System for monolithic casting of a sunk pipe and method for precasting a sunk pipe
By adopting an integrated casting-in-place tunnel system and method, the problems of long construction period and cracking in the tunnel prefabrication process have been solved, achieving rapid and reliable tunnel prefabrication and improving construction efficiency and quality.
Patent Information
- Application Number
- CN202410579411.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-11
- Publication Date
- 2026-11-20
- Estimated Expiration
- 2044-05-11
AI Technical Summary
Existing technologies for immersed tube prefabrication have problems such as long construction periods and easy cracking at the interface between new and old concrete, especially in the post-cast strip method, which is time-consuming and difficult to construct.
An integral casting and sinking system is adopted. Through the relative sliding and elastic sealing mechanism between the precast platform and the bottom formwork, the integral casting of the sinking tube is realized, eliminating the process of segmented casting and post-cast strip casting. By utilizing the lap structure of the steel cage and the mutual locking of the formwork, it is ensured that the concrete can slide freely during the casting and curing process, releasing shrinkage stress.
It significantly shortened the construction period, reduced the risk of cracking in the prefabricated immersed tubes, and improved construction efficiency, waterproofing, and durability of the immersed tubes.
Smart Images

Figure CN118386390B_ABST
Abstract
Description
Technical Field
[0001] This application belongs to the field of immersed tube manufacturing technology, and in particular relates to a system for integral casting of immersed tubes and a method for prefabricating immersed tubes. Background Technology
[0002] Precasting of immersed tubes is a major concern in the construction of immersed tunnels due to its long construction period, difficulty in crack control, and high precasting cost. After the precast immersed tube is poured, the shrinkage of the immersed tube concrete as a large-volume reinforced concrete structure during the construction period is constrained, which is the main reason for its cracking. The stress generated by the constraint of concrete can be divided into self-constraining stress and external constraint stress. At present, the self-constraining stress formed by the temperature difference between the inside and outside of the large-volume concrete can be well controlled by technologies such as laying cooling water pipes in the concrete. The external constraints on the immersed tube structure during the construction period are mainly two aspects: (1) the constraint of the steel reinforcement in the immersed tube; (2) the frictional constraint of the ground or bottom formwork on the immersed tube. For the external constraints of the immersed tube concrete, the existing technology usually adopts the post-pouring strip method to reduce the constraints of the above two aspects. The post-pouring strip method of precast immersed tubes refers to dividing each section of the immersed tube into several segments along the length of the immersed tube for pouring. After each segment of concrete is poured, it is cured for 40-60 days and then the post-pouring strip is poured (connecting the segments) to avoid the shrinkage of the concrete being constrained during the curing process and causing cracks. The disadvantages of this process are: the post-pouring strip construction can only be carried out after 40-60 days, which takes a long time and seriously delays the construction period; in addition, the construction of the post-pouring strip creates a bonding surface between the old and new concrete, and the concrete in the post-pouring strip area becomes a new area prone to cracking, so the construction of the post-pouring strip method is more difficult. Summary of the Invention
[0003] In view of the shortcomings of the related technologies, this application provides a system for integral casting of immersed tubes and a method for prefabricating immersed tubes.
[0004] The first aspect of this application provides a system for integral cast-in-place pipe laying, which includes: Precast platforms are used to provide casting space for the integral casting of precast immersed tubes; and Multiple bottom molds are used for binding and supporting the segmented steel cages, and serve as part of the formwork for the precast tunnel; at least during the casting of the precast tunnel, each bottom mold is located on a precast platform and connected end to end. The precast platform and each bottom mold are configured to slide relative to each other, and adjacent bottom molds are configured to move relative to each other; the precast immersed tube is formed by non-segmented casting.
[0005] In one embodiment, each bottom formwork supports only one section of reinforcing cage, the ends of which are formed with extended lap joints, and the lap joints between adjacent reinforcing cages are staggered to form an lap structure that can be used for pouring concrete.
[0006] In one embodiment, the interior of each steel cage is mechanically connected and has a length of 18-25m; the lap length between adjacent steel cages is not less than 28d, where d is the diameter of the lapped steel bars.
[0007] In one embodiment, at least during the curing of the precast tunnel, the precast platform and each bottom mold are configured to slide relative to each other, so that adjacent bottom molds can move relative to each other.
[0008] In one embodiment, the precast platform is provided with a track, and each bottom mold has rollers at its bottom that cooperate with the track. The rollers move along the track, achieving relative sliding or braking between the precast platform and each bottom mold. In a specific embodiment, the precast platform is provided with multiple rows of parallel tracks; each track has a raised elongated guide rail extending along the length of the precast tube; each bottom mold has multiple rows of rollers at its bottom that cooperate with the guide rails; each roller has a recessed groove in the middle to engage with the guide rail and slide along it.
[0009] In an alternative embodiment, a plurality of inflatable and ventable airbags and a limiting mechanism are provided between the precast platform and each bottom mold; wherein the airbags are distributed along the width direction of the precast tube; the airbags are configured to allow relative sliding between the precast platform and each bottom mold when inflated; and the limiting mechanism is configured to restrict or allow relative sliding between the precast platform and each bottom mold.
[0010] In one embodiment, the limiting mechanism includes a lifting column disposed on a precast platform and a limiting groove disposed on a bottom mold that cooperates with the lifting column; wherein the lifting column is configured to extend from the precast platform to engage in the limiting groove of the bottom mold, thereby limiting the relative sliding between the precast platform and each bottom mold; and to retract from the limiting groove to allow the relative sliding between the precast platform and each bottom mold.
[0011] In one embodiment, an elastic sealing mechanism is provided between adjacent bottom molds to achieve relative movement between the adjacent bottom molds; wherein the elastic sealing mechanism is selected from one or more combinations of the following: Option 1: The elastic sealing mechanism is a flat joint structure, including a first gap that is generally vertically straight between adjacent bottom molds, and a first elastic sealing element located in the first gap; the first elastic sealing element is configured to: be pre-pressed between adjacent bottom molds when concrete is poured for the precast tube; and be able to expand or continue to be compressed after concrete is poured.
[0012] Option 2: The elastic sealing mechanism is a tongue-and-groove connection structure, including a bent second gap extending downward from top to bottom between adjacent bottom molds, and a second elastic seal and a third elastic seal located in the second gap, respectively located at the upper and lower parts of the second gap; the second elastic seal and the third elastic seal are respectively configured to: be pre-pressed between adjacent bottom molds when concrete is poured for the precast tube; and be able to expand or continue to be compressed after concrete is poured.
[0013] Option 3: The elastic sealing mechanism is a stepped connection structure, with adjacent bottom molds defined as the first bottom mold and the second bottom mold, respectively. The first bottom mold has a stepped first extension, and the second bottom mold has a stepped second extension, with the two extensions staggered. A third gap is formed between the body of the first bottom mold and the second extension, in which a fourth elastic seal is provided. A fourth gap is formed between the body of the second bottom mold and the first extension, in which a fifth elastic seal is provided. The fourth and fifth elastic seals are configured to: be pre-pressed between adjacent bottom molds during concrete pouring of the precast tunnel; and be able to expand or continue to be compressed after concrete pouring.
[0014] In one embodiment, the precast platform is located within a dock, allowing the precast tunnel section to be cast and cured within the dock. The system for integrally cast tunnel sections also includes an inner formwork located within a reinforcing cage and an outer formwork erected outside the reinforcing cage during concrete casting; wherein the bottom formwork, inner formwork, and outer formwork together constitute the formwork for concrete casting.
[0015] The second aspect of this application provides a method for prefabricating immersed tunnel sections, which can be implemented using the monolithic casting system for immersed tunnel sections described in any of the preceding embodiments, and can be used for the monolithic casting of prefabricated immersed tunnel sections; the prefabrication method includes the following steps: Reinforcing cage binding: Binding the reinforcing cage to the bottom formwork; Rebar cage movement: Move the tied rebar cage onto the precast platform and position it. Erecting the inner formwork: Lift the top slab reinforcement of the steel cage, remove the steel cage support, push the inner formwork into the steel cage, and lower the top slab reinforcement to complete the load-bearing system conversion; Integrated construction: For a precast immersed tube, the steps of binding the steel cage, moving the steel cage and erecting the inner formwork are carried out separately for the multiple steel cages; then the lap joints of the adjacent steel cages are bound together to assemble the inner formwork into one piece; an elastic sealing mechanism is set between the adjacent bottom formworks to achieve elastic fit and sealing. Concrete pouring: The outer formwork of the steel cage is erected, and each bottom formwork is locked to the precast platform; at this time, the elastic sealing mechanism is in a pre-compression state and can be stretched or continued to be compressed; the formwork is controlled to be tightened so that there is no relative sliding between the formwork; then the concrete pouring of a precast pipe section is completed in one go in the multi-section steel cage surrounded by the formwork, so that all the steel cages are connected into a whole. Post-pouring adjustment: After the concrete reaches the initial forming state, release the locking between the bottom formwork and the precast platform so that the adjacent bottom formswork can be moved relative to each other. Maintenance of the immersed tunnel: After curing with the template, remove the inner and outer templates and continue to maintain the maintenance of the immersed tunnel; maintain the sliding state between each bottom template and the precast platform, as well as the relative movable state between the bottom templates.
[0016] In one embodiment, when the precast platform is equipped with a track and each bottom mold has rollers that match the track at its bottom: during the rebar cage moving step, the tied rebar cage is moved onto the precast platform and positioned by the cooperation of the rollers and the track; during the concrete pouring step, the rollers are braked and locked onto the track, thereby locking each bottom mold and the precast platform together; during the post-pouring adjustment step, the braking of the rollers is released, thereby unlocking the bottom mold and the precast platform.
[0017] In another embodiment, when multiple airbags and limiting mechanisms are provided between the precast platform and each bottom mold; during the concrete pouring step, the multiple airbags located below the bottom mold are inflated, with each airbag parallel to each other and arranged along the width direction of the precast tube; the limiting mechanisms are activated to lock each bottom mold and the precast platform together; during the adjustment step after pouring, the air pressure of each airbag is adjusted so that each bottom mold is approximately on the same horizontal plane; within 24-48 hours after pouring, the limiting mechanisms are withdrawn, releasing the lock between the bottom mold and the precast platform, thereby allowing the bottom mold to slide along the length direction of the precast tube under the support of the airbags; during the curing step of the tube, the sliding state of the bottom mold is maintained.
[0018] The monolithic cast-in-place tunnel system provided in at least one embodiment of this application can overcome the problems of long construction period and easy cracking at the interface between new and old concrete in the conventional post-cast strip method for tunnel prefabrication. This system can shorten the construction period, reduce the risk of cracking, thereby achieving rapid monolithic prefabrication of the tunnel, while giving the tunnel structure good waterproofness and durability.
[0019] The prefabrication method for immersed tubes provided in at least one embodiment of this application enables each segment of the immersed tube to slide freely along its length after concrete pouring, minimizing shrinkage constraints of the immersed tube concrete along its length and significantly reducing the risk of cracking. Since the curing process between the completion of segmental pouring and the pouring of the post-pouring strip is eliminated, the prefabrication period for the immersed tube is expected to be significantly shortened by 40-60 days. Attached Figure Description
[0020] The accompanying drawings, which are included to provide a further understanding of this application and form part of this application, illustrate exemplary embodiments and are used to explain this application, but do not constitute an undue limitation of this application. In the drawings: Figure 1 This is a schematic diagram of a system for integral cast-in-place pipe installation, one implementation method. Figure 2 This is a schematic diagram of a prefabricated platform as one implementation method; Figure 3 This is a schematic diagram of the bottom mold in one implementation method; Figure 4 This is a schematic diagram of a system for integral cast-in-place pipe installation, one implementation method. Figure 5 This is a schematic diagram of an elastic sealing mechanism according to one implementation method; Figure 6 This is a schematic diagram of an elastic sealing mechanism according to one implementation method; Figure 7 This is a schematic diagram of an elastic sealing mechanism according to one implementation method; In the diagram: 1 Precast platform, 101 Track, 102 Guide rail; 2 Bottom mold, 21 First bottom mold, 22 Second bottom mold, 201 Roller, 202 Groove; 3 Reinforcing cage, 31 First reinforcing cage, 32 Second reinforcing cage; 41 Airbag; 42 Limiting mechanism, 421 Lifting column, 422 Limiting groove; 5 Elastic sealing mechanism; 6 Flat joint structure, 601 First gap, 602 First elastic seal; 7 Tongue and groove connection structure, 701 Second gap, 702 Second elastic seal, 703 Third elastic seal; 8 Stepped connection structure, 801 First extension, 802 Second extension, 803 Third gap, 804 Fourth elastic seal, 805 Fourth gap, 806 Fifth elastic seal; 9 Overlap structure, 901 First lap joint, 902 Second lap joint. Detailed Implementation
[0021] The technical solutions in the embodiments of this application will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only a part of the embodiments of this application, and not all of them. All other embodiments obtained by those skilled in the art based on the embodiments of this application without creative effort are within the scope of protection of this application.
[0022] In the description of this application, it should be understood that the terms "center", "lateral", "longitudinal", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are only for the convenience of describing this application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on this application.
[0023] The terms "first," "second," and "third" are used for descriptive purposes only and should not be construed as indicating or implying relative importance or implicitly specifying the number of technical features indicated. Therefore, a feature defined as "first," "second," or "third" may explicitly or implicitly include one or more of that feature.
[0024] In the description of this application, it should be noted that, unless otherwise expressly specified and limited, the terms "installation," "connection," and "joining" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a direct connection or an indirect connection through an intermediate medium; and they can refer to the internal communication between two components. Those skilled in the art can understand the specific meaning of the above terms in this application based on the specific circumstances.
[0025] The first embodiment of this application provides a system for integral cast-in-place pipes, such as... Figure 1-4 As shown, it includes: a precast platform 1 for providing a casting space for the precast immersed tube and multiple bottom molds 2 located on the precast platform 1. The precast platform 1 can be located within a dock, so that the precast immersed tube is cast and cured within the dock, and then floated out of the dock. The precast platform 1 and each bottom mold 2 are configured to slide relative to each other; adjacent bottom molds 2 are configured to move relative to each other. The bottom mold 2 carries segmented reinforcing cages 3, and the bottom mold 2 serves as part of the formwork for casting concrete for the precast immersed tube. Generally, only one segment of reinforcing cage 3 is carried on a single bottom mold 2.
[0026] In one implementation, such as Figure 1-3As shown, a track 101 is provided on the precast platform 1; each bottom mold 2 is provided with a roller 201 that matches the track, so that the movement of the roller 201 on the track 101 realizes the relative sliding between the precast platform 1 and each bottom mold 2. More specifically, as shown... Figure 2 As shown, the precast platform 1 is provided with multiple rows of parallel tracks 101, each track 101 having a raised elongated guide rail 102 extending along the length of the precast immersed tube. Figure 3 As shown, each bottom mold 2 has multiple rows of rollers 201 at its bottom that mate with the guide rails 102 of each track 101. Each roller 201 has a recessed groove 202 in the middle. By engaging the groove 202 of the roller 201 with the guide rail 102 of the track 101, the rollers 201 can slide along the track 101. At least during the curing period of the precast tunnel section, the rollers 201 can slide along the track 101. The figure shows an example of three tracks 101 and three rows of rollers 201, with each row containing five rollers. The number of tracks and rollers can be configured according to actual needs, which is understandable.
[0027] In another alternative implementation, such as Figure 4 As shown, multiple airbags 41 are provided between the precast platform 1 and each bottom mold 2. The airbags 41 are distributed along the width direction of the precast tunnel and can roll when inflated. At least during the curing period of the precast tunnel, the airbags 41 are inflated so that the bottom molds 2 can slide relative to the precast platform 1. With a sufficient number of airbags 41 and sufficient rigidity, the leveling of each bottom mold 2 can be achieved effectively, ensuring the stability of the bottom molds in the vertical direction while ensuring good sliding ability in the horizontal direction. Airbag sliding also has advantages such as low cost and high maneuverability. When sliding airbags 41 are used, in order to limit the longitudinal movement between adjacent bottom molds 2 during concrete pouring of the precast tunnel, a limiting mechanism 42 is also provided between the precast platform 1 and the bottom molds 2. Specifically, as shown... Figure 4 As shown, the limiting mechanism 42 includes a retractable lifting column 421 mounted on the precast platform 1 and a limiting groove 422 mounted on the bottom mold 2; the lifting column 421 can extend or retract from the precast platform 1; the opening of the limiting groove 422 faces the precast platform 1 and can cooperate with the extended lifting column 421. The extension and retraction of the lifting column 421 can adopt existing technologies such as anti-collision posts or road barrier posts, and generally hydraulic control is used to realize the lifting and lowering of the column. When it is necessary to prevent the bottom mold 2 from moving along the length direction ( Figure 1 (Move left and right in the middle), the lifting column 421 extends from the top surface of the precast platform 1 and is inserted into the limiting groove 422 of the bottom mold 2, thereby preventing the bottom mold from swinging in the length direction (left and right); when it is not necessary to prevent the bottom mold from moving, the lifting column 421 retracts and can be located below the ground.
[0028] like Figure 1 As shown, each bottom formwork 2 carries a section of tied reinforcing cage 3. This reinforcing cage 3 can be tied in the tying area and transported to the precast platform 1, or the bottom formwork 2 can be laid directly on the precast platform 1, and then the reinforcing cage 3 tied on it. To improve work efficiency, the bottom formwork 2 is generally set up in the tying area outside the precast platform 1 for tying the reinforcing cage 3. The internal connections of each section of the reinforcing cage are generally mechanical, such as conventional reinforcing bar sleeve extrusion connections and reinforcing bar tapered thread sleeve connections. Rigid connections have advantages such as high reliability, good force transmission performance, and fast construction speed; however, they are not conducive to the release of concrete shrinkage stress during construction between sections of the reinforcing cage. Therefore, the reinforcing bars between sections of the reinforcing cage are connected by lap splicing. To prevent shrinkage or expansion cracking after concrete pouring caused by excessive length of each section of the reinforcing cage (which has a rigid internal connection), the length of the reinforcing cage 3 is generally controlled between 18-25m, such as 20m, 22m, 24m, etc.; the length of each bottom formwork 2 is roughly equal to the length of the reinforcing cage 3, and is also generally controlled between 18-25m.
[0029] An elastic sealing mechanism 5 is installed between adjacent bottom molds 2 to achieve sealing and relative movement between them. This prevents leakage during concrete pouring of the precast tunnel and allows for sufficient clearance between adjacent bottom molds, preventing excessive restriction of concrete expansion and contraction during tunnel prefabrication and thus avoiding cracking and other adverse conditions. To achieve the above functions, the elastic sealing mechanism 5 can be one or more of the following combinations: like Figure 5 As shown, the elastic sealing mechanism 5 is a flat-joint structure 6, including a generally straight first gap 601 formed between adjacent bottom molds 21, 22, and a first elastic sealing element 602 located in the first gap 601. The first elastic sealing element 602 is elastic and abuts against the two bottom molds 21, 22 respectively. The first elastic sealing element 602 can be made of rubber, such as a rubber waterstop; it is tightly attached between the two adjacent bottom molds 2, and can play a sealing and leak-proof role during concrete pouring. In addition, the first elastic sealing element is elastic and is configured such that: when the precast tunnel is poured with concrete, it is pre-compressed between the two bottom molds 21, 22; after the concrete is poured, it can expand or continue to be compressed, thereby accommodating the expansion and contraction of the concrete during the precast tunnel process.
[0030] like Figure 6As shown, the elastic sealing mechanism 5 is a tongue-and-groove connection structure 7, including a bent second gap 701 formed between adjacent bottom molds 21, 22, and a second elastic seal 702 and a third elastic seal 703 located in the second gap 701, which are respectively located at the top and bottom of the second gap 701 and are spaced apart. Each elastic seal 702, 703 is elastic and abuts against the two bottom molds 21, 22 respectively; their function is the same as that of the first elastic seal 602, and they can also be made of rubber; they can be pre-compressed and can be stretched or further compressed.
[0031] like Figure 7 As shown, the elastic sealing mechanism 5 is a stepped connection structure 8. Adjacent bottom molds 2 are defined as a first bottom mold 21 and a second bottom mold 22, respectively. The first bottom mold 21 has a stepped first extension 801, and the second bottom mold 22 has a stepped second extension 802. The first extension 801 and the second extension 802 are staggered. In the figure, the first extension 801 is located at the lower part, and the second extension 802 is located at the upper part. Their staggered portions are in contact with each other (i.e., the upper surface of the first extension 801 is in contact with the lower surface of the second extension 802). Of course, their positions can also be interchanged, i.e., the first extension is located at the upper part, and the second extension is located at the lower part. A third gap 803 is formed between the body of the first bottom mold 21 and the second extension 802, in which a fourth elastic sealing element 804 is provided, respectively abutting against the bottom molds 21 and 22. A fourth gap 805 is formed between the body of the second bottom mold 22 and the first extension 801, in which a fifth elastic sealing element 806 is provided, respectively abutting against the bottom molds 21 and 22. The elastic sealing elements in the above three elastic sealing mechanisms 5 have basically the same function, so they can use the same material and the same configuration, and can all refer to the first elastic sealing element 602.
[0032] In addition, such as Figure 1 As shown, adjacent reinforcing cages 3 on the bottom formwork 2 have an lap structure 9. The two adjacent reinforcing cages are defined as a first reinforcing cage 31 and a second reinforcing cage 32, respectively. The lap structure 9 includes a first lap joint 901 extending from the first reinforcing cage 31 and a second lap joint 902 extending from the second reinforcing cage 32. The first lap joint 901 and the second lap joint 902 are interlocked to form the lap structure 9. By integrally casting concrete in the lap structure 9, multiple segmented reinforcing cages can be connected to form an integral immersed tube. Furthermore, to ensure the strength and stability of the connection, the lap length is not less than 28d, where d is the diameter of the lapped reinforcing bars. The lap structure 9 approximately coincides with the elastic sealing mechanism 5 in the vertical direction, so that the longitudinal movement of the elastic sealing mechanism 5 can provide a margin for the expansion and contraction of the concrete at the lap structure 9.
[0033] It is worth understanding that: the precast immersed tube section in this application is cast as a whole, not cast in sections and then assembled according to the conventional technology; however, the precast immersed tube section contains multiple segmented steel cages 3, and each steel cage 3 is tied and overlapped together in sections; therefore, the "segmented" mentioned in this application mainly refers to each segment of steel cage, or the part of the precast immersed tube corresponding to each segment of steel cage, rather than the segmented precast immersed tube itself.
[0034] By setting the rollers 201 or airbags 41 on the bottom formwork, the bottom formwork 2 can roll freely, reducing the friction between the bottom formwork 2 and the precast platform 1; by setting the elastic sealing mechanism, the bottom formwork 2 can be prevented from leaking out during concrete pouring, while meeting the expansion and contraction requirements of large-volume concrete during pouring and curing; by setting the lap structure 9 of the reinforcing cage, the expansion and contraction requirements of large-volume concrete during pouring and curing can be further met, and the connection of the reinforcing cage 2 in the overall immersed tube can be realized.
[0035] The integral casting and sinking system in this embodiment also includes an inner mold located in the reinforcing cage 3 when the precast sinking pipe is poured with concrete, and an outer mold (generally including side molds and end molds) erected outside the reinforcing cage 3; the bottom mold, inner mold and outer mold together form a template for pouring concrete, so that the precast sinking pipe is formed by pouring in the space enclosed by the template.
[0036] The second embodiment of this application provides a method for prefabricating a immersed tunnel, employing the monolithic casting immersed tunnel system described in any of the preceding embodiments. This prefabrication method includes the following steps: Reinforcing cage 3 binding: Erect a reinforcing cage support on the bottom formwork 2, and then bind the reinforcing bars. The two are erected and bound alternately to form the reinforcing cage 3; lap joints are reserved at the ends of the reinforcing cage 3.
[0037] More specifically, firstly, the bottom slab reinforcement is tied on the bottom formwork 2; then, a reinforcement cage support is erected, and the side wall reinforcement and top slab reinforcement are tied. When tying the side wall reinforcement, lap joints are reserved at the ends, thus forming a mechanically connected section of the reinforcement cage 3.
[0038] Moving the reinforcing cage 3: Move the tied reinforcing cage 3 onto the precast platform 1 and position it. If the reinforcing cage 3 is tied in an external tying area, it needs to be moved; if the reinforcing cage 3 is tied directly on the precast platform 1, its position can be adjusted according to the actual situation.
[0039] Erecting the inner formwork: Lift the top slab reinforcement bars, remove the reinforcement cage support, push the inner formwork into the reinforcement cage 3, and the top slab reinforcement bars fall down, completing the load-bearing system conversion.
[0040] The steps of binding the reinforcing cage, moving the reinforcing cage, and erecting the inner formwork can all be achieved using conventional techniques in this field, which are common construction methods in the field of immersed tunnel prefabrication.
[0041] Integrated construction: The steps of binding the steel cage, moving the steel cage and erecting the inner formwork are carried out separately for the multiple steel cages of a precast immersed tube; then the lap joints 901 and 902 of the adjacent steel cages 3 are bound and spliced together to assemble the inner formwork into one piece; the adjacent bottom formwork 2 are cooperated and sealed by the elastic sealing mechanism 5.
[0042] Concrete pouring: An outer formwork is erected for the reinforcing cage 3, and each bottom formwork 2 is locked to the precast platform 1 (i.e., the bottom formwork 2 cannot slide relative to the precast platform 1). At this time, the elastic sealing mechanism 5 between adjacent bottom formsworks is in a pre-compressed state and can expand and continue to be compressed. Tie rods are used to tighten the inner and outer formswork, and tie rods are also used to tighten adjacent sections of the outer formwork, ensuring no relative sliding between the formwork sections. Then, the concrete pouring of one section of the precast tunnel is completed in one go within the multiple sections of the reinforcing cage surrounded by the formwork, connecting all the reinforcing cages into a single unit. During pouring, two concrete pump stations can be used to pour from one end to the other, or multiple concrete pump stations can be used to accelerate the pouring speed.
[0043] Post-pouring adjustment: After pouring, for example, within 24-48 hours, you can choose to unlock the lock between the bottom formwork 2 and the precast platform 1 at approximately 24, 26, 28, 30, 32, 35, 38, 40, 42, or 45 hours after pouring, allowing relative movement between adjacent bottom formworks. Release the tension between other formworks approximately 7 days later.
[0044] For concrete used in construction, the composition varies due to different building requirements, resulting in differences in setting time and strength. For concrete used in existing precast tunnel sections, generally, the concrete reaches its initial forming state within 24-48 hours after pouring, at which point its compressive strength is approximately 20-30% of its strength 28 days after pouring. After approximately 7 days of curing with the formwork (i.e., approximately 7 days after pouring), the concrete's compressive strength is approximately 70-80% of its strength 28 days after pouring, basically meeting the demolding requirements. 40-60 days after pouring, the concrete strength development is complete, and the shrinkage or expansion during the tunnel precasting process is essentially finished, thus completing the tunnel precasting. Those skilled in the art will understand that in the post-pouring adjustment steps, to unlock the lock between the bottom mold 2 and the precast platform 1, the poured concrete is unlikely to be in a flowing state at this time. This application defines the unlocking point as the initial forming state. In the initial forming stage, even if the platform and bottom formwork are unlocked, it will not structurally disturb the prefabrication process of the immersed tube. For example, at this time, the compressive strength of the concrete is approximately 20-30% of its strength 28 days after pouring. Moreover, unlocking at this time allows the shrinkage and expansion during the prefabrication process of the immersed tube to be unrestricted, thus preventing cracking. With the development of concrete technology, even if the concrete does not reach the initial forming stage within 24-48 hours in the future, the unlocking time point of this application can be adjusted accordingly.
[0045] During the prefabrication of the immersed tunnel, the shrinkage and expansion of the concrete itself causes the bottom mold 2 to move slightly along the length of the tunnel, thus increasing or decreasing the compression of the elastic seal. Since the elastic seal is pre-compressed and can be further compressed or expanded, no gaps are created between adjacent bottom molds 2 due to movement. This design allows the poured concrete to effectively release internal stress during the prefabrication process, preventing cracking of the prefabricated tunnel.
[0046] Curing of the immersed tunnel: After the concrete pouring of the precast immersed tunnel is completed, it is cured with the formwork in place for about 7 days. After the concrete strength develops to meet the requirements for demolding, the inner and outer formwork are removed, and the immersed tunnel continues to be cured. During the curing process, the bottom formwork is kept in a state where limited relative movement is allowed. The poured concrete can effectively release shrinkage stress during the curing process; and curing each section of the immersed tunnel together can greatly save construction time compared to the conventional method of pouring and curing immersed tunnels in sections.
[0047] The prefabrication method for the immersed tube provided in this embodiment allows each segment of the immersed tube to slide freely along the length of the immersed tube, minimizing the shrinkage constraint of the immersed tube concrete along the length direction and significantly reducing the risk of cracking. In addition, it eliminates the conventional curing process between the completion of the immersed tube segment pouring and the pouring of the post-pouring strip, which is expected to significantly shorten the construction period of the immersed tube prefabrication by 40-60 days and effectively improve construction efficiency.
[0048] In one embodiment, when the precast platform 1 is provided with a track 101 and each bottom mold 2 is provided with a roller 201 matching the track at its bottom; in the rebar cage moving step, the tied rebar cage 3 can be moved onto the precast platform 1 and positioned by the cooperation of the roller 201 and the track 101; in the concrete pouring step, the roller 201 is braked and locked onto the track 101, so that each bottom mold 2 and the precast platform 1 are mutually locked; in the post-pouring adjustment step, the roller 201 is released from braking, thereby unlocking the bottom mold 2 and the precast platform 1.
[0049] In another embodiment, when multiple airbags 41 and limiting mechanisms 42 are provided between the precast platform 1 and each bottom mold 2; In the concrete pouring step, the following scheme is adopted to achieve mutual locking between each bottom mold 2 and the precast platform 1: multiple airbags 41 located below the bottom mold 2 are inflated, and each airbag is arranged along the width direction of the sinking pipe and parallel to each other; the limiting mechanism 42 starts to work (that is, the lifting column 421 extends upward from the precast platform 1 and gets stuck in the limiting groove 422 of the bottom mold 2), thereby restricting the movement of the bottom mold 2 in the length and width directions.
[0050] In the post-pouring adjustment step, the air pressure of each airbag 41 is adjusted so that each bottom mold 2 is approximately on the same horizontal plane. Within 24-48 hours after pouring, the limiting mechanism 42 is retracted (i.e., the lifting column 421 retracts into the precast platform 1), unlocking the lock between the bottom mold 2 and the precast platform 1, allowing the bottom mold to slide freely along the length of the precast tunnel under the support of the airbags 41. During the tunnel curing step, the bottom mold remains in a slidable state.
[0051] Furthermore, considering that the stability of the airbag 41 may not be as good as that of the roller, in order to limit the mutual misalignment of the bottom molds 2 during the casting process, the bottom molds 2 in this embodiment preferably adopt a tongue and groove connection structure 7, such as... Figure 4 and Figure 6 As shown.
[0052] Finally, it should be noted that the various embodiments in this specification are described in a progressive manner, with each embodiment focusing on the differences from other embodiments. The same or similar parts between the various embodiments can be referred to each other.
[0053] The above embodiments are only used to illustrate the technical solutions of this application and not to limit them; although this application has been described in detail with reference to preferred embodiments, those skilled in the art should understand that modifications can still be made to the specific embodiments of this application or equivalent substitutions can be made to some technical features without departing from the spirit of the technical solutions of this application, and all such modifications should be covered within the scope of the technical solutions claimed in this application.
Claims
1. A system for integral cast-in-place pipe laying, characterized in that, include: Precast platforms are used to provide casting space for the overall casting of precast immersed tubes; as well as Multiple bottom molds are used for binding and supporting the segmented steel cages, and also serve as part of the formwork for the precast immersed tube; At least during the casting of the precast immersed tube, each bottom mold is located on the precast platform and connected end to end; The precast platform and each bottom mold are configured to slide relative to each other, and adjacent bottom molds are configured to move relative to each other; the precast immersed tube is formed by non-segmented casting. During the casting of the precast immersed tube, the precast platform and each bottom mold are locked together; after the casting is completed, the lock between the precast platform and each bottom mold is unlocked. Furthermore, during the curing of the precast immersed tube, the precast platform and each bottom mold are configured to slide relative to each other, so that adjacent bottom molds can move relative to each other. Multiple inflatable and ventable airbags and limiting mechanisms are provided between the precast platform and each bottom mold; wherein, the airbags are arranged along the width direction of the precast tube; the airbags are configured to allow relative sliding between the precast platform and each bottom mold when inflated; the limiting mechanisms are configured to restrict or allow relative sliding between the precast platform and each bottom mold.
2. The system for integral cast-in-place pipes according to claim 1, characterized in that, Each bottom formwork supports a section of reinforcing cage; the ends of the reinforcing cages form extended lap joints, and the lap joints between adjacent reinforcing cages are staggered to form a lap structure that can be used for pouring concrete.
3. The system for integral cast-in-place pipes according to claim 2, characterized in that, Each section of the reinforcing cage is mechanically connected internally, with a length of 18-25m; the lap length between adjacent reinforcing cages is not less than 28d, where d is the diameter of the lapped reinforcing bars.
4. The system for integral cast-in-place pipes according to claim 1, characterized in that, The limiting mechanism includes a lifting column disposed on the precast platform and a limiting groove disposed on the bottom mold that cooperates with the lifting column; wherein the lifting column is configured to extend from the precast platform to engage in the limiting groove of the bottom mold, thereby limiting the relative sliding between the precast platform and each bottom mold; and to retract from the limiting groove to allow the relative sliding between the precast platform and each bottom mold.
5. The system for integral cast-in-place pipes according to any one of claims 1-4, characterized in that, An elastic sealing mechanism is provided between adjacent bottom molds to enable relative movement between them; wherein the elastic sealing mechanism is selected from one or more of the following combinations: Option 1: The elastic sealing mechanism is a flat joint structure, including a vertical straight first gap formed between adjacent bottom molds, and a first elastic sealing element located in the first gap; the first elastic sealing element is configured to: be pre-pressed between adjacent bottom molds when concrete is poured for the precast tube; and be able to expand or continue to be compressed after concrete is poured. Option 2: The elastic sealing mechanism is a tongue-and-groove connection structure, including a bent second gap extending downwards between adjacent bottom molds, and a second elastic seal and a third elastic seal located in the second gap, respectively located at the upper and lower parts of the second gap; the second elastic seal and the third elastic seal are respectively configured to: be pre-compressed between adjacent bottom molds when concrete is poured for the precast tube; and be able to expand or continue to be compressed after concrete is poured; Option 3: The elastic sealing mechanism is a stepped connection structure, with adjacent bottom molds defined as the first bottom mold and the second bottom mold, respectively. The first bottom mold has a stepped first extension, and the second bottom mold has a stepped second extension, with the two extensions staggered. A third gap is formed between the body of the first bottom mold and the second extension, in which a fourth elastic seal is provided. A fourth gap is formed between the body of the second bottom mold and the first extension, in which a fifth elastic seal is provided. The fourth and fifth elastic seals are configured to: be pre-pressed between adjacent bottom molds during concrete pouring of the precast tunnel; and be able to expand or continue to be compressed after concrete pouring.
6. The system for integral cast-in-place pipes according to any one of claims 1-4, characterized in that, The precast platform is located inside the dock so that the precast immersed tube can be poured and cured inside the dock; the integrated casting immersed tube system also includes an inner formwork located in the reinforcing cage when the precast immersed tube is poured with concrete, and an outer formwork erected outside the reinforcing cage; wherein, the bottom formwork, the inner formwork and the outer formwork together constitute the template when pouring concrete.
7. A method for prefabricating immersed tubes, characterized in that, The system for integral casting of immersed tubes, as described in any one of claims 1-6, is used for the integral casting of precast immersed tubes; the precasting method includes the following steps: Reinforcing cage binding: Binding the reinforcing cage to the bottom formwork; Rebar cage movement: Move the tied rebar cage onto the precast platform and position it. Erecting the inner formwork: Lift the top slab reinforcement of the steel cage, remove the steel cage support, push the inner formwork into the steel cage, and lower the top slab reinforcement to complete the load-bearing system conversion; Integrated construction: For a precast immersed tube, the steps of binding the steel cage, moving the steel cage and erecting the inner formwork are carried out separately for the multiple steel cages; then the lap joints of the adjacent steel cages are bound together to assemble the inner formwork into one piece; an elastic sealing mechanism is set between the adjacent bottom formworks to achieve elastic fit and sealing. Concrete pouring: The outer formwork of the steel cage is erected, and each bottom formwork is locked to the precast platform; at this time, the elastic sealing mechanism is in a pre-compression state and can be stretched or continued to be compressed; the formwork is controlled to be tightened so that there is no relative sliding between the formwork; then the concrete pouring of a precast pipe section is completed in one go in the multi-section steel cage surrounded by the formwork, so that all the steel cages are connected into a whole. Post-pouring adjustment: After the concrete reaches the initial forming state, release the locking between the bottom formwork and the precast platform so that the adjacent bottom formswork can be moved relative to each other. Maintenance of the immersed tunnel: After curing with the template, remove the inner and outer templates and continue to maintain the maintenance of the immersed tunnel; maintain the sliding state between each bottom template and the precast platform, as well as the relative movable state between the bottom templates.
8. The prefabrication method for immersed tubes according to claim 7, characterized in that, When multiple airbags and limiting mechanisms are installed between the precast platform and each bottom mold; during the concrete pouring step, the multiple airbags located below the bottom mold are inflated, with each airbag parallel to each other and arranged along the width direction of the precast tube; the limiting mechanisms are activated to lock each bottom mold and the precast platform together; during the adjustment step after pouring, the air pressure of each airbag is adjusted so that each bottom mold is on the same horizontal plane; within 24-48 hours after pouring, the limiting mechanisms are withdrawn, releasing the lock between the bottom mold and the precast platform, so that the bottom mold can slide along the length direction of the precast tube under the support of the airbags; during the curing step of the tube, the sliding state of the bottom mold is maintained.