Multi-functional tower crane foundation conversion installation mechanism and installation leveling method thereof

CN118324047BActive Publication Date: 2026-10-30NINGBO CONSTR ENG GROUP
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202410234681.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-03-01
Publication Date
2026-10-30
Estimated Expiration
2044-03-01

AI Technical Summary

Technical Problem

[0003]本发明所要解决的技术问题:现有的塔吊转换机构较为复杂,受力分布较差,且无法实现对塔吊基础的水平度偏差进行补偿

Benefits of technology

[0007]作为优选,所述第一调平槽和第二调平槽的截面形状均设置为V型,所述调平楔块的截面形状设置为相应的矩形或者菱形。

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118324047B_ABST
    Figure CN118324047B_ABST
Patent Text Reader

Abstract

The present application relates to the technical field of tower crane, and particularly relates to a multifunctional tower crane foundation conversion installation mechanism and a leveling method thereof, wherein the multifunctional tower crane foundation conversion installation mechanism comprises a first connecting seat for connecting with several standard sections of different specifications, a second connecting seat for connecting with corresponding foundation sections, and a connecting bracket for connecting the first connecting seat and the second connecting seat, the connecting bracket is provided with several connecting arms arranged in a radial manner, the top surface of each connecting arm is sequentially provided with several connecting seat mounting positions along the extending direction of the connecting arm, and the middle part of the end of the connecting arm is provided with a leveling mechanism for adjusting the spacing of the corresponding first connecting seat and the second connecting seat. The present application can be applied to the conversion installation of tower cranes of various specifications, facilitates the turnover configuration of the tower crane, and can realize the timely correction of the deviation of the level by using the leveling mechanism, so as to avoid the occurrence of shutdown or even accidents caused by the inclination of the tower crane foundation due to external factors.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of tower crane technology, specifically to a multifunctional tower crane foundation conversion and installation mechanism and its installation and leveling method. Background Technology

[0002] Because tower cranes need to meet anti-overturning requirements for safe operation, their foundations are generally made of large-volume concrete with pre-embedded foundation sections that connect to the tower body for subsequent overall installation. However, in some long-term construction projects requiring conversion between different tower crane specifications, the traditional approach is to pre-embed foundation sections matching multiple specifications simultaneously to accommodate the installation of various tower crane sizes. Existing technology uses conversion sections to accommodate the installation of multiple tower crane sizes, such as a tower crane conversion section disclosed in Chinese Patent No. CN116750667A. This patent technology includes a mounting base, an outer casing, fixed legs, and an upper mounting plate. The mounting base connects to the anchor piles in the tower crane mounting base. The legs of the standard section at the bottom of the tower crane are vertically mounted on the upper mounting plate and connected to the fixed legs with bolts. The device is installed on an adjustment unit, which includes an upper mounting structure for mounting fixed legs. The upper mounting structure includes two parallel first slides and two second slides perpendicular to the first slides below them. Fixed legs are installed at the intersection of the first and second slides, and the fixed legs can slide on the first and second slides. The fixed legs can swing, thus better fitting with the standard section at the bottom of the tower crane. They can move freely along the horizontal plane, thus adapting to a wider range of tower crane sizes. However, the structure of this patent is relatively complex, and the stress distribution is poor. In addition, during a long construction period, the tower crane foundation may tilt due to uneven settlement of the underlying pad layer caused by the excessive weight of the large volume of concrete, or soil disturbance caused during basement construction. This patented technology cannot compensate for the levelness. Summary of the Invention

[0003] The technical problem to be solved by this invention is that the existing tower crane conversion mechanism is relatively complex, has poor force distribution, and cannot compensate for the level deviation of the tower crane foundation.

[0004] To solve the above-mentioned technical problems, the first part of the present invention adopts the following technical solution: a multifunctional tower crane foundation conversion and installation mechanism, including a first connecting seat for connecting with several standard sections of various specifications, a second connecting seat for connecting with corresponding foundation sections, and a connecting bracket for connecting the first connecting seat and the second connecting seat. The connecting bracket is provided with several radially arranged connecting arms. The top surface of each connecting arm is provided with several connecting seat mounting positions arranged sequentially along its extension direction. Several first connecting seats are provided and fixedly installed at the top of the end of their respective connecting arms. Several second connecting seats are provided and fixedly installed at the bottom of the end of their respective connecting arms. The middle part of the end of each connecting arm is provided with a leveling mechanism for adjusting the distance between the corresponding first connecting seats and the second connecting seats. After the distance between the corresponding first connecting seats and the second connecting seats is adjusted at the control end of the driving leveling mechanism, the several first connecting seats are kept in the same horizontal plane.

[0005] When in operation, this invention is applicable to the conversion and installation of tower cranes of various specifications, facilitating tower crane turnover configuration. It can configure tower cranes of appropriate specifications for different stages of construction requirements, reducing resource waste and saving construction costs. At the same time, the leveling mechanism can realize timely correction of level deviations, making it suitable for use in scenarios with long construction cycles and avoiding work stoppages or even accidents caused by tower crane foundation tilting due to external factors.

[0006] Preferably, the connecting bracket includes a first connecting plate, a second connecting plate, and a support plate. The first connecting plate has a plurality of radially arranged first arm plates, and the second connecting plate has second arm plates corresponding one-to-one with the plurality of first arm plates. The first and second connecting plates are arranged vertically at intervals, and the middle portions of the first and second connecting plates are connected as one unit by the support plate. The leveling mechanism includes a first leveling seat, a second leveling seat, a leveling wedge, and a leveling screw. The first leveling seat is fixedly installed on the bottom surface of the first arm plate, and the second leveling seat is fixedly installed on the top surface of the second arm plate. The bottom surface of the first leveling seat is recessed with a first leveling groove, and the second leveling... The top surface of the seat is recessed with a second leveling groove. The first and second leveling grooves cooperate with each other to form a funnel-shaped leveling space. The leveling wedge is slidably installed in the leveling space. The outer surface of the leveling wedge is provided with a leveling inclined surface that cooperates with the inner wall surface of the first and second leveling grooves. The leveling wedge is provided with a threaded hole extending along its length. The leveling screw is threadedly connected in the threaded hole. One end of the leveling screw extends outward to the outside of the connecting arm and is connected to the output end of the corresponding leveling drive device through a transmission assembly. The other end of the leveling screw extends inward and is rotatably limited between the first and second arm plates.

[0007] Preferably, the cross-sectional shape of the first leveling groove and the second leveling groove is set to V-shape, and the cross-sectional shape of the leveling wedge is set to a corresponding rectangle or rhombus.

[0008] When the present invention is working, the distance between the first connecting seat and the second connecting seat is adjusted by moving the leveling block in the leveling space. At the same time, the screw self-locking method is used to prevent the displacement of the leveling block during use, which is safe, reliable and has a strong load-bearing capacity. The control accuracy is improved by the cooperation between the leveling inclined surface and the first and second leveling grooves, the adjustment effect is high and the levelness consistency among the several first connecting seats after adjustment is good.

[0009] Preferably, the top surface of the middle part of the first connecting seat is provided with several lifting rings protruding upwards.

[0010] Preferably, a pressure sensor is also provided between the first connecting seat and the second connecting seat.

[0011] The second part of this invention adopts the following technical solution: an installation and leveling method for a multifunctional tower crane foundation conversion and installation mechanism, applied to the aforementioned multifunctional tower crane foundation conversion and installation mechanism, comprising the following steps:

[0012] S1: Measure the levelness of the tower crane foundation. Then, hoist the multi-functional tower crane foundation conversion installation mechanism to the top of the tower crane foundation and fix it to the tower crane foundation by connecting it to the foundation section embedded in the tower crane foundation through several second connecting seats.

[0013] S2: Install the first connecting seat of the corresponding specification in sequence according to the specifications of the tower crane standard section to be installed. Then, according to the measured level deviation, drive the leveling mechanism to adjust several first connecting seats to the same horizontal plane.

[0014] S3: Install the standard tower crane sections and the tower crane lifting and slewing mechanism in sequence, and enter the tower crane usage stage;

[0015] S4: Real-time monitoring of pressure changes between several sets of corresponding first and second connecting seats, and recording of pressure data;

[0016] S5: The pressure data recorded by the pressure distribution measurement system is processed to establish a pressure distribution model. The center of gravity offset data of the tower crane is obtained through the pressure distribution model, and a correction equation is established based on the center of gravity offset data. When the tower crane is working, the leveling mechanism is driven to adjust the spacing between several sets of first and second connecting seats according to the correction equation, the weight of the hoisted material and the displacement distance, thereby adjusting the center of gravity position of the tower crane, optimizing the force distribution of the tower crane and suppressing the overturning tendency of the tower crane.

[0017] Preferably, in step S5, when adjusting the spacing between several sets of first and second connecting seats according to the corrected equation, the weight of the hoisted material, and the displacement distance, thereby adjusting the center of gravity of the tower crane, optimizing the force distribution of the tower crane, and suppressing the overturning tendency of the tower crane, the following sub-steps are adopted:

[0018] A1: The center of gravity deviation value is obtained by calculating the weight and displacement distance of the suspended material using a modified equation;

[0019] A2: Before hoisting materials, the leveling mechanism is driven to adjust the spacing between several sets of first and second connecting seats according to the center of gravity deviation value, so that the pressure distribution model established by the adjusted pressure distribution data can compensate for the pressure distribution model of the tower crane during operation, thereby correcting the deviation.

[0020] When this invention is in operation, it can achieve leveling of several first connecting seats. By processing the pressure data through the pressure distribution measurement system, the center of gravity position of the tower crane is adjusted to optimize the force distribution of the tower crane, which can suppress the overturning tendency of the tower crane and prevent further tilting of the tower crane foundation. This greatly improves the safety factor of construction and avoids personal and property losses caused by tower crane overturning.

[0021] The beneficial technical effects of this invention include:

[0022] 1. This invention is applicable to the conversion and installation of tower cranes of various specifications, facilitating tower crane turnover configuration. It can configure tower cranes of appropriate specifications for different stages of construction requirements, reducing resource waste and saving construction costs. At the same time, the leveling mechanism can realize timely correction of level deviations, making it suitable for use in scenarios with long construction cycles and avoiding work stoppages or even accidents caused by tower crane foundation tilting due to external factors.

[0023] 2. This invention adjusts the distance between the first and second connecting seats by moving the leveling block within the leveling space. At the same time, it uses a screw self-locking method to prevent displacement of the leveling block during use, which is safe, reliable, and has a strong load-bearing capacity. The cooperation between the leveling inclined surface and the first and second leveling grooves improves the control accuracy, has a high adjustment effect, and the levelness consistency among the several first connecting seats after adjustment is good.

[0024] 3. This invention can achieve leveling of several first connecting seats. By processing the pressure data through the pressure distribution measurement system, the center of gravity position of the tower crane is adjusted to optimize the force distribution of the tower crane, which can suppress the overturning tendency of the tower crane and prevent further tilting of the tower crane foundation. This greatly improves the safety factor of construction and avoids personal and property losses caused by tower crane overturning.

[0025] Other features and advantages of the present invention will be disclosed in detail in the following detailed description and accompanying drawings. Attached Figure Description

[0026] The invention will be further described below with reference to the accompanying drawings:

[0027] Figure 1 This is a structural schematic diagram of a multifunctional tower crane foundation conversion and installation mechanism;

[0028] Figure 2 A partial sectional view of a multifunctional tower crane foundation conversion and installation mechanism;

[0029] Figure 3 An exploded view of some components of a multifunctional tower crane foundation conversion and installation mechanism;

[0030] Figure 4 for Figure 3 A magnified view of a portion of point A in the middle.

[0031] Among them: 1. First connecting seat,

[0032] 2. Second connecting seat,

[0033] 3. Connecting bracket; 31. Connecting arm; 32. First connecting plate; 321. First arm plate; 33. Second connecting plate; 331. Second arm plate; 34. Support plate; 35. Lifting ring; 4. Leveling mechanism; 41. First leveling seat; 411. First leveling groove; 42. Second leveling seat; 421. Second leveling groove; 43. Leveling wedge; 431. Leveling inclined plane; 44. Leveling screw. Detailed Implementation

[0034] The technical solutions of the embodiments of the present invention will be explained and described below with reference to the accompanying drawings. However, the following embodiments are only preferred embodiments of the present invention and not all of them. Other embodiments obtained by those skilled in the art based on the embodiments in the implementation methods without creative effort are all within the protection scope of the present invention.

[0035] In the following description, terms such as “inner,” “outer,” “upper,” “lower,” “left,” and “right” are used only to facilitate the description of embodiments and simplify the description, and are not intended to indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation, and therefore should not be construed as a limitation of the present invention.

[0036] Example 1

[0037] Please see the appendix Figure 1This embodiment discloses a multifunctional tower crane foundation conversion and installation mechanism, including a first connecting seat 1 for connecting with several standard sections of various specifications, a second connecting seat 2 for connecting with corresponding foundation sections, and a connecting bracket 3 for connecting the first connecting seat 1 and the second connecting seat 2. The differences are described in detail below with reference to the accompanying drawings.

[0038] In this embodiment, the connecting bracket 3 is provided with a plurality of radially arranged connecting arms 31. The top surface of each connecting arm 31 is provided with a plurality of connecting seat mounting positions arranged sequentially along its extension direction. A plurality of first connecting seats 1 are provided and are respectively fixedly installed at the top of the end of their respective connecting arm 31. A plurality of second connecting seats 2 are provided and are respectively fixedly installed at the bottom of the end of their respective connecting arm 31. The middle of the end of the connecting arm 31 is provided with a leveling mechanism 4 for adjusting the distance between the corresponding first connecting seats 1 and second connecting seats 2. After the distance between the corresponding first connecting seats 1 and second connecting seats 2 is adjusted at the control end of the driving leveling mechanism 4, the plurality of first connecting seats 1 are kept in the same horizontal plane.

[0039] This embodiment is applicable to the conversion and installation of tower cranes of various specifications, facilitating tower crane turnover configuration. It can configure tower cranes of appropriate specifications to meet the construction requirements of different stages, reducing resource waste and saving construction costs. At the same time, the leveling mechanism 4 can realize timely correction of level deviations, which is suitable for use in scenarios with long construction cycles and avoids work stoppages or even accidents caused by tower crane foundation tilting due to external factors.

[0040] Please see the appendix Figure 2 To be continued Figure 4The connecting bracket 3 includes a first connecting plate 32, a second connecting plate 33, and a support plate 34. The first connecting plate 32 has a plurality of radially arranged first arm plates 321, and the second connecting plate 33 has second arm plates 331 corresponding one-to-one with the plurality of first arm plates 321. The first connecting plate 32 and the second connecting plate 33 are arranged vertically at intervals. The middle part of the first connecting plate 32 and the middle part of the second connecting plate 33 are connected as one unit by the support plate 34. The leveling mechanism 4 includes a first leveling seat 41, a second leveling seat 42, a leveling wedge 43, and a leveling screw 44. The first leveling seat 41 is fixedly installed on the bottom surface of the first arm plate 321, and the second leveling seat 42 is fixedly installed on the top surface of the second arm plate 331. The bottom surface of the first leveling seat 41 is recessed with a first leveling groove 411. The top surface of the leveling seat 42 is recessed with a second leveling groove 421. The first leveling groove 411 and the second leveling groove 421 cooperate with each other to form a funnel-shaped leveling space. The leveling wedge 43 is slidably installed in the leveling space. The outer surface of the leveling wedge 43 is provided with a leveling inclined surface 431 that cooperates with the inner wall surface of the first leveling groove 411 and the inner wall surface of the second leveling groove 421. The leveling wedge 43 is provided with a threaded hole that extends along its length. The leveling screw 44 is threadedly connected in the threaded hole. One end of the leveling screw 44 extends outward to the outside of the connecting arm 31 and is connected to the output end of the corresponding leveling drive device through the transmission assembly. The other end of the leveling screw 44 extends inward and is rotatably limited between the first arm plate 321 and the second arm plate 331.

[0041] Preferably, the cross-sectional shape of the first leveling groove 411 and the second leveling groove 421 is set to V-shape, and the cross-sectional shape of the leveling wedge 43 is set to a corresponding rectangle or rhombus, which can change the horizontal torque when the tower crane rotates and improve the support effect of the standard section of the crane boom near the tower crane.

[0042] In this embodiment, the distance between the first connecting seat 1 and the second connecting seat 2 is adjusted by moving the leveling block within the leveling space. At the same time, the screw self-locking method is used to prevent the displacement of the leveling block during use, which is safe, reliable and has a strong load-bearing capacity. The cooperation between the leveling inclined surface 431 and the first leveling groove 411 and the second leveling groove 421 improves the control accuracy and adjustment effect. The levelness consistency among the several first connecting seats 1 after adjustment is good.

[0043] In specific implementation, a number of lifting rings 35 are provided on the top surface of the middle part of the first connecting seat 1 to facilitate the hoisting of the multi-functional tower crane foundation conversion installation mechanism. Preferably, a pressure sensor is also provided between the first connecting seat 1 and the second connecting seat 2 to facilitate monitoring the pressure changes of each connecting arm 31 and to facilitate the establishment of a pressure distribution model.

[0044] Example 2

[0045] Please see the appendix Figure 1 This embodiment provides an installation and leveling method for a multi-functional tower crane foundation conversion and installation mechanism, which is applied to the multi-functional tower crane foundation conversion and installation mechanism in Embodiment 1. The following is a detailed description.

[0046] This embodiment includes the following steps:

[0047] S1: Measure the levelness of the tower crane foundation, then hoist the multi-functional tower crane foundation conversion installation mechanism to the top of the tower crane foundation, and fix it to the tower crane foundation by connecting it to the foundation section pre-embedded in the tower crane foundation through several second connecting seats 2;

[0048] S2: Install the first connecting seat 1 of the corresponding specifications in sequence according to the specifications of the tower crane standard section to be installed. Then, according to the measured level deviation, drive the leveling mechanism 4 to adjust several first connecting seats 1 to the same horizontal plane.

[0049] S3: Install the standard tower crane sections and the tower crane lifting and slewing mechanism in sequence, and enter the tower crane usage stage;

[0050] S4: Real-time monitoring of pressure changes between several sets of corresponding first connecting seats 1 and second connecting seats 2, and recording pressure data;

[0051] S5: The recorded pressure data is processed by the pressure distribution measurement system to establish a pressure distribution model. The center of gravity offset data of the tower crane is obtained through the pressure distribution model, and a correction equation is established based on the center of gravity offset data. When the tower crane is working, the leveling mechanism 4 is driven to adjust the spacing of several sets of first connecting seats 1 and second connecting seats 2 according to the correction equation, the weight of the hoisted material and the displacement distance, thereby adjusting the center of gravity position of the tower crane, optimizing the force distribution of the tower crane and suppressing the overturning tendency of the tower crane.

[0052] In specific implementation, in step S5, the leveling mechanism 4 is driven to adjust the spacing between several sets of first connecting seats 1 and second connecting seats 2 according to the correction equation, the weight of the hoisted material, and the displacement distance, thereby adjusting the center of gravity position of the tower crane, optimizing the force distribution of the tower crane, and suppressing the overturning tendency of the tower crane. The following sub-steps are adopted:

[0053] A1: The center of gravity deviation value is obtained by calculating the weight and displacement distance of the suspended material using a modified equation;

[0054] A2: Before hoisting the material, the leveling mechanism 4 is driven to adjust the spacing of several sets of first connecting seats 1 and second connecting seats 2 according to the center of gravity deviation value, so that the pressure distribution model established by the adjusted pressure distribution data can compensate for the pressure distribution model of the tower crane during operation, thereby correcting the deviation.

[0055] In operation, this embodiment can achieve leveling of several first connecting seats 1. By processing the pressure data through the pressure distribution measurement system, the center of gravity position of the tower crane is adjusted to optimize the force distribution of the tower crane, which can suppress the overturning tendency of the tower crane and prevent further tilting of the tower crane foundation, greatly improving the safety factor of construction and avoiding personal and property losses caused by tower crane overturning.

[0056] The beneficial technical effects of this embodiment include: the present invention can be applied to the conversion and installation of tower cranes of various specifications, which facilitates the turnover configuration of tower cranes. It can configure tower cranes of appropriate specifications for different stages of construction requirements, reduce the waste of resources, and save construction costs. At the same time, the leveling mechanism can realize timely correction of level deviations, which is suitable for use in scenarios with long construction cycles and avoids work stoppages or even accidents caused by the tilting of the tower crane foundation due to external factors.

[0057] The above description is merely a specific embodiment of the present invention, but the scope of protection of the present invention is not limited thereto. Those skilled in the art should understand that the present invention includes, but is not limited to, the contents described in the accompanying drawings and the specific embodiments above. Any modifications that do not depart from the functional and structural principles of the present invention will be included within the scope of the claims.

Claims

1. A multifunctional tower crane foundation conversion and installation mechanism, characterized in that: It includes a first connecting seat (1) for connecting with standard sections of several specifications, a second connecting seat (2) for connecting with corresponding base sections, and a connecting bracket (3) for connecting the first connecting seat (1) and the second connecting seat (2). The connecting bracket (3) is provided with several connecting arms (31) arranged radially. Each connecting arm (31) has several connecting seat mounting positions arranged sequentially along its extension direction on its top surface. The first connecting seat (1) is provided with several and is fixedly installed at the top of the end of its corresponding connecting arm (31). The second connecting seat (2) is provided with several and is fixedly installed at the bottom of the end of its corresponding connecting arm (31). The middle part of the end of the connecting arm (31) is provided with a leveling mechanism (4) for adjusting the distance between the corresponding first connecting seat (1) and the second connecting seat (2). After the distance between the corresponding first connecting seat (1) and the second connecting seat (2) is adjusted by the control end of the driving leveling mechanism (4), the several first connecting seats (1) are kept in the same horizontal plane. The connecting bracket (3) includes a first connecting plate (32), a second connecting plate (33), and a support plate (34). The first connecting plate (32) has a plurality of radially arranged first arm plates (321). The second connecting plate (33) has second arm plates (331) that correspond one-to-one with the plurality of first arm plates (321). The first connecting plate (32) and the second connecting plate (33) are arranged vertically at intervals. The middle part of the first connecting plate (32) and the middle part of the second connecting plate (33) are connected as one unit by the support plate (34). The leveling mechanism (4) includes a first leveling seat (41), a second leveling seat (42), a leveling wedge (43), and a leveling screw (44). The first leveling seat (41) is fixedly installed on the bottom surface of the first arm plate (321), and the second leveling seat (42) is fixedly installed on the top surface of the second arm plate (331). The bottom surface of the first leveling seat (41) is recessed with a first leveling screw. The top surface of the second leveling seat (42) is recessed with a second leveling groove (421). The first leveling groove (411) and the second leveling groove (421) cooperate with each other to form a funnel-shaped leveling space. The leveling wedge (43) is slidably installed in the leveling space. The outer surface of the leveling wedge (43) is provided with a leveling inclined surface (431) that cooperates with the inner wall surface of the first leveling groove (411) and the inner wall surface of the second leveling groove (421). The leveling wedge (43) is provided with a threaded hole that extends along its length. The leveling screw (44) is threadedly connected in the threaded hole. One end of the leveling screw (44) extends outward to the outside of the connecting arm (31) and is connected to the output end of the corresponding leveling drive device through the transmission assembly. The other end of the leveling screw (44) extends inward and is rotatably limited between the first arm plate (321) and the second arm plate (331).

2. The multifunctional tower crane foundation conversion and installation mechanism according to claim 1, characterized in that: The cross-sectional shape of the first leveling groove (411) and the second leveling groove (421) is set to V-shape, and the cross-sectional shape of the leveling wedge (43) is set to the corresponding rectangle or rhombus.

3. The multifunctional tower crane foundation conversion and installation mechanism according to claim 1, characterized in that: The top surface of the middle part of the first connecting seat (1) is provided with several lifting rings (35).

4. The multifunctional tower crane foundation conversion and installation mechanism according to claim 1, characterized in that: A pressure sensor is also provided between the first connecting seat (1) and the second connecting seat (2).

5. A method for installing and leveling a multi-functional tower crane foundation conversion and installation mechanism, applied to the multi-functional tower crane foundation conversion and installation mechanism described in any one of claims 1 to 4, characterized in that, Includes the following steps: S1: Measure the level of the tower crane foundation. Then, hoist the multi-functional tower crane foundation conversion installation mechanism to the top of the tower crane foundation and fix it to the tower crane foundation by connecting it with the foundation section embedded in the tower crane foundation through several second connecting seats (2). S2: Install the first connecting seat (1) of the corresponding specification according to the specifications of the tower crane standard section to be installed in sequence. Then, according to the measured level deviation, drive the leveling mechanism (4) to adjust several first connecting seats (1) to the same horizontal plane. S3: Install the standard tower crane sections and the tower crane lifting and slewing mechanism in sequence, and enter the tower crane usage stage; S4: Monitor the pressure changes between several sets of corresponding first connecting seats (1) and second connecting seats (2) in real time and record the pressure data; S5: The pressure data recorded by the pressure distribution measurement system is processed to establish a pressure distribution model. The center of gravity offset data of the tower crane is obtained through the pressure distribution model. A correction equation is established based on the center of gravity offset data. When the tower crane is working, the leveling mechanism (4) is driven to adjust the spacing between several sets of first connecting seats (1) and second connecting seats (2) according to the correction equation, the weight of the suspended material and the displacement distance, thereby adjusting the center of gravity position of the tower crane, optimizing the force distribution of the tower crane and suppressing the overturning tendency of the tower crane.

6. The installation and leveling method for a multifunctional tower crane foundation conversion and installation mechanism according to claim 5, characterized in that, In step S5, the leveling mechanism (4) is driven to adjust the spacing between several sets of first connecting seats (1) and second connecting seats (2) according to the correction equation, the weight of the suspended material, and the displacement distance, thereby adjusting the center of gravity of the tower crane, optimizing the force distribution of the tower crane, and suppressing the overturning tendency of the tower crane. The following sub-steps are adopted: A1: The center of gravity deviation value is obtained by calculating the weight and displacement distance of the suspended material using a modified equation; A2: Before hoisting the material, the leveling mechanism (4) is driven to adjust the distance between several sets of first connecting seats (1) and second connecting seats (2) according to the center of gravity deviation value, so that the pressure distribution model established by the adjusted pressure distribution data can compensate for the pressure distribution model of the tower crane during operation, thereby correcting the deviation.

Citation Information

Patent Citations

  • Tower crane conversion joint

    CN116750667A

  • Leveling device for walking underframe of tower crane, walking underframe and tower crane

    CN203582329U

  • Mounting method and mounting system for megawatt tower solar thermal power generation heat collector

    WO2022078035A1