 connected to the roof truss structure 2 are installed on the reinforcing steel beams 18. D. Install the steel truss layer by layer from bottom to top on the wind-resistant column 3 according to the construction drawings and the modeling model; E. Based on the construction drawings and the modeling model, install the cantilevered steel frame 22 connected to the reinforcing steel beam 18 on the outer side of the wind-resistant column 3; F. Based on the construction drawings and the modeling model, install each steel cable 6 that passes through the sunshade steel truss of each floor between the cantilever steel frame 22 and the floor slab 1. G. Install aluminum crossbeams 8 one by one between two adjacent wind-resistant columns 3, according to the construction drawings and the modeling model. H. Install the tempered glass 9 one by one according to the construction drawings and the modeling model. The tempered glass 9 located at the upper edge node 10 and the lower edge node 11 will be installed later. I. Based on the construction drawings and the modeling model, install insulation board 26 between the cantilever steel frame 22 and the reinforcing steel beam 18 and on the outer side of the roof truss structure 2, and install sealing steel frame 24 between the roof truss structure 2 and the cantilever steel frame 22, and then install tempered glass 9 at the edge finishing node 10. J. Install aluminum plate 25 on the sealing steel frame 24 according to the construction drawings and in conjunction with the modeling model; install aluminum plate 25 and honeycomb panel 23 on the cantilever steel frame 22; and install decorative panel 7 on the sunshade steel truss 5. K. Install the tempered glass 9 of the lower edge finishing node 11 on the floor slab 1 according to the construction drawings and the modeling model; L. According to the construction drawings and in conjunction with the modeling model, install the honeycomb panel 23 on the connecting steel frame 45 and connect the honeycomb panel 23 to the lower edge node 11. M. According to the construction drawings and the model, install the aluminum alloy adapter 50 on the wall grid 49, install the aluminum alloy grille 51 on the aluminum alloy adapter 50, and install the aluminum alloy rodent-proof mesh 52.

[0029] This invention installs a metal panel curtain wall 54 on the outer side of the first-floor wall 57 of the main structure, and a tempered glass curtain wall 55 between the floor slab 1 and the roof truss structure 2 of the main structure. A connecting part 53 is installed on the floor slab 1 to connect the metal panel curtain wall 54 and the tempered glass curtain wall 55 into a whole, thus making the GTC main building's appearance harmonious, beautiful, and simpler. At the same time, the connecting part 53 reduces the difficulty of connecting the metal panel curtain wall 54 and the tempered glass curtain wall 55, meeting design and construction requirements. Several wind-resistant columns 3 are sequentially and obliquely installed along the contour of the floor slab 1 between the floor slab 1 and the roof truss structure 2 to achieve initial fixation of the wind-resistant columns 3. A cantilevered part 4 connected to the roof truss structure 2 is installed on the outer side of the several wind-resistant columns 3. A sunshade steel truss 5 is installed between each adjacent wind-resistant column 3, and the sunshade steel trusses 5 at the same height are enclosed together. Several layers of sunshade steel trusses 5, arranged from bottom to top on several wind-resistant columns 3, are connected into a whole by cantilevered sections 4 and sunshade steel trusses 5, thereby reinforcing the wind-resistant columns 3. Several steel cables 6 are sequentially installed along the outline of the floor slab 1 between the cantilevered section 4 and the floor slab 1, and each steel cable 6 passes through each layer of sunshade steel trusses 5 from top to bottom. The connection between the steel cables 6 and the sunshade steel trusses 5 strengthens the stability of the sunshade steel trusses 5. The several wind-resistant columns 3, cantilevered sections 4, and sunshade steel trusses 5 together form the overall load-bearing structure of the tempered glass curtain wall 55. While realizing the inclined setting of the tempered glass curtain wall 55, it also solves the defects of poor overall stability and poor wind resistance of the tempered glass curtain wall 55 due to the dual effects of its own weight and inclined setting. At the same time, it also reduces the construction difficulty of the inclined tempered glass curtain wall 55 and ensures the construction quality.

[0030] The above description is merely a preferred embodiment of the present invention and is not intended to limit the scope of the present invention. All equivalent changes made based on the description and drawings of the present invention are included within the scope of the present invention.

Claims

1. A composite curtain wall of metal panels and tempered glass used in the same building, wherein the composite curtain wall of metal panels and tempered glass is installed on the main structure of the GTC main building, characterized in that: The composite curtain wall of metal panels and tempered glass includes a metal panel curtain wall and a tempered glass curtain wall. The main structure includes a foundation raft slab and floor slabs. The floor slabs are located above the foundation raft slab and separate the first and second floors of the main structure. A wall is set between the foundation raft slab and the floor slabs. A roof truss structure is set on the floor slabs. The metal panel curtain wall is set on the outer side of the wall, and the tempered glass curtain wall is set between the floor slabs and the roof truss structure. The tempered glass curtain wall is set from bottom to top and from the inside to the outside. A connection is set between the metal panel curtain wall and the tempered glass curtain wall. The tempered glass curtain wall includes several wind-resistant columns, which are arranged sequentially along the outline of the floor slabs. The system is configured with adjacent wind-resistant columns spaced apart. The lower ends of the wind-resistant columns are inclined and fixed to the edge of the upper surface of the floor slab, while the upper ends are connected to the roof truss structure. A cantilever section is formed on the outer side of the upper ends of several wind-resistant columns, enclosing the outline of the floor slab. This cantilever section is connected to the roof truss structure. Sunshade steel trusses are fixed at intervals along the height direction on the outer side of adjacent wind-resistant columns. Sunshade steel trusses at the same height are arranged enclosing the outline of the floor slab, positioned between the cantilever section and the floor slab. Steel cables are fixed between the floor slab and the cantilever section, passing sequentially through the sunshade steel trusses and connected to them. Furthermore, steel cables are spaced apart along the length of the sunshade steel truss, which is covered with decorative panels. An aluminum crossbeam is fixed to the inner side of each truss, positioned between adjacent wind-resistant columns. Tempered glass is installed between adjacent upper and lower aluminum crossbeams. An upper edge-receiving node is provided between the tempered glass and the cantilever section, and a lower edge-receiving node is provided between the tempered glass and the floor slab. The lower edge-receiving node connects to the connecting part. The connecting part is located on the floor slab and includes a connecting steel frame fixed to the outer edge of the floor slab. A honeycomb panel is installed on the outer surface of the connecting steel frame, and the honeycomb panel connects to the lower edge-receiving node. Metal panel curtain wall. The wall includes a wall frame located on the outer side of the wall. The upper part of the wall frame is connected to a connecting steel frame, and the lower part of the wall frame is fixed to the foundation raft. Several aluminum alloy adapters are fixedly connected to the wall frame. The aluminum alloy adapters are spaced apart along the length of the wall frame. Each aluminum alloy adapter is vertically continuous along the height of the wall frame. Several aluminum alloy grilles are installed on the aluminum alloy adapters. The aluminum alloy grilles are spaced apart along the height of the wall frame. The aluminum alloy adapters and aluminum alloy grilles together form a grid structure, and each grid block is equipped with an aluminum alloy rodent-proof mesh.

2. The composite curtain wall of metal panels and tempered glass used in the same building as described in claim 1, characterized in that: A first embedded part is pre-embedded in the floor slab. Three first steel ear plates are vertically fixed on the upper surface of the first embedded part. Two adjacent first steel ear plates are spaced apart from each other, and the three first steel ear plates together form two slots. A second steel ear plate perpendicular to the first embedded part is inserted into each of the two slots. A through hole is provided on the three first steel ear plates and the two second steel ear plates. A set of fastening bolts is installed in the through hole. The upper side of the two second steel ear plates is inclined from the inner side close to the main structure to the outer side away from the main structure. The wind-resistant column has a rectangular cross section. A connecting plate is fixed on the lower end face of the wind-resistant column. The two second steel ear plates are fixedly connected to the connecting plate. The wind-resistant column is inclined according to the slope of the upper side of the two second steel ear plates. Several reinforcing plates are fixed on the outer side of the left first steel ear plate and the right first steel ear plate. The several reinforcing plates are spaced apart along the length direction of the first steel ear plate. The several reinforcing plates are fixed on the upper surface of the first embedded part.

3. The composite curtain wall of metal panels and tempered glass used in the same building as described in claim 1, characterized in that: A reinforcing steel beam is fixedly connected between the upper parts of two adjacent wind-resistant columns. A first base is fixed on the inner side of the reinforcing steel beam. A steel tie rod is connected to the first base. A second base is fixed on the bottom surface of the roof truss structure. The other end of the steel tie rod is connected to the second base.

4. The composite curtain wall of metal panels and tempered glass used in the same building as described in claim 3, characterized in that: The cantilever section includes a cantilever steel frame fixed to a reinforcing steel beam. A honeycomb panel is installed on the bottom surface of the cantilever steel frame. The upper surface of the cantilever steel frame gradually slopes from the side closest to the tempered glass to the side furthest from the tempered glass. A sealing steel frame is installed between the cantilever steel frame and the roof truss structure. An aluminum plate is installed on the sealing steel frame, the upper surface of the cantilever steel frame, and the outer surface furthest from the tempered glass. An insulation board is installed between the cantilever steel frame and the reinforcing steel beam, and between the sealing steel frame and the roof truss structure. An upper edge finishing node is located between the cantilever steel frame and the insulation board. The upper edge finishing node includes a positioning steel frame fixed to the cantilever steel frame and located between the cantilever steel frame and the insulation board. An edge finishing piece is connected to the bottom surface of the positioning steel frame. The tempered glass connected to the cantilever section is installed on the edge finishing piece. An edge sealing plate is installed at the bottom of the insulation board and fixed between the edge finishing piece and the reinforcing steel beam.

5. The composite curtain wall of metal panels and tempered glass used in the same building as described in claim 4, characterized in that: An upper anchor plate is fixed on the cantilevered steel frame. One end of the steel cable is connected to the upper anchor plate. A second embedded part is pre-embedded in the floor slab. A lower anchor plate is fixed on the upper surface of the second embedded part. The other end of the steel cable passes through the sunshade steel truss from top to bottom and is connected to the lower anchor plate.

6. The composite curtain wall of metal panels and tempered glass used in the same building as described in claim 1, characterized in that: Several connecting columns are vertically fixed to the outer surface of each wind-resistant column, spaced apart along the height. The sunshade steel truss is fixed between two connecting columns at the same height of adjacent wind-resistant columns. Two inserts are vertically fixed to the side of one of the connecting columns. One end of the sunshade steel truss is inserted into these two inserts, both of which are bolted to the truss. The other end of the truss is fixed to the side of another connecting column. The sunshade steel truss includes an upper chord and a lower chord, which are spaced apart from each other. The structure consists of several inclined web members arranged sequentially from left to right between the upper and lower chords. These inclined web members form a continuous zigzag shape. A vertical web member is installed between the beginning and end of two adjacent inclined web members, and the vertical web member is fixed vertically between the upper and lower chords. A steel cable is correspondingly installed on each vertical web member located in the middle of the sunshade steel truss. A through-hole is provided in the middle of each vertical web member, and a cable clamp is installed in each through-hole. The steel cable passes through the through-hole and connects to the cable clamp.

7. The composite curtain wall of metal panels and tempered glass used in the same building as described in claim 1, characterized in that: The decorative panel includes a first decorative aluminum panel, a second decorative aluminum panel, and a honeycomb panel. The first decorative aluminum panel is installed on the upper surface of the sunshade steel truss, and the honeycomb panel is installed on the lower surface of the sunshade steel truss. The second decorative aluminum panel has a U-shaped cross section and is fixed on the outer side of the sunshade steel truss away from the tempered glass. The first decorative aluminum panel, the second decorative aluminum panel, and the honeycomb panel together cover the sunshade steel truss.

8. The composite curtain wall of metal panels and tempered glass used in the same building as described in claim 1, characterized in that: An aluminum beam is fixed to the inner sides of two adjacent wind-resistant columns facing each other. A connecting assembly is provided between the aluminum beam and the tempered glass. The connecting assembly includes an inclined positioning member. A connecting part is provided on the left side of the positioning member. The connecting part and the aluminum beam are connected by a bolt group. A limiting part is provided in the middle of the right side of the positioning member. Tempered glass is provided above and below the limiting part. One side of each of the two tempered glass pieces abuts against the right side of the positioning member. A fastening member abuts against the other side of the two tempered glass pieces. The fastening member and the limiting part are connected, and the fastening member and the positioning member together clamp the two tempered glass pieces. A decorative buckle is fastened and installed on the other side of the fastening member.

9. The composite curtain wall of metal panels and tempered glass used in the same building as described in claim 1, characterized in that: The lower edge node includes a supporting steel pipe, which is fixed to the floor slab and connected to the connecting steel frame. A clamping assembly is connected to the supporting steel pipe. The clamping assembly includes a first clamping member with an inclined protrusion on the lower left side. Tempered glass abuts against the inclined protrusion, and one side of the tempered glass abuts against the left side of the first clamping member. A second clamping member abuts against the other side of the tempered glass. The second clamping member is connected to the first clamping member, and the first and second clamping members together clamp the tempered glass. The second clamping member is connected to a honeycomb panel located on the upper surface of the connecting steel frame. A flashing plate is connected to the right side of the first clamping member and is fixed to the floor slab.

10. A construction method for a composite curtain wall using metal panels and tempered glass in the same building according to any one of claims 1-9, characterized in that: Includes the following steps: A. Model according to the construction drawings, install the wall grid on the outer side of the wall according to the model, and install the connecting steel frame on the floor slab; B. Model according to the construction drawings, and mark the positioning points of each wind-resistant column on the floor slab based on the model and with the help of a total station; C. Install each wind-resistant column in sequence according to the construction drawings and the model. The wind-resistant columns are installed between the floor slab and the roof truss structure. Reinforcing steel beams are installed on the upper part between two adjacent wind-resistant columns. Steel tie rods connected to the roof truss structure are installed on the reinforcing steel beams. D. Install steel trusses layer by layer from bottom to top on the wind-resistant columns according to the construction drawings and the modeling model; E. Based on the construction drawings and the modeling model, install the cantilevered steel frame connected to the reinforcing steel beam on the outer side of the wind-resistant column; F. Based on the construction drawings and the modeling model, install each steel cable passing through the sunshade steel truss of each floor between the cantilevered steel frame and the floor slab. G. Install aluminum crossbeams one by one between adjacent wind-resistant columns according to the construction drawings and the modeling model; H. Install the tempered glass one by one according to the construction drawings and the modeling model. The tempered glass located at the upper edge node and the lower edge node will be installed later. I. Based on the construction drawings and the modeling model, install insulation boards between the cantilevered steel frame and the reinforcing steel beam and on the outer side of the roof truss structure, and install sealing steel frames between the roof truss structure and the cantilevered steel frame, and then install the tempered glass at the edge finishing nodes. J. Install aluminum plates on the sealing steel frame, aluminum plates and honeycomb panels on the cantilever steel frame, and decorative panels on the sunshade steel truss, based on the construction drawings and modeling. K. Install the tempered glass at the lower edge joint on the floor slab according to the construction drawings and the modeling model; L. Install the honeycomb panels on the connecting steel frame according to the construction drawings and the modeling model, and connect the honeycomb panels to the lower edge node. M. According to the construction drawings and the model, install aluminum alloy adapters on the wall frame, install aluminum alloy grilles on the aluminum alloy adapters, and install aluminum alloy rodent-proof mesh.

Citation Information

Patent Citations

  • Transverse-visible and vertical-hidden inclined glass curtain wall construction structure and construction method

    CN118187331A