Construction method of connecting section of underground station of super-large rectangular continuous sinking well in soft soil layer
By using the N-Jet method for ultra-high pressure grouting reinforcement and retaining and water-blocking plate support, the safety and waterproofing issues of continuous caisson connection section construction in soft soil strata were solved, achieving rapid and low-cost construction results.
Patent Information
- Application Number
- CN202410807948.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-21
- Publication Date
- 2026-11-20
- Estimated Expiration
- 2044-06-21
AI Technical Summary
In soft soil strata, it is difficult to construct the connecting sections between continuous caissons safely, quickly, and cost-effectively, especially in confined water environments where traditional excavation methods are difficult to implement.
The N-Jet method was used for ultra-high pressure grouting reinforcement. The excavation was carried out in layers and retaining walls and water barriers were erected for support. Combined with temporary steel supports and the layered removal of sealing walls, the side walls and floor slabs of the connecting sections were constructed step by step to ensure the waterproofing effect.
It enables safe and rapid construction of the connection section, reduces construction costs, and effectively ensures waterproofing during and after construction. It is suitable for the construction of underground station connection sections in soft soil strata.
Smart Images

Figure CN118517018B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of underground space engineering construction technology, and in particular to a construction method for the connection section of an underground station with an ultra-large rectangular continuous caisson in soft soil strata. Background Technology
[0002] The single-shaft method has a long history and is mainly used for bridges and large-scale foundation projects. Currently, its application is gradually increasing in municipal pipeline networks, underground utility tunnels, and urban underground multi-level parking garages. The continuous caisson method for underground rail transit stations is a first in China. The continuous caisson construction process for underground stations involves prefabricating structures on the ground and then sinking them to predetermined underground locations to complete the station construction. This is a novel construction method for underground stations in soft soil and water-rich areas. For example, a station is a two-level underground island platform station with a main structure of a two-level underground rectangular frame structure. The station is 283.4 meters long and is formed by the continuous sinking of seven caisson sections at close range to form the main framework. The connecting sections between the caissons are then connected to form the entire station. Since the construction of an underground station using continuous caissons is a first in China, there is no experience to draw upon for the construction of the connecting sections between the continuous caissons. If traditional trenching machines were used for direct excavation, the large excavation depth would make construction difficult in the event of confined water, resulting in high water control costs. Summary of the Invention
[0003] To address the problems existing in the prior art, the present invention aims to provide a construction method for the connection section of an underground station with an ultra-large rectangular continuous caisson in soft soil strata, so as to achieve safe and rapid construction of the connection section.
[0004] To achieve the above objectives, this invention proposes a construction method for the connection section of an underground station with an ultra-large rectangular continuous caisson in soft soil strata, comprising the following steps: S1. After the internal structure of the two adjacent sections of the caisson is completed, the bottom and sides of the connecting section between the two sections of the caisson are reinforced by grouting using the N-Jet method. S2. Excavate the soil layer of the connecting section in stages until the bottom of the connecting section pit is reached, and erect retaining and water-blocking plates along the excavation direction. After each section is excavated, the retaining and water-blocking plates of that section are installed. The retaining and water-blocking plates are erected on the left and right sides of the connecting section and cooperate with the walls of the two caissons to form a rectangle. All the retaining and water-blocking plates on the same side of the connecting section are connected together to form a sealing wall. S3. Temporary steel supports are erected between the floor slabs of each floor of the caisson, and the temporary steel supports are erected close to the connecting section. S4. End sealing walls and temporary side columns are pre-installed on the adjacent side of the two caissons. The end sealing walls and temporary side columns are arranged according to the floor level. The end sealing walls and temporary side columns on the adjacent side of the two caissons are removed from bottom to top in sequence, and the floor slabs of the corresponding floors are then constructed. At the same time, the left and right side walls of the connecting section are constructed. During the pouring of the left and right side walls, the retaining and water-blocking plates act as the side wall formwork and are poured together with the side walls. The floor slabs of each floor of the connecting section are at the same height as the floor slabs of each floor of the caisson, so as to realize the connection between the corresponding floors of the two caissons. S5. After the floor slabs of each connecting section reach the design strength, remove the temporary steel supports, pour the post-cast layer of each floor slab, and lay the waterproof layer. S6. Backfill the top of the caisson and connecting section and restore the road surface to its original state.
[0005] In the above scheme: In step S2, the earthwork excavation of the connecting section proceeds from the middle to both sides. The excavation advance of each section does not exceed 1m, and the excavation advance is the same as the height of a single retaining and water-retaining plate. Each section is equipped with two retaining and water-retaining plates, which are erected on the left and right sides of the connecting section.
[0006] In the above scheme: the spacing between the connecting sections is small, making it impossible to use large machinery for earthwork excavation. During excavation, small excavators and grab cranes are used to remove soil, and manual labor is used to make local adjustments before the installation of retaining walls and water barriers. During construction, rigid guardrails are installed at the top edge of the caisson to prevent personnel from falling from height.
[0007] In the above scheme: the distance between two adjacent caissons is 2.5m; the retaining and water-retaining plate is 2m long and 1m high; steel plate embedded parts are provided as protrusions at the four corners of the connecting section between the two adjacent caissons; the front and rear ends of the retaining and water-retaining plate are welded to the steel plate embedded parts of the two caissons respectively. The caissons are connected by steel retaining and water-retaining plates, and the retaining and water-retaining plates are connected to the steel plate embedded parts as a whole, providing soil retention and waterproofing functions for the foundation pit.
[0008] In the above scheme: the retaining and water-retaining plate includes a vertical sealing steel plate and a T-shaped steel beam extending forward and backward. The vertical sealing steel plate is welded between the steel plate embedded parts of the two caissons. The vertical section of the T-shaped steel beam is welded to the inner side of the vertical sealing steel plate. Several steel reinforcement through holes are provided at intervals on the transverse section of the T-shaped steel beam. The two retaining and water-retaining plates of the same segment are arranged opposite each other. The retaining and water-retaining plates are welded together, which is convenient for processing. The steel reinforcement through holes are reserved on the T-shaped steel beam, which facilitates the subsequent construction of structural steel reinforcement connections.
[0009] In the above scheme: the caisson is a single-column, double-span box-type structure, and the caisson includes a lower layer and a lower second layer.
[0010] In the above scheme: In step S4, firstly, the end sealing wall and temporary side columns of the second floor below the caisson are removed, and the bottom floor slab of the connecting section is poured; then, the end sealing wall and temporary side columns of the first floor below the caisson are removed, and the middle floor slab of the connecting section is poured; finally, the top floor slab of the connecting section is poured. The caisson and connecting section include the bottom floor slab, the middle floor slab and the top floor slab from bottom to top. Except for the bottom floor slab, which is composed only of slabs, the other floor slabs are composed of beams and slabs, with the slabs laid on the corresponding beams.
[0011] In the above scheme: In step S4, when pouring the left and right side walls, the reinforcement connection of the retaining and water-retaining plates is carried out in advance. All the reinforcement holes on the same longitudinal line are connected by reinforcement bars. During pouring, the retaining and water-retaining plates on the left side and their reinforcement bars are integrally poured into the left wall, and the retaining and water-retaining plates on the right side and their reinforcement bars are integrally poured into the right wall. The retaining and water-retaining plates are poured into the side wall concrete as a whole, forming reinforced concrete, which does not need to be removed. This saves construction steps, increases the load-bearing capacity of the left and right side walls, and ensures the waterproof effect after the station is completed.
[0012] The beneficial effects of this invention are: 1. By employing the N-jet method for ultra-high pressure grouting reinforcement and water stoppage, layered excavation is carried out and retaining walls and water-blocking plates are erected to support the bottom of the pit. Temporary replacement supports are then erected, and the temporary sealing walls are removed from bottom to top, followed by the sequential construction of the connecting section side walls and each floor slab. After the top slab of the connecting section reaches the design strength, the replacement supports are removed, and the post-cast layer is poured. Backfilling and restoring the road surface to its original state are then achieved, realizing safe and rapid construction of the connecting section with low cost and good construction effect. 2. Based on the N-jet method reinforcement, retaining walls and water-blocking plates are erected promptly after each segment of the connecting section is excavated. The retaining walls and water-blocking plates can prevent external soil from flowing into the connecting section and also play a waterproof role, preventing external water from seeping in. This effectively ensures the waterproof effect of the station during and after construction, making this invention applicable to the construction of underground station connecting sections in soft soil strata. Attached Figure Description
[0013] Figure 1 This is a structural schematic diagram of the station project.
[0014] Figure 2 This is a schematic diagram of reinforcement using the N-Jet method.
[0015] Figure 3 This is a schematic diagram of the installation of retaining walls and water barriers.
[0016] Figure 4 This is a schematic diagram of the temporary steel support erection.
[0017] Figure 5 This is a schematic diagram of the removal of the second-floor end sealing wall and temporary side columns under the caisson, and the pouring of the bottom floor slab of the connecting section.
[0018] Figure 6This is a schematic diagram of the removal of the lower end sealing wall and temporary side columns of the caisson, and the pouring of the middle floor slab of the connecting section.
[0019] Figure 7 This is a schematic diagram of the top floor slab of the pouring connection section.
[0020] Figure 8 This is a schematic diagram of the removal of temporary steel supports.
[0021] Figure 9 This is a schematic diagram of backfilling and restoring the road surface to its original state.
[0022] Figure 10 This is a top view of the retaining wall and water barrier.
[0023] Figure 11 This is a left or right view of the retaining wall and water barrier.
[0024] Figure 12 This is a front or rear view of the retaining wall and water barrier.
[0025] Figure 13 This is a schematic diagram of the skeleton platform construction.
[0026] Figure 14 This is a top view of the skeleton platform.
[0027] Figure 15 This is a schematic diagram of the full-span scaffolding setup. Detailed Implementation
[0028] like Figure 1 As shown in Figure 15, a construction method for the connection section of an underground station with an ultra-large rectangular continuous caisson in soft soil mainly consists of the following steps: S1. After the internal structure of the two adjacent sections of caisson 1 is completed, the bottom and sides of the connecting section 2 between the two sections of caisson 1 are reinforced by grouting using the N-Jet method. Specifically, the sides are reinforced by N-Jet method ultra-high pressure jet grouting φ4600 to the ground level of -40.00m, and the bottom is reinforced by N-Jet method ultra-high pressure jet grouting φ4600@2800 to the bottom of the cutting edge to the elevation of -38.500m.
[0029] 1. Construction process flow Pre-drilling → Lowering the shotcrete rod → Shotcreting → Forming the reinforced pile → Completing cleaning and relocation 2. On-site preparation ① Pile location layout The control points for jet grouting construction were determined using a total station, and the marks were buried. After the test lines were verified to be qualified, the pile positions were laid out on the ground using a steel ruler and test lines, and wooden piles were driven in to ensure that the center displacement deviation of the pile hole was less than 20mm.
[0030] ② Sewage discharge and mortar mixing system During the jet grouting process, 80-100% of the grout will be returned. This waste grout will be introduced into a sedimentation tank, and the settled water can be discharged in a pollution-free manner, depending on site conditions. The settled soil will be excavated and piled in a collection pit for centralized off-site transportation. Sedimentation and wastewater discharge will be integrated into the site's overall wastewater treatment system. The grout mixing system will be located near the cement silo for easy operation.
[0031] The 1N-jet requires a large volume of slurry to be discharged during the replacement of soil, so two slurry pits need to be set up, with the volume of each pit not less than 1.3 times the daily construction volume, and the volume of each sump pit not less than the daily completed volume.
[0032] The 2N-jet equipment occupies a large area, approximately 150 square meters. The distance between the shotcrete pump and the center of the pile should not exceed 50 meters. In particular, when the shotcrete depth exceeds 30 meters, the distance between the high-pressure shotcrete pump and the shotcrete machine should be controlled. When the distance exceeds 50 meters, the shotcrete pressure needs to be increased.
[0033] 3. Reinforcement Construction ①Pre-hole 1. Pre-drilling: The borehole diameter is φ180~220mm. After the drilling rig is in place, use a spirit level to align the rig body so that the drill rod axis is vertically aligned with the center of the borehole, with a deviation of no more than 20mm. After the borehole reaches the designed depth, remove the drill rod, inject stabilizing fluid into the hole to protect the borehole wall, and then remove the steel casing.
[0034] 2. Casing Protection: After drilling is completed, the drill pipe is pulled out, and stabilizing fluid is injected into the hole to protect the casing. A hydraulic casing puller is then used to pull out the casing in sections. The pilot hole depth can be more than 1m deeper than the designed depth.
[0035] ② Positioning of the jet drilling rig and lowering of the drill rod After drilling the pilot hole, position and center the N-jet ultra-high pressure jet drilling rig and adjust its level. Lower the drill rod section by section to the design elevation (the upper nozzle reaches the bottom elevation of the pile). When lowering each section of the drill rod, check whether the seals of the drill rod are intact. Replace any worn seals in time.
[0036] ③ Spraying After the drill rod reaches the design elevation (nozzle area), the rotation speed, lifting time, and step distance are set in the control computer. The high-pressure grouting pump and high-pressure air are turned on, and grouting is started slowly with increased pressure. Ultra-high pressure grouting is used during grouting. To ensure the quality of the pile bottom, after the nozzle sinks to the design depth and reaches the design pressure, it is rotated in the original position for more than 5 minutes. After the grout is flowing normally from the borehole opening, grouting and lifting can begin. To ensure the required pile diameter at the bottom, a second grouting stroke can be performed at the pile bottom.
[0037] ④ Jet boost After starting the high-pressure jet pump, spray from bottom to top, simultaneously clearing and discharging the mud. During jetting, first reach the predetermined jetting pressure, then gradually raise the jetting pipe to prevent it from twisting and breaking. The rotation and lifting of the drill rod should be continuous and uninterrupted. If the drilling rig malfunctions, stop lifting the drill rod to prevent pile breakage, and immediately inspect and troubleshoot the problem.
[0038] ⑤ Cleaning Each section of pipe must be flushed after disassembly and arranged neatly to ensure unobstructed flow.
[0039] ⑥ Drilling rig relocation To ensure the pile top elevation and quality, the grout nozzle is raised to 200mm above the designed pile top elevation and then spraying is stopped. The drill rod is then lifted and the outlet section is removed one by one. The drill rod, grouting pump and delivery pipeline are cleaned, and then the drilling rig is moved to the next hole.
[0040] ⑦ Waste slurry treatment The N-jet method uses 100% soil replacement, resulting in a large amount of mud. A dedicated mud storage pond is required. After the mud has solidified the next day, an excavator will dig out the solidified cement soil from the pond, let it dry, and then transport it to a designated disposal site. The mud pond is divided into two compartments, each with a volume of 1.5 times the daily completed work volume. A temporary stockpile with a volume of 1.3 times the daily completed work volume is also required.
[0041] 4N-jet reinforcement construction requirements The curing time for 1N-Jet ultra-high pressure jet grouting piles should not be less than 28 days, and the unconfined compressive strength of the cement-soil pile body at 28 days should not be less than 1.0 MPa.
[0042] For 2N-Jet ultra-high pressure jet grouting piles, ordinary Portland cement or Portland cement with a strength grade not lower than P•O42.5 should be used, and the cement content should not be less than 40% and the bentonite content should not be less than 10%.
[0043] The axial deviation of the pile body in the 3N-Jet method ultra-high pressure jet grouting should not exceed 1 / 200.
[0044] When using the 4N-Jet method for ultra-high pressure jet grouting in waterproof curtain systems, the pile body should meet self-seepage prevention requirements, and the permeability coefficient should not exceed 1*10. -7 / cm / s.
[0045] 5. The following regulations shall be met for jet grouting pile construction: ①After the cement grout injection pressure reaches the set value, the injection time at the bottom of the pile should be increased by no less than 1 minute based on the set time; ② The pile should be constructed by lifting and spraying in steps from bottom to top; the spraying position when the pile is completed should be higher than the design elevation, and the spraying can be stopped when the front spraying grouting device is lifted to 100mm above the design pile top elevation; ③ When spraying in a full circle, the step lifting distance should be 25mm~100mm; when spraying in a fan shape, the step lifting distance should be 50mm~200mm; and the number of rotations within each step lifting distance should not be less than 2.
[0046] After 60% of the piles are in place, the pile length, pile strength, and impermeability (when used as a water-stop curtain) should be inspected.
[0047] 7. The pile length and pile strength are tested by core drilling, and the impermeability can be tested by core drilling or field permeability test.
[0048] The quality inspection of piles for 8N-Jet ultra-high pressure jet grouting should be carried out 28 days after pile completion. The unconfined compressive strength test should be conducted using the core drilling method. The number of samples tested should not be less than 1% of the total number of piles, and not less than 3 piles.
[0049] S2. Excavate the soil layer of connecting section 2 in stages until the bottom of the connecting section pit is reached, and erect retaining and water-retaining plates 3 along the excavation direction, with a total depth of 18.19m. After each segment is excavated, the retaining and water-retaining plates 3 for that segment are installed. The retaining and water-retaining plates 3 are erected on the left and right sides of connecting section 2 and cooperate with the walls of the two caissons to form a rectangle. All the retaining and water-retaining plates 3 on the same side of connecting section 2 are connected together to form a sealing wall.
[0050] S3. Temporary steel supports 4 are erected between the floor slabs of each floor of the caisson 1, and the temporary steel supports 4 are erected close to the connecting section 2.
[0051] S4. End sealing walls 5 and temporary side columns are pre-installed on the adjacent side of the two caissons 1. The end sealing walls 5 and temporary side columns are arranged according to the floor level. The end sealing walls 5 and temporary side columns on the adjacent side of the two caissons 1 are removed sequentially from bottom to top, and the floor slabs of the corresponding floors are then constructed. At the same time, the left and right side walls of the connecting section 2 are constructed. During the pouring of the left and right side walls, the retaining and water-blocking plate 3 acts as the side wall template and is poured integrally with the side wall. The floor slabs of each floor of the connecting section 2 are at the same height as the floor slabs of each floor of the caisson 1, so as to realize the connection between the corresponding floors of the two caissons 1.
[0052] S5. After the floor slabs of each connecting section 2 reach the design strength, remove the temporary steel support 4, pour the post-cast layer of each floor slab, and lay the waterproof layer; the bottom slab is covered with a rolled waterproof layer, the top slab is sprayed with a waterproof layer, and the construction joint is filled with grouting pipe + expansion sealant.
[0053] S6, the top of caisson 1 and connecting section 2 were backfilled and the road surface was restored to its original state.
[0054] In step S2, the earthwork excavation of connecting section 2 proceeds from the middle to both sides. The excavation advance of each section does not exceed 1m, and the excavation advance is the same as the height of a single retaining and water-retaining plate 3. Two retaining and water-retaining plates 3 are provided on each section, and the two retaining and water-retaining plates 3 are erected on the left and right sides of connecting section 2.
[0055] Due to the small spacing between connecting sections 2, large machinery could not be used for earthwork excavation. During excavation, small excavators and grab cranes were used to remove soil, and manual labor was used to make local adjustments before the installation of retaining and water-blocking plates 3. During construction, rigid guardrails were installed at the top edge of the caisson 1 to prevent personnel from falling from height.
[0056] The distance between two adjacent caissons 1 is 2.5m. The retaining and water-retaining plate 3 is 2m long and 1m high. At the four corners of the connecting section 2, steel plate embedded parts are provided as protrusions for the two adjacent caissons 1. That is, the steel plate embedded parts are partially embedded in the caissons 1. The front and rear ends of the retaining and water-retaining plate 3 are welded to the steel plate embedded parts of the two caissons 1 respectively. The caissons 1 are connected by steel retaining and water-retaining plates. The retaining and water-retaining plate 3 and the steel plate embedded parts are connected as a whole, providing soil retention and waterproofing functions for the foundation pit.
[0057] The retaining and water-retaining plate 3 includes a vertical sealing steel plate 31 and a T-shaped steel beam 32 extending forward and backward with a T-shaped cross-section. The vertical sealing steel plate 31 is 20mm thick, and the T-shaped steel beam 32 is 16mm thick. The vertical sealing steel plate 31 is welded between the steel plate embedded parts of the two caissons 1. The vertical section of the T-shaped steel beam 32 is welded to the inner side of the vertical sealing steel plate 31. Several steel bar through holes 33 are provided at intervals on the transverse section of the T-shaped steel beam 32. The two retaining and water-retaining plates 3 of the same segment are arranged opposite each other. The retaining and water-retaining plates are welded together, which is convenient for processing. The T-shaped steel beam 32 has φ50 steel bar through holes 33 reserved for subsequent structural steel bar connection construction.
[0058] Caisson 1 is a single-column, double-span box-type structure, comprising a lower first floor and a lower second floor.
[0059] In step S4, firstly, the end sealing wall 5 and temporary side columns of the second floor below the caisson 1 are removed, and the bottom floor slab of the connecting section 2 is poured; then, the end sealing wall 5 and temporary side columns of the next floor below the caisson 1 are removed, and the middle floor slab of the connecting section 2 is poured; finally, the top floor slab of the connecting section 2 is poured. The caisson 1 and the connecting section 2 include a bottom floor slab, a middle floor slab and a top floor slab from bottom to top. Except for the bottom floor slab, which is composed only of slabs, the other floor slabs are composed of beams and slabs, with the slabs laid on the corresponding beams.
[0060] In step S4, when pouring the left and right side walls, the reinforcement connection of the retaining and water-retaining plates 3 is carried out in advance. All the reinforcement through holes 33 on the same longitudinal line are connected by reinforcement bars. During pouring, each retaining and water-retaining plate 3 on the left side and its reinforcement bars are poured as a whole into the left wall, and each retaining and water-retaining plate 3 on the right side and its reinforcement bars are poured as a whole into the right wall. The retaining and water-retaining plates 3 are poured as a whole with the side wall concrete to form reinforced concrete, which does not need to be removed. This saves construction steps, increases the load-bearing capacity of the left and right side walls, and ensures the waterproof effect after the station is completed.
[0061] The main structure of the caisson was constructed using the cast-in-place method. Each section of the caisson 1 can be constructed in four stages and sunk twice. The first two stages are used to construct the bottom support structure A of the caisson 1. Then, the bottom support structure A is sunk. After the bottom support structure A is sunk into place, the last two stages of the caisson 1 are constructed directly above the bottom support structure A using the cast-in-place method. This completes the construction of the main structure B of the caisson 1 and also completes the connection between the bottom support structure A and the main structure B. Finally, the entire caisson 1 is sunk into place. Specifically: A cutting edge 11 is provided around the bottom of the wall of the bottom support structure A. A cross beam 12 is provided inside the bottom support structure A. The top of the cross beam 12 is flush with the top of the cutting edge 11. The inner side of the cutting edge 11 protrudes from the wall of the bottom support structure A, thus forming a support platform a at the top of the cutting edge 11. Several longitudinal steel sections 6 are overlapped between the front support platform a and the cross beam 12, and between the rear support platform a and the cross beam 12. The longitudinal steel sections 6 are laid horizontally at intervals, and both ends of the longitudinal steel sections 6 are fixed to the corresponding support platform a or cross beam 12. Several transverse steel sections 7 are provided above the longitudinal steel sections 6. The transverse steel sections 7 extend between the left and right support platforms a and are laid horizontally at intervals. The longitudinal steel sections 6 and transverse steel sections 7 are combined to form a skeleton platform b. A full-span scaffold 8 is erected on the skeleton platform b. The height of the full-span scaffold 8 matches the design height of the main structure B. The cast-in-place construction of the main structure is completed through the full-span scaffold 8.
Claims
1. A construction method for the connection section of an underground station with an ultra-large rectangular continuous caisson in soft soil strata, characterized in that, Includes the following steps: S1. After the internal structure of the two adjacent sections of the caisson (1) is completed, the bottom and sides of the connecting section (2) between the two sections of the caisson (1) are reinforced by grouting using the N-Jet method. S2. Excavate the soil layer of the connecting section (2) in stages until the bottom of the connecting section pit is reached, and erect retaining and water-blocking plates (3) along the excavation direction. After each section is excavated, the retaining and water-blocking plates (3) of that section are installed. The retaining and water-blocking plates (3) are erected on the left and right sides of the connecting section (2) and are used in conjunction with the walls of the two caissons to form a rectangle. All the retaining and water-blocking plates (3) on the same side of the connecting section (2) are connected together to form a sealing wall. S3. Temporary steel supports (4) are erected between the floor slabs of each floor of the caisson (1), and the temporary steel supports (4) are erected close to the connecting section (2); S4. Remove the end sealing wall (5) and temporary side column on the adjacent side of the two caissons (1) from bottom to top, and then construct the floor slabs of the corresponding floors. At the same time, construct the left and right side walls of the connecting section (2). During the pouring of the left and right side walls, the retaining wall (3) serves as the side wall template and is poured together with the side wall. The floor slabs of each floor of the connecting section (2) are at the same height as the floor slabs of each floor of the caisson (1) so as to realize the connection between the corresponding floors of the two caissons (1). S5. After the floor slabs of each floor of the connecting section (2) reach the design strength, remove the temporary steel support (4), pour the post-cast layer of each floor slab, and lay the waterproof layer. S6. The top of the caisson (1) and connecting section (2) shall be backfilled and the road surface restored to its original state; In step S2, the earthwork excavation of the connecting section (2) proceeds from the middle to both sides. The excavation advance of each section does not exceed 1m, and the excavation advance is the same as the height of the single retaining and water-blocking plate (3). Two retaining and water-blocking plates (3) are provided on each section, and the two retaining and water-blocking plates (3) are erected on the left and right sides of the connecting section (2). During excavation, a small excavator and a grab crane are used to remove soil, and manual labor is used to make local repairs before the installation of the retaining and water-blocking plate (3). During construction, a hard guardrail is installed on the top edge of the caisson (1). The distance between two adjacent caissons (1) is 2.5m. The retaining and water-blocking plate (3) is 2m long and 1m high. At the four corners of the connecting section (2) of the two adjacent caissons (1), steel plate embedded parts are provided as protrusions. The front and rear ends of the retaining and water-blocking plate (3) are welded to the steel plate embedded parts of the two caissons (1) respectively. The retaining and water-blocking plate (3) includes a vertical sealing steel plate (31) and a T-shaped steel beam (32) extending forward and backward with a T-shaped cross section. The vertical sealing steel plate (31) is welded between the steel plate embedded parts of the two caissons (1). The vertical section of the T-shaped steel beam (32) is welded to the inner side of the vertical sealing steel plate (31). Several steel bar through holes (33) are provided at intervals in the transverse section of the T-shaped steel beam (32). The two retaining and water-blocking plates (3) of the same segment are arranged opposite to each other. In step S4, when pouring the left and right walls, the steel reinforcement connection of the retaining and water-blocking plates (3) is carried out in advance. All steel reinforcement holes (33) on the same longitudinal line are connected by steel reinforcement. During pouring, the retaining and water-blocking plates (3) on the left side and their steel reinforcement are poured into the left wall as a whole, and the retaining and water-blocking plates (3) on the right side and their steel reinforcement are poured into the right wall as a whole.
2. The construction method for the underground station connection section of an ultra-large rectangular continuous caisson in soft soil strata according to claim 1, characterized in that: The caisson (1) is a single-column double-span box-type structure, and the caisson (1) includes a lower layer and a lower second layer.
3. The construction method for the underground station connection section of an ultra-large rectangular continuous caisson in soft soil strata according to claim 2, characterized in that: In step S4, first remove the end sealing wall (5) and temporary side columns of the second floor below the caisson (1), and pour the bottom floor slab of the connecting section (2); then remove the end sealing wall (5) and temporary side columns of the next floor below the caisson (1), and pour the middle floor slab of the connecting section (2); finally pour the top floor slab of the connecting section (2).
Citation Information
Patent Citations
Subway station construction method based on open caisson method
CN111877382A
Continuous open caisson type subway station construction method and structure
CN116335188A