A shield tunneling advance drilling and injecting construction device and method

By fixing the pitching frame with the hydraulic cylinder of the shield machine's foot shoe and using a snap-fit ​​mechanism, the problem of vibration transmission of the advanced drilling rig was solved, realizing the stability and safety of shield tunneling construction, and enabling the drilling and grouting reinforcement functions of the advanced hole.

CN118499005BActive Publication Date: 2026-11-24CHINA RAILWAY SOUTHWEST SCI RES INST CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410778382.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-06-17
Publication Date
2026-11-24
Estimated Expiration
2044-06-17

AI Technical Summary

Technical Problem

During tunnel boring machine (TBM) construction, vibrations caused by the pre-drilling rig are transmitted to the segment assembly machine, causing damage, which is difficult to effectively solve with existing technologies.

Method used

The pitching frame is fixed to the installed tunnel segments by the hydraulic cylinder of the shield machine's foot shoe. The connection between the pitching mechanism and the mounting frame is disconnected. The clamping mechanism is used to prevent vibration transmission. The drilling and grouting mechanisms are combined to realize the drilling and grouting construction of the advance hole.

Benefits of technology

It effectively avoids damage to the segment assembly machine caused by vibration during drilling and grouting, ensuring construction stability and safety, while also realizing the functions of drilling and grouting reinforcement of the pre-hole.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118499005B_ABST
    Figure CN118499005B_ABST
Patent Text Reader

Abstract

This invention relates to the field of shield tunneling pre-drilling construction technology, and discloses a shield tunneling pre-drilling construction device and method. The device includes a mounting frame, a pitching mechanism, a drilling mechanism, and several clamping mechanisms. The pitching mechanism includes a pitching frame and a pitching hydraulic cylinder, and the drilling mechanism includes a propulsion beam. One end of the mounting frame can be connected to a segment assembly machine. The pitching frame is mounted on the other end of the mounting frame through the clamping mechanisms. The propulsion beam and the pitching frame are rotatably connected. Both ends of the pitching hydraulic cylinder are rotatably connected to the propulsion beam and the pitching frame, respectively. A clamping and fixing plate is provided on the pitching frame. During construction, the clamping and fixing plate can be pressed against the front end of the installed tunnel segment by the shield machine's foot shoe hydraulic cylinder, thereby fixing the pitching frame and separating it from the mounting frame to prevent the vibration generated during the drilling construction from being directly transmitted to the segment assembly machine and causing damage to the segment assembly machine.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of shield tunneling pre-drilling and grouting construction technology, specifically to a shield tunneling pre-drilling and grouting construction device and method. Background Technology

[0002] During shield tunneling, the complex geological conditions of the surrounding rock mean that preliminary geological surveys often fail to provide a detailed understanding of the entire mountain's geological situation, leading to frequent unpredictable geological disasters. Therefore, it is necessary to conduct advanced geological forecasting concurrently with the tunneling process, utilizing advanced drilling rigs for pre-drilling or grouting reinforcement of weak geological formations ahead. The advanced drilling hole of the shield tunneling machine is located around the perimeter of the shield shell and slopes outwards. The relatively narrow internal structural space of the shield tunneling machine presents challenges for the installation of the advanced drilling rig. Current technology involves directly fixing the advanced drilling rig to the segment assembler for pre-drilling. However, the advanced drilling rig vibrates during operation, and this vibration is transmitted to the segment assembler through the connection between the advanced drilling rig and the segment assembler, inevitably causing damage to the segment assembler. Summary of the Invention

[0003] The purpose of this invention is to overcome the shortcomings of the prior art and provide a shield tunneling pre-drilling construction device and method. Before drilling construction, the device can press the pitching frame onto the installed tunnel segments by the shield machine's foot shoe cylinder, thereby fixing the drilling mechanism and simultaneously disconnecting the pitching machine from the installation frame to avoid the vibration generated during drilling construction being directly transmitted to the segment assembly machine and causing damage to the segment assembly machine.

[0004] The objective of this invention is achieved through the following technical solution: A shield tunneling pre-drilling and grouting construction device includes an installation frame, an elevation mechanism, a drilling and grouting mechanism, and several clamping mechanisms. The elevation mechanism includes an elevation frame and an elevation hydraulic cylinder. The drilling and grouting mechanism includes a propulsion beam, which is rotatably connected to the elevation frame. Both ends of the elevation hydraulic cylinder are rotatably connected to the propulsion beam and the elevation frame, respectively. A clamping and fixing plate is provided on the elevation frame. One side of the clamping and fixing plate is adapted to the shield machine's foot shoe cylinder, and the other side of the clamping and fixing plate is adapted to the front end of the installed tunnel segment. One end of the mounting frame can be connected to the segment assembly machine, and the pitching frame is slidably mounted on the other end of the mounting frame. The sliding direction of the pitching frame is parallel to the extension and retraction direction of the piston rod of the shield machine's foot shoe cylinder. The locking mechanism includes a locking block, a locking groove, and a spring. The locking groove is fixedly mounted on the pitching frame, the locking block is fixedly connected to the mounting frame, the locking groove is adapted to the locking block, the locking block is located on the side of the locking groove near the shield machine's foot shoe cylinder, and the spring is used to provide elastic force to press the locking groove towards the locking block.

[0005] Furthermore, the card block and the card slot are engaged by a wedge-shaped connection.

[0006] Furthermore, the drilling mechanism includes a rock drill and a clamping device. The rock drill is slidably mounted on the propulsion beam, and the clamping device is fixedly installed at one end of the propulsion beam. The clamping device is located in front of the output end of the rock drill.

[0007] Furthermore, the drilling and injection mechanism also includes a grouting mechanism, which includes a grouting housing and a connecting shaft. The connecting shaft passes through the grouting housing and is rotatably connected to it. A cavity is provided inside the grouting housing. A grouting hole is machined inward at one end of the connecting shaft, and the grouting hole communicates with the cavity. A grouting joint communicating with the cavity is also provided on the grouting housing. The grouting mechanism is located between the clamping device and the rock drill. The grouting housing is slidably connected to the propulsion beam. An external thread is machined at one end of the connecting shaft near the grouting hole, and the other end of the connecting shaft is connected to the output end of the rock drill.

[0008] Furthermore, the drilling mechanism also includes a support plate and an adjusting hydraulic cylinder. The support plate is rotatably connected to the pitching frame, and both ends of the pitching hydraulic cylinder are rotatably connected to the support plate and the pitching frame, respectively. The propulsion beam is slidably mounted on the support plate, and both ends of the adjusting hydraulic cylinder are connected to the support plate and the propulsion beam, respectively.

[0009] A method for advanced drilling and grouting construction in shield tunneling involves a aforementioned advanced drilling and grouting construction device for shield tunneling, and also involves a segment assembly machine, a shield machine foot shoe cylinder, and installed tunnel segments. The mounting frame is fixedly installed on the segment assembly machine. The method refers to: before the drilling and grouting mechanism is started to carry out drilling and grouting construction, the piston rod of the shield machine foot shoe cylinder extends to press the clamping and fixing plate against the end of the installed tunnel segment to fix the pitching frame.

[0010] Specifically, the advanced drilling and grouting construction method for shield tunneling includes the following steps: S1. The axial position and circumferential outward placement of the propulsion beam in the tunnel are adjusted by the segment assembly machine, and the tilt angle of the propulsion beam is adjusted by the pitch hydraulic cylinder. S2. The piston rod of the shield machine foot shoe cylinder, which is directly opposite the clamping and fixing plate, extends to press the clamping and fixing plate against the front end of the installed tunnel segment. At the same time, the pitching frame slides on the mounting frame under the push of the shield machine foot shoe cylinder, compressing the spring and causing the slot to disengage from the block. S3. The drilling and injection mechanism completes the drilling and injection process; S4. The piston rod of the shield machine foot shoe cylinder facing the clamping and fixing plate retracts, and under the action of the spring, pushes the pitching frame to slide on the mounting frame until the slot engages with the block.

[0011] The beneficial effects of this invention are: The shield tunneling advance drilling and grouting construction device includes an installation frame, an elevation mechanism, a drilling and grouting mechanism, and several clamping mechanisms. The drilling and grouting mechanism is mounted on the elevation mechanism, which can be mounted on the segment assembly machine via the installation frame. The segment assembly machine can transport the elevation mechanism and the installation frame to the borehole area to be constructed. The elevation mechanism can adjust the angle of the drilling and grouting mechanism, enabling the drilling and grouting construction of the advance hole. Based on this, a clamping and fixing plate is installed on the elevation frame. During drilling and grouting, the piston rod of the shield machine's foot shoe cylinder extends, pressing the clamping and fixing plate against the front end of the installed tunnel segment. The clamping mechanism includes a spring and matching clamping blocks and slots. The clamping blocks are located on the installation frame, and the slots are located on the elevation mechanism. The elevation mechanism and the installation frame are clamped together by these blocks and slots. When the piston rod of the shield machine's foot shoe cylinder extends, it can push the elevation mechanism to slide on the installation frame, causing the clamping blocks and slots (i.e., the elevation mechanism and the installation frame) to separate. Therefore, when the drilling and injection mechanism is started, the vibration generated by the drilling and injection mechanism during the drilling and injection process can be avoided from being directly transmitted to the segment assembly machine and causing damage to the segment assembly machine. Attached Figure Description

[0012] Figure 1 This is a schematic diagram of the overall structure of a shield tunneling pre-drilling and injection construction device according to the present invention; Figure 2 This is a schematic diagram of the clamping mechanism and the connection structure between the pitching frame and the mounting frame in a shield tunneling pre-drilling construction device of the present invention. Figure 3 This is a schematic diagram of the usage state of the shield tunneling pre-drilling and injection construction device of the present invention; Figure 4 This is a schematic diagram of the assembly structure of the pitching mechanism and the drilling mechanism in a shield tunneling pre-drilling and grouting construction device of the present invention. Figure 5 This is a schematic diagram of the internal structure of the grouting mechanism in a shield tunneling pre-drilling and grouting construction device of the present invention; In the diagram, 1-drilling mechanism, 2-pitch mechanism, 3-mounting frame, 4-segment assembly machine, 5-tunnel segment, 6-advance hole, 7-shield shell, 8-slot, 9-block, 10-spring, 11-propulsion beam, 12-rock drill, 13-clamping mechanism, 14-grouting shell, 15-connecting shaft, 16-cavity, 17-grouting hole, 18-grouting joint, 19-support plate, 20-adjusting hydraulic cylinder, 21-pitch frame, 22-pitch hydraulic cylinder, 23-clamping plate. Detailed Implementation

[0013] The technical solution of the present invention will be further described in detail below with reference to the accompanying drawings, but the scope of protection of the present invention is not limited to the following description.

[0014] like Figures 1 to 5 As shown, a shield tunneling pre-drilling construction device includes a mounting frame 3, an elevation mechanism 2, a drilling mechanism 1, and several clamping mechanisms. The elevation mechanism 2 includes an elevation frame 21 and an elevation hydraulic cylinder 22, and the drilling mechanism 1 includes a propulsion beam 11. One end of the mounting frame 3 can be connected to a segment assembly machine 4, and the elevation frame 21 is mounted on the other end of the mounting frame 3. When the construction device is mounted on the segment assembly machine 4, it can be moved along the tunnel excavation direction and circumferentially by the segment assembly machine 4 during tunnel excavation to adjust the drilling position. The propulsion beam 11 is rotatably connected to the elevation frame 21, and both ends of the elevation hydraulic cylinder 22 are rotatably connected to the propulsion beam 11 and the elevation frame 21, respectively. The extension and retraction of the elevation hydraulic cylinder 22 can change the inclination angle of the propulsion beam 11 on the elevation frame 21, thereby adjusting the drilling direction.

[0015] A clamping and fixing plate 23 is provided on the pitching frame 21. One side of the clamping and fixing plate 23 is adapted to the shield machine's foot shoe cylinder, and the other side of the clamping and fixing plate 23 is adapted to the front end of the installed tunnel segment 5. The pitching frame 21 is slidably connected to the end of the mounting frame 3 away from the segment assembly machine 4, and the sliding direction of the pitching frame 21 is parallel to the extension and retraction direction of the piston rod of the shield machine's foot shoe cylinder. The locking mechanism includes a locking block 9, a locking groove 8, and a spring 10. The locking groove 8 is fixedly installed on the pitching frame 21, the locking block 9 is fixedly connected to the mounting frame 3, and the locking block 9 is located on the side of the locking groove 8 near the shield machine's foot shoe cylinder. The spring 10 is used to provide elastic force to press the locking groove 8 towards the locking block 9.

[0016] like Figure 3 As shown, during shield tunneling, as the excavation progresses, the segment assembler 4 and the shield machine's hydraulic cylinder simultaneously assemble the tunnel segments 5 in the area behind the excavated tunnel. Several pre-drilling holes 6 inclined outwards are arranged around the shield shell 7 in front of the tunnel. This shield tunneling pre-drilling and grouting construction device is specifically used for drilling or grouting these pre-drilling holes 6. During construction, this shield tunneling pre-drilling and grouting construction device must be used in conjunction with the shield machine's hydraulic cylinder and the segment assembler 3. The shield tunneling pre-drilling and grouting construction method for each pre-drilling hole 6 includes the following steps: S1. Adjust the axial position and circumferential outward orientation of the propulsion beam 11 in the tunnel using the segment assembly machine 3, so that the front end of the propulsion beam 11 is directly facing the opening of the advance hole 6; then adjust the tilt angle of the propulsion beam 11 using the pitch hydraulic cylinder 22, so that the propulsion beam 11 is advanced along the axial direction of the advance hole 6.

[0017] S2. After completing the above position adjustment, extend the piston rod of the shield machine foot shoe cylinder facing the clamping and fixing plate 23. During its extension, the piston rod can push the pitching frame 21 to slide on the mounting frame 3 via the clamping and fixing plate 23. During this sliding process, the spring 10 is compressed until the shield machine foot shoe cylinder presses the clamping and fixing plate 23 against the front end of the installed tunnel segment 5. At this time, the slot 8 is just separated from the locking block 9. It should be noted that in specific implementation, in order to ensure that the slot 8 is just separated from the locking block 9 when the clamping and fixing plate 23 is pressed against the front end of the tunnel segment 5 by the shield machine foot shoe cylinder, the axial position needs to be adjusted more accurately in step S1.

[0018] S3. Start the drilling and grouting mechanism 1 to complete the drilling or grouting process.

[0019] S4. After drilling is completed, the piston rod of the shield machine foot shoe cylinder facing the clamping and fixing plate 23 retracts. During this retraction, the spring 8 pushes the pitching frame 21 to slide back on the mounting frame 3 until the slot 8 engages with the block 9. Under the elastic force of the spring 8, the slot 8 can be pressed against the block 9 to make the two securely engaged, thus completing the connection between the pitching frame 21 and the mounting frame 3.

[0020] As can be seen from the above working process, before the drilling mechanism 1 of the shield tunneling advanced drilling and grouting construction device starts drilling and grouting construction, the shield machine's foot shoe cylinder first anchors and fixes the pitching frame 21 by pressing, and at the same time disconnects the connection between the pitching frame 21 and the mounting frame 3. This can effectively reduce and avoid the vibration generated during the drilling and grouting construction process from being directly transmitted to the segment assembly machine 4 and causing damage to the segment assembly machine 4.

[0021] It should be noted that the aforementioned shield machine foot shoe cylinder is a component of the shield machine, also called a segment propulsion cylinder. Multiple cylinders are arranged circumferentially along the shield machine and are used for the splicing and installation of tunnel segments. The shield machine foot shoe cylinder is arranged parallel to the tunnel axis, and when its piston rod extends, it is directly opposite the front end of the installed tunnel segment 5. During the advance drilling construction in front of the shield, tunnel segments 5 have already been assembled at the rear, and the assembly work at the rear has been suspended. During construction, by setting up the clamping and fixing plate 23, the shield machine foot shoe cylinder can be used to clamp and fix the pitching frame 21. Thus, within the confined space inside the shield machine, without adding too many structures, the installation and fixing method of this construction device is switched, avoiding damage to the segment assembly machine 4 caused by vibration transmission during construction. As for the impact of vibration generated during construction on this clamping and fixing method, since the shield machine foot shoe cylinder is a hydraulic cylinder structure, it will not be damaged by rigid vibration and can also play a certain role in shock absorption.

[0022] The aforementioned snap-fit ​​mechanism is used to connect the pitching frame 21 to the mounting frame 3 via a snap-fit ​​connection, so as to smoothly complete the circumferential outward adjustment of the propulsion beam 11 within the tunnel as described in step S1. In specific implementation, such as... Figure 2 As shown, the locking block 9 and the locking groove 8 are engaged by a wedging mechanism. Specifically, the two sides of the locking block 9 are beveled, and the opening of the locking groove 8 is V-shaped. A beveled plate is connected to the end of the locking block 9 away from the mounting bracket 3, and the top of the groove 9 is machined into a bevel that fits the beveled plate. Through the above-mentioned beveled surfaces, the locking block 9 and the locking groove 8 form a wedging engagement. In the aforementioned step S4, on the one hand, these beveled surfaces can guide the locking block 9 and the locking groove 8 to engage smoothly, and on the other hand, under the elastic force of the spring 10, the wedging becomes tighter and tighter, ensuring the stability of the engagement.

[0023] In specific implementation, such as Figure 4 As shown, the aforementioned drilling mechanism 1 includes a rock drill 12 and a clamping device 13. The rock drill 12 is slidably mounted on the feed beam 11, and the clamping device 13 is fixedly mounted on one end of the feed beam 12, positioned in front of the output end of the rock drill 12. The output end of the rock drill 12 can be connected to a drill rod, which is driven to rotate by the rock drill. The rock drill 12 can also slide on the feed beam 11 under the drive of a drive mechanism (such as a hydraulic cylinder, a chain drive mechanism driven by a motor, etc.), thereby completing the drilling process described in step S3. The clamping device 13 can clamp or release the drill rod to facilitate the extension or disassembly of the drill rod.

[0024] Furthermore, the drilling and injection mechanism 1 also includes a grouting mechanism, such as... Figure 5As shown, the grouting mechanism includes a grouting housing 14 and a connecting shaft 15. The connecting shaft 15 passes through the grouting housing 14 and is rotatably connected to it. A cavity 16 is provided inside the grouting housing 14. One end of the connecting shaft 15 has a grouting hole 17 machined inwards, communicating with the cavity 16. A grouting connector 18 communicating with the cavity 16 is also provided on the grouting housing 14. The grouting mechanism is positioned between the clamping device 13 and the rock drill 12. The grouting housing 14 is slidably connected to the propulsion beam 11. One end of the connecting shaft 15 near the grouting hole 17 has an external thread, and the other end of the connecting shaft 15 is connected to the output end of the rock drill 12. The threaded end of the connecting shaft 15 is used to connect to a drill rod to complete the drilling process or to a grouting pipe to complete the grouting process. Specifically, when connecting the drill rod, the end of the drill rod is threadedly connected to the front end of the connecting shaft 15. When the rock drill 12 rotates, it drives the drill rod to rotate through the connecting shaft 15. The rock drill 12 and the grouting housing 14 slide together on the propulsion beam 11, thereby realizing the drilling process in step S3. When connecting the grouting pipe, the end of the grouting pipe is threadedly connected to the front end of the connecting shaft 15. The grouting pipe can be sent into the drilled hole by sliding together on the propulsion beam 11 with the rock drill 12 and the grouting housing 14. During this sending process, the external grout can be pumped to the grouting pipe in sequence through the grouting joint 18, the cavity 16, and the grouting hole 17, thereby realizing the grouting construction process in step S3. It can be seen that by setting this grouting mechanism, the construction device can simultaneously have the functions of advanced hole drilling and grouting reinforcement. It should also be noted that during grouting, because the diameter of the grouting pipe is smaller than the diameter of the borehole, the axis of the grouting pipe section already pushed into the borehole will deviate from the center of the borehole under its own weight. According to the existing grouting method, it is difficult to guarantee the grouting quality if grouting is carried out after the grouting pipe is fully installed. With the above setting, grouting can be carried out simultaneously with the grouting pipe being pushed into the borehole. The injected grout can support the part of the grouting pipe that is pushed into the borehole, so that the axis of the grouting pipe is basically coincident with the axis of the borehole, thus ensuring the grouting quality.

[0025] In specific implementation, such as Figure 4 As shown, the aforementioned drilling mechanism 1 also includes a support plate 19 and an adjusting hydraulic cylinder 20. The support plate 19 is rotatably connected to the pitching frame 21. Both ends of the pitching hydraulic cylinder 22 are rotatably connected to the support plate 19 and the pitching frame 21, respectively. When the piston rod of the pitching hydraulic cylinder 22 extends or retracts, it can adjust the tilt angle of the support plate 19 on the pitching frame 21, thereby adjusting the tilt angle of the propulsion beam 11. The propulsion beam 11 is slidably mounted on the support plate 19. Both ends of the adjusting hydraulic cylinder 20 are connected to the support plate 19 and the propulsion beam 11, respectively. When the piston rod of the adjusting hydraulic cylinder 20 extends or retracts, it can drive the propulsion beam 11 to slide on the support plate 19, thereby adjusting the distance between the front end of the propulsion beam 11 and the opening of the lead hole 6.

[0026] The above description is merely a preferred embodiment of the present invention. It should be understood that the present invention is not limited to the forms disclosed herein and should not be construed as excluding other embodiments. It can be used in various other combinations, modifications, and environments, and can be altered within the scope of the concept described herein through the above teachings or related technologies or knowledge. Modifications and variations made by those skilled in the art that do not depart from the spirit and scope of the present invention should be within the protection scope of the appended claims.

Claims

1. A shield tunneling pre-drilling and grouting construction device, characterized in that, Includes mounting bracket, pitching mechanism, drilling mechanism and several clamping mechanisms; The pitch mechanism includes a pitch frame and a pitch hydraulic cylinder. The drilling mechanism includes a propulsion beam, a rock drill, and a clamping device. The rock drill is slidably mounted on the propulsion beam. The clamping device is fixedly mounted on one end of the propulsion beam and is located in front of the output end of the rock drill. The propulsion beam is rotatably connected to the pitch frame. Both ends of the pitch hydraulic cylinder are rotatably connected to the propulsion beam and the pitch frame, respectively. The pitching frame is equipped with a clamping and fixing plate. One side of the clamping and fixing plate is adapted to the shield machine's foot shoe cylinder, and the other side of the clamping and fixing plate is adapted to the front end of the installed tunnel segment. When the piston rod of the shield machine's foot shoe cylinder, which is directly opposite the clamping and fixing plate, extends, the clamping and fixing plate can be pressed against the front end of the installed tunnel segment. One end of the mounting frame can be connected to the segment assembly machine, and the pitching frame is slidably mounted on the other end of the mounting frame. The sliding direction of the pitching frame is parallel to the extension and retraction direction of the piston rod of the shield machine's foot shoe cylinder. The locking mechanism includes a locking block, a locking groove, and a spring. The locking groove is fixedly mounted on the pitching frame, and the locking block is fixedly connected to the mounting frame. The locking groove is adapted to the locking block, and the locking block is located on the side of the locking groove near the shield machine's foot shoe cylinder. The spring is used to provide elastic force to press the locking groove towards the locking block. When the clamping and fixing plate is pressed against the front end of the installed tunnel segment by the shield machine's foot shoe cylinder, the locking groove disengages from the locking block. When the shield machine's foot shoe cylinder releases the fixing state of the clamping and fixing plate, the locking groove and the locking block engage under the action of the spring.

2. The shield tunneling pre-drilling and grouting construction device according to claim 1, characterized in that, The card block and card slot are engaged by a wedge-type engagement.

3. The shield tunneling pre-drilling and grouting construction device according to claim 1, characterized in that, The drilling and injection mechanism also includes a grouting mechanism, which includes a grouting housing and a connecting shaft. The connecting shaft passes through the grouting housing and is rotatably connected to the grouting housing. A cavity is provided inside the grouting housing. A grouting hole is machined inward at one end of the connecting shaft and communicates with the cavity. A grouting joint communicating with the cavity is also provided on the grouting housing. The grouting mechanism is located between the clamping device and the rock drill. The grouting housing is slidably connected to the propulsion beam. The end of the connecting shaft near the grouting hole is machined with an external thread, and the other end of the connecting shaft is connected to the output end of the rock drill.

4. The shield tunneling advance drilling and grouting construction device according to claim 3, characterized in that, The drilling mechanism further includes a support plate and an adjusting hydraulic cylinder. The support plate is rotatably connected to the pitching frame, and both ends of the pitching hydraulic cylinder are rotatably connected to the support plate and the pitching frame, respectively. The propulsion beam is slidably mounted on the support plate, and the two ends of the adjusting hydraulic cylinder are respectively connected to the support plate and the propulsion beam.

5. A method for advance drilling and grouting construction in shield tunneling, characterized in that, The invention relates to a shield tunneling pre-drilling and grouting construction device as described in any one of claims 1 to 4, and further relates to a segment assembly machine, a shield machine foot shoe cylinder, and installed tunnel segments, wherein the mounting frame is fixedly installed on the segment assembly machine, and the method refers to: Before the drilling mechanism starts drilling, the piston rod of the shield machine's foot shoe cylinder extends to press the clamping and fixing plate against the end of the installed tunnel segment to fix the pitching frame.

6. The method for advance drilling and grouting construction in shield tunneling according to claim 5, characterized in that, Includes the following steps: S1. The axial position and circumferential outward orientation of the propulsion beam in the tunnel are adjusted by the segment assembly machine, and the tilt angle of the propulsion beam is adjusted by the pitch hydraulic cylinder. S2. The piston rod of the shield machine foot shoe cylinder, which is directly opposite the clamping and fixing plate, extends to press the clamping and fixing plate against the front end of the installed tunnel segment. At the same time, the pitching frame slides on the mounting frame under the push of the shield machine foot shoe cylinder, compressing the spring and causing the slot to disengage from the block. S3. The drilling and injection mechanism completes the drilling and injection process; S4. The piston rod of the shield machine foot shoe cylinder facing the clamping and fixing plate retracts, and under the action of the spring, pushes the pitching frame to slide on the mounting frame until the slot engages with the block.

Citation Information

Patent Citations

  • Shield tunneling advance drilling and grouting construction device

    CN222162609U

  • Shield tunneling advance drilling and grouting construction device facilitating hole alignment adjustment

    CN223767497U