Visual aid-based open-pit coal mine slope deformation monitoring method and system

By using drones for multi-angle photography and intelligent algorithm analysis, the problems of real-time performance and accuracy in monitoring slope deformation in open-pit coal mines have been solved, achieving efficient and automated slope deformation detection and ensuring safe production.

CN118670262BActive Publication Date: 2026-11-24ZHUNGEER JINZHENGTAI COAL CO LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202410835162.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-06-26
Publication Date
2026-11-24
Estimated Expiration
2044-06-26

AI Technical Summary

Technical Problem

Traditional open-pit coal mine slope deformation monitoring methods suffer from blind spots, low efficiency, and poor data continuity, making it impossible to achieve real-time and accurate slope deformation monitoring, which makes it difficult to prevent safety hazards.

Method used

Drones equipped with high-definition cameras are used to capture images of the markers from multiple angles. Combined with intelligent algorithm analysis, slope deformation is monitored in real time, and the stability of the markers is assessed through grid units. Thresholds are set for early warning.

Benefits of technology

It enables high-precision detection of minute deformations on slopes, improves the level of automation in monitoring, timely detects early signs of deformation, ensures safety, reduces labor costs, improves the accuracy and timeliness of early warnings, and avoids geological disasters.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118670262B_ABST
    Figure CN118670262B_ABST
Patent Text Reader

Abstract

The present application relates to the technical field of open coal mine slope deformation monitoring, and discloses an open coal mine slope deformation monitoring method based on visual assistance, which comprises the following steps: using a UAV to divide monitoring areas on the surface of the open coal mine slope, and forming a monitoring area set by multiple monitoring areas; dividing multiple sub-monitoring areas in each monitoring area, and containing feature points in the sub-monitoring areas; and setting one feature point in each sub-monitoring area; the present application realizes high-precision detection of the slight deformation of the slope by using the UAV to carry high-definition camera equipment to shoot the open coal mine slope from multiple angles and at high frequency, and combining advanced image processing technology. This method not only improves the automation level of monitoring and reduces the labor cost, but also can discover early deformation signs of the slope in time through real-time data analysis, thereby providing a basis for preventing landslides and other geological disasters.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of slope deformation monitoring technology, specifically to a vision-assisted method and system for monitoring slope deformation in open-pit coal mines. Background Technology

[0002] Traditional open-pit coal mine slope deformation monitoring mainly relies on manual measurement and ground equipment. These methods suffer from problems such as monitoring blind spots, low efficiency, and poor data continuity. Slope stability is one of the key factors for safe production in open-pit coal mines. In the field of open-pit coal mine slope deformation monitoring technology, especially vision-assisted monitoring methods, various monitoring technologies and equipment are applied. These technologies include satellite navigation positioning measurement, 3D laser scanning measurement, digital close-range photogrammetry, total station corner measurement, total station trigonometric leveling, and geometric leveling.

[0003] Furthermore, emerging technologies such as ground-based SAR interferometry (GB-InSAR) have been applied to the real-time and accurate measurement of open-pit mine slopes in recent years, providing reliable early warning and management information. Slope radar technology also integrates various monitoring devices such as GNSS, inclinometers, crack gauges, rain gauges, and video surveillance to achieve comprehensive, all-weather, real-time automated monitoring. With the development of UAV technology, image processing technology, and big data analytics, vision-assisted monitoring methods are gradually becoming possible. These methods can overcome the shortcomings of traditional methods and achieve rapid and accurate monitoring of slope deformation.

[0004] Slope deformation monitoring is a crucial aspect of ensuring safety in open-pit coal mines, and the accuracy of this monitoring directly impacts the safety of personnel and equipment in the mining area. Slope deformation is often accompanied by the risk of geological disasters such as landslides, which can have severe consequences, potentially leading to casualties and property damage. Therefore, achieving real-time and accurate monitoring of slope deformation to promptly detect and warn of potential landslide risks is an urgent problem to be solved in the safety management of open-pit coal mines. Summary of the Invention

[0005] This invention provides a vision-assisted method for monitoring slope deformation in open-pit coal mines, effectively addressing the limitations of traditional monitoring methods in terms of real-time performance, accuracy, and automation. Real-time monitoring of slope deformation is a crucial task for ensuring mine safety during open-pit coal mining. Slope deformation monitoring requires integrating various real-time monitoring data and processing and risk assessment through an intelligent analysis system to make accurate decision-making. Existing slope monitoring systems largely rely on manual inspections or contact sensors, methods that are not only inefficient but also lack comprehensive coverage and real-time response. This invention utilizes high-definition cameras mounted on drones to proactively acquire real-time slope deformation data and analyzes it using intelligent algorithms, providing an innovative solution for open-pit coal mine slope safety management.

[0006] This invention provides the following technical solution: a vision-assisted method for monitoring slope deformation in open-pit coal mines, comprising:

[0007] Drones are used to delineate monitoring areas on the surface of open-pit coal mine slopes. Multiple monitoring areas form a monitoring area set, which is represented as S = {monitoring area A, monitoring area B, ..., monitoring area N}.

[0008] Each monitoring area is divided into multiple sub-monitoring areas, and each sub-monitoring area contains feature points. One feature point is set in each sub-monitoring area.

[0009] The feature point is the center position of the sub-monitoring area, which is a rectangle, and the center position is selected at the intersection of the two diagonals of the rectangle;

[0010] Feature points include the marker and the coordinates of the marker's initial position;

[0011] The drone takes photos of the sign from multiple angles. The drone selects angles A, B, C, D and E to take photos of the sign. Angles A and D are the front and back views of the sign, angles B and C are the left and right side views, and angle E is the top view of the sign.

[0012] Optional, including:

[0013] Set a fixed time interval to repeatedly photograph the marker from multiple angles;

[0014] The time interval between repeated shootings of the same landmark from multiple angles is T;

[0015] Get the drone's real-time battery level;

[0016] A drone shooting strategy is formulated based on time intervals and the drone's real-time battery level.

[0017] Optionally, the drone shooting strategy includes:

[0018] Set a power threshold;

[0019] The power threshold includes a minimum takeoff power threshold, which sets the minimum power percentage that the drone must meet before takeoff;

[0020] Set a power threshold, which is the percentage of battery the drone should maintain during mission execution;

[0021] The power level of each sub-monitoring area is obtained, and the power level of each sub-monitoring area is the power required for each sub-monitoring area to complete the shooting task.

[0022] After the shooting task in each sub-monitoring area is completed, determine whether the real-time battery level of the drone is less than the execution battery threshold.

[0023] If the drone's real-time battery level is greater than the execution battery threshold, it will continue to perform shooting tasks in other sub-monitoring areas;

[0024] If the drone's real-time battery level is lower than the execution battery threshold, it will not perform the shooting task, will return to the charging position to charge until it is fully charged, and will call on a drone that is not currently on a task to shoot the remaining sub-monitoring area.

[0025] Optional, including:

[0026] When the drone completes its shooting mission in a monitoring area, it executes a marker offset verification strategy.

[0027] The marker offset verification strategy is divided into preliminary screening and assessment and risk assessment.

[0028] The initial screening assessment is determined by analyzing the offset of individual markers in the sub-monitoring area;

[0029] The aforementioned risk assessment review involves reviewing sub-monitoring areas that were initially identified as unstable.

[0030] Analyze the horizontal and vertical displacements of the markers, where horizontal displacement refers to the lateral movement of the slope and vertical displacement indicates the subsidence or elevation of the slope.

[0031] Optionally, during the process of shooting a monitoring area, the UAV executes a marker offset verification strategy, including:

[0032] S1: After the marker is buried, the drone takes pictures from multiple angles to construct the three-dimensional coordinates of the marker, providing initial position information for offset detection, denoted as (X,Y,Z).

[0033] S2: After each time interval T, the drone takes a multi-angle photograph of the same landmark and calculates the landmark's coordinate information P.t = (X t ,Y t Z t );

[0034] Pt represents the coordinate information of the marker, which is divided into P1, P2, ..., Pn. P1 represents the coordinates of the marker after the first T cycle, and Pn represents the coordinates of the marker after the nth T cycle.

[0035] S3: Calculate the position offset between the marker coordinates and the initial position information (X, Y, Z), and calculate the position offset at the corresponding shooting time point. ;

[0036] Formula for calculating position offset:

[0037]

[0038] For the collected location data P1, P2, ..., P n Calculate the position offset separately;

[0039] ;

[0040] S4: Based on the position offset calculation formula, the position offset of the marker after a certain point in time is obtained;

[0041] S5: Conduct preliminary screening and evaluation, and set the offset threshold Δd;

[0042] S6: After each time interval T, the positional offset of the marker is compared with the offset threshold Δd;

[0043] If the position offset If Δd is found, the preliminary screening evaluation result of the marker is determined to be unstable and it can be marked as failing the preliminary screening evaluation.

[0044] If the position offset If Δd is obtained, the marker will continue to undergo position offset calculation and preliminary screening evaluation.

[0045] Optionally, during the process of shooting a monitoring area, the UAV executes a marker offset verification strategy, including:

[0046] S7: For markers that fail the initial screening assessment, a review risk assessment will be conducted. The review risk assessment is divided into vertical analysis and horizontal analysis.

[0047] The vertical direction analysis refers to the offset of the marker in the z-axis direction;

[0048] The horizontal analysis defines the offset and direction of each marker along the horizontal x-axis and y-axis.

[0049] A grid cell is defined, which is a sub-monitoring area 8 adjacent to a marker that has not passed the initial screening evaluation.

[0050] A risk threshold for neighboring markers is set, which is the proportion of unstable markers within a grid cell to all markers within that grid cell, and is set to 30%.

[0051] S8: Within the grid cell, calculate the vertical offset of the marker, with a vertical offset risk threshold of 50mm;

[0052] If the vertical offset of a marker within a grid cell is ≥50mm, it is considered an unstable marker.

[0053] If the vertical offset of the marker is ≤50mm, then the horizontal direction of the marker should be analyzed.

[0054] If the proportion of unstable markers in the grid cell is greater than the risk threshold of neighboring markers, then the area where the markers that failed the preliminary screening assessment are located is considered to have slope deformation.

[0055] If the proportion of unstable markers within a grid cell is less than the risk threshold of neighboring markers, then the markers are analyzed in the horizontal direction.

[0056] Set a horizontal offset risk threshold of 75 mm to determine the risk threshold of the horizontal offset of the marker within the grid cell.

[0057] If the horizontal offset of a marker is ≥75mm and its offset direction is consistent with the center marker of the grid cell, it is marked as an unstable marker.

[0058] Obtain the translation direction of the markers that failed the initial screening evaluation, and record it as the positive direction;

[0059] Specifically, the coordinates of all markers in the grid cell are obtained. A horizontal analysis line is drawn based on the coordinates of the markers that failed the initial screening evaluation. This analysis line is perpendicular to the horizontal translation direction of the markers that failed the initial screening evaluation. All markers located on the positive side of the horizontal analysis line are identified and denoted as reference markers. The number of reference markers is denoted as U.

[0060] The number of reference markers whose horizontal offset direction is the same as the positive direction and whose horizontal offset is ≥75mm is denoted as Q;

[0061] If Q / U≥30%, then the area where the marker that failed the preliminary screening assessment is located is considered to have slope deformation.

[0062] S9: Set the risk threshold for the monitoring area to 20%. If the proportion of unstable grid cell areas in the monitoring area is greater than the risk threshold, then the monitoring area is unstable.

[0063] If the proportion of unstable grid cell regions in the monitoring area is less than the risk threshold of the monitoring area, then the monitoring area is stable.

[0064] A system for monitoring slope deformation in open-pit coal mines based on vision assistance.

[0065] The drone monitoring module is used to select feature points on the slope surface and photograph markers to collect visual data;

[0066] The information acquisition module is used to acquire real-time location information of markers, slope environmental parameters, and UAV status information, and transmit them to the data processing center;

[0067] The control module, connected to the UAV monitoring module and the information acquisition module, is used to control the UAV monitoring module to execute the shooting strategy based on the information collected by the information acquisition module.

[0068] Optionally, the control module further includes:

[0069] The threshold management unit is used for historical data analysis and setting standard displacement thresholds, and triggers an alert when the monitored data exceeds the threshold.

[0070] The task scheduling unit is used to intelligently plan the drone's shooting tasks and flight routes based on the needs of slope deformation monitoring and the drone's battery status.

[0071] Optionally, the control module further includes:

[0072] The data analysis unit is used to process the data transmitted by the information acquisition module, calculate the displacement and displacement ratio of the markers, and provide quantitative basis for stability assessment.

[0073] The stability assessment unit is used to evaluate the stability status of the slope based on the results of the data analysis unit.

[0074] Optionally, the system further includes:

[0075] The user interaction module provides users with functions such as real-time monitoring data display, historical data analysis, and early warning information reception, and allows users to set and adjust monitoring parameters as needed;

[0076] The report generation unit is used to generate regular monitoring reports, including displacement data, stability assessment results, and early warning records, for users and managers to review and archive.

[0077] This invention provides a vision-assisted method and system for monitoring slope deformation in open-pit coal mines, which has the following advantages:

[0078] 1. This invention achieves high-precision detection of minute deformations in open-pit coal mine slopes through multi-angle, high-frequency imaging. This method not only improves the automation level of monitoring and reduces labor costs, but also enables timely detection of early signs of slope deformation through real-time data analysis, providing a basis for preventing geological disasters such as landslides.

[0079] 2. It can intelligently plan shooting tasks and flight routes based on the drone's real-time battery level and preset battery thresholds. This battery management strategy ensures that the drone shoots when it has sufficient battery power and automatically returns to charge when the battery is low, thus guaranteeing the continuity of monitoring work and the safe use of the drone.

[0080] 3. This invention provides comprehensive coordinate information for the marker. By comparing and analyzing continuously captured images, the system can accurately calculate the displacement of the marker in the horizontal and vertical directions, thereby assessing the overall stability of the slope. Compared to traditional single-point monitoring, this method provides more comprehensive and accurate deformation data.

[0081] 4. The system's set risk thresholds for nearby landmarks and horizontal offset provide quantitative criteria for assessing landmark stability. When a landmark's displacement exceeds these thresholds, the system automatically marks it as unstable and triggers a review risk assessment process. This threshold-based assessment method improves the accuracy and timeliness of early warnings, helping to take preventative measures and avoid potential safety incidents.

[0082] 5. The slope deformation monitoring method of this invention introduces grid cells and, taking a marker that failed the initial screening and evaluation as the center, performs detailed analysis on its eight adjacent sub-monitoring areas, establishing a local monitoring mechanism based on spatial distribution. A risk threshold for adjacent markers is set. The method can quickly identify concentrated areas of unstable markers within the grid cells, providing a basis for further analysis.

[0083] 6. This invention introduces a positive direction, using analysis lines and reference markers to quantitatively assess the horizontal offset direction and amount of the markers. When the offset in a certain direction exceeds the risk threshold, and the offset direction is consistent with the central marker, these markers are marked as unstable, further confirming the existence of slope deformation.

[0084] 7. When implementing the marker offset verification strategy, the system comprehensively considers the horizontal and vertical displacement of the markers and uses set thresholds and risk assessment models to make a comprehensive judgment on the stability of the slope. If the slope is confirmed to be in an unstable state, the system will issue a timely warning, prompting the implementation of appropriate safety measures to effectively prevent geological disasters such as landslides. Attached Figure Description

[0085] Figure 1 This is a flowchart illustrating the slope monitoring task performed by the present invention. Detailed Implementation

[0086] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0087] Example 1, see Figure 1 The present invention provides the following technical solution: a vision-assisted method for monitoring slope deformation in open-pit coal mines, comprising:

[0088] Drones are used to divide the surface of the open-pit coal mine slope into monitoring areas. Multiple monitoring areas form a monitoring area set, which is represented as S = {monitoring area A, monitoring area B, ..., monitoring area N}. Drones are used to monitor the deformation of the open-pit coal mine slope by using the monitoring area set. The monitoring area is a rectangle with an equal area.

[0089] Each monitoring area is divided into multiple sub-monitoring areas. For example, in monitoring area A, the set of sub-monitoring areas is represented as A={SA1,SA2,SA3……SAN}; in monitoring area B, the set of sub-monitoring areas is represented as B={SB1,SB2,SB3……SBN}; the sub-monitoring areas are also rectangles of equal area.

[0090] The sub-monitoring area contains feature points. Each sub-monitoring area has one feature point, which is the center of the sub-monitoring area. Since the sub-monitoring area is rectangular, the center is selected at the intersection of the two diagonals of the rectangle. The feature point includes the marker and the coordinates of the initial position of the marker. After the feature point is selected, the marker will be buried at the point and the initial three-dimensional coordinates of the marker will be recorded for subsequent determination of the marker's offset.

[0091] The drone captured images of the landmark from multiple angles: angles A, B, C, D, and E. Angles A and D captured the front and back views of the landmark, angles B and C captured the left and right side views, and angle E captured the top view. These images were then used to analyze the landmark's real-time 3D coordinates at each point in time.

[0092] Furthermore, the time interval for the drone's photography specifically includes:

[0093] Set a fixed time interval to repeatedly photograph the marker from multiple angles. The time interval for repeatedly photographing the same marker from multiple angles is T.

[0094] While performing the shooting task, the drone's real-time battery level is obtained, and a drone shooting strategy is formed based on the time interval and the drone's real-time battery level.

[0095] Furthermore, the drone shooting strategy specifically includes the following steps:

[0096] Set power thresholds, including a minimum takeoff power threshold and an execution power threshold. The minimum takeoff power threshold is the lowest battery percentage the drone must maintain before takeoff. The execution power threshold is the percentage of battery the drone should maintain during mission execution. The minimum takeoff power threshold must be lower than the execution power threshold.

[0097] The battery level of each sub-monitoring area is determined. This battery level represents the amount of power required for each sub-monitoring area to complete its imaging task. The imaging task involves repeatedly photographing the markers within the sub-monitoring area at time points within a time interval T. The time interval for repeated imaging is T.

[0098] After each sub-monitoring area's shooting task is completed, it is determined whether the drone's real-time battery level is lower than the execution battery threshold. If the drone's real-time battery level is higher than the execution battery threshold, it continues to execute shooting tasks in other sub-monitoring areas. If the drone's real-time battery level is lower than the execution battery threshold, it does not execute shooting tasks, returns to the charging location to recharge to full power, and then uses a drone that is not currently on a task to shoot the remaining sub-monitoring areas.

[0099] Furthermore, when the UAV completes a shooting task in a monitoring area, the marker offset verification strategy includes:

[0100] The offset verification strategy for markers is divided into preliminary screening and assessment and risk assessment.

[0101] The initial screening and assessment is determined by analyzing the offset of individual markers in the sub-monitoring area;

[0102] The review risk assessment is to review the sub-monitoring areas that were initially identified as unstable by analyzing the horizontal and vertical displacement of the markers. Horizontal displacement refers to the lateral movement of the slope, while vertical displacement indicates the subsidence or elevation of the slope.

[0103] Furthermore, during the process of shooting a monitoring area, the UAV executes a marker offset verification strategy, including:

[0104] S1: After the marker is buried, the drone takes pictures from multiple angles to construct the three-dimensional coordinates of the marker, providing initial position information for offset detection, denoted as (X,Y,Z).

[0105] S2: After each time interval T, the drone takes a multi-angle photograph of the same landmark and calculates the landmark's coordinate information P. t = (X t ,Y t Z t );

[0106] Pt represents the coordinate information of the marker, which is divided into P1, P2, ..., Pn. P1 represents the coordinates of the marker after the first T cycle, and Pn represents the coordinates of the marker after the nth T cycle.

[0107] S3: Calculate the position offset between the marker coordinates and the initial position information (X, Y, Z), and calculate the position offset at the corresponding shooting time point. ;

[0108] Formula for calculating position offset:

[0109]

[0110] For the collected location data P1, P2, ..., P n Calculate the position offset separately

[0111] ;

[0112] S4: Based on the position offset calculation formula, the position offset of the marker after a certain point in time is obtained;

[0113] S5: Conduct preliminary screening and evaluation, and set the offset threshold Δd;

[0114] S6: After each time point, compare the positional offset of the marker with the offset threshold Δd.

[0115] If the position offset If Δd is found, the preliminary screening evaluation result of the marker is determined to be unstable and it can be marked as failing the preliminary screening evaluation.

[0116] If the position offset If Δd is obtained, the marker will continue to undergo position offset calculation and preliminary screening evaluation.

[0117] During the process of the UAV performing a shooting mission in a monitoring area, it executes a marker offset verification strategy, including:

[0118] S7: For markers that fail the initial screening assessment, a review risk assessment will be conducted. The review risk assessment is divided into vertical analysis and horizontal analysis.

[0119] The vertical direction analysis refers to the offset of the marker in the z-axis direction;

[0120] The horizontal analysis defines the offset and direction of each marker along the horizontal x-axis and y-axis.

[0121] A grid cell is defined, which is a sub-monitoring area 8 adjacent to a marker that has not passed the initial screening evaluation.

[0122] A risk threshold for neighboring markers is set, which is the proportion of unstable markers within a grid cell to all markers within that grid cell. This threshold is set to 30%.

[0123] S8: Within the grid cell, calculate the vertical offset of the marker. The vertical offset risk threshold is 50mm.

[0124] If the vertical offset of a marker within a grid cell is ≥50mm, it is considered an unstable marker.

[0125] If the vertical offset of the marker is ≤50mm, then the horizontal direction of the marker should be analyzed.

[0126] If the proportion of unstable markers in the grid cell is greater than the risk threshold of neighboring markers, then the area where the markers that failed the preliminary screening assessment are located is considered to have slope deformation.

[0127] If the proportion of unstable markers within a grid cell is less than the risk threshold of neighboring markers, then the markers are analyzed in the horizontal direction.

[0128] Set a horizontal offset risk threshold of 75 mm to determine the risk threshold of the horizontal offset of the marker within the grid cell.

[0129] If the horizontal offset of a marker is ≥75mm and its offset direction is consistent with the center marker of the grid cell, it is marked as an unstable marker.

[0130] Obtain the translation direction of the markers that failed the initial screening evaluation, and record it as the positive direction;

[0131] Specifically, the coordinates of all markers in the grid cell are obtained. A horizontal analysis line is drawn based on the coordinates of the markers that failed the initial screening evaluation. This analysis line is perpendicular to the horizontal translation direction of the markers that failed the initial screening evaluation. All markers located on the positive side of the horizontal analysis line are identified and denoted as reference markers. The number of reference markers is denoted as U.

[0132] The number of reference markers whose horizontal offset direction is the same as the positive direction and whose horizontal offset is ≥75mm is denoted as Q;

[0133] If Q / U ≥ 30%, then the area where the marker that failed the preliminary screening assessment is located is considered to have slope deformation.

[0134] S9: Set the risk threshold for the monitoring area to 20%. If the proportion of unstable grid cell areas in the monitoring area is greater than the risk threshold, the monitoring area is considered unstable.

[0135] If the proportion of unstable grid cell regions to the monitoring area is less than the risk threshold of the monitoring area, then the monitoring area is stable.

[0136] Furthermore, the system for monitoring slope deformation in open-pit coal mines based on vision assistance includes:

[0137] The drone monitoring module is used to select feature points on the slope surface and photograph markers to collect visual data;

[0138] The information acquisition module is used to acquire real-time location information of markers, slope environmental parameters, and UAV status information, and transmit them to the data processing center;

[0139] The control module, connected to the UAV monitoring module and the information acquisition module, is used to control the UAV monitoring module to execute the shooting strategy based on the information collected by the information acquisition module.

[0140] Specifically, in the system for monitoring slope deformation in open-pit coal mines based on vision assistance, the control module further includes:

[0141] The threshold management unit is used for historical data analysis and setting standard displacement thresholds, and triggers an alert when the monitored data exceeds the threshold.

[0142] The task scheduling unit is used to intelligently plan the drone's shooting tasks and flight routes based on the needs of slope deformation monitoring and the drone's battery status.

[0143] Furthermore, in the system for monitoring slope deformation in open-pit coal mines based on vision assistance, the control module further includes:

[0144] The data analysis unit is used to process the data transmitted by the information acquisition module, calculate the displacement and displacement ratio of the markers, and provide quantitative basis for stability assessment.

[0145] The stability assessment unit is used to evaluate the stability status of the slope based on the results of the data analysis unit, and to make maintenance or early warning recommendations when necessary.

[0146] A further system for monitoring slope deformation in open-pit coal mines based on vision assistance, the system further comprising:

[0147] The user interaction module provides users with functions such as real-time monitoring data display, historical data analysis, and early warning information reception, and allows users to set and adjust monitoring parameters as needed;

[0148] The report generation unit is used to generate regular monitoring reports, including displacement data, stability assessment results, and early warning records, for users and managers to review and archive.

[0149] Furthermore, the system for monitoring slope deformation in open-pit coal mines based on vision assistance further includes the following units:

[0150] The on-site verification unit coordinates with on-site personnel to conduct on-site investigations and verifications after the early warning module issues an alert, ensuring the accuracy and reliability of the monitoring data. The strategy adjustment unit automatically or manually adjusts the monitoring strategy and threshold settings based on the on-site verification results and user feedback, optimizing the monitoring process and improving the responsiveness and accuracy of the monitoring system.

[0151] It should be noted that, in this document, relational terms such as "first" and "second" are used only to distinguish one entity or operation from another, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Furthermore, the terms "comprising," "including," or any other variations thereof are intended to cover non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements includes not only those elements but also other elements not expressly listed, or elements inherent to such process, method, article, or apparatus.

[0152] The above description is only a preferred embodiment of the present invention. It should be noted that for those skilled in the art, several improvements and modifications can be made without departing from the technical principles of the present invention, and these improvements and modifications should also be considered within the scope of protection of the present invention.

Claims

1. A vision-assisted method for monitoring slope deformation in open-pit coal mines, characterized in that, include: Drones are used to delineate monitoring areas on the surface of open-pit coal mine slopes. Multiple monitoring areas form a monitoring area set, denoted as S = {Monitoring Area A, Monitoring Area B, ..., Monitoring Area N}. Each monitoring area is further divided into multiple sub-monitoring areas, each containing a feature point. Each sub-monitoring area has one feature point; the feature point is the center position of the sub-monitoring area, which is rectangular. The center position is selected at the intersection of the two diagonals of the rectangle. The feature point includes a marker and the coordinates of its initial position. The drone takes multiple photos of the marker from different angles: angle A, angle B, angle C, angle D, and angle E. Angles A and D represent the front and back views of the marker, angles B and C represent the left and right side views, and angle E represents the top view. When the drone completes its shooting mission in a monitoring area, it executes a marker offset verification strategy. This strategy includes a preliminary screening assessment and a review risk assessment. The preliminary screening assessment is conducted by analyzing the offset of individual markers in the sub-monitoring area. The review risk assessment is conducted by reviewing the sub-monitoring areas that are deemed unstable by the preliminary screening assessment, and analyzing the horizontal and vertical displacement of the markers. Horizontal displacement refers to the lateral movement of the slope, and vertical displacement indicates the subsidence or elevation of the slope. During the process of the UAV taking pictures of a monitoring area, the marker offset verification strategy is implemented, which also includes: S1: After the marker is buried, the UAV takes pictures from multiple angles to construct the three-dimensional coordinates of the marker and provide initial position information for offset detection, denoted as (X,Y,Z). S2: After each time interval T, the drone takes a multi-angle photograph of the same landmark and calculates the landmark's coordinate information P. t = (X t ,Y t Z t Pt represents the coordinate information of the marker, which is divided into P1, P2, ..., Pn. P1 represents the coordinates of the marker after the first T cycle, and Pn represents the coordinates of the marker after the nth T cycle. S3: Calculate the position offset between the marker coordinates and the initial position information (X, Y, Z), and calculate the position offset at the corresponding shooting time point. The formula for calculating the position offset is: For the collected location data P1, P2, ..., P n Calculate the position offset separately; ; S4: Calculate the positional offset of the marker after a certain time point based on the positional offset calculation formula; S5: Conduct preliminary screening and evaluation, and set the offset threshold Δd; S6: After each time interval T, the positional offset of the marker is compared with the offset threshold Δd. If the positional offset... If Δd is found, the initial screening assessment result of the marker is determined to be unstable, and it can be marked as failing the initial screening assessment. If the positional offset is... If Δd is calculated, the marker will continue to undergo position offset calculation and preliminary screening evaluation; S7: For markers that fail the initial screening assessment, a review risk assessment is performed. The review risk assessment is divided into vertical and horizontal analysis. The vertical analysis is the marker's offset in the z-axis direction, and the horizontal analysis is the offset and offset direction of each marker in the x and y axes in the horizontal direction. A grid cell is set, with the marker that failed the initial screening assessment as the center and its eight adjacent sub-monitoring areas. A neighboring marker risk threshold is set, which is the proportion of unstable markers within the grid cell to the total number of markers within the grid cell, and is set to 30%. S8: Within a grid cell, the vertical offset of the marker is calculated. The vertical offset risk threshold is 50mm. If the vertical offset of the marker within the grid cell is ≥50mm, it is determined to be an unstable marker. If the vertical offset of the marker is ≤50mm, the marker is analyzed horizontally. If the proportion of unstable markers in the grid cell is greater than the risk threshold of adjacent markers, the area where the marker that failed the initial screening assessment is located is considered to have slope deformation. If the proportion of unstable markers in the grid cell is less than the risk threshold of adjacent markers, the marker is analyzed horizontally. A horizontal offset risk threshold of 75mm is set to determine the risk threshold of the horizontal offset of the marker within the grid cell. If the horizontal offset of the marker is ≥75mm and its offset direction is consistent with the marker at the center of the grid cell, it is marked as an unstable marker. To obtain the translation direction of the markers that failed the initial screening assessment, we denote it as the positive direction. Specifically, we obtain the coordinates of all markers in the grid cell, and draw a horizontal analysis line based on the coordinates of the markers that failed the initial screening assessment. The analysis line is perpendicular to the horizontal translation direction of the markers that failed the initial screening assessment. We obtain all markers located on the side of the horizontal analysis line that is in the positive direction, and denote them as reference markers. The number of reference markers is denoted as U. We obtain the number of reference markers whose horizontal offset direction is the same as the positive direction and whose horizontal offset is ≥75mm, and denote it as Q. If Q / U≥30%, we determine that there is slope deformation in the area where the markers that failed the initial screening assessment are located. S9: Set the risk threshold for the monitoring area to 20%. If the proportion of unstable grid cell areas to the monitoring area is greater than the risk threshold, the monitoring area is unstable. If the proportion of unstable grid cell areas to the monitoring area is less than the risk threshold, the monitoring area is stable.

2. The method for monitoring slope deformation in open-pit coal mines based on vision assistance according to claim 1, characterized in that: include: Set a fixed time interval to repeatedly photograph the marker from multiple angles; The time interval between repeated shootings of the same landmark from multiple angles is T; Get the drone's real-time battery level; A drone shooting strategy is formulated based on time intervals and the drone's real-time battery level.

3. The method for monitoring slope deformation in open-pit coal mines based on vision assistance according to claim 2, characterized in that: The drone photography strategy includes: Set a power threshold; The power threshold includes a minimum takeoff power threshold, which sets the minimum power percentage that the drone must meet before takeoff; Set a power threshold, which is the percentage of battery the drone should maintain during mission execution; The power level of each sub-monitoring area is obtained, and the power level of each sub-monitoring area is the power required for each sub-monitoring area to complete the shooting task. After the shooting task in each sub-monitoring area is completed, determine whether the real-time battery level of the drone is less than the execution battery threshold. If the drone's real-time battery level is greater than the execution battery threshold, it will continue to perform shooting tasks in other sub-monitoring areas; If the drone's real-time battery level is lower than the execution battery threshold, it will not perform the shooting task, will return to the charging position to charge until it is fully charged, and will call on a drone that is not currently on a task to shoot the remaining sub-monitoring area.

4. A system for implementing the vision-assisted open-pit coal mine slope deformation monitoring method as described in claim 3, characterized in that: The drone monitoring module is used to select feature points on the slope surface and photograph markers to collect visual data; The information acquisition module is used to acquire real-time location information of markers, slope environmental parameters, and UAV status information, and transmit them to the data processing center; The control module, connected to the UAV monitoring module and the information acquisition module, is used to control the UAV monitoring module to execute the shooting strategy based on the information collected by the information acquisition module.

5. The system for monitoring slope deformation in open-pit coal mines based on vision assistance according to claim 4, characterized in that: The control module also includes: The threshold management unit is used for historical data analysis and setting standard displacement thresholds, and triggers an alert when the monitored data exceeds the threshold. The task scheduling unit is used to intelligently plan the drone's shooting tasks and flight routes based on the needs of slope deformation monitoring and the drone's battery status.

6. The system for monitoring slope deformation in open-pit coal mines based on vision assistance according to claim 5, characterized in that: The control module also includes: The data analysis unit is used to process the data transmitted by the information acquisition module, calculate the displacement and displacement ratio of the markers, and provide quantitative basis for stability assessment. The stability assessment unit is used to evaluate the stability status of the slope based on the results of the data analysis unit.

7. The system for monitoring slope deformation in open-pit coal mines based on vision assistance according to claim 6, characterized in that: The system also includes: The user interaction module provides users with real-time monitoring data display, historical data analysis, and early warning information reception functions, and allows users to set and adjust monitoring parameters as needed; The report generation unit is used to generate regular monitoring reports, including displacement data, stability assessment results, and early warning records, for users and managers to review and archive.

Citation Information

Patent Citations

  • Drone-based non-contact high slope surface displacement monitor method and monitor system

    CN109579712A

  • Landform measurement method and system based on unmanned aerial vehicle

    CN115657706A

  • Track monitoring system and monitoring method

    CN115675566A