A method for fixing a submarine pipeline by using a flow state solidified soil combined hoop device
By using a combination of fluidized solidified soil and clamps, the problems of high cost, poor stability, and inadequate scour prevention in the construction of submarine pipeline fixing have been solved, achieving efficient and low-cost submarine pipeline fixing and scour prevention.
Patent Information
- Application Number
- CN202410959465.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-17
- Publication Date
- 2026-11-20
- Estimated Expiration
- 2044-07-17
AI Technical Summary
Existing methods for fixing submarine pipelines suffer from high costs, high construction difficulty, poor stability, and difficulty in effectively preventing bottom current erosion.
A combined fluidized solidified soil clamp device is adopted. By installing upper and lower clamps and anchor bolt components on the seabed foundation, the fluidized solidified soil is used to wrap the subsea pipeline and clamp device to enhance the anchoring force and prevent bottom current erosion.
While reducing construction difficulty and cost, it improves the stability of submarine pipelines, prevents bottom flow erosion, is applicable to a wide range of soil types, and has high construction efficiency.
Smart Images

Figure CN118669609B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to a method for fixing submarine pipelines, specifically a method for fixing submarine pipelines using a combination of fluidized solidified soil and clamping device, belonging to the field of pipeline fixing construction technology. Background Technology
[0002] Submarine energy pipelines, whether exposed or buried on the seabed, are susceptible to horizontal displacement due to bottom current impacts, erosion of the subgrade by ocean currents, and soil loosening induced by earthquakes and pipe vibrations. This displacement can adversely affect the pipeline system, leading to increased stress on the pipeline cross-section, lateral buckling, or even pipeline rupture. Therefore, engineering practices require controlling lateral displacement within a certain range to maintain the lateral stability of the submarine pipeline. Furthermore, submarine pipelines are subject to buoyancy; when their own weight is insufficient to maintain stability, appropriate artificial measures must be implemented to ensure system stability. Simultaneously, long-term ocean currents can cause soil erosion and seabed evolution around the pipeline, resulting in localized suspension and potential damage. Given the complex underwater current environment, these erosion processes and evolutionary patterns are difficult to predict; therefore, securing the submarine pipeline is often essential to ensure its safe and stable operation.
[0003] Currently, submarine pipelines can be broadly categorized into three types based on their burial methods: First, exposed pipelines; when laid bare on the seabed with a rocky or relatively hard soil foundation, the pipeline's lateral movement can be directly caused by the forces of waves and currents, relying solely on its own weight to maintain lateral stability. Second, partially buried pipelines; shallow trenches are excavated, utilizing the lateral resistance of the soil to balance the pipeline's forces, maintaining stability through natural backfilling or no backfilling. Third, fully buried or deeply buried pipelines; in this case, the pipeline is no longer subject to wave or current loads, maintaining stability through its own weight and the weight of the top soil. All three burial methods have certain limitations. Exposed and partially buried pipelines require relatively good seabed soil (even rock), while fully buried or deeply buried pipelines require significant excavation and backfilling, making submarine construction more difficult and hindering efficient construction. Moreover, the stability of all three types of submarine pipeline burial methods is challenged by wave erosion and seismic induced loads.
[0004] Currently used construction methods to enhance the stability of subsea pipelines include: First, the weight-adding method; this involves increasing the weight of the pipeline by increasing the mass of the steel and adding a weighting layer to the outside. Although this method is the most convenient and requires no other engineering measures, only dimensional considerations in the design, its disadvantages include high cost and the inconvenience of constructing the concrete weighting layer, limiting its use to specific cases or localized sections. Second, the block method; this involves adding the required mass (such as specially made block concrete) to the pipeline after it has been laid, but a problem is that the pipeline and the block are prone to detachment under the influence of ocean currents. Third, the anchor bolt stabilization method; this uses special clamps, anchor bolts, and bonding materials to fix the pipeline to the seabed on a rocky foundation. Fourth, the helical anchor bolt or anchor pile anchoring method; for non-rocky soils, helical anchor bolts can be inserted into the seabed to fix the pipeline while it is laid bare. These methods are difficult to construct on the seabed, costly, and unsuitable for large-scale pipeline reinforcement.
[0005] Therefore, existing methods for fixing submarine pipelines are limited by factors such as cost, efficiency, safety, and construction efficiency, and cannot effectively prevent bottom current erosion. Summary of the Invention
[0006] Based on the above background, the purpose of this invention is to provide a method for fixing submarine pipelines using a combination of fluidized solidified soil and clamping device, which can ensure the stability of submarine pipelines under relatively small excavation conditions and achieve the effect of preventing bottom flow erosion.
[0007] To achieve the above-mentioned objectives, the present invention provides the following technical solution:
[0008] A method for fixing a subsea pipeline using a fluidized solidified soil combined clamp device, the clamp device comprising an upper clamp, a lower clamp, a fixing component, a top-pressing component, and multiple anchor bolt components, wherein a first end of the upper clamp is hingedly connected to a first end of the lower clamp, a second end of the upper clamp is detachably fixedly connected to a second end of the lower clamp via the fixing component, the top-pressing component is located at the top of the upper clamp, and the multiple anchor bolt components are spaced apart at the bottom of the lower clamp. The method includes the following steps:
[0009] A trench is excavated in the seabed foundation, the depth of which allows part of the outer contour of the clamping device to be exposed above the trench;
[0010] A clamping device is installed in the trench, so that the outer wall of the lower clamp abuts against the trench wall, the second end of the upper clamp is separated from the second end of the lower clamp, and the upper clamp is rotated along the first direction with the hinge part of the upper and lower clamps as the center, so that an opening is formed between the second end of the upper clamp and the second end of the lower clamp. The subsea pipeline is installed on the lower clamp through the opening, and the bottom outer wall of the subsea pipeline abuts tightly against the top of each anchor bolt component, so that at least a portion of the bottom end of at least two anchor bolt components is squeezed into the seabed foundation under the weight of the subsea pipeline.
[0011] Pull the second end of the upper clamp to make it rotate in a second direction opposite to the first direction, with the hinge of the upper and lower clamps as the center. During this time, the pressure is continuously applied to the subsea pipeline through the top pressure member, causing the subsea pipeline to sink relative to the lower clamp and press down on the anchor bolt components, so that at least two anchor bolt components are further squeezed into the seabed foundation until the second end of the upper clamp is connected to the second end of the lower clamp. Install the fixing member to fix the second end of the upper clamp to the second end of the lower clamp.
[0012] The pressure is continued to be applied to the subsea pipeline by the pressure jacking component, which will continue to squeeze the anchor bolt components into the seabed foundation until the pressure jacking component reaches the predetermined position.
[0013] The fluidized solidified soil is injected into the trench, filling the gaps between the clamping device, the subsea pipeline, and the trench to encase the subsea pipeline and the clamping device. The fluidized solidified soil then flows onto the seabed foundation around the clamping device. Once the fluidized solidified soil has hardened, the construction is complete.
[0014] Preferably, the pressing component includes a screw, a first spring, a pressing support, and a throttle. The throttle is fixedly connected to the top end of the screw. The screw is threadedly connected to the top end of the upper clamp, and the screw passes through the top end of the upper clamp. The pressing support is movably connected to the bottom end of the screw, and the relative position of the pressing support and the bottom end of the screw along the screw axis is fixed. The first spring is sleeved on the outside of the screw, with the top end of the first spring abutting against the inner wall of the upper clamp and the bottom end of the first spring abutting against the top end of the pressing support.
[0015] The pressure is continuously applied to the subsea pipeline by the pressure-pressing component, specifically by: rotating the handle to move the screw downward relative to the upper clamp until the pressure-pressing support abuts against the top of the subsea pipeline, and continuing to rotate the handle to continuously apply downward pressure to the subsea pipeline by the pressure-pressing support.
[0016] Preferably, the anchor bolt component includes an anchor bolt, a second spring, and a rotating support. The rotating support is hinged to the top end of the anchor bolt. The anchor bolt passes through the lower clamp and is movable relative to the lower clamp along the axial direction of the anchor bolt.
[0017] As a preferred option, pulling the second end of the upper clamp specifically includes:
[0018] An adjustable-length tension chain is used to pull the upper clamp. One end of the tension chain is connected to the second end of the upper clamp, and the other end of the tension chain is connected to the second end of the lower clamp. During the continuous application of downward pressure to the subsea pipeline through the top pressure component, the length of the tension chain is adjusted to keep it in a tensile state.
[0019] Preferably, the method further includes: after the second end of the upper clamp is fixed to the second end of the lower clamp by the installation fastener, the tension chain is removed.
[0020] Preferably, the number of anchor bolt components is three, one of which is vertically located at the bottom arc apex of the lower clamp, and the other two anchor bolt components are symmetrically distributed around the anchor bolt component located at the bottom arc apex of the lower clamp, and the extended lines of the axes of the three anchor bolt components all pass through the center of the ring formed by the upper clamp and the lower clamp.
[0021] Preferably, the trench has a V-shaped cross-section.
[0022] Preferably, the method further includes: when the second end of the upper clamp is connected to the second end of the lower clamp, two symmetrically distributed anchor bolt components are pressed into the seabed foundation according to a set length, and another anchor bolt component is pressed into the bottom of the trench according to a set length.
[0023] Preferably, the two symmetrically distributed anchor bolt components are located at the junction of the bottom of the lower clamp and the V-shaped groove.
[0024] Preferably, the fluidized solidified soil covers at least two-thirds of the outer surface area of the subsea pipeline.
[0025] Compared with the prior art, the present invention has the following advantages:
[0026] This invention discloses a subsea pipeline fixing construction method using a fluidized solidified soil combined with a clamp device. By setting multiple anchor bolt components, the anchoring force between the clamp device and the seabed foundation is increased, improving the stability of the clamp device on the seabed foundation. Simultaneously, pressure is applied to the anchor bolt components as they are pressed into the foundation while the subsea pipeline is fixed between the upper and lower clamps, reducing the construction difficulty of pressing the anchor bolt components into the foundation and improving construction efficiency. By injecting fluidized solidified soil, it is made into close contact with the trench, clamp device, and subsea pipeline. After hardening, the anchoring force is further improved, preventing bottom current erosion. This subsea pipeline fixing construction method overcomes the shortcomings of existing subsea pipeline fixing and erosion prevention methods, avoiding the large-scale excavation and backfilling work required for deeply buried pipelines. It has the advantage of a wide range of applicable soil types, and the number and length of the anchor bolt components can be flexibly adjusted according to soil conditions, solving problems such as difficulty in fixing subsea pipelines and poor erosion prevention effects. Attached Figure Description
[0027] To more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are only embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on the provided drawings without creative effort.
[0028] Figure 1 This is a schematic diagram of the clamp device in this invention;
[0029] Figure 2 This is a schematic diagram of the clamp device in the open state in this invention;
[0030] Figure 3 This is a partial schematic diagram of the lower structure of the clamp device in this invention;
[0031] Figure 4 This is a schematic diagram of step S1 of the subsea pipeline fixing construction method of the fluidized solidified soil combined clamp device of the present invention;
[0032] Figure 5 This is a schematic diagram of step S2 of the subsea pipeline fixing construction method of the fluidized solidified soil combined clamp device of the present invention;
[0033] Figure 6 This is a schematic diagram of step S3 in the subsea pipeline fixing construction method of the fluidized solidified soil combined clamp device of the present invention;
[0034] Figure 7 This is a schematic diagram of step S4 in the subsea pipeline fixing construction method of the fluidized solidified soil combined clamp device of the present invention;
[0035] Figure 8 This is a schematic diagram of step S5 in the construction method for fixing a submarine pipeline using a fluidized solidified soil combined clamp device according to the present invention.
[0036] Figure 9 This is a schematic diagram of step S6 in the subsea pipeline fixing construction method of the fluidized solidified soil combined clamp device of the present invention;
[0037] Figure 10 This is a cross-sectional view of the subsea pipeline after the subsea pipeline fixing construction is completed in this invention;
[0038] Figure 11 This is a top view of the subsea pipeline after the subsea pipeline fixing construction is completed in this invention;
[0039] Figure 12 This is a side view of the subsea pipeline after the subsea pipeline fixing construction is completed in this invention;
[0040] In the diagram: 1. Upper clamp; 2. Lower clamp; 3. Fixing component; 4. Top pressure component; 5. Anchor bolt component; 6. Seabed foundation; 7. Trench; 8. Subsea pipeline; 9. Tension chain; 10. Pump grout pipe; 11. Fluidized solidified soil; 401. Screw; 402. First spring; 403. Top pressure support; 404. Turning handle; 501. Anchor bolt; 502. Second spring; 503. Rotating support. Detailed Implementation
[0041] The technical solution of the present invention will be further described in detail below through specific embodiments and in conjunction with the accompanying drawings. It should be understood that the implementation of the present invention is not limited to the following embodiments, and any modifications and / or alterations made to the present invention will fall within the protection scope of the present invention.
[0042] In this invention, unless otherwise specified, all parts and percentages are by weight, and the equipment and raw materials used are commercially available or commonly used in the art. Unless otherwise specified, the methods in the following embodiments are conventional methods in the art. Unless otherwise specified, the components or equipment in the following embodiments are general standard parts or components known to those skilled in the art, and their structures and principles can be learned by those skilled in the art through technical manuals or conventional experimental methods.
[0043] The embodiments of the present invention will now be described in detail with reference to the accompanying drawings. In this detailed description, numerous specific details are set forth to facilitate explanation and provide a thorough understanding of the embodiments of the present invention. However, one or more embodiments may be practiced by those skilled in the art without these specific details.
[0044] This invention discloses a method for fixing submarine pipelines using a combination of fluidized solidified soil and clamping device. For example... Figure 1-3 As shown, the clamping device used in this method includes an upper clamp 1, a lower clamp 2, a fixing member 3, a pressing member 4, and three anchor bolt components 5. The first end of the upper clamp 1 is hinged to the first end of the lower clamp 2, and the second end of the upper clamp 1 is detachably fixed to the second end of the lower clamp 2 via the fixing member 3. The pressing member 4 is located at the top of the upper clamp 1, and the three anchor bolt components 5 are spaced apart at the bottom of the lower clamp 2. Specifically, one anchor bolt component 5 is vertically positioned at the bottom arc apex of the lower clamp 2, and the other two anchor bolt components 5 are symmetrically distributed around the anchor bolt component 5 located at the bottom arc apex of the lower clamp 2, with the extended axes of all three anchor bolt components 5 passing through the center of the ring formed by the upper clamp 1 and the lower clamp 2. Of course, the number of anchor bolt components 5 can be adjusted according to actual usage needs.
[0045] Specifically, the pressing component 4 includes a screw 401, a first spring 402, a pressing support 403, and a throttle 404. The throttle 404 is fixedly connected to the top end of the screw 401, and the screw 401 is threadedly connected to the top end of the upper clamp 1, with the screw 401 passing through the top of the upper clamp 1. The pressing support 403 is movably connected to the bottom end of the screw 401, and the relative position of the pressing support 403 and the bottom end of the screw 401 along the axis of the screw 401 is fixed. The first spring 402 is sleeved on the outside of the screw 401, with its top end abutting against the inner wall of the upper clamp 1 and its bottom end abutting against the top of the pressing support 403.
[0046] Specifically, the anchor bolt component 5 includes an anchor bolt 501, a second spring 502, and a rotating support 503. The rotating support 503 is hinged to the top end of the anchor bolt 501. The anchor bolt 501 passes through the lower clamp 2, and the anchor bolt 501 can move relative to the lower clamp 2 along the axial direction of the anchor bolt 501.
[0047] The method includes the following steps:
[0048] S1, such as Figure 4 As shown, a trench 7 is excavated on the seabed foundation 6. The depth of the trench 7 allows part of the outer contour of the clamping device to be exposed above the trench 7. The cross-section of the trench 7 is V-shaped. Of course, the shape and size of the trench 7 can be adjusted according to the specific conditions such as the diameter of the subsea pipeline and geological conditions.
[0049] S2, such as Figure 5 As shown, a clamping device is installed in the trench 7, so that the outer wall of the lower clamp 2 abuts against the trench wall of the trench 7. Since the cross-section of the trench 7 is V-shaped, the two symmetrically distributed anchor bolt components 5 are located at the junction of the bottom of the lower clamp 2 and the V-shaped trench 7. At this time, the first spring 402 of the top pressure component 4 and the second spring 502 of each anchor bolt component 5 are in a naturally extended state. The upper clamp 1 and the lower clamp 2 provide static pressure load for the three anchor bolt components 5 to press into the seabed foundation 6.
[0050] S3, such as Figure 6As shown, the second end of the upper clamp 1 is separated from the second end of the lower clamp 2, and the upper clamp 1 is rotated along the first direction with the hinge joint of the upper clamp 1 and the lower clamp 2 as the center, so that an opening is formed between the second ends of the upper clamp 1 and the lower clamp 2. The handle 404 is rotated so that the screw 401 is relative to the upper clamp 1 and compresses the first spring 402, providing sufficient construction space for the installation of the subsea pipeline 8. The subsea pipeline 8 is installed on the lower clamp 2 through the opening. The bottom outer wall of the subsea pipeline 8 is tightly abutted against the top of each anchor bolt component 5, that is, the rotating support 503 of each anchor bolt component 5. Since the rotating support 503 is hinged to the top of the anchor bolt 501, the surface of the rotating support 503 is always in close contact with the outer surface of the subsea pipeline 8 and is subjected to uniform force. Part of the bottom end of the two anchor bolt components 5 is squeezed into the seabed foundation 6 under the self-weight of the subsea pipeline 8. At this time, the second spring 502 of each anchor bolt 501 is under compression.
[0051] S4, such as Figure 7 As shown, an adjustable-length tension chain 9 is used to pull the upper clamp 1. One end of the tension chain 9 is connected to the second end of the upper clamp 1, and the other end of the tension chain 9 is connected to the second end of the lower clamp 2. Pulling the second end of the upper clamp 1 causes it to rotate in a second direction opposite to the first direction, with the hinge point of the upper clamp 1 and the lower clamp 2 as the center. During this process, the handle 404 is rotated to move the screw 401 downward relative to the upper clamp 1 until the top pressure support 403 abuts against the top of the subsea pipeline 8. The handle 404 is rotated again to make the top pressure support 403 continuously apply downward pressure to the subsea pipeline 8. The length of the tension chain 9 is adjusted to keep it under tension, causing the subsea pipeline 8 to sink relative to the lower clamp 2 and press down on the anchor bolt component 5. The two anchor bolt components 5 are then pressed into the seabed foundation 6 until the second end of the upper clamp 1 connects with the second end of the lower clamp 2. The fixing component 3 is installed to fix the second end of the upper clamp 1 and the second end of the lower clamp 2. After that, the tension chain 9 is removed. When the second end of the upper clamp 1 connects with the second end of the lower clamp 2, two symmetrically distributed anchor bolt components 5 are pressed into the seabed foundation 6 according to the set length, and another anchor bolt component 5 is pressed into the bottom of the trench 7 according to the set length.
[0052] S5, such as Figure 8 As shown, downward pressure continues to be applied to the subsea pipeline 8 through the top pressure member 4. The ring clamp acts as a reaction frame, providing static pressure reaction force, which causes the anchor bolt member 5 to continue to be squeezed into the seabed foundation 6 until the top pressure member 4 reaches the predetermined position and the locking screw 401 is locked. Under the joint support of the top pressure support 403, the first spring 402, the rotating support 503, and the second spring 502, the subsea pipeline 8 is firmly fixed in the ring clamp, becoming an integral structure with internal pre-compression and joint force. This structure is further fixed to the seabed foundation 6 by the anchor bolt member 5 to maintain its stability.
[0053] S6, such as Figure 9 As shown, fluidized solidified soil 11 is injected into trench 7 using a pump pipe 10 and other devices. Relying on the controllable fluidity of the slurry, the fluidized solidified soil 11 fills the gaps between the clamping device, the subsea pipeline 8, and the trench 7 to encapsulate the subsea pipeline 8 and the clamping device. The height of the pump pipe 10 is appropriately increased to allow the fluidized solidified soil 11 to flow onto the seabed foundation 6 around the clamping device. Preferably, the fluidized solidified soil 11 encapsulates at least two-thirds of the outer surface area of the subsea pipeline 8. Construction is completed after the fluidized solidified soil 11 hardens. The hardened fluidized solidified soil 11 increases the bearing capacity of the foundation around the anchor bolt component 5 and enhances the scour resistance of the seabed near the subsea pipeline 8, preventing the pipeline from becoming suspended due to bottom current erosion caused by excavation, and preventing pipeline structural damage and lateral slippage.
[0054] After construction is completed according to this method, the sectional view, top view, and side view of the submarine pipeline 8, the clamping device, and the fluidized solidified soil 11 are as follows: Figure 10-12 As shown.
[0055] This method increases the anchoring force between the clamping device and the seabed foundation 6 by setting multiple anchor bolt components 5, thereby improving the stability of the clamping device on the seabed foundation 6. Simultaneously, while the subsea pipeline 8 is fixed between the upper clamp 1 and the lower clamp 2, pressure is applied to press the anchor bolt components 5 into the foundation, reducing the construction difficulty of pressing the anchor bolt components 5 into the foundation and improving construction efficiency. By injecting fluidized solidified soil 11, it is made into close contact with the trench 7, the clamping device, and the subsea pipeline 8. After hardening, the anchoring force is further improved, preventing bottom current erosion.
[0056] This method makes up for the shortcomings of existing methods for fixing and preventing scour of submarine pipelines 8. It can avoid the large-scale excavation and backfilling work of deep-buried pipelines, and has the advantage of being applicable to a wide range of soil types. The number and length of anchor bolt components 5 can be flexibly adjusted according to the soil conditions, thus solving problems such as difficulty in fixing submarine pipelines 8 and poor scour prevention effect.
[0057] This article uses specific examples to illustrate the principles and implementation methods of the present invention. The descriptions of the above embodiments are only for the purpose of helping to understand the method and core ideas of the present invention. It should be noted that those skilled in the art can make several improvements and modifications to the present invention without departing from the principles of the present invention, and these improvements and modifications also fall within the protection scope of the claims of the present invention.
Claims
1. A method for fixing submarine pipelines using a combination of fluidized solidified soil and clamping device, characterized in that: The clamp device includes an upper clamp (1), a lower clamp (2), a fixing member (3), a pressing member (4), and multiple anchor bolt components (5). The first end of the upper clamp (1) is hinged to the first end of the lower clamp (2), and the second end of the upper clamp (1) is detachably fixed to the second end of the lower clamp (2) through the fixing member (3). The pressing member (4) is located on the top of the upper clamp (1), and the multiple anchor bolt components (5) are spaced apart at the bottom of the lower clamp (2). The method includes the following steps: A trench (7) is excavated on the seabed foundation (6), the depth of which allows part of the outer contour of the clamp device to be exposed above the trench (7); Install a clamping device in the trench (7) so that the outer wall of the lower clamp (2) abuts against the trench wall of the trench (7), separate the second end of the upper clamp (1) from the second end of the lower clamp (2), and rotate the upper clamp (1) along the first direction with the hinge part of the upper clamp (1) and the lower clamp (2) as the center, so that an opening is formed between the second end of the upper clamp (1) and the second end of the lower clamp (2), and install the submarine pipeline (8) on the lower clamp (2) through the opening. The bottom outer wall of the submarine pipeline (8) abuts tightly against the top of each anchor bolt component (5), so that at least a portion of the bottom end of at least two anchor bolt components (5) is squeezed into the seabed foundation (6) under the weight of the submarine pipeline (8). Pull the second end of the upper clamp (1) so that it rotates in a second direction opposite to the first direction with the hinge of the upper clamp (1) and the lower clamp (2) as the center. During this period, the pressure is continuously applied to the submarine pipeline (8) by the top pressure member (4), so that the submarine pipeline (8) sinks relative to the lower clamp (2) and presses down the anchor bolt member (5), so that at least two anchor bolt members (5) are continued to be squeezed into the seabed foundation (6) until the second end of the upper clamp (1) is connected to the second end of the lower clamp (2). Install the fixing member (3) to fix the second end of the upper clamp (1) to the second end of the lower clamp (2). The pressure is applied to the subsea pipeline (8) by the pressure member (4), so that the anchor bolt component (5) is pressed into the seabed foundation (6) until the pressure member (4) reaches the predetermined position. The fluidized solidified soil (11) is injected into the trench (7) to fill the gap between the clamp device, the subsea pipeline (8) and the trench (7) to wrap the subsea pipeline (8) and the clamp device, and the fluidized solidified soil (11) flows to the seabed foundation (6) around the clamp device. After the fluidized solidified soil (11) hardens, the construction is completed.
2. The method for fixing a subsea pipeline using a fluidized solidified soil combined with a clamp device according to claim 1, characterized in that: The top-pressing component (4) includes a screw (401), a first spring (402), a top-pressing support (403), and a throttle (404). The throttle (404) is fixedly connected to the top end of the screw (401). The screw (401) is threadedly connected to the top end of the upper clamp (1), and the screw (401) passes through the top end of the upper clamp (1). The top-pressing support (403) is movably connected to the bottom end of the screw (401), and the relative position of the top-pressing support (403) and the bottom end of the screw (401) along the axis of the screw (401) is fixed. The first spring (402) is sleeved on the outside of the screw (401). The top end of the first spring (402) abuts against the inner wall of the upper clamp (1), and the bottom end of the first spring (402) abuts against the top end of the top-pressing support (403). The pressure is continuously applied to the subsea pipeline (8) by the pressure member (4), specifically by rotating the handle (404) to move the screw (401) down relative to the upper clamp (1) until the pressure support (403) abuts the top of the subsea pipeline (8), and continuing to rotate the handle (404) to make the pressure support (403) continuously apply downward pressure to the subsea pipeline (8).
3. The method for fixing a subsea pipeline using a fluidized solidified soil combined clamp device according to claim 1, characterized in that: The anchor bolt component (5) includes an anchor bolt (501), a second spring (502), and a rotating support (503). The rotating support (503) is hinged to the top end of the anchor bolt (501). The anchor bolt (501) passes through the lower clamp (2), and the anchor bolt (501) can move relative to the lower clamp (2) along the axial direction of the anchor bolt (501).
4. The method for fixing a subsea pipeline using a fluidized solidified soil combined with a clamp device according to claim 1, characterized in that: Pulling the second end of the upper clamp (1) specifically includes: An adjustable-length tension chain (9) is used to pull the upper clamp (1). One end of the tension chain (9) is connected to the second end of the upper clamp (1), and the other end of the tension chain (9) is connected to the second end of the lower clamp (2). During the continuous application of downward pressure to the subsea pipeline (8) by the top pressure member (4), the length of the tension chain (9) is adjusted to keep it in a tensile state.
5. The method for fixing a subsea pipeline using a fluidized solidified soil combined with a clamp device according to claim 4, characterized in that: The method further includes removing the tension chain (9) after the second end of the upper clamp (1) is fixed to the second end of the lower clamp (2) by the installation fastener (3).
6. The method for fixing a subsea pipeline using a fluidized solidified soil combined with a clamp device according to claim 1, characterized in that: The number of anchor bolt components (5) is three. One anchor bolt component (5) is vertically located at the bottom arc top of the lower clamp (2). The other two anchor bolt components (5) are symmetrically distributed with the anchor bolt component (5) located at the bottom arc top of the lower clamp (2) as the center. The extended lines of the axes of the three anchor bolt components (5) all pass through the center of the ring formed by the upper clamp (1) and the lower clamp (2).
7. The method for fixing a subsea pipeline using a fluidized solidified soil combined with a clamp device according to claim 6, characterized in that: The cross-section of the groove (7) is V-shaped.
8. The method for fixing a submarine pipeline using a fluidized solidified soil combined with a clamp device according to claim 7, characterized in that: The method further includes: when the second end of the upper clamp (1) is connected to the second end of the lower clamp (2), two symmetrically distributed anchor bolt components (5) are pressed into the seabed foundation (6) according to a set length, and another anchor bolt component (5) is pressed into the bottom of the trench (7) according to a set length.
9. The method for fixing a submarine pipeline using a fluidized solidified soil combined with a clamp device according to claim 8, characterized in that: Two symmetrically distributed anchor bolt components (5) are located at the junction of the bottom sides of the lower clamp (2) and the V-shaped groove (7).
10. The method for fixing a subsea pipeline using a fluidized solidified soil combined clamp device according to claim 1, characterized in that: The fluidized solidified soil (11) covers at least two-thirds of the outer surface area of the submarine pipeline (8).