大型钢结构框架结构的安装方法

By using installation devices and node connection technology, the problem of large tower cranes being unable to install cantilevered space frame structures has been solved, achieving stable splicing of steel frames and low-cost construction, while reducing the technical requirements of welding processes.

CN118309280BActive Publication Date: 2026-07-17CHINA GEZHOUBA (GRP) FIRST ENG CO LTD

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
CHINA GEZHOUBA (GRP) FIRST ENG CO LTD
Filing Date
2024-04-19
Publication Date
2026-07-17

AI Technical Summary

Technical Problem

Large tower cranes are not suitable for the installation of cantilevered space frame structures. The complex shape of cantilevered space frame structures interferes with the operating space of large tower cranes, making it difficult to align and splice the steel frames. In addition, welding operations require high-altitude work and have high construction costs.

Method used

The steel structure frame is installed using an installation device, including BIM modeling, the use of steel pipes and node connection devices, and the stable movement and splicing of the steel frame is achieved through a lifting mechanism and an opening and closing mechanism. The adjustable rotating rods and grouting nails of the node connection device are used for fixing, reducing welding work.

Benefits of technology

The use of large tower cranes was avoided, saving costs, reducing the risk of safety accidents, improving work efficiency, achieving stable alignment and splicing between steel frames, and reducing the quality requirements of personnel and materials for welding processes.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118309280B_ABST
    Figure CN118309280B_ABST
Patent Text Reader

Abstract

本发明提供大型钢结构框架结构的安装方法,包括待水平架、竖直架和倾斜架拼接完成后,向节点连接装置的注浆钉中注浆;驱动顶升机构和开合机构,直至水平架达到水平位置,通过边行走轮和第二行走轮,以使水平架与节点连接装置连接,向节点连接装置的注浆钉中注浆,通过调节节点连接装置,以保持两组连杆件竖直,通过两个安装装置,以使多个倾斜架相互连接安装。本方法避免使用大型的吊塔,节约成本的同时,避免引发安全事故的现象发生;不使用大型的吊塔,避免而大型塔吊操作空间可能会受到这种结构的干扰,作业效率低的现象发生。注浆实现多个钢结构连接增强的效果,减少焊接工作,适合推广使用。