Water delivery system and arrangement method thereof

By introducing regulating pools and pressurized components into the water delivery system, combined with gravity flow and pressurized water delivery, the problem of insufficient water supply guarantee rate in water delivery systems with large water level changes is solved, and operation and management costs are reduced.

CN118756783APending Publication Date: 2024-10-11SHANGHAI INVESTIGATION DESIGN & RES INST CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411128724.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-16
Publication Date
2024-10-11

Smart Images

  • Figure CN118756783A_ABST
    Figure CN118756783A_ABST
Patent Text Reader

Abstract

The invention provides a water conveying system and an arrangement method thereof, and belongs to the technical field of water conservancy projects and water supply engineering.The water conveying system comprises a water taking facility, an adjusting water pool, a pressurizing assembly and a water using facility which are sequentially arranged in the water flow direction, and further comprises a water conveying tunnel and a water conveying pipeline; water is conveyed into the adjusting water pool through the water conveying tunnel by the water taking facility, whether the water needs to be pressurized and conveyed to the water using facility by the pressurizing assembly or not is judged according to the water head condition of the adjusting water pool, water is conveyed in a gravity self-flowing mode at the high water level, and water is conveyed in a gravity self-flowing and pressurizing assembly combined mode at the low water level; the water supply rate of the whole water conveying system is guaranteed, and the operation management cost of the whole water conveying system is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of water conservancy engineering and water supply engineering, and in particular to a water delivery system and a layout method thereof. Background Art

[0002] With the development of society, the construction of various projects has increased the water consumption, and the problem of water shortage has become increasingly prominent, which has seriously restricted the construction of various projects and also affected the daily water demand of residents. In order to ensure the daily water supply of residents and the construction of various projects, various measures need to be taken to allocate water resources.

[0003] There are many ways to allocate water resources, involving a wide variety of equipment and facilities. Combined with the actual operation and scheduling, the scheduling of water resources faces various difficulties. In water transfer projects, tunnels, pipelines, and channels are usually used as water transfer channels. According to the water pressure of the water transfer channel, it is divided into pressurized water transfer and non-pressurized water transfer. In actual projects, a variety of water transfer channels and a combination of pressurized and non-pressurized water transfer are sometimes used to establish a water transfer system. Water transfer projects usually need to take into account factors such as water supply demand, topography, project investment, operating costs, and operation scheduling.

[0004] In general, the locations of water-using facilities and water-intake facilities are relatively fixed, but the water level at the water-intake facilities varies greatly, causing the water head of the entire water supply system to vary greatly. When the water head at the water-using facilities is lower than a certain value, the water-using facilities cannot obtain water, resulting in insufficient water supply guarantee rate for the entire water supply system. If the elevation of the water-intake facilities is lowered so that the water-intake facilities are always below the lowest water level, deep excavation is required. However, if the elevation of the water-using facilities remains unchanged, water may not be obtained. If a pressurized component is used, the pressurized component needs to be continuously operated to ensure the water supply guarantee rate. This measure will increase project investment and operating costs during the operation period. Therefore, reasonable planning and design of such a water supply system with a large water level variation is of great significance to the stable operation of the water supply system. Summary of the invention

[0005] Therefore, the technical problem to be solved by the present invention is to overcome the defect that the water delivery system in the prior art cannot cope with large changes in water level, thereby providing a water delivery system and its arrangement method.

[0006] In order to solve the above problems, the present invention provides a water delivery system, including water intake facilities, regulating water tanks, pressurizing components and water use facilities arranged in sequence along the water flow direction; and also including:

[0007] A water conveyance tunnel is arranged between the water intake facility and the regulating water tank; the water conveyance tunnel conveys water to the regulating water tank by gravity flow;

[0008] A water delivery pipeline is arranged between the regulating water tank and the water-using facility; the water delivery pipeline is suitable for delivering water from the regulating water tank to the water-using facility;

[0009] The pressurizing component is suitable for pressurizing the water flow in the water delivery pipeline and driving the water flow toward the water-using facility; the pressurizing component determines whether to pressurize according to the water head condition between the water-using facility and the water-intake facility.

[0010] As a preferred solution, the bottom of the water transfer tunnel is horizontal or has a slope inclined along the direction of water flow, ensuring that water can flow into the regulating water tank by gravity.

[0011] As a preferred solution, when the water head of the water intake facility is less than the water head of the water use facility, the pressurizing component is started; otherwise, the pressurizing component is closed.

[0012] As a preferred solution, the regulating water pool is a closed structure; a vent is provided on the top of the regulating water pool.

[0013] As a preferred embodiment, the pressurizing component comprises:

[0014] A pressurized water pump is arranged in the regulating water tank; the pressurized water pump is suitable for connecting to the water delivery pipeline; the pressurized water pump is suitable for driving the water in the regulating water tank to flow to the water delivery pipeline;

[0015] A first pipeline is arranged between the pressurized water pump and the water delivery pipeline;

[0016] The second pipeline has one end connected to the regulating water tank and the other end connected to the first pipeline.

[0017] As a preferred solution, the pressurizing component further comprises:

[0018] A valve is arranged on the second pipeline; the valve is suitable for controlling the on-off of the second pipeline.

[0019] As a preferred solution, the water intake facility further comprises:

[0020] The dirt intercepting structure is arranged upstream of the water intake facility, and the dirt intercepting structure is suitable for intercepting dirt in the water flow.

[0021] In order to solve the above problems, the present invention provides a method for arranging a water delivery system, comprising any of the above water delivery systems, and further comprising the steps of:

[0022] Step 1: Arrange the water delivery route according to the water delivery task and target, and determine the location of water intake facilities, regulating pools, and water use facilities;

[0023] Step 2: Combine water flow rate Q and economic flow rate VP , determine the water diversion tunnel diameter D; substitute into the formula Where D is the hole diameter; Q is the flow rate; V P Economic flow rate;

[0024] Step 3: According to the highest water level H at the water intake location h With the lowest water level H l , while considering the minimum flooding depth S, determine the water intake level H of the water intake facility g , so that H g ≤H l -DS; Substitute into the formula S = cvd 1 / 2 ; Where S is the minimum flooding depth; Where v is the average flow velocity of the cross section at the narrow mouth of the diffusion section; Where d is the height of the narrow mouth of the diffusion section; Where c is a coefficient related to the geometric shape of the water inlet;

[0025] Step 4: Calculate the local head loss h according to the layout of the water delivery system m and head loss along the way h f , the total head loss h=h f +h m ;in in Where v is the average flow velocity of the cross section; L is the calculated length of the water channel; C is the Schertz coefficient, calculated using the Manning formula; R is the hydraulic radius; n is the roughness value; v 2 / 2g is the average velocity head of the calculation part; g is the weight acceleration; ξ is the local head loss coefficient value;

[0026] Step 5: Between the water pipeline and the water-using facilities, the maximum elevation of the pipeline or water-using facilities is H max , the water level at the water intake facility is H(H l ≤H≤H h ), the net head difference of the water delivery system is Δh, where Δh=HhH max ; When Δh>0, the water supply system can use gravity to supply water. When Δh≤0, a pressurizing component is required to pressurize the water supply system for water supply.

[0027] As a preferred solution, when the water delivery system uses gravity to deliver water, the vent holes of the regulating pool are closed, and when the water delivery system needs to use a pressurized component to deliver water, the vent holes of the regulating pool are opened.

[0028] As a preferred solution, when the water delivery system uses gravity to deliver water, the valve set on the second pipeline connected to the regulating water tank is opened; when the water delivery system uses a pressurized water pump to deliver water, the valve set on the second pipeline connected to the regulating water tank is closed.

[0029] The technical solution of the present invention has the following advantages:

[0030] 1. A water delivery system provided by the present invention comprises a water intake facility, a regulating water tank, a pressurizing component and a water use facility which are sequentially arranged along the direction of water flow; and further comprises: a water delivery tunnel and a water delivery pipeline, wherein the water delivery tunnel is arranged between the water intake facility and the regulating water tank; the water delivery tunnel delivers water to the regulating water tank by gravity flow; the water delivery pipeline is arranged between the regulating water tank and the water use facility; the water delivery pipeline is suitable for delivering water from the regulating water tank to the water use facility; the pressurizing component is suitable for pressurizing the water flow in the water delivery pipeline and driving the water flow toward the water use facility; the pressurizing component determines whether to perform pressurization according to the water head between the water use facility and the water intake facility. In the present invention, water is transported to a regulating water tank through a water transfer tunnel by a water intake facility. Depending on the water head condition of the regulating water tank, whether a pressurizing component is needed to pressurize and transport water to the water use facility is determined. At high water levels, water is transported by gravity flow, and at low water levels, water is transported by a combination of gravity flow and a pressurizing component. This not only ensures the water supply rate of the entire water transfer system, but also reduces the operating and management costs of the entire water transfer system.

[0031] 2. The present invention provides a water delivery system, wherein the bottom of the water delivery tunnel is horizontal or has a slope inclined along the direction of water flow, ensuring that water can be transported from the water intake facility to the regulating pool by its own weight. BRIEF DESCRIPTION OF THE DRAWINGS

[0032] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0033] Figure 1 This is a plan view of a water delivery system provided by the present invention.

[0034] Figure 2 The present invention is a longitudinal sectional view of a water delivery system provided by the present invention.

[0035] Figure 3 A schematic structural diagram of a regulating water tank and a pressurizing component of a water delivery system provided by the present invention.

[0036] Description of reference numerals:

[0037] 1. Water intake facilities; 2. Water transfer tunnel; 3. Regulating pool; 4. Pressurizing component; 5. Water transfer pipeline; 6. Water use facilities; 7. Pressurized water pump; 8. Second pipeline; 9. First pipeline; 10. Valve; 11. Vent. DETAILED DESCRIPTION

[0038] The technical solution of the present invention will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0039] In the description of the present invention, it should be noted that the terms "center", "up", "down", "left", "right", "vertical", "horizontal", "inside", "outside", etc. indicate directions or positional relationships based on the directions or positional relationships shown in the accompanying drawings. They are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction. Therefore, they cannot be understood as limitations on the present invention.

[0040] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0041] In addition, the technical features involved in the different embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other.

[0042] Example 1

[0043] like Figure 1 As shown, a water delivery system provided by the present invention comprises a water intake facility 1, a regulating water tank 3, a pressurizing component 4 and a water use facility 6 which are sequentially arranged along the water flow direction; it also comprises: a water delivery tunnel 2 and a water delivery pipeline 5, the water delivery tunnel 2 is arranged between the water intake facility 1 and the regulating water tank 3; the water delivery tunnel 2 delivers water to the regulating water tank 3 by gravity flow; the water delivery pipeline 5 is arranged between the regulating water tank 3 and the water use facility 6; the water delivery pipeline 5 is suitable for delivering water from the regulating water tank 3 to the water use facility 6; the pressurizing component 4 is suitable for pressurizing the water flow in the water delivery pipeline 5 and driving the water flow toward the water use facility 6; the pressurizing component 4 determines whether to pressurize according to the water head condition between the water use facility 6 and the water intake facility 1.

[0044] In the present invention, water is transported to the regulating water tank 3 through the water transfer tunnel 2 by the water intake facility 1. Depending on the water head condition of the regulating water tank 3, whether the pressurizing component 4 is needed to pressurize and transport the water to the water use facility 6, gravity flow is used for water transport at high water levels, and gravity flow combined with the pressurizing component 4 is used for water transport at low water levels. This not only ensures the water supply rate of the entire water transfer system, but also reduces the operation and management costs of the entire water transfer system.

[0045] Furthermore, the water intake facility 1 also includes a dirt intercepting structure, which is arranged upstream of the water intake facility 1 and is suitable for intercepting dirt in the water flow; it should be noted that a working gate and a maintenance gate are also arranged upstream of the water intake facility 1, which are used to control the water flow and shut down for maintenance respectively. It should be noted that the dirt intercepting structure generally uses a filter screen structure to intercept dirt by filtering.

[0046] It should be noted that the locations of the water intake facilities 1, regulating pools 3 and water use facilities 6 must first be determined based on the terrain conditions and the scope of land acquisition for construction, and then the lines between the key nodes must be arranged.

[0047] Furthermore, the bottom of the water conveyance tunnel 2 is horizontal or has a slope inclined along the water flow direction, ensuring that the water can flow into the regulating water tank 3 by gravity. The water intake facility 1 conveys the water flow to the water conveyance tunnel 2, and the water flows along the water conveyance tunnel 2 under the action of its own weight.

[0048] Furthermore, when the water head of the water intake facility 1 is less than the water head of the water use facility 6, the pressurizing component 4 is started; otherwise, the pressurizing component 4 is turned off.

[0049] like Figure 3 As shown, further, the regulating water pool 3 is a closed structure; a vent 11 is provided on the top of the regulating water pool 3; when the water delivery system adopts gravity water delivery, the vent 11 is closed to prevent the water in the regulating water pool from overflowing; when the water delivery system adopts pressurized water delivery by the pressurizing component 4, the vent 11 is opened to ensure that the air pressure in the regulating water pool 3 is equal to the external atmospheric pressure, thereby preventing negative pressure from occurring in the regulating water pool 3.

[0050] like Figure 3 As shown, further, the pressurizing component 4 includes a pressurized water pump 7, a first pipeline 9 and a second pipeline 8; the pressurized water pump 7 is suitable for being connected to the water supply pipeline 5, and the pressurized water pump 7 is suitable for driving the water in the regulating water tank 3 to flow to the water supply pipeline 5, the first pipeline 9 is arranged between the pressurized water pump 7 and the water supply pipeline 5, one end of the second pipeline 8 is connected to the regulating water tank 3, and the other end is connected to the first pipeline 9.

[0051] Furthermore, the pressurizing component 4 also includes a valve 10 , which is disposed on the second pipeline 8 , and the valve 10 is suitable for controlling the on-off of the second pipeline 8 .

[0052] It should be noted that the water flow rate Q and the maximum water level H h , minimum water level H l The parameters are clear, and an economic flow rate V is initially proposed P The following formula is used to calculate the size D of the water conveyance tunnel 2. The size D of the water conveyance tunnel 2 can be finally determined by comprehensively considering the geological conditions and construction conditions.

[0053]

[0054] The average flow velocity v of the cross section of the water conveyance tunnel 2 can be determined by the water conveyance flow rate Q and the size D of the water conveyance tunnel 2. According to the specific shape of the water intake of the water intake facility 1, the coefficient c related to the geometric shape of the water inlet and the height d of the narrow mouth of the diffusion section are obtained by looking up the relevant table. The minimum flooding depth S is calculated using the following formula.

[0055] S=cvd 1 / 2

[0056] According to the highest water level H at the water intake location h With the lowest water level H l , while considering the minimum flooding depth S, determine the water intake level H of water intake facility 1 g , so that H g =H l -DS, considering factors such as sediment, actual H g Comparable calculated H g Small.

[0057] According to the layout of the water delivery system, calculate the local head loss h m and head loss along the way h f , the total head loss h=h f +h m . Local head loss h m It is mainly caused by the change of water flow caused by the change of local boundaries of various parts. According to the flow velocity of the local boundary and the local head coefficient table, the total local head loss h of the water delivery system is calculated. m . Head loss along the way h f It is mainly generated by the water conveyance tunnel 2 and the water conveyance pipeline 5 sections. It is necessary to calculate the flow velocity v, hydraulic radius R and Xie Cai coefficient of each section respectively. The total head loss along the way of the water conveyance system h is obtained by adding the head loss along the two sections. f . Local head loss h m and head loss along the way h f Calculate according to the following formula.

[0058]

[0059] Between the water pipeline 5 and the water-using facility 6, the maximum elevation of the water pipeline 5 or the water-using facility 6 is H max , the water level at the water intake facility 1 is H(H l ≤H≤H h ), the net head difference Δh of the water delivery system is calculated by the following formula.

[0060] Δh=HhH max

[0061] like Figure 2 As shown, since the water level at the water intake facility 1 is a changing value, the calculated Δh>0 at a high water level, the water can flow into the water use facility 6 by gravity flow, and the pressurizing component 4 does not need to be operated. The entire water delivery system relies on gravity flow to deliver water. When the water level is low, the calculated Δh≤0, the water can only flow into the regulating water tank 3 by gravity flow. The pressurizing component 4 needs to pressurize the water in order to deliver it to the water use facility 6. The entire water delivery system uses a combination of gravity flow and the pressurizing component 4 to deliver water.

[0062] It should be noted that this solution can reasonably switch between a method that relies entirely on gravity flow and a method that combines gravity flow with a pressurizing component 4 according to the water level at the water intake facility 1, which not only ensures the water supply rate of the entire water supply system, but also reduces the operating and management costs of the entire water supply system.

[0063] The regulating water pool 3 is a closed structure, and a vent hole 11 is arranged on the top of the regulating water pool 3. When the net water head difference Δh of the water delivery system is greater than 0, the vent hole 11 is closed, and when the net water head difference Δh of the water delivery system is less than or equal to 0, the vent hole 11 is opened.

[0064] A first pipeline 9 and a second pipeline 8 are arranged at the front end of the water supply pipeline 5 connected to the regulating water tank 3. When the net water head difference Δh of the water supply system is greater than 0, the valve 10 is opened, the pressure water pump 7 does not run, and the water flow in the regulating water tank 3 enters the water supply pipeline 5 through the second pipeline 8; when the net water head difference Δh of the water supply system is less than or equal to 0, the valve 10 is closed, the pressure water pump 7 runs, and the water flow in the regulating water tank 3 enters the water supply pipeline 5 through the first pipeline 9.

[0065] Example 2

[0066] A method for arranging a water delivery system, comprising the water delivery system described in embodiment 1, further comprising the steps of:

[0067] Step 1: Arrange the water delivery route according to the water delivery task and water delivery target, and determine the locations of the water intake facility 1, the regulating pool 3, and the water use facility 6;

[0068] Step 2: Combine water flow rate Q and economic flow rate V P , determine the water diversion tunnel diameter D; substitute into the formula Where D is the hole diameter; Q is the flow rate; V P Economic flow rate;

[0069] Step 3: According to the highest water level H at the water intake location h With the lowest water level H l , while considering the minimum flooding depth S, determine the water intake level H of water intake facility 1 g , so that H g ≤H l -DS; Substitute into the formula S = cvd 1 / 2 ; Where S is the minimum flooding depth; Where v is the average flow velocity of the cross section at the narrow mouth of the diffusion section; Where d is the height of the narrow mouth of the diffusion section; Where c is a coefficient related to the geometric shape of the water inlet;

[0070] Step 4: Calculate the local head loss h according to the layout of the water delivery system m and head loss along the way h f , the total head loss h=h f +h m ;in in Where v is the average flow velocity of the cross section; L is the calculated length of the water channel; C is the Schertz coefficient, calculated using the Manning formula; R is the hydraulic radius; n is the roughness value; v 2 / 2g is the average velocity head of the calculation part; g is the weight acceleration; ξ is the local head loss coefficient value;

[0071] Step 5: Between the water pipeline 5 and the water-using facility 6, the maximum elevation of the water pipeline 5 or the water-using facility 6 is H max , the water level at the water intake facility 1 is H(H l ≤H≤H h ), the net head difference of the water delivery system is Δh, where Δh=HhH max When Δh>0, the water delivery system can deliver water by gravity flow. When Δh≤0, the pressurizing component 4 is required to deliver water to the water delivery system.

[0072] Furthermore, when the water delivery system delivers water by gravity, the vent 11 of the regulating pool 3 is closed, and when the water delivery system needs to deliver water by the pressurizing component 4, the vent 11 of the regulating pool 3 is opened.

[0073] Furthermore, when the net water head difference Δh of the water delivery system is greater than 0, water is delivered by gravity flow, and the valve 10 provided on the second pipeline 8 connected to the regulating water tank 3 is opened; when the net water head difference Δh of the water delivery system is less than or equal to 0, water is delivered by a pressurized water pump 7, and the valve 10 provided on the second pipeline 8 connected to the regulating water tank 3 is closed.

[0074] Obviously, the above embodiments are merely examples for the purpose of clear explanation, and are not intended to limit the implementation methods. For those skilled in the art, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the implementation methods here. The obvious changes or modifications derived therefrom are still within the scope of protection of the invention.

Claims

1. A water delivery system, characterized in that: The invention comprises a water intake facility (1), a regulating water tank (3), a pressurizing component (4) and a water use facility (6) which are arranged in sequence along the water flow direction; and further comprises: A water conveyance tunnel (2) is arranged between the water intake facility (1) and the regulating water pool (3); the water conveyance tunnel (2) conveys water to the regulating water pool (3) by gravity flow; A water delivery pipeline (5) is arranged between the regulating water tank (3) and the water-using facility (6); the water delivery pipeline (5) is suitable for delivering water from the regulating water tank (3) to the water-using facility (6); The pressurizing component (4) is suitable for pressurizing the water flow in the water delivery pipeline (5) and driving the water flow toward the water-using facility (6); the pressurizing component (4) determines whether to pressurize according to the water head conditions between the water-using facility (6) and the water-intake facility (1).

2. The water delivery system according to claim 1, characterized in that: The bottom of the water conveyance tunnel (2) is horizontal or has a slope inclined along the direction of water flow, ensuring that the water can flow into the regulating water tank (3) by gravity.

3. The water delivery system according to claim 1, characterized in that: When the water head of the water intake facility (1) is less than the water head of the water use facility (6), the pressurizing component (4) is started; otherwise, the pressurizing component (4) is closed.

4. The water delivery system according to claim 1, characterized in that: The regulating water pool (3) is a closed structure; a vent hole (11) is provided on the top of the regulating water pool (3).

5. The water delivery system according to claim 1, characterized in that: The pressurizing component (4) comprises: A pressurized water pump (7) is arranged in the regulating water pool (3); the pressurized water pump (7) is suitable for being connected to the water delivery pipeline (5); the pressurized water pump (7) is suitable for driving the water in the regulating water pool (3) to flow toward the water delivery pipeline (5); A first pipeline (9) is arranged between the pressurized water pump (7) and the water delivery pipeline (5); A second pipeline (8) has one end connected to the regulating water tank (3) and the other end connected to the first pipeline (9).

6. The water delivery system according to claim 5, characterized in that: The pressurizing component (4) further comprises: A valve (10) is arranged on the second pipeline (8); the valve (10) is suitable for controlling the on-off of the second pipeline (8).

7. The water delivery system according to claim 1, characterized in that: The water intake facility (1) further comprises: A dirt intercepting structure is arranged upstream of the water intake facility (1), and the dirt intercepting structure is suitable for intercepting dirt in the water flow.

8. A method for arranging a water delivery system, characterized in that: The water delivery system according to any one of claims 1 to 7 further comprises the steps of: Step 1: Arrange the water delivery route according to the water delivery task and water delivery target, and determine the locations of the water intake facilities (1), the regulating pool (3), and the water use facilities (6); Step 2: Combine water flow rate Q and economic flow rate V P , determine the water diversion tunnel diameter D; substitute into the formula Where D is the hole diameter; Q is the flow rate; V P Economic flow rate; Step 3: According to the highest water level H at the water intake location h With the lowest water level H l , taking into account the minimum flooding depth S, determine the water intake level H of the water intake facility (1) g , so that H g ≤H l -DS; Substitute into the formula S = cvd 1 / 2 ; Where S is the minimum flooding depth; Where v is the average flow velocity of the cross section at the narrow mouth of the diffusion section; Where d is the height of the narrow mouth of the diffusion section; Where c is a coefficient related to the geometric shape of the water inlet; Step 4: Calculate the local head loss h according to the layout of the water delivery system m and head loss along the way h f , the total head loss h=h f +h m ;in in Where v is the average flow velocity of the cross section; L is the calculated length of the water channel; C is the Schertz coefficient, calculated using the Manning formula; R is the hydraulic radius; n is the roughness value; v 2 / 2g is the average velocity head of the calculation part; g is the weight acceleration; ξ is the local head loss coefficient value; Step 5: Between the water pipeline (5) and the water-using facility (6), the maximum elevation of the water pipeline (5) or the water-using facility (6) is H max , the water level at the water intake facility (1) is H(H l ≤H≤H h ), the net head difference of the water delivery system is Δh, where Δh=HhH max When Δh>0, the water delivery system can deliver water by gravity flow. When Δh≤0, a pressurizing component (4) is required to pressurize the water delivery system.

9. The method for arranging a water delivery system according to claim 8, characterized in that: When the water delivery system delivers water by gravity, the vent (11) of the regulating water pool (3) is closed; when the water delivery system needs to deliver water by the pressurizing component (4), the vent (11) of the regulating water pool (3) is opened.

10. The method for arranging a water delivery system according to claim 8, characterized in that: When the net water head difference Δh of the water delivery system is greater than 0, water is delivered by gravity flow, and a valve (10) provided on the second pipeline (8) connected to the regulating water tank (3) is opened; when the net water head difference Δh of the water delivery system is less than or equal to 0, water is delivered by a pressurized water pump (7), and the valve (10) provided on the second pipeline (8) connected to the regulating water tank (3) is closed.