Robot bolt installation method based on six-dimensional force information
By using a robot bolt installation method based on six-dimensional force information, combined with 'M'-shaped variable step size search and admittance control, the automation requirements of bolt assembly in the prior art have been solved, realizing an efficient and stable bolt installation process and improving assembly accuracy and consistency.
Patent Information
- Application Number
- CN202410680621.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-29
- Publication Date
- 2026-11-20
- Estimated Expiration
- 2044-05-29
AI Technical Summary
In the existing technology, the assembly of threaded connections mainly relies on manual operation, which has problems such as high labor intensity, high cost and poor assembly consistency. In particular, there is a lack of automated bolt assembly solutions in automobile manufacturing, aerospace manufacturing and heavy machinery manufacturing. Moreover, visual positioning technology fails in the presence of initial pose error and occlusion, and cannot accurately identify the pose relationship between bolts and optical holes.
A robotic bolt installation method based on six-dimensional force information is adopted. By using an industrial robot equipped with a six-dimensional force sensor, combined with a "rice" shaped variable step size search strategy, admittance control and the perpendicularity theorem, the precise alignment and tightening of bolts and optical holes are achieved, including bolt search, insertion, hole center positioning and buckle recognition processes.
It improves the accuracy and efficiency of bolt installation, realizes efficient and stable automated bolt assembly, adapts to the initial positional errors of bolts and holes, ensures accurate alignment of bolts and threaded holes, reduces labor costs and improves assembly consistency.
Smart Images

Figure CN118385936B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to a robot bolt installation method, and more particularly to a robot bolt installation method based on six-dimensional force information, belonging to the field of automatic assembly technology. Background Technology
[0002] Threaded connection assembly is a common and critical process, playing a vital role in mechanical systems that require regular replacement or maintenance. Currently, threaded connection assembly is mostly performed manually with the aid of relevant tools, which suffers from drawbacks such as high labor intensity, high labor costs, and poor assembly consistency. There is an urgent need for automated bolt assembly in industries such as automotive manufacturing, aerospace manufacturing, construction engineering, and heavy machinery manufacturing.
[0003] Industrial robots, with their extremely high repeatability and open functional interfaces, have become one of the most important technologies in the field of intelligent manufacturing. Since industrial robot systems are rigid systems, their application in current manufacturing largely relies on offline programming or manual teaching methods to control robot trajectories. Furthermore, traditional trajectory control strategies for industrial robots can only accept end-effector pose and joint angles as input, and cannot directly accept the forces and torques of the end-effector and joints as input. To enable industrial robots to compliantly adjust their end-effector pose based on real-time external loads, active compliant force control strategies are needed for bolt installation. For bolt installation applications with certain initial pose errors, visual positioning technology fails in such scenarios due to unavoidable visual obstruction between bolts and holes, as well as visual positioning errors. To accurately and efficiently identify the pose relationships between bolts and holes, and bolts and threaded holes, reliance must be placed on force and torque information generated during assembly. This necessitates the development of a force-information-based bolt installation strategy. Summary of the Invention
[0004] For the reasons mentioned above, this invention aims to propose a robot bolt installation method based on six-dimensional force information, laying a technical foundation for the eventual realization of automated robot bolt assembly.
[0005] This invention proposes a robot bolt installation method based on six-dimensional force information, according to the bolt installation process and robot force control assembly technology. The basic idea is as follows: First, an end effector equipped with a six-dimensional force sensor is installed on an industrial robot, and the bolt and the optical hole to be installed on the end effector are in a coarse initial positioning state. Then, the bolt installation process is divided into three basic sequential execution processes: bolt searching for the optical hole, bolt insertion into the optical hole, and adjusting the bolt and threaded hole axis to coincide. A "rice" shaped variable step size search strategy is used to identify the relative position of the bolt and the optical hole, obtaining the optimal search direction and search step size. The robot moves according to the optimal search direction and search step size, continuously repeating the above iterative process, and judging whether the search is complete based on the search end marker. When the search is complete, the bolt end face circle is included by the optical hole. Next, an admittance control end effector pose adjustment strategy is used to achieve compliant posture adjustment of the robot end effector during the bolt insertion process, making the bolt and optical hole axes parallel. Finally, a hole center positioning method based on the perpendicular bisector theorem is used, along... X shaft and Y Hole center positioning is performed along the axial direction to ensure that the bolt and the hole axis coincide; finally, bolt snapping and tightening are performed to achieve automated installation of robot bolts based on six-dimensional force information.
[0006] The robot bolt installation method based on six-dimensional force information includes the following steps: (1) An industrial robot equipped with a six-dimensional force sensor grips a bolt so that the end of the bolt is close to the optical hole, thus satisfying the coarse positioning condition; (2) Use a "rice" shaped variable step size search strategy to search for the light hole with bolts; (3) Admittance control is used to insert the bolt into the aperture; (4) Use the hole center positioning method based on the perpendicular bisector theorem to make the bolt and threaded hole axes coincide; (5) Bolt snapping and tightening.
[0007] The "rice" shaped variable step size search strategy includes the following steps: (1) Use a "rice" shaped trajectory to search for holes; (2) Determine the optimal hole-searching direction and hole-searching step size; (3) The robot grips the bolt and moves to the target position.
[0008] The method for locating the center of a hole based on the perpendicular bisector theorem includes the following steps: (1) Perform X Hole center positioning in the axial direction; (2) Perform Y Hole center positioning in the axial direction.
[0009] Beneficial technical effects of the present invention: Based on the rough positioning result, integrating industrial robot and force-controlled assembly technology, a robot bolt installation strategy based on six-dimensional force information is proposed: (1) The proposed "meter"-shaped variable-step search strategy includes the design of the "meter"-shaped search trajectory, search direction discrimination and search step calculation, and identifies the position of the unthreaded hole according to the force information, so as to realize that the end face of the bolt is contained in the unthreaded hole, which effectively improves the search accuracy and efficiency; (2) The proposed bolt insertion strategy based on admittance control is used to realize the compliant insertion of the bolt into the target unthreaded hole, which enhances the adaptability and stability of the strategy; (3) The proposed hole center positioning method based on the perpendicular diameter theorem and force information realizes the center alignment of the bolt and the threaded hole, which improves the accuracy and stability of installation; (4) The proposed robot bolt installation strategy based on six-dimensional force information can realize efficient, accurate and stable bolt installation, and provides a reliable solution for the industrial automation demand of bolt installation. Brief Description of the Drawings
[0010] Figure 1 is a flowchart of the robot bolt installation method based on six-dimensional force information of the present invention; Figure 2 is a working configuration diagram of the bolt installation of the present invention; Figure 3 is the effect diagram after the bolt installation of the present invention; Figure 4 is a flowchart of the "meter"-shaped variable-step search strategy of the present invention; Figure 5 is a flowchart of the hole center positioning based on the perpendicular diameter theorem of the present invention; Figure 6 is a schematic diagram of the "meter"-shaped search trajectory of the present invention; Figure 7 is a schematic diagram of the hole center positioning along the X axis direction of the present invention; Figure 8 is a schematic diagram of the hole center positioning along the Y axis direction of the present invention. Detailed Implementation Modes
[0011] With reference to the attached Figure 1-8 , the steps and specific operations of the present invention are described.
[0012] The bolt installation scenario targeted by the present invention belongs to the screw connection type in threaded connections, where a bolt is installed without a gasket. The initial state of bolt installation is the coarse positioning state of the unthreaded hole. At this time, the distance from the TCP at the bolt end to the axis of the unthreaded hole is less than the radius of the unthreaded hole. Due to positioning errors, there will also be a certain included angle between the bolt axis and the unthreaded hole axis. The bolt installation process includes the processes of the bolt end face circle being enclosed by the unthreaded hole, inserting into the unthreaded hole, aligning the axes of the bolt and the threaded hole, thread finding, and tightening. The adjustment of the bolt pose during the installation process relies on an industrial robot equipped with a six-dimensional force sensor, and the gravity compensation and zero-point calibration of the six-dimensional force sensor need to be completed in advance.
[0013] 1. An industrial robot equipped with a six-dimensional force sensor grips the bolt to bring the end of the bolt close to the unthreaded hole and meet the coarse positioning condition There are multiple methods to reach the coarse positioning state, and the specific method for realizing coarse positioning is not limited, provided that the initial condition that the distance from the TCP at the bolt end to the axis of the unthreaded hole is less than the radius of the unthreaded hole is ensured. The simplest method to realize coarse positioning is to manually control the industrial robot to reach the end pose that meets the coarse positioning condition. The automated method to realize coarse positioning is to obtain the pose of the unthreaded hole through visual positioning technology, obtain a target end pose of the robot that meets the coarse positioning condition, and then control the robot end to reach the target pose.
[0014] 2. Adopt a "*"-shaped variable-step search strategy for the bolt to search for the unthreaded hole The present invention proposes a "*"-shaped search trajectory, which determines the search direction according to the relative magnitude of the axial force in each corresponding direction, improving the reliability of search direction determination. A variable-step function model is established, which increases the theoretical basis and adaptability for determining the search step size.
[0015] The "*"-shaped variable-step search strategy includes the following steps: (1) Search for the hole along the "*"-shaped trajectory; (2) Determine the optimal hole search direction and hole search step size; (3) The robot grips the bolt to move to the target pose.
[0016] The specific steps of searching for the hole along the "*"-shaped trajectory are as follows: 1) The robot grips the bolt along the tool coordinate system Z moves in the axial direction until a stable axial force is generated between the bolt and the unthreaded hole plane F z0 , at this time the pose of the bolt is T 0; 2) The pose of the bolt at the robot TCP is T , define V 0, V 1, V 2, V 3,V 4. V 5. V 6. V 7 has 8 directions, among which V 0 is X The unit direction vector along the positive axis, in homogeneous coordinates is... V 0=[1,0,0,0] T ; V 4 is X The unit direction vector in the negative direction of the axis, with homogeneous coordinates as... V 4 = [-1, 0, 0, 0] T ; V 2 is Y The unit direction vector along the positive axis, in homogeneous coordinates is... V 2=[0,1,0,0] T ; V 6 is Y The unit direction vector in the negative direction of the axis, with homogeneous coordinates as... V 6 = [0, -1, 0, 0] T ; V 1 is X positive direction of axis and Y The unit direction vector of the positive direction of the bisector of the positive axis, with homogeneous coordinates as... ; V 5 is V 1. The unit direction vector in the opposite direction, with homogeneous coordinates as ; V 3 is X negative direction of axis and Y The unit direction vector of the positive direction of the bisector of the positive axis, with homogeneous coordinates as... ; V 7 is V 3. The unit direction vector in the opposite direction, with homogeneous coordinates as Eight directions formed V 0- V 4. V 1- V 5. V 2- V 6. V 3- V There are 7 groups of directions in total. This allows the robot to navigate around the target area from its current position. V 0、 V 1. V 2 and V 3. Rotate the search path clockwise and counterclockwise by a set angle (5° is set here). The resulting search path is called a "rice" shaped search path. Move along the "rice" shaped search path (i.e., successively around...). V 0 axis V 1 axis V2-axis and V The three axes rotate clockwise and counterclockwise by set angles respectively, outputting the search directions. Z The maximum force on the shaft, i.e.: F V0 , F V4 , F V1 , F V5 , F V2 , F V6 , F V3 , F V7 .
[0017] The specific steps to determine the optimal hole-searching direction are as follows: Calculate the pairwise relative search directions Z The absolute value of the difference in force values along the axial direction is used to obtain the search direction group with the largest value. This search direction group is then used for further analysis. Z The direction in which the absolute value of the axial force is smaller is the hole-searching direction.
[0018] For example, | F V0 - F V4 |=max{| F V0 - F V4 |,| F V1 - F V5 |,| F V2 - F V6 |,| F V3 - F V7 |}, and | F V0 |<| F V4 |, thus obtaining the search direction group as V 0- V 4. Search direction is V 0.
[0019] The specific steps for determining the hole-searching step size are as follows: Formula for calculating the hole search step length: λ = ε ×(1-| F zmin / F zmax|), where, F zmin and F zmax These are the smallest and largest absolute values in the hole-searching motion of the search direction group in a certain iteration. Z Axial force, ε This is the maximum hole-finding step size set based on experience; here we take... ε It is 0.5mm.
[0020] The specific steps for the robot to move the bolt to the target pose are as follows: Assuming the robot grasps the bolt from its pose T 0 along vector , V ∈{ V 0, V 1, V 2, V 3, V 4, V 5, V 6, V 7}, a , b Directions V exist X shaft and Y Projection of axis, distance moved λ The pose transformation matrix is trans( V , λ ), T 0trans( V , λ Let be the target pose, where: , , , , , , , .
[0021] This completes one iteration of the hole-searching motion. The above iterative process is repeated continuously until the bolt end face circle is contained within the hole, thus completing the bolt's search for the hole.
[0022] 3. Admittance control is used to insert the bolt into the aperture. After the bolt search for the optical aperture is completed, the next step is to insert the bolt into the aperture. The position and attitude changes based on admittance control are calculated as follows: , in, M ,B , K These are the robot's inertia, damping, and stiffness coefficients (the values of these admittance control-related parameters were determined through experimental testing in this invention as follows:) dt= 0.001, M =1, B =10, K =30), F e This refers to the force or torque information between the robot's end effector and the environment. X e It is the actual position information of the robot's end effector. dX e It is the actual speed information of the robot's end effector. ddX e It is the actual acceleration information of the robot's end effector. dt It is a time interval. N It is the maximum number of iterations. i It is the number of iterations ( i =0,1,…, N ).
[0023] During the insertion of the bolt into the optical hole, the bolt posture can be continuously adjusted according to the admittance-controlled insertion strategy to achieve compliant bolt insertion into the optical hole. At this time, the bolt end face and the bottom surface of the optical hole are flush, and the bolt and the optical hole axis are parallel.
[0024] 4. Employ a hole center positioning method based on the perpendicular bisector theorem to ensure the bolt and threaded hole axes coincide. When the insertion is complete, the bolt is parallel to the axis of the hole. To ensure the bolt can be smoothly screwed into the threaded hole, the bolt and the axis of the hole need to coincide. To achieve alignment of the two centers, based on the geometric characteristics of the bolt and the hole, and combined with the perpendicular bisector theorem in geometry, a hole center alignment method based on the perpendicular bisector theorem and force feedback is proposed. The principle of this hole center alignment method is introduced. For ease of explanation, the bolt end face circle is drawn with an exaggerated style. C 2, O 1 indicates aperture C The center of 1 O 2 indicates the bolt end face circle C The center of 2, the bolt end face circle is contained within the smooth hole. X Represents the tool coordinate system X axis, Y Represents the tool coordinate system Y axis, O 2 and O The initial position of 1 is random.
[0025] The method for locating the center of a hole based on the perpendicular bisector theorem includes the following steps: (1) Perform X Hole center positioning in the axial direction; (2) Perform Y Hole center positioning in the axial direction.
[0026] conduct X The specific steps for axial hole center positioning are as follows: 1) The robot grips the bolt, maintaining its posture, from... O 2. Depart, along X Move in the positive direction of the axis C 2, until C 2 and C 1 is internally connected, at this time C The location of the center is denoted as O 21 ; 2) The robot grips the bolt, maintaining its posture, from... O 21 Depart, along X movement in the negative direction of the axis C 2, until C 2 and C 1 is internally connected, at this time C The location of the center is denoted as O 21 ′ , O 21 ″ For line segments O 21 O 21 ′ The midpoint, O 21 ′ and O 21 ″ The distance between them is denoted as d 1; 3) The robot grips the bolt, maintaining its posture, from... O 21 ′ Depart, along X Move in the positive direction of the axis d 1. Arrival O 21 ″ ,Finish X Hole center positioning in the axial direction.
[0027] conduct Y The specific steps for axial hole center positioning are as follows: 1) The robot grips the bolt, maintaining its posture, from... O 21 ″ Depart, along Y Move in the positive direction of the axisC 2, until C 2 and C 1 is internally connected, at this time C The location of the center is denoted as O 22 ; 2) The robot grips the bolt, maintaining its posture, from... O 22 Depart, along Y movement in the negative direction of the axis C 2, until C 2 and C 1 is internally connected, at this time C The location of the center is denoted as O 22 ′ , O 22 ″ For line segments O 22 O 22 ′ The midpoint, O 22 ″ and O 1 o'clock coincides, O 22 ′ and O 22 ″ The distance between them is denoted as d 2; 3) The robot grips the bolt, maintaining its posture, from... O 22 ′ Depart, along Y positive direction of axis movement d 2. Arrival O 22 ″ ,Finish Y Axial hole center positioning, to achieve O 2 and O 1. Overlap.
[0028] C 2 and C 1. Whether the force is internally tangent is determined by whether the force in the corresponding direction reaches a preset force threshold: For X The axial direction, and the force information used for judgment, are in the tool coordinate system. X The absolute value of the force in the axial direction; for Y The axial direction, and the force information used for judgment, are in the tool coordinate system. Y The absolute value of the force in the axial direction.
[0029] 5. Bolt threading and tightening After the bolt and threaded hole axes are aligned, the bolt threads are checked and tightened.
[0030] Specific steps for bolt threading and tightening: First, make the robot move along the tool coordinate system. Z The shaft is fed to bring the bolt end face into contact with the threaded hole end face; then, while maintaining... Z While applying axial pressure, rotate the shaft counterclockwise two times; then, screw the bolt in clockwise. Z Tightening is considered complete when the torque in the axial direction exceeds a set threshold; finally, the robot moves along the tool coordinate system... Z Retract the shaft to allow the bolt head to exit the sleeve, completing the bolt installation.
Claims
1. A robot bolt installation method based on six-dimensional force information, used for screw connections in threaded connections, where bolts are installed without washers, the method comprising the following steps: (1) An industrial robot equipped with a six-dimensional force sensor grips a bolt so that the end of the bolt is close to the optical hole, thus satisfying the coarse positioning condition; (2) The optical aperture is searched using a "rice" shaped variable step size search strategy, which includes the following steps: ① Use a "rice" shaped trajectory to search for holes. The specific steps include: 1) The robot grips the bolt along the tool coordinate system. Z Move along the axis until a stable axial force is generated between the bolt and the hole plane. F z0 At this time, the bolt's position is T 0; 2) The pose of the bolt at the robot's TCP is: T ,definition V 0、 V 1. V 2. V 3. V 4. V 5. V 6. V 7 has 8 directions, among which V 0 is X The unit direction vector along the positive axis, in homogeneous coordinates is... V 0=[1,0,0,0] T ; V 4 is X The unit direction vector in the negative direction of the axis, with homogeneous coordinates as... V 4 = [-1, 0, 0, 0] T ; V 2 is Y The unit direction vector along the positive axis, in homogeneous coordinates is... V 2=[0,1,0,0] T ; V 6 is Y The unit direction vector in the negative direction of the axis, with homogeneous coordinates as... V 6 = [0, -1, 0, 0] T ; V 1 is X positive direction of axis and Y The unit direction vector of the positive direction of the bisector of the positive axis, with homogeneous coordinates as... V 1=[ , ,0,0] T ; V 5 is V 1. The unit direction vector in the opposite direction, with homogeneous coordinates as V 5=[ , ,0,0] T ; V 3 is X negative direction of axis and Y The unit direction vector of the positive direction of the bisector of the positive axis, with homogeneous coordinates as... V 3=[ , ,0,0] T ; V 7 is V 3. The unit direction vector in the opposite direction, with homogeneous coordinates as V 7=[ , ,0,0] T Eight directions formed V 0- V 4. V 1- V 5. V 2- V 6. V 3- V There are 7 groups of directions in total, which allow the robot to circle around the target location in succession from its current position. V 0、 V 1. V 2 and V 3. Rotate the set angle clockwise and counterclockwise respectively. Here, the rotation set value is 5°. The resulting search trajectory is called the "rice" shaped search trajectory. Move along the "rice" shaped search trajectory, successively circling... V 0 axis V 1 axis V 2-axis and V The three axes rotate clockwise and counterclockwise by a set angle respectively, outputting the search directions. Z The maximum force on the shaft, i.e.: F V0 , F V4 , F V1 , F V5 , F V2 , F V6 , F V3 , F V7 ; ② Determine the optimal hole-searching direction and step size. The specific steps for determining the optimal hole-searching direction are as follows: Calculate the pairwise relative search directions Z The absolute value of the difference in force values along the axial direction is used to obtain the search direction group with the largest value. This search direction group is then used for further analysis. Z The direction in which the absolute value of the axial force is smaller is the hole-searching direction; The specific steps for determining the hole-searching step size are as follows: Formula for calculating the hole search step length: λ = ε ×(1-| F zmin / F zmax |), where, F zmin and F zmax These are the smallest and largest absolute values in the hole-searching motion of the search direction group in a certain iteration. Z Axial force, ε It is the maximum hole-searching step size set based on experience; ③ The robot grips the bolt and moves it to the target pose. The specific steps are as follows: Assuming the robot grasps the bolt from its pose T 0 along vector V= ( , ,0,0), V ∈{ V 0, V 1, V 2, V 3, V 4, V 5, V 6, V 7}, a , b Directions V exist X shaft and Y Projection of axis, distance moved λ The pose transformation matrix is trans( V , λ ), T 0trans( V , λ Let be the target pose, where: , , , , , , , ; (3) Admittance control is used to insert the bolt into the aperture; (4) Use the hole center positioning method based on the perpendicular bisector theorem to make the bolt and threaded hole axes coincide; (5) Bolt snapping and tightening.
2. The robot bolt installation method based on six-dimensional force information as described in claim 1, characterized in that, Method steps (1) The method to achieve coarse positioning is to manually control the industrial robot to reach the end pose that meets the coarse positioning conditions, or to obtain the aperture pose through visual positioning technology to obtain a target pose of the robot end that meets the coarse positioning conditions, and then control the robot end to reach the target pose.
3. The robot bolt installation method based on six-dimensional force information as described in claim 1, characterized in that, Step (3) During the process of inserting the bolt into the aperture using admittance control, the bolt position is continuously adjusted according to the insertion strategy of admittance control to achieve compliant bolt insertion into the aperture. At this time, the bolt end face and the bottom surface of the aperture are flush. The position and attitude change based on admittance control are calculated as follows: , in, M , B , K These are the robot's inertia, damping, and stiffness coefficients, respectively. F e This refers to the force or torque information between the robot's end effector and the environment. X e It is the actual position information of the robot's end effector. dX e It is the actual speed information of the robot's end effector. ddX e It is the actual acceleration information of the robot's end effector. dt It is a time interval. N It is the maximum number of iterations. i It is the number of iterations ( i =0,1,…, N ).
4. The robot bolt installation method based on six-dimensional force information as described in claim 1, characterized in that, In step (4) O 1 indicates aperture C The center of 1 O 2 indicates the bolt end face circle C The center of 2, the bolt end face circle is contained within the smooth hole. X Represents the tool coordinate system X axis, Y Represents the tool coordinate system Y axis, O 2 and O The initial position of 1 is random. The hole center location method based on the perpendicular bisector theorem includes the following steps: ① to carry out X The specific steps for centering the hole in the axial direction are as follows: 1) The robot grips the bolt, maintaining its posture, from... O 2. Depart, along X Move in the positive direction of the axis C 2, until C 2 and C 1 is internally connected, at this time C The location of the center is denoted as O 21 ; 2) The robot grips the bolt, maintaining its posture, from... O 21 Depart, along X movement in the negative direction of the axis C 2, until C 2 and C 1 is internally connected, at this time C The location of the center is denoted as O 21 ′ , O 21 ″ For line segments O 21 O 21 ′ The midpoint, O 21 ′ and O 21 ″ The distance between them is denoted as d 1; 3) The robot grips the bolt, maintaining its posture, from... O 21 ′ Depart, along X Move in the positive direction of the axis d 1. Arrival O 21 ″ ,Finish X Axial hole center positioning; ②to proceed Y The specific steps for centering the hole in the axial direction are as follows: 1) The robot grips the bolt, maintaining its posture, from... O 21 ″ Depart, along Y Move in the positive direction of the axis C 2, until C 2 and C 1 is internally connected, at this time C The location of the center is denoted as O 22 ; 2) The robot grips the bolt, maintaining its posture, from... O 22 Depart, along Y movement in the negative direction of the axis C 2, until C 2 and C 1 is internally connected, at this time C The location of the center is denoted as O 22 ′ , O 22 ″ For line segments O 22 O 22 ′ The midpoint, O 22 ″ and O 1 o'clock coincides, O 22 ′ and O 22 ″ The distance between them is denoted as d 2; 3) The robot grips the bolt, maintaining its posture, from... O 22 ′ Depart, along Y positive direction of axis movement d 2. Arrival O 22 ″ ,Finish Y Axial hole center positioning, to achieve O 2 and O 1. Overlap; C 2 and C 1. Whether the force is internally tangent is determined by whether the force in the corresponding direction reaches a preset force threshold: For X The axial direction, and the force information used for judgment, are in the tool coordinate system. X The absolute value of the force in the axial direction; for Y The axial direction, and the force information used for judgment, are in the tool coordinate system. Y The absolute value of the force in the axial direction.
5. The robot bolt installation method based on six-dimensional force information as described in claim 1, characterized in that, The specific steps for bolt engagement and tightening in step (4) are as follows: First, move the robot along the tool coordinate system... Z The shaft is fed to bring the bolt end face into contact with the threaded hole end face; then, while maintaining... Z While applying axial pressure, rotate the shaft counterclockwise two times; then, screw the bolt in clockwise. Z Tightening is considered complete when the torque in the axial direction exceeds a set threshold; finally, the robot moves along the tool coordinate system... Z Retract the shaft to allow the bolt head to exit the sleeve, completing the bolt installation.