A construction method of a first layer reinforced concrete step without removing formwork

CN118547888BActive Publication Date: 2026-10-30CCCC RUITONG CONSTR ENG CO LTD +1
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410736354.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-06-07
Publication Date
2026-10-30
Estimated Expiration
2044-06-07

Smart Images

  • Figure CN118547888B_ABST
    Figure CN118547888B_ABST
Patent Text Reader

Abstract

The application relates to a first-layer reinforced concrete step formwork construction method, which comprises the following steps: S1, earthwork piling; S2, beam plate position excavation: the beam plate position of earthwork is excavated to form multiple beam plate excavation grooves; S3, brick formwork masonry: brick formwork is masoned in each beam plate excavation groove, and brick formwork is also masoned on the uppermost end and the lowermost end of the inclined surface of the pre-formed step earthwork; S4, cushion layer pouring; S5, steel bar binding and formwork entering: steel bar binding is carried out to form a steel framework, and the steel framework is put into each brick formwork; S6, bottom plate concrete pouring: concrete is poured in the brick formwork to form a concrete beam plate, concrete is poured on the concrete beam plate and the cushion layer to form a flat concrete inclined bottom plate; S7, secondary formwork setting: the step positions are determined on the concrete inclined bottom plate, and step formworks are set between the adjacent two step positions; and S8, step concrete pouring.
Need to check novelty before this filing date? Find Prior Art

Citation Information

Patent Citations

  • Construction method for brick forms of foundation platforms and grade beams

    CN104196049A

  • Construction method of slope step

    CN115095092A