Fabricated ductile PEC recycled concrete beam-column joint with compressive form composite floor

By using prefabricated PEC recycled concrete beam-column joints with profiled composite floor slabs in the frame structure, and utilizing PEC columns, composite floor slabs, and shape memory alloy cables, the residual deformation and damage problems of beam-column joints under seismic loading are solved, achieving efficient and economical seismic performance improvement and self-resetting capability.

CN118327148BActive Publication Date: 2026-11-24JILIN JIANZHU UNIVERSITY
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410390278.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-04-02
Publication Date
2026-11-24
Estimated Expiration
2044-04-02

AI Technical Summary

Technical Problem

In existing frame structure systems, beam-column joints are prone to large residual deformation and irreparable damage under seismic loads. Traditional construction methods require a large amount of labor, have long construction periods, high costs, and offer limited improvement in seismic performance.

Method used

The prefabricated PEC recycled concrete beam-column joint adopts a profiled composite floor slab, which combines PEC columns, composite profiled composite floor slabs and H-shaped steel beams. Shape memory alloy cables and dog bone connection plates are used to enhance the strength, stiffness and energy dissipation capacity of the joint. Energy is shared through the rotation of the joint, the tension of the cable and the plastic deformation of the connection plate.

Benefits of technology

It improves the strength, stiffness, and load-bearing capacity of nodes, shortens the construction period, reduces post-earthquake maintenance costs, has self-resetting capabilities, reduces residual structural deformation and damage, and is in line with sustainable development goals.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118327148B_ABST
    Figure CN118327148B_ABST
Patent Text Reader

Abstract

A prefabricated, resilient PEC recycled concrete beam-column joint with a profiled steel composite floor slab includes a PEC column. From top to bottom, the steel side of the PEC column consists of a recycled concrete floor slab, a profiled steel sheet, and an H-shaped steel beam. The H-shaped steel beam is formed by upper and lower flanges and a central web. The H-shaped steel beam is divided into two parts: a short beam welded to the PEC column and a long beam. Semi-circular grooves are provided on the upper and lower flanges of the right side of the short beam at the break point, and semi-circular groove butt plates are provided on the upper and lower flanges of the left side of the long beam. The semi-circular grooves are butt-jointed with the semi-circular groove butt plates. Rectangular end plates are located on the right side of the short beam and welded to the web, and on the right side of the long beam and connected to the web. Each end plate has four holes in its center for placing shape memory alloy cables, which are then connected via clamps. A dog-bone connecting plate is connected to the inner side of the upper flange at the break point between the short and long beams. This invention can reduce residual displacement and damage to the structure under seismic loading, saving post-earthquake maintenance costs.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of beam-column joint technology in seismic resistance and vibration reduction in civil engineering, specifically to a prefabricated tough PEC recycled concrete beam-column joint with a pressure-type composite floor slab. Background Technology

[0002] In frame structures, beam-column joints are the force transmission hubs between structural members, requiring enhanced joint design to comply with the principle of "strong joints, weak members." my country's current seismic fortification goals are "no damage in minor earthquakes, repairable damage in moderate earthquakes, and no collapse in major earthquakes." However, due to the complexity and randomness of earthquakes, structures often suffer significant residual deformation and irreparable damage after an earthquake, necessitating demolition and reconstruction, resulting in incalculable economic losses.

[0003] Traditional construction methods for reinforced concrete structures, such as casting concrete after formwork erection, suffer from problems such as high labor demand, long construction period, high pollution, high energy consumption, low efficiency, and low degree of industrialization. Traditional beam-column joints increase costs by increasing the cross-sectional area of ​​the components, but have little effect on improving their seismic performance and energy dissipation capacity. Summary of the Invention

[0004] To overcome the problems existing in the prior art, the present invention aims to provide a prefabricated tough PEC recycled concrete beam-column joint with profiled composite floor slab. The presence of profiled composite floor slab increases the strength, stiffness and load-bearing capacity of the joint; shape memory alloy cable gives the joint a certain energy dissipation capacity and self-resetting capacity, which can reduce the residual deformation and damage of the structure under seismic action and save post-earthquake maintenance costs.

[0005] To achieve the above objectives, the technical solution adopted by the present invention is as follows: A prefabricated tough PEC recycled concrete beam-column joint with profiled composite floor slab includes a PEC column. The right side of the PEC column, from top to bottom, consists of a recycled concrete floor slab, profiled steel sheet, semi-circular groove, clamp, rectangular end plate, semi-circular joint, high-strength bolt, dog-bone type upper end plate, semi-circular protruding butt plate, and H-beam. The H-shaped steel beam is formed by upper and lower flanges and a middle web. The H-shaped steel beam is divided into two parts: one part is a short beam welded to the right side of the PEC column steel, and the other part is a long beam away from the right side of the PEC column steel. The semi-circular groove includes a semi-circular groove one and a semi-circular groove two. The semi-circular groove one and the semi-circular groove two are provided at the upper and lower flanges on the right side of the short beam at the break point. The semi-circular protruding connecting plate includes a semi-circular protruding connecting plate one and a semi-circular protruding connecting plate two. The semi-circular protruding connecting plate one and the semi-circular protruding connecting plate two are provided at the upper and lower flanges on the left side of the long beam. The semi-circular groove and the semi-circular protruding connecting plate are connected. The rectangular end plate includes rectangular end plate one and rectangular end plate two. Rectangular end plate one is located on the right side of the short beam and is connected to the web plate. Rectangular end plate two is located on the left side of the long beam and is connected to the web plate. Each rectangular end plate has four holes arranged in the middle for placing shape memory alloy cables and connecting them with clamps. The semi-circular joint includes semi-circular joint one and semi-circular joint two, and the high-strength bolts include bolt one, bolt two, and bolt three; semi-circular joint one is located in the middle of rectangular end plate one, and semi-circular joint two is located in the middle of rectangular end plate two; holes are arranged in the middle of semi-circular joint one and semi-circular joint two, and the two are connected by bolt two after splicing; the dog-bone type upper end plate is connected to the inner side of the upper flange at the break between the short beam and the long beam by bolt one; the dog-bone type lower end plate with long groove is connected to the outer side of the lower flange at the break between the short beam and the long beam by bolt three; The dog-bone-type upper end plate consists of two smaller dog-bone-type connecting plates. The middle of each small dog-bone-type connecting plate is weakened into an arc shape, and four bolt holes are symmetrically arranged on the left and right sides of each small dog-bone-type connecting plate. The middle of the slotted dog-bone-type lower end plate is weakened into an arc shape, and three rectangular slots are opened in the middle. The local weakening concentrates the damage on the slotted dog-bone-type lower end plate. Eight bolt holes are symmetrically arranged on the left and right sides of the slotted dog-bone-type lower end plate.

[0006] The recycled concrete floor slab is generally rectangular in shape, with a flat rectangle on the upper side and a corrugated steel sheet on the lower side. The upper and lower flanges of the corrugated steel sheet have the same width, and the inner web is arranged obliquely in a corrugated pattern.

[0007] Three semicircular connectors are arranged in one position, and two semicircular connectors are arranged in another position.

[0008] The PEC column and the H-beam are connected by welding, and the concrete inside the PEC column is recycled concrete.

[0009] The recycled concrete floor slab and the profiled steel sheet form a composite floor slab, and the recycled concrete floor slab and the profiled steel sheet are connected to the upper flange of the beam by studs; the recycled concrete floor slab is made of recycled concrete.

[0010] Rectangular end plate one is located on the right side of the short beam and is welded to the web plate; rectangular end plate two is located on the left side of the long beam and is welded to the web plate; each end plate has four holes arranged in the middle. Multiple shape memory alloy cables are placed in the hole and connected by a clamp.

[0011] A method for using prefabricated tough PEC recycled concrete beam-column joints with profiled composite floor slabs includes the following steps: The PEC column and the H-beam are connected by welding. A rectangular end plate is welded to the web of the disconnected H-beam on both sides. The semi-circular joints on both sides are connected by bolts. The upper and lower flanges of the beam at this node are connected by semi-circular grooves and semi-circular protrusions. The upper and lower parts of this node are connected by dog ​​bone upper end plates and dog bone lower end plates with long grooves, respectively. The composite floor slab is connected to the H-beam by studs, and flexible material is filled between the slab and the beam. The PEC column is welded to the left side of the broken short beam. The semi-circular grooves extending from the upper and lower flanges of the short beam and the semi-circular protrusions extending from the upper and lower flanges of the long beam fit perfectly into each other. At the break point, a dog-bone-style upper end plate is bolted to the lower part of the upper flange of the beam. A rectangular end plate is welded to the web of the short beam on the right side and the long beam on the left side. Three semi-circular joints are arranged on the rectangular end plate of the short beam on the right side, with a spacing of one semi-circular joint thickness between each two joints. Two semi-circular joints are arranged on the rectangular end plate of the long beam on the left side, with a spacing of one semi-circular joint thickness between them. The semi-circular joints and the rectangular end plates are connected... The rectangular end plates and beam webs are welded together in the factory. A bolt hole is installed through the center of each of the five semi-circular joints, and bolts are used for connection. Four holes are opened in the center of the rectangular end plates on both the left and right sides. Four strands of SMA shape memory alloy cables are anchored to the outside of the rectangular end plates through the holes using clamps. A dog-bone type lower end plate with long grooves is connected to the lower flange of the disconnected beam using bolts. The profiled steel sheet is bolted to the H-beam through studs on the upper flange of the H-beam. The profiled steel sheet is used as the bottom formwork for the upper recycled concrete floor slab, and recycled concrete is poured to form the recycled concrete floor slab.

[0012] The beneficial effects of this invention are: This invention proposes a prefabricated, resilient PEC recycled concrete beam-column joint with a composite profiled floor slab. It fully leverages the advantages of prefabricated PEC columns, composite profiled floor slabs, and H-beams, providing higher strength, stiffness, and load-bearing capacity under seismic loading. Compared to traditional concrete structures, it improves the strength, stiffness, and stability of components and shortens the construction period. The steel components are connected by high-strength bolts, adapting to prefabricated construction. Compared to steel structures, it improves fire resistance while reducing costs. Both the semi-circular joint and the dog-bone weakened end plates contribute to energy dissipation. The semi-circular arrangement of the joint avoids stress concentration at the joint. Under seismic loading, the semi-circular joint design dissipates energy through the rotation of the joint, the tensile deformation of the shape memory alloy cable, and the plastic deformation caused by the yielding of the dog-bone connection plate. This coexistence of three energy dissipation mechanisms allows the joint to adapt to various seismic conditions. The shape memory alloy cable arrangement dissipates energy during earthquakes and has a certain self-resetting ability after earthquakes, effectively reducing residual deformation of components and mitigating damage to the main structure.

[0013] Steel has high tensile strength and good plasticity; PEC columns have good fire resistance, high load-bearing capacity, and high strength and stiffness; the presence of floor slabs increases the stiffness of joints and the load-bearing capacity of the structure, meeting the needs of practical applications; the concrete inside the PEC columns and the concrete inside the composite floor slabs of this invention are all recycled concrete. The internal steel sections of the steel-recycled concrete PEC columns can enhance the bending capacity of the recycled concrete columns, thereby improving the structural load-bearing capacity and seismic performance. Recycled concrete columns have advantages such as high load-bearing capacity, good seismic performance, and convenient construction.

[0014] Composite floor slabs have advantages such as high degree of industrialization, factory prefabrication and on-site assembly, environmental protection, greenness, safety, aesthetics and practicality. The profiled steel sheets in the composite floor slab not only serve as permanent formwork, but also act as the lower tensile reinforcement of the floor slab. Working together with the concrete, the composite floor slab has good fire resistance. The installation of studs can effectively reduce the relative slippage at the ends, thereby improving its bending load-bearing capacity.

[0015] Recycled concrete, as a green and environmentally friendly material, not only solves the problem of waste concrete disposal, but also plays a significant role in conserving natural aggregates, protecting the environment, and achieving sustainable development goals. It effectively addresses the pollution and difficulty in processing waste concrete, aligning with China's sustainable development strategy. It possesses significant social and economic value.

[0016] The upper and lower connecting end plates of the semi-circular node are made of low-yield-point steel and are weakened using a dog-bone design. The dog-bone connecting plate used for the lower flange has an arc-shaped weakening on its outer side, and three rectangular slots are set inside the weakened middle section to reduce the initial stiffness of the steel plate. This end plate design increases the energy dissipation capacity of the node, reduces self-resetting resistance, and concentrates damage on the bolted dog-bone connecting plate, facilitating later maintenance and disassembly. The semi-circular node design increases the node's energy dissipation and avoids stress concentration when the node rotates. This combination also transfers the plastic hinge to this node, reducing damage to the main body.

[0017] The beam and column ends are welded together, resulting in clear force transmission, simple construction, convenient processing, and steel savings. The profiled composite floor slab is connected to the upper flange of the beam using 19mm diameter studs. Elongated semi-circular grooved steel plates are butt-jointed at both the upper and lower flanges of the beam, ensuring clear rotational force transmission at this joint. The semi-circular joints are connected using 45mm diameter high-strength bolts. The upper end plate of this joint is connected to the inner side of the upper flange of the beam using 10mm diameter high-strength bolts, while the lower end plate is connected to the outer side of the lower flange of the beam using 20mm diameter high-strength bolts. Bolted connections facilitate construction and can be performed even in harsh environments, effectively accelerating construction progress and shortening the construction period.

[0018] SMA cables have advantages such as super elasticity, shape memory, high damping, fatigue resistance and corrosion resistance. Under earthquake action, shape memory alloy cables undergo elastoplastic tensile deformation to dissipate energy, and after the earthquake action dissipates, they have a certain self-resetting ability through heating or electrical excitation, which can reduce the residual displacement, damage and destruction of the main structure.

[0019] While ensuring the strength of the prefabricated components, the energy-consuming and weakened parts are designed as replaceable components and connected with high-strength bolts, making the components easy to disassemble and replace after earthquake damage.

[0020] The semi-circular connectors, end plates, dog-bone connecting plates, etc. required for this invention can all be processed in the factory. Each component is prefabricated in the factory and assembled on site, which is flexible in assembly and highly economical. Attached Figure Description

[0021] Figure 1 This is a 3D diagram of the nodes in this invention.

[0022] Figure 2 This is a detailed view of the PEC column of the present invention.

[0023] Figure 3 This is a detailed drawing of the composite floor slab of the present invention.

[0024] Figure 4 This is a detailed drawing of a corrugated steel plate.

[0025] Figure 5 Remove floor slab details from the nodes.

[0026] Figure 6 Detailed diagram of the semi-circular node.

[0027] Figure 7 This is a detailed view of the left side of the semi-circular node.

[0028] Figure 8 This is a detailed view of the right side of the semi-circular node.

[0029] Figure 9 Detailed drawing of the dog-bone type connecting plate at the top of the node.

[0030] Figure 10 Detailed drawing of the dog-bone type connecting plate with long slots at the bottom of the node.

[0031] Figure label: In the diagram: 1-PEC column, 2-recycled concrete slab, 3-stud, 4-profiled steel sheet, 5-semi-circular groove, 6-clamp, 7-rectangular end plate, 8-semi-circular joint, 9-high-strength bolt, 10-dog bone type upper end plate, 11-semi-circular raised butt plate, 12-H-shaped steel beam, 13-shape memory alloy cable, 14-dog bone type lower end plate with long groove, 5-1-semi-circular groove one, 5-2-semi-circular groove two, 7-1-left rectangular end plate one, 7-2-right rectangular end plate two, 8-1-semi-circular joint one, 8-2-semi-circular joint two, 9-1-bolt one, 9-2-bolt two, 9-3-bolt three, 11-1-semi-circular raised butt plate one, 11-2-semi-circular raised butt plate two. Detailed Implementation

[0032] The present invention will be further described in detail below with reference to the embodiments.

[0033] like Figure 1 As shown, the present invention discloses a prefabricated resilient PEC recycled concrete beam-column joint with a profiled composite floor slab, comprising a PEC column 1, a recycled concrete floor slab 2, studs 3, a profiled steel sheet 4, a semi-circular groove 5-1, a clamp 6, a rectangular end plate 7-1, a semi-circular joint 8-1, a dog-bone type upper end plate 10, a semi-circular protruding butt plate 11-1, a shape memory alloy cable 13, a dog-bone type lower end plate with a long groove 14, a 10mm diameter bolt 9-1, a 45mm diameter bolt 9-2, and a 25mm diameter bolt 9-3.

[0034] like Figure 2 As shown, PEC column 1 is a steel-concrete composite column with H-beams on the outside and recycled concrete poured on both sides of the web of the H-beams. Pouring recycled concrete at the web can improve the stability of the steel and avoid local instability.

[0035] like Figures 3 to 4 The image shows the composite floor slab portion of the present invention, comprising a profiled steel sheet 4 and a recycled concrete floor slab 2. A certain number of studs 3 are arranged to connect the composite floor slab to the upper flange of the beam. The recycled concrete floor slab 2 is generally rectangular, with a flat rectangle on its upper side and a corrugated distribution on its lower side corresponding to the profiled steel sheet 4.

[0036] like Figures 5 to 8 For the semi-circular node part of the present invention, the semi-circular groove 5-1 is connected to the semi-circular protrusion butt plate 11-1, the rectangular end plate 7-1 is welded to the web of the beam, the shape memory alloy cable 13 is connected by the clamp 6, and the three semi-circular connectors 8-1 welded to the left rectangular end plate 7-1 are connected to the two semi-circular connectors 8-1 welded to the right rectangular end plate 7-2 by bolts 9-2 with a diameter of 45mm.

[0037] like Figure 6 The diagram shows a detailed view of the semi-circular node. On the left and right sides of this node are rectangular end plates 7 welded to the web of the H-beam 12. These end plates facilitate the arrangement of shape memory alloy cables 13 and semi-circular connectors 8. In this node, the groove 5 is the semi-circular groove 1 5-1 and semi-circular groove 2 5-2 extending from the upper and lower flanges on the right side of the short beam. The semi-circular raised connecting plate 11 is the semi-circular raised connecting plate 1 11-1 and semi-circular raised connecting plate 2 11-2 extending from the upper and lower flanges on the left side of the long beam. The semi-circular cross-sectional shape can rotate and dissipate energy under external force and avoid stress concentration.

[0038] like Figure 7 The diagram shows a detailed view of the left side of the semi-circular node. This is the section at the break point on the right side of the short beam. A rectangular end plate 7-1 is welded to the inner side of its web. Three semi-circular joints 8-1 are welded on the rectangular end plate for rotational energy dissipation. Four holes are symmetrically arranged above and below the joints. These holes facilitate the placement of shape memory alloy cables 13.

[0039] like Figure 8 The diagram shows a detailed view of the right side of the semi-circular node. This is the section at the break point on the left side of the long beam. A rectangular end plate 7-2 is welded to the inner side of its web. Two semi-circular joints 8-2 are welded to the rectangular end plate for rotational energy dissipation. A shape memory alloy cable 13 is used to connect the rectangular end plate 7-1 and the rectangular end plate 7-2 to form a whole, and it is anchored by the clamp 6.

[0040] like Figures 9 to 10 The node connection plate of this invention is divided into an upper connection plate and a lower connection plate. The upper dog-bone type upper end plate 10 is connected to the inner end plate of the upper flange of the beam by a 10mm diameter bolt 9-1; the lower slotted dog-bone type lower end plate 14 is connected to the outer side of the lower flange of the beam by a 20mm diameter bolt 9-3.

[0041] This invention discloses a prefabricated tough PEC recycled concrete beam-column joint with a profiled composite floor slab. The PEC column and H-shaped steel beam are connected by welding. This joint has a clear force transmission, and bending moment and shear force can be directly transmitted to the column through the beam. The presence of the composite floor slab increases the strength and stiffness of the joint, effectively improving the load-bearing capacity of the joint.

[0042] The upper and lower beam flanges are joined in a semi-circular manner, which provides a certain degree of rotational capability and clear force transmission, allowing the plastic hinge to be transferred from the beam end to the node. The semi-circular joint design avoids stress concentration at the node, and the presence of the upper and lower dog-bone connecting plates participates in energy dissipation. Under seismic loading, the semi-circular node forms an energy-dissipating section. Under minor earthquakes, energy is dissipated through the rotation of the semi-circular node, and the semi-circular design avoids stress concentration at the contact points during rotation, preventing premature damage. Under moderate earthquakes, the energy dissipation function of the semi-circular node rotation ceases, and energy is dissipated through the tensile deformation of the shape memory alloy cable. Under major earthquakes, the energy dissipation capacity of the shape memory alloy cable increases as it enters the hardening stage, and the plastic deformation of the dog-bone connecting plates in the yielding state further dissipates energy.

[0043] This invention applies to the arrangement of SMA cables for "minor earthquake node rotational energy dissipation, moderate earthquake elasto-plastic energy dissipation, major earthquake overall elasto-plastic energy dissipation, and local plastic energy dissipation," enabling nodes to have a certain self-resetting capability after an earthquake. After an earthquake, based on the damage to the nodes, after inspection and evaluation, if the overall structure is intact, damaged components can be partially disassembled and replaced, allowing the structure to continue operating, thereby reducing post-earthquake repair costs, minimizing economic losses, and meeting post-earthquake structural safety requirements.

[0044] Example: A prefabricated resilient PEC recycled concrete beam-column joint with profiled composite floor slab includes a PEC column 1, a profiled composite floor slab (first assembling the bottom profiled steel sheet 4, then pouring the upper recycled concrete), two dog-bone upper connecting plates, a semi-circular joint, four-strand shape memory alloy cables 13 connecting the semi-circular joint, and a dog-bone lower connecting plate with a long groove below the joint.

[0045] Recycled concrete is poured inside PEC column 1. A semi-circular node is set at a certain distance from the beam-column joint. The H-shaped steel beams 12 are connected by the designed node. Under seismic action, energy is dissipated by the rotation of the node, the yielding of the low yield point soft steel connecting plate, and the tensile deformation of the shape memory alloy (SMA) cable 13. The SMA cable is used to give the node a certain self-resetting ability, reducing the residual displacement after the earthquake.

[0046] The semi-circular node consists of two rectangular end plates 7, five semi-circular joint plates 8, semi-circular grooves 5 extending from the upper and lower flanges on the left side, and semi-circular protrusions extending from the upper and lower flanges on the right side. This allows the plastic hinge to be transferred from the beam-column node to this location. The extended semi-circular grooves 5 and the semi-circular protrusions fit together perfectly, preventing stress concentration at the beam flanges from causing failure when the node rotates. The two rectangular end plates 7 are respectively arranged at the position of the beam web and connected by welding. Four holes are evenly arranged at the end plates for later installation of SMA cables.

[0047] The height of the two rectangular end plates 7 is equal to the height of the beam web. Three semi-circular joint plates 8 are arranged on the left rectangular end plate 7, with the two intervals being the thickness of the two semi-circular joint plates 8. Two semi-circular joint plates 8 are arranged on the right rectangular end plate 7, with the spacing being the thickness of the semi-circular joint plate 8 in the middle of the left side. The semi-circular joint plates 8 are welded to the rectangular end plates 7 and the rectangular end plates 7 are welded to the beam web in the factory. A hole is set through the middle of the five semi-circular joint plates 8 and connected later by high-strength bolts 9 to prevent large deformation of the semi-circular joint plates 8 without affecting the rotation of the nodes.

[0048] Due to the limitations of the composite floor slab, two dog-bone connecting plates are used to connect the lower part of the upper flange of the beam at the semi-circular node. The length of the connecting plate is equal to the length of the extension of the left and right flanges. A dog-bone connecting plate with a long groove is arranged at the lower flange of the beam. The material of the dog-bone connecting plate is low yield point mild steel. When the node rotates, the dog-bone connecting plate will yield and dissipate energy, and the damage will be concentrated in the dog-bone connecting plate. The flange and the dog-bone connecting plate are connected by high-strength bolts 9, which are easy to repair and replace after damage.

[0049] Each shape memory alloy cable 13 consists of 7 bundles of shape memory alloy wires, each with a diameter of 0.885mm. Four shape memory alloy cables 13 are fixed to the outside of the node through the pre-reserved holes in the rectangular end plates 7 on the left and right sides of the semi-circular node. When the node rotates, the shape memory alloy cables undergo tensile deformation to dissipate energy. Even after one or more shape memory alloy cables fail due to tensile deformation, the cable can still continue to work and dissipate energy. Due to the material properties of the shape memory alloy cables, the node has a certain self-resetting ability after the external force is unloaded, which can effectively reduce residual displacement and damage at the node.

[0050] Bolt holes are pre-drilled at the upper flange and corrugated steel plate of H-beam 12, and the two are connected by high-strength bolts 9. Flexible material (3mm thick rubber pads are placed between the beam and the plate to allow for small relative deformation between the beam and the plate) is filled around the stud 3 section. The corrugated steel plate is made of Q235 steel. The floor slab is a composite floor slab formed by profiled corrugated steel plate and recycled concrete. The corrugated steel plate is used as a formwork for pouring concrete floor slab, reducing the formwork erection and dismantling construction process and adapting to the requirements of prefabricated construction.

[0051] PEC column 1 is an H-beam with recycled concrete poured into the web. This effectively inhibits the local instability and failure of the H-beam column under pressure, thereby improving the column's load-bearing capacity. Recycled concrete is made by reusing and reprocessing waste building materials and concrete, which can effectively reduce the pollution of construction waste to the environment and help protect the ecological environment. At the same time, recycled concrete has low raw material costs and is simple to prepare, which can save manufacturing costs.

[0052] A cross-section consisting of 7 bundles of 0.885mm diameter SMA cables is placed in each of the holes in the semi-circular node steel plate. The SMA cables are arranged from the left steel plate of the disconnected beam to the right steel plate of the disconnected beam. The dog-bone connection plates above and below the flange of the semi-circular node beam are made of low yield point steel. The upper and lower dog-bone connection plates of the semi-circular node are connected by 9 high-strength bolts. The concrete in the PEC column 1 and the concrete in the composite floor slab are both recycled concrete. The three sections of studs between the slab and the beam are filled with flexible material (a 3mm thick rubber pad is placed between the beam and the slab to allow relative deformation between the beam and the slab).

[0053] The force transmission mechanism of the beam-column joint is clearly defined. Under seismic action, energy is dissipated through three mechanisms: rotational deformation of the joint, yielding of the dog-bone connecting plate, and tensile deformation of the SMA cable. The joint adopts a semi-circular connecting plate and a semi-circular groove 5 to avoid stress concentration at the joint when it rotates. The material properties of the SMA cable are fully utilized to give the joint a certain self-resetting ability, thereby reducing structural damage, post-earthquake residual displacement, and post-earthquake repair costs.

[0054] A method for using prefabricated resilient PEC recycled concrete beam-column joints with profiled composite floor slabs includes the following steps: The PEC column 1 and the H-beam 12 are connected by welding. A rectangular end plate 7 is welded to the web of each side of the disconnected beam. The semi-circular joint is connected with high-strength bolts 9 with a diameter of 45mm. The upper part of this joint is butted with a semi-circular groove 5. Both the upper and lower parts of this joint are connected with low yield point dog bone type connecting plates. The composite floor slab is connected to the H-beam 12 with studs 3, and flexible material is filled between the slab and the beam.

[0055] The PEC column 1 is welded to the H-beam 12 on the left side of the semi-circular node. The semi-circular grooves 5 extending from the upper and lower flanges on the left and the semi-circular protrusions extending from the upper and lower flanges on the right are connected to the plates 11. The extended semi-circular grooves 5 and the semi-circular protrusions fit together perfectly. Two dog-bone type connecting plates are connected at the lower part of the upper flange using high-strength bolts 9. A rectangular end plate 7 is welded to the web of each of the left and right H-beams 12. Three semi-circular joints 8 are arranged on the left rectangular end plate 7, with the distance between the two semi-circular joints 8 being the thickness of the two semi-circular joints 8 on the right. The distance between the two semi-circular joints 8 on the right rectangular end plate 7 is the thickness of the semi-circular joint 8 in the middle of the left. The semi-circular joints 8 are connected to the rectangular end plate 12. End plate 7 and rectangular end plate 7 are welded to the beam web in the factory. A bolt hole is set through the middle of the five semi-circular joints 8, and high-strength bolts 9 are used for later connection. Four holes are opened in the middle of the rectangular end plates 7 on the left and right sides respectively. Four SMA cables are anchored to the outside of the end plate through the holes using anchors. A dog bone type connecting plate with a rectangular groove in the middle is connected to the lower part of the flange of the H-beam 12 using high-strength bolts 9. Bolt holes are reserved on the upper flange of the H-beam 12. The corrugated steel floor slab is bolted to the H-beam 12 on the construction site using high-strength bolts 9. The profiled steel sheet 4 is used as the bottom formwork for the upper recycled concrete floor slab 2. Recycled concrete is poured to form the recycled concrete floor slab 2.

[0056] In a prefabricated tough PEC recycled concrete beam-column joint with a profiled composite floor slab, all steel components are prefabricated in the factory and assembled on site; the recycled concrete on the upper layer of the profiled composite floor slab is poured on site; the rectangular end plate 7 and the semi-circular connecting plate in the semi-circular joint are fabricated and welded into a whole in the factory according to the given dimensions.

[0057] Under minor earthquakes, energy is dissipated through the rotation of each semi-circular node. The semi-circular design avoids stress concentration at the contact points during rotation, preventing premature damage. Under moderate earthquakes, the rotation of each semi-circular node dissipates energy and the energy is dissipated by the tensile deformation of the four SMA cables. Under major earthquakes, the energy dissipation capacity of the four SMA cables increases as they enter the hardening stage, and the upper and lower dog-bone connecting plates undergo plastic deformation as they yield. Both processes contribute to energy dissipation. Even if one or more SMA cables fail during the energy dissipation process, the cables can still continue to dissipate energy. The use of SMA cables gives the nodes a certain self-resetting ability, reducing the residual displacement of the structure. Under major earthquakes, damage is concentrated on the dog-bone connecting plates. Later, by replacing the dog-bone connecting plates, the structure can be restored to its functional state as quickly as possible.

[0058] The SMA cable has a cross-section consisting of 7 strands, each 0.885mm in diameter. Each cable comprises 7 SMA bundles, with a central core bundle and the remaining six bundles wound in a right-hand spiral around the core bundle at a 15° upward spiral angle. The SMA cable is inserted into the anchor cavity, ensuring sufficient extension at the end. A clamping head is placed on the end of the SMA cable, and mechanical pressure is used to tighten the clamping head to constrain the cable. The SMA cable with the clamping head is then placed inside the anchor cavity and positioned on the mounting platform. A clamping screw is inserted and tightened using a hex wrench to secure the clamping head and prevent it from loosening. All of these steps can be pre-completed at the factory.

Claims

1. A fabricated ductile PEC-recycled concrete beam-column joint with a composite floor slab under compression, characterized by The structure includes a PEC column (1), and from top to bottom on the right side of the PEC column (1) are a recycled concrete floor slab (2), a profiled steel sheet (4), a semi-circular groove (5), a clamp (6), a rectangular end plate (7), a semi-circular joint (8), a high-strength bolt (9), a dog-bone type upper end plate (10), a semi-circular protruding butt plate (11), and an H-beam (12). The H-shaped steel beam (12) is formed by upper and lower flanges and a middle web. The H-shaped steel beam (12) is divided into two parts: one part is a short beam welded to the right side of the PEC column (1) steel, and the other part is a long beam away from the right side of the PEC column (1) steel. The semi-circular groove (5) includes a semi-circular groove one (5-1) and a semi-circular groove two (5-2). The semi-circular groove one (5-1) and the semi-circular groove two (5-2) are provided at the upper and lower flanges on the right side of the short beam at the break point. The semi-circular protruding connecting plate (11) includes a semi-circular protruding connecting plate one (11-1) and a semi-circular protruding connecting plate two (11-2). The semi-circular protruding connecting plate one (11-1) and the semi-circular protruding connecting plate two (11-2) are provided at the upper and lower flanges on the left side of the long beam. The semi-circular groove and the semi-circular protruding connecting plate are connected. The rectangular end plate (7) includes rectangular end plate one (7-1) and rectangular end plate two (7-2). Rectangular end plate one (7-1) is located on the right side of the short beam and is connected to the web plate. Rectangular end plate two (7-2) is located on the left side of the long beam and is connected to the web plate. The rectangular end plate has four holes arranged in the middle for placing shape memory alloy cables (13) and connecting them through clamps (6). The semi-circular joint (8) includes a semi-circular joint one (8-1) and a semi-circular joint two (8-2), and the high-strength bolt (9) includes a bolt one (9-1), a bolt two (9-2), and a bolt three (9-3); the semi-circular joint one (8-1) is located in the middle of the rectangular end plate one (7-1), and the semi-circular joint two (8-2) is located in the middle of the rectangular end plate two (7-2); holes are arranged in the middle of the semi-circular joint one (8-1) and the semi-circular joint two (8-2), and the two are connected by bolt two (9-2) after splicing; the dog bone type upper end plate (10) is connected to the inner side of the upper flange at the break between the short beam and the long beam by bolt one (9-1); the dog bone type lower end plate (14) with long groove is connected to the outer side of the lower flange at the break between the short beam and the long beam by bolt three (9-3); The dog bone type upper end plate (10) is composed of two smaller dog bone type connecting plates. The middle of each small dog bone type connecting plate is weakened into an arc shape and four bolt holes are symmetrically arranged on the left and right sides of each small dog bone type connecting plate. The middle of the grooved dog bone type lower end plate (14) is weakened into an arc shape and three rectangular grooves are opened in the middle. The local weakening makes the damage concentrated on the grooved dog bone type lower end plate (14). Eight bolt holes are symmetrically arranged on the left and right sides of the grooved dog bone type lower end plate (14).

2. A fabricated ductile PEC-recycled concrete beam-column joint with compressive form composite floor slab according to claim 1, characterized in that, The recycled concrete floor slab (2) is generally rectangular, with a flat rectangle on the upper side and a corrugated steel sheet (4) on the lower side. The upper and lower flanges of the corrugated steel sheet (4) have the same width, and the inner web is arranged in an inclined manner with a corrugated distribution.

3. A fabricated ductile PEC-recycled concrete beam-column joint with compressive form composite floor slab according to claim 2, characterized in that, Three semicircular connectors (8-1) are arranged, and two semicircular connectors (8-2) are arranged.

4. The fabricated ductile PEC-recycled concrete beam-column joint with compressive form composite floor slab according to claim 3, characterized in that, The PEC column (1) and the H-beam (12) are connected by welding, and the concrete inside the PEC column (1) is recycled concrete.

5. A fabricated ductile PEC-recycled concrete beam-column joint with compressive form composite floor slab according to claim 4, characterized in that, The recycled concrete floor slab (2) and the profiled steel sheet (4) form a composite floor slab. The recycled concrete floor slab (2) and the profiled steel sheet (4) are connected to the upper flange of the beam by studs (3). The recycled concrete floor slab (2) is made of recycled concrete.

6. The prefabricated tough PEC recycled concrete beam-column joint with a profiled composite floor slab according to claim 5, characterized in that, Rectangular end plate one (7-1) is located on the right side of the short beam and is welded to the web plate. Rectangular end plate two (7-2) is located on the left side of the long beam and is welded to the web plate. There are four holes arranged in the middle of each end plate. Multiple shape memory alloy cables (13) are placed in the hole and connected by a clamp (6).

7. The method of using the prefabricated tough PEC recycled concrete beam-column joint with a profiled composite floor slab as described in claim 6, characterized in that, Includes the following steps: The PEC column (1) and the H-beam (12) are connected by welding. A rectangular end plate (7) is welded to the web of the disconnected H-beam (12) on both sides. The semi-circular joints (8) on both sides are connected by bolts (9-2). The upper and lower flanges of the beam at this node are connected by semi-circular grooves (5) and semi-circular protruding butt plates (11). The upper and lower parts of this node are connected by dog ​​bone upper end plates (10) and dog bone lower end plates with long grooves (14). The composite floor slab is connected to the H-beam (12) by studs (3), and flexible material is filled between the slab and the beam. The PEC column (1) is welded to the left side of the broken short beam. The semi-circular groove (5) extending from the upper and lower flanges of the short beam and the semi-circular protrusion butt plate (11) extending from the upper and lower flanges of the long beam fit together perfectly. At the break point, the lower part of the upper flange of the beam is connected to the dog-bone type upper end plate (10) using bolt 1 (9-1). A rectangular end plate (7) is welded to the web of the right side of the short beam and the left side of the long beam. Three semi-circular joints (8) are arranged on the rectangular end plate (7) of the right side of the short beam, with a spacing of one semi-circular joint (8) between them. Two semi-circular joints (8) are arranged on the rectangular end plate (7) of the left side of the long beam, with a spacing of one semi-circular joint (8) between them. The semi-circular joints (8) are connected to the rectangular end plate (7) and the rectangular end plate (8). The end plate (7) and the beam web are welded together in the factory. A bolt hole is set through the middle of the five semi-circular joints (8) and connected by bolt two (9-2). Four holes are opened in the middle of the rectangular end plates (7) on the left and right sides respectively. Four strands of SMA shape memory alloy cable (13) are anchored to the outside of the rectangular end plate through the holes using clamp (6). A dog bone type lower end plate (14) with long groove is connected to the lower flange of the disconnected beam using bolt three (9-3). The profiled steel sheet (4) is bolted to the H-shaped steel beam (12) through studs (3) on the upper flange of the H-shaped steel beam (12). The profiled steel sheet (4) is used as the bottom formwork for the upper recycled concrete floor slab (2) to pour recycled concrete to form the recycled concrete floor slab (2).