Process for the preparation of urea solution for thermal power plants

By adjusting the hydrophobic rinsing time and concentration using a controller, the problems of high ammonia content and crystallization in the preparation of urea solution in thermal power plants were solved, achieving low-cost and high-efficiency urea solution preparation and improving the reliability of equipment operation and transportation efficiency.

CN118356865BActive Publication Date: 2026-11-24SHANGHAI HUADIAN ELECTRIC POWER DEV CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410536352.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-04-30
Publication Date
2026-11-24
Estimated Expiration
2044-04-30

AI Technical Summary

Technical Problem

The existing process of preparing urea solution in thermal power plants has problems such as high ammonia content leading to crystallization and pipeline corrosion and blockage, and the transportation efficiency of 50% urea solution is low and the economy is poor.

Method used

By adjusting the hydrophobic rinsing time and concentration using a controller, a urea solution with a concentration of less than 50% can be prepared, reducing the ammonia content and crystallization temperature. The efficient preparation of urea solution is achieved by using a PLC logic controller and multiple parallel pipelines.

Benefits of technology

It reduces the crystallization temperature of urea solution and pipeline corrosion and blockage, improves the reliability of environmental parameter adjustments for the unit, reduces the workload of operation and maintenance, and saves transportation costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118356865B_ABST
    Figure CN118356865B_ABST
Patent Text Reader

Abstract

This invention discloses a method for preparing urea solution in a thermal power plant. The preparation equipment includes a urea dissolving tank, a urea storage tank, a drain pipe, at least one outlet branch pipe, a urea storage main pipe, and a drain flushing pipe. The urea storage main pipe is equipped with a main inlet valve for the storage tank. It also includes a controller. The preparation method includes: after the urea dissolving pump stops operating, the controller executes the following control strategy: adjusting the drain flushing time of the pipeline from the inlet of the urea dissolving pump to the urea storage tank according to the required concentration of the urea solution, with the time increasing as the required urea concentration decreases. Through control logic adjustment, the urea solution concentration is configured to be below 50% by mass, thereby reducing the ammonia content in the product gas, lowering the crystallization temperature of the urea solution, reducing pipeline crystallization, corrosion, and blockage, improving the reliability of environmental parameter adjustments for the unit, and correspondingly reducing the workload of operation and maintenance.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of power plant urea solution production technology, and relates to a method for preparing urea solution for thermal power plants. Background Technology

[0002] Currently, our plant uses urea granules for urea solution preparation. The urea granules are unloaded from tank trucks into a urea dissolving tank. Steam heating maintains the solution temperature between 40℃ and 50℃ (above the crystallization temperature). The condensate from this steam is pumped to the dissolving tank as a hot water source for the solution, thus producing a 50% mass concentration urea solution. This solution is then pumped to a urea solution storage tank, completing the urea solution preparation. After urea solution preparation, the pipelines need to be flushed to prevent corrosion and blockage. A urea transfer pump delivers the 50% mass concentration urea solution to the urea hydrolyzer. Saturated steam, after desuperheating and depressurization, heats the urea solution through a heat exchange coil built into the hydrolyzer. Under conditions of 130–145℃ and approximately 0.3–0.6 MPa, the urea solution undergoes a rapid hydrolysis reaction with the aid of a catalyst, producing a mixture of ammonia, carbon dioxide, and water vapor. This mixture is separated by a steam-water separator at the top of the hydrolyzer, and the final product, ammonia, is output. However, in actual production, on the one hand, due to the high ammonia content in the product gas of 50% urea solution, the crystallization temperature of the urea solution and product gas is high, resulting in severe crystallization and pipeline corrosion and blockage. On the other hand, because the product gas produced by the hydrolysis of 50% urea solution also has a high ammonia content, and the crystallization temperature of this ammonia is high, with a small temperature difference compared to the normal operating temperature of the system, it crystallizes more easily than at lower crystallization temperatures. Similarly, 50% urea solution also suffers from a high crystallization temperature and is prone to crystallization during operation, seriously affecting the unit's environmental parameter adjustment requirements and significantly increasing the workload of operation and maintenance. The urea solution preparation process is limited by the capacity of the urea dissolving tank and the tanker truck; a single tanker truck has a full load capacity of 25 tons, and the urea dissolving tank has a capacity of 55 m³. Under existing conditions, if it is necessary to prepare a urea solution with a mass concentration below 50%, the simplest way is to reduce the mass of urea, but this wastes transportation costs and is not economically viable. This invention addresses this issue. Summary of the Invention

[0003] The purpose of this invention is to provide a method for preparing urea solution for thermal power plants.

[0004] The technical solution of this invention is: a method for preparing urea solution for a thermal power plant, the preparation equipment including a urea dissolving tank, a urea storage tank for storing urea of ​​the required concentration, a condensate drain pipe connected to the condensate drain inlet of the urea dissolving tank, at least one outlet branch pipe connected to the outlet end of the urea dissolving tank, a urea storage main pipe connected to the outlet end of the outlet branch pipe and the inlet end of the urea storage tank, and a condensate flushing pipe with one end connected to the condensate drain pipe and the other end connected to the outlet branch pipe; the urea dissolving tank is equipped with a stirring device and a heating device, and a urea dissolving inlet valve, a urea dissolving pump, and a urea dissolving outlet valve are sequentially arranged along the outlet direction on any of the outlet branch pipes, and any of the condensate flushing pipes is connected to its corresponding outlet branch pipe and located opposite to the outlet branch pipe. The equipment includes a urea dissolving inlet valve and a urea dissolving pump, and a condensate flushing valve on any of the condensate flushing pipes. A storage tank inlet valve is provided on the urea storage main pipe, and a condensate inlet valve is provided on the condensate pipe near the condensate inlet of the urea dissolving tank. The preparation equipment also includes a controller electrically connected to the stirring device, heating device, urea dissolving inlet valve, urea dissolving pump, urea dissolving outlet valve, condensate inlet valve, condensate flushing valve, and storage tank inlet valve. The preparation method includes: after the urea dissolving pump stops operating, the controller controls the execution of the following control strategy: adjusting the condensate flushing time of the pipeline from the urea dissolving pump inlet to the urea storage tank according to the required concentration of the urea solution to be prepared, with the time increasing as the required urea concentration decreases.

[0005] Preferably, the connection circuit between the controller and the main inlet valve of the storage tank is further provided with a timer, so that when preparing a urea solution of a corresponding concentration, the main inlet valve of the storage tank is delayed for a corresponding duration by the timer.

[0006] Preferably, the control strategy for adjusting the hydrophobic flushing time of the pipeline from the inlet of the urea dissolving pump to the urea storage tank according to the required concentration of the urea solution to be prepared is as follows: When the concentration of the urea solution to be prepared is 50%, the main inlet valve of the storage tank is delayed for 3 minutes; When the concentration of the urea solution to be prepared is 45%, the main inlet valve of the storage tank is delayed for 10 minutes; When the concentration of the urea solution to be prepared is 40%, the main inlet valve of the storage tank is delayed for 20 minutes.

[0007] Preferably, the controller is a PLC logic controller, and its control panel is equipped with multiple urea solution concentration selection buttons corresponding to different concentrations and an input button. When preparing any desired concentration of urea solution, the corresponding urea solution concentration selection button is selected first, and then the input button is selected. After that, the controller controls the main inlet valve of the storage tank to execute the corresponding control strategy.

[0008] Preferably, the controller only allows the main inlet valve of the storage tank to open after both the concentration selection button and the injection button for the corresponding urea solution are selected.

[0009] Preferably, the control panel is also provided with a cut-off button. When the urea solution concentration selection button has been selected and / or the input button has not been selected or has been selected, the other urea solution concentration selection buttons can be switched by selecting the cut-off button.

[0010] Preferably, a reflux pipe connected to the urea storage manifold at the inlet end of the main urea inlet valve of the storage tank is also provided with a reflux pipe connected to the reflux port of the urea dissolving tank, and a reflux valve is also provided on the reflux pipe.

[0011] Preferably, there are two liquid outlet branch pipes and two hydrophobic flushing pipes, with the two liquid outlet branch pipes connected in parallel and the two hydrophobic flushing pipes connected in parallel.

[0012] Preferably, the inlet end of the drain pipe is connected to the outlet end of the drain tank, the inlet end of the drain tank is connected to the drain outlet pipe at the drain outlet of the urea dissolving tank, the drain outlet is connected to the condensate outlet end of the heating device, and a drain valve is provided on the drain outlet pipe.

[0013] The beneficial effects of this invention are: The present invention provides a method for preparing urea solution in thermal power plants. By adjusting control logic, the concentration of the urea solution is configured to be below 50% by mass, thereby reducing the ammonia content in the product gas, lowering the crystallization temperature of the urea solution, reducing pipeline crystallization, corrosion, and blockage, improving the reliability of environmental parameter adjustments for the unit, and correspondingly reducing the workload of operation and maintenance. The present invention can also increase the body temperature of the hydrolyzer, from 130℃ to 140℃ under the same operating conditions, allowing for a more complete urea hydrolysis reaction. Attached Figure Description

[0014] The present invention will be further described below with reference to the accompanying drawings and embodiments: Figure 1 This is a flowchart of the equipment for preparing urea solution according to an embodiment of the present invention; Figure 2 This is a logic control diagram of the controller in an embodiment of the invention; Figure 3 This is a schematic diagram of the control panel of the controller according to an embodiment of the present invention. Detailed Implementation

[0015] This invention provides a method for preparing urea solution for thermal power plants, in conjunction with reference to [reference needed]. Figures 1 to 3 , among which Figure 1As shown, the equipment for preparing urea solution includes a urea dissolving tank 10, a urea storage tank (not shown) for storing urea of ​​the required concentration, a hydrophobic pipe 60 connected to the hydrophobic inlet (not shown) of the urea dissolving tank 10, at least one outlet branch pipe 20 connected to the outlet end of the urea dissolving tank 10, a urea storage main pipe 40 connected to the outlet end of the outlet branch pipe 20 and the inlet end of the urea storage tank, and a hydrophobic flushing pipe 70 with one end connected to the hydrophobic pipe 60 and the other end connected to the outlet branch pipe 20. The urea dissolving tank 10 is equipped with a stirring device 12 and a heating device 11. A urea dissolving inlet valve 21, a urea dissolving pump 30, and a urea dissolving outlet valve 22 are sequentially arranged along the outlet direction on any of the outlet branch pipes 20. A condensate flushing pipe 70 is connected to its corresponding outlet branch pipe 20 and located between the corresponding urea dissolving inlet valve 21 and the urea dissolving pump 30. A condensate flushing valve 71 is installed on any of the condensate flushing pipes 70. A storage tank inlet valve 50 is installed on the urea storage main pipe 40. A condensate inlet valve 61 is installed on the condensate drain pipe 60 near the condensate inlet of the urea dissolving tank 10. The preparation equipment also includes a controller 100 electrically connected to the stirring device 12, the heating device 11, the urea dissolving inlet valve 21, the urea dissolving pump 30, the urea dissolving outlet valve 22, the condensate inlet valve 61, the condensate flushing valve 71, and the storage tank inlet valve 50. It should be noted that the concentration of the urea solution prepared in the urea dissolving tank 10 is not less than 50%. The urea solution in the urea dissolving tank 10, after passing through the outlet branch pipe 20 and the urea dissolving pump 30, mixes with the hydrophobic material in the condensate drain pipe 60 and the condensate flushing pipe 70 to prepare a urea solution with a concentration of less than 50%, such as 40% or 45%. This can reduce the problems of high ammonia content, high crystallization temperature, easy crystallization, corrosion and pipeline blockage caused by urea concentrations above 50%, thereby reducing maintenance workload and costs.

[0016] When preparing urea solutions of different concentrations, it is necessary to solve the problem of controlling the amount of hydrophobicity to achieve the desired concentration of urea solution. In this embodiment of the invention, after the urea solution preparation is completed and the urea dissolving pump 30 stops running, the controller 100 executes the following control strategy to achieve this, specifically as follows: the hydrophobic flushing time of the pipeline between the inlet of the urea dissolving pump 30 and the urea storage tank is adjusted according to the desired concentration of urea solution, and the time is extended as the desired concentration of urea decreases.

[0017] More specifically, as follows: when the concentration of the urea solution to be prepared is 50%, the main inlet valve of the storage tank is fully opened and kept open for 3 minutes. When the required concentration of the urea solution to be prepared is 45%, the main inlet valve of the storage tank is fully opened and kept open for 10 minutes. When the required concentration of the urea solution to be prepared is 40%, the main inlet valve 50 of the storage tank is fully open and remains open for 20 minutes. It should be noted that the concentration mentioned above refers to mass concentration. Furthermore, the connection circuit between the controller 100 and the main inlet valve 50 of the storage tank is also equipped with a timer (not shown). When preparing a urea solution of the corresponding concentration, the timer causes the main inlet valve 50 of the storage tank to delay for the corresponding duration. Specifically, when the required concentration of the urea solution to be prepared is 50%, after the main inlet valve 50 of the storage tank is selected from both the corresponding concentration selection button and the inlet button, and the main inlet valve 50 is allowed to open, a 3-minute delay occurs. When the required concentration of the urea solution to be prepared is 45%, the main inlet valve 50 of the storage tank is delayed for 10 minutes; When the required concentration of the urea solution to be prepared is 40%, the main inlet valve 50 of the storage tank is delayed for 20 minutes. This delay time ensures sufficient condensation in the pipeline to achieve the desired concentration of urea solution. This method is simple and effectively lowers the crystallization temperature of the urea solution, preventing pipeline crystallization, corrosion, and blockage, improving the reliability of environmental parameter adjustments for the unit, and correspondingly reducing the workload of operation and maintenance.

[0018] According to some preferred embodiments of the present invention, such as Figure 2 and Figure 3 As shown, the controller 100 in this embodiment of the invention is a PLC logic controller, and its control panel is provided with multiple urea solution concentration selection buttons corresponding to different concentrations (exemplary, such as...). Figure 3 The diagram shows three concentration selection buttons: a 50% urea solution selection button 110, a 45% urea solution selection button 120, and a 40% urea solution selection button 130. (In practice, those skilled in the art can choose to design other numbers of selection buttons, such as more than three concentration selection buttons, according to actual needs.) It also includes an input button 140. Figure 2 The control logic principle shown is as follows: when the desired urea solution concentration is determined, the corresponding urea solution concentration selection button is selected first, followed by the input button. Only then does the controller execute the corresponding control strategy. The input button 140 is designed to prevent accidental operation, ensuring that the operator selects the wrong concentration selection button, thus saving time and preventing the preparation of the desired urea solution. More specifically, when the operator wants to prepare a 40% urea solution, they first select the 40% urea solution selection button 130 on the control panel, and then select the input button 140. After that, the controller 100 continues to the next step, specifically controlling the storage tank inlet valve 50 to open and remain open for 20 minutes. In other words, the controller 100 only allows the storage tank inlet valve 50 to open after both the corresponding urea solution concentration selection button and the input button 140 have been selected. Figure 2The control logic diagram shown indicates that the urea storage tank inlet valve 50 is fully open. This design aims to prevent the urea storage tank inlet valve 50 from opening before the concentration selection button is engaged (i.e., both the concentration selection and inlet buttons are not selected), which would lead to inaccurate timing of the urea solution preparation and consequently, inaccurate concentration of the final prepared urea solution. It should be noted that the execution time of the urea storage tank inlet valve 50 corresponding to the preparation of different concentrations of urea solution in the above control strategy begins timing after the urea storage tank inlet valve 50 is fully open.

[0019] More preferably, such as Figure 3 As shown, the control panel also includes a cut-off button 150. When the urea solution concentration selection button is already selected, and / or the input button 140 is either not selected or already selected (that is, it doesn't matter whether the input button 140 is selected or not, as long as the controller 100 has not yet executed the corresponding control strategy, i.e., it has not yet controlled the storage tank inlet valve 50 to be fully open), selecting the cut-off button 150 allows switching between other urea solution concentration selection buttons. In other words, if the operator intends to prepare a 50% urea solution 110, but mistakenly selects the 40% urea solution concentration selection button 130, or if the operator initially intended to prepare a 50% urea solution and indeed selected the 50% urea solution concentration selection button 110, but later receives a notification to prepare a 40% urea solution, then only the cut-off button 150 needs to be selected, followed by the desired urea solution concentration selection button, and then the input button.

[0020] According to some preferred embodiments of the present invention, such as Figure 1 As shown, a return pipe 80, which is connected to the return port (not shown) of the urea dissolving tank 10, is also connected to the urea storage manifold 40 at the inlet end of the storage tank inlet valve 50. A return valve 81 is also provided on the return pipe 80. The return valve 81 is configured such that when the storage tank inlet valve 50 is closed after the corresponding control strategy is executed, the controller 100 controls the return valve 81 to open, so that the excess urea solution in the pipeline flows back into the urea dissolving tank 10 through the return pipe 80.

[0021] According to some preferred embodiments of the present invention, such as Figure 1 As shown, there are two outlet branch pipes 20 and two hydrophobic flushing pipes 70, with the two outlet branch pipes 20 and the two hydrophobic flushing pipes 70 connected in parallel. By arranging multiple outlet branch pipes 20 and multiple hydrophobic flushing pipes 70 in parallel, with one end connected to the hydrophobic pipe 60 and the other end connected to the corresponding outlet branch pipe 20, the preparation efficiency of urea solution can be improved.

[0022] It should be noted that a condensate pump (not shown) is installed on the condensate drain pipe 60, which pumps water from the condensate tank to the condensate flushing pipe 70 and / or the urea dissolving tank 10. This achieves flushing of the storage main pipe 40 and the urea dissolving tank 10.

[0023] According to some preferred embodiments of the present invention, such as Figure 1 As shown, the inlet end of the drain pipe 60 is connected to the outlet end of the drain tank (not shown), and the inlet end of the drain tank is connected to the drain outlet pipe 90 at the drain outlet (not shown) of the urea dissolving tank 10. The drain outlet is connected to the condensate outlet end (not shown) of the heating device 11. A drain valve 91 is provided on the drain outlet pipe 90. Using the water generated by the condensation of steam from the heating device 11 (heating coil) as the water source for drain rinsing and for dissolving urea in the urea dissolving tank 10 can save energy and reduce costs. It should be noted that, in this embodiment of the invention, the urea dissolving tank 10 also has a urea inlet (not shown) on one side of its top, i.e., on one side of the urea dissolving tank 10... Figure 1 The left side shown also includes a lifting device (not shown) for raising urea to the urea inlet (not labeled) and feeding it into the urea dissolving tank 10. In addition, the urea dissolving tank 10 is connected to other components such as an ammonia steam header (not labeled), a demineralized water header (not labeled), a water source pipe for dissolving urea (not labeled), a miscellaneous gas pipe (not labeled), a dilution recovery tank (not labeled), a dilution recovery pipe (not labeled), and corresponding switching valves on the aforementioned pipes, as well as an exhaust fan (not labeled) and a urea discharge valve (not labeled) connected to the urea dissolving tank 10, etc.

[0024] In the urea solution preparation method of this embodiment of the invention, urea granules are first transported to the lifting device of the urea dissolving tank 10 using a urea granule tanker truck. The lifting device then lifts the urea granules and sends them into the urea dissolving tank 10. Water is added, and the heating device 11 and stirring device 12 are turned on to dissolve the urea granules in the urea dissolving tank 10 to prepare a urea solution with a mass concentration of not less than 50% (preferably 50% in this embodiment of the invention). The urea dissolving pump 30 is then turned on to pump the urea solution to the urea storage tank, and then the pumping is stopped. The operation of the urea dissolving pump 30 involves selecting the desired urea solution concentration on the control panel and then selecting the input button 140. The controller 100 then opens the main inlet valve 50 of the storage tank and executes a corresponding control strategy. This controls the amount of condensate entering the urea dissolving pump 30 inlet via the condensate flushing pipe 70, leading to the urea storage main pipe 40 or the urea storage tank. After the required duration, the main inlet valve 50 of the storage tank is closed, completing the preparation process and yielding the desired urea solution concentration below 50%. Excess condensate is returned to the urea dissolving tank 10 via the return pipe 80. This embodiment of the invention, through control logic adjustment, achieves a urea solution concentration below 50% without altering the existing single-vehicle transport capacity, urea dissolving tank capacity, or preparation process flow. This reduces the ammonia content in the product gas, lowers the crystallization temperature of the urea solution, reduces pipeline crystallization, corrosion, and blockage, improves the reliability of environmental parameter adjustments, and correspondingly reduces the workload of operation and maintenance. This invention can also increase the body temperature of the hydrolyzer, raising it from 130℃ to 140℃ under the same operating conditions, allowing the urea hydrolysis reaction to be more complete. The urea solution prepared in this embodiment can be sent to the urea hydrolyzer (not shown) via a urea transfer pump (not shown). The saturated steam, after being depressurized and cooled, heats the urea solution through a heat exchange plate (not shown) built into the urea hydrolyzer. The urea solution undergoes a hydrolysis reaction with a catalyst at a temperature of 130~145℃ and a pressure of approximately 0.3~0.6MPa, producing a mixture of ammonia, carbon dioxide, and water vapor. This mixture is then separated by a steam-water separator (not shown) at the top of the hydrolyzer, outputting the final product, ammonia.

[0025] The sequence numbers of the embodiments in this application are for descriptive purposes only and do not represent the superiority or inferiority of the embodiments.

[0026] The above description is only a preferred embodiment of this application and is not intended to limit this application. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of this application should be included within the protection scope of this application.

Claims

1. A method for preparing urea solution for a thermal power plant, characterized in that, The preparation equipment includes a urea dissolving tank, a urea storage tank for storing urea of ​​the required concentration, a hydrophobic pipe connected to the hydrophobic inlet of the urea dissolving tank, at least one outlet branch pipe connected to the outlet end of the urea dissolving tank, a urea storage main pipe connected to the outlet end of the outlet branch pipe and the inlet end of the urea storage tank, and a hydrophobic flushing pipe with one end connected to the hydrophobic pipe and the other end connected to the outlet branch pipe. The urea dissolving tank is equipped with a stirring device and a heating device. A urea dissolving inlet valve, a urea dissolving pump, and a urea dissolving outlet valve are sequentially arranged along the outlet direction on any of the outlet branch pipes. Each of the hydrophobic flushing pipes is connected to its corresponding outlet branch pipe and is located between the corresponding urea dissolving inlet valve and the urea dissolving... A condensate flushing valve is provided between the pumps and on any condensate flushing pipe; a storage tank inlet valve is provided on the urea storage main pipe; and a condensate inlet valve is provided on the condensate pipe near the condensate inlet of the urea dissolving tank. The preparation equipment also includes a controller electrically connected to the stirring device, heating device, urea dissolving inlet valve, urea dissolving pump, urea dissolving outlet valve, condensate inlet valve, condensate flushing valve, and storage tank inlet valve. The preparation method includes: after the urea dissolving pump stops running, the controller controls the execution of the following control strategy: adjusting the condensate flushing time of the pipeline from the inlet of the urea dissolving pump to the urea storage tank according to the concentration of the urea solution to be prepared, and extending the time as the concentration of the urea to be prepared decreases.

2. The method for preparing urea solution for thermal power plants according to claim 1, characterized in that, The controller is also equipped with a timer on the connection circuit between the controller and the main inlet valve of the storage tank. When preparing a urea solution of a corresponding concentration, the timer causes the main inlet valve of the storage tank to delay for a corresponding duration.

3. The method for preparing urea solution for thermal power plants according to claim 2, characterized in that, The control strategy for adjusting the hydrophobic flushing time of the pipeline between the inlet of the urea dissolving pump and the urea storage tank according to the required concentration of the urea solution is as follows: When the concentration of the urea solution to be prepared is 50%, the main inlet valve of the storage tank is delayed for 3 minutes; When the concentration of the urea solution to be prepared is 45%, the main inlet valve of the storage tank is delayed for 10 minutes; When the concentration of the urea solution to be prepared is 40%, the main inlet valve of the storage tank is delayed for 20 minutes.

4. The method for preparing urea solution for thermal power plants according to claim 3, characterized in that, The controller is a PLC logic controller. Its control panel has multiple urea solution concentration selection buttons corresponding to different concentrations and an input button. When preparing any desired concentration of urea solution, first select the corresponding urea solution concentration selection button, then select the input button. After that, the controller controls the main inlet valve of the storage tank to execute the corresponding control strategy.

5. The method for preparing urea solution for thermal power plants according to claim 4, characterized in that, The controller only allows the main inlet valve of the storage tank to open after both the concentration selection button and the injection button for the corresponding urea solution are selected.

6. The method for preparing urea solution for thermal power plants according to claim 4, characterized in that, The control panel is also equipped with a cut-off button. When the urea solution concentration selection button has been selected, and / or the input button has not been selected or has been selected, the other urea solution concentration selection buttons can be switched by selecting the cut-off button.

7. The method for preparing urea solution for thermal power plants according to claim 1, characterized in that, A reflux pipe is also connected to the urea storage manifold at the inlet end of the main urea inlet valve of the storage tank, and a reflux valve is also provided on the reflux pipe.

8. The method for preparing urea solution for thermal power plants according to claim 1, characterized in that, The number of liquid outlet branch pipes and hydrophobic flushing pipes is two, with the two liquid outlet branch pipes connected in parallel and the two hydrophobic flushing pipes connected in parallel.

9. The method for preparing urea solution for thermal power plants according to claim 1, characterized in that, The inlet end of the drain pipe is connected to the outlet end of the drain tank, the inlet end of the drain tank is connected to the drain outlet pipe at the drain outlet of the urea dissolving tank, the drain outlet is connected to the condensate outlet of the heating device, and a drain valve is provided on the drain outlet pipe.

Citation Information

Patent Citations

  • System for preventing urea solution conveying pipeline from being blocked

    CN114733336A

  • Concentration-adjustable urea solution preparation device utilizing pneumatic energy to load