Steel plate dry-wet combination laying structure with rainwater collecting function and construction method

By combining wet and dry laying structures and a rainwater harvesting system, the problems of rainwater retention and abnormal noise in the outdoor application of patterned steel plates have been solved, extending the service life and improving the user experience, while also realizing the reuse of rainwater.

CN118773981BActive Publication Date: 2026-11-20ZHONGTIAN CONSTR GROUP
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202411121708.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-15
Publication Date
2026-11-20
Estimated Expiration
2044-08-15

AI Technical Summary

Technical Problem

When patterned steel plates are used in permanent outdoor structures, they can cause rainwater retention and abnormal noise, which can affect their service life and pedestrian experience.

Method used

The structure adopts a combination of dry and wet paving, including a crushed stone layer, a concrete layer, C-type connectors, a dry-hardened cement mortar layer, a patterned steel plate, drainage pipes, and floor drains. The patterned steel plate is connected to the concrete ground through C-type connectors to form an overhead connection, and drainage pipes are pre-buried to collect rainwater.

Benefits of technology

It effectively solves the problems of rainwater retention and abnormal noise, extends the service life of patterned steel plates, improves the pedestrian experience, and realizes the reuse of rainwater.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118773981B_ABST
    Figure CN118773981B_ABST
Patent Text Reader

Abstract

The application discloses a steel plate dry-wet combined laying structure with rainwater collecting function and a construction method, and belongs to the technical field of building construction. The gravel layer is laid on the tamped and leveled ground soil, and the concrete layer is cast on the gravel layer. A plurality of C-shaped connecting pieces for placing the patterned steel plates are fixed on the concrete layer at intervals, the C-shaped connecting piece comprises mutually parallel upper and lower flanges and a web plate vertically arranged between the upper and lower flanges, and fixing holes are formed in the upper and lower flanges; the fixing piece penetrates through the fixing hole in the lower flange of the C-shaped connecting piece, and the C-shaped connecting piece is fixed on the concrete layer; the dry hard cement mortar layer is cast on the concrete layer; and the patterned steel plate is fixed on the upper flange of the C-shaped connecting piece. The ground soil, the gravel layer and the concrete layer below the gap between the adjacent patterned steel plates are provided with a drainage pipe in advance. The laying structure solves the problem of abnormal sound of the patterned steel plate applied to the outdoor environment, and has the rainwater collecting function.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of building construction technology, specifically relating to a steel plate dry-wet combined laying structure and construction method that also has rainwater collection function. Background Technology

[0002] Patterned steel plates, a common building material, are widely used for paving indoor floors in industrial buildings and for temporary roads on construction sites. Two common methods are dry laying and elevated laying. However, their practical application as a permanent outdoor structure is relatively rare. Currently, some industrial renovation projects are experimenting with using patterned steel plates as permanent outdoor structures to achieve an industrial design aesthetic. In this process, if dry laying is chosen, rainwater may accumulate between the patterned steel plate and the foundation, negatively impacting the plate's lifespan. While elevated laying can initially alleviate rainwater accumulation, prolonged water accumulation will still affect its lifespan and may cause noise when walking on it, interfering with pedestrian experience.

[0003] Therefore, when selecting patterned steel plates for permanent outdoor structural applications, it is necessary to develop a new laying structure system and corresponding construction methods to ensure its long-term stability and performance. Summary of the Invention

[0004] The purpose of this invention is to overcome the shortcomings of the prior art and provide a dry and wet combined laying structure and construction method for steel plates with rainwater harvesting function, which can effectively solve the problems of rainwater retention and abnormal noise when patterned steel plates are used as permanent structures in outdoor environments.

[0005] The specific technical solution adopted in this invention is as follows:

[0006] In a first aspect, the present invention provides a steel plate dry-wet combined laying structure with rainwater collection function, including a crushed stone layer, a concrete layer, C-type connectors, a dry hardened cement mortar layer, a patterned steel plate, a drainage pipe and a floor drain.

[0007] The crushed stone layer is laid on the compacted and leveled foundation soil; the concrete layer is poured on the crushed stone layer; several C-shaped connectors for placing patterned steel plates are fixed at intervals on the concrete layer; the C-shaped connector includes an upper flange and a lower flange that are parallel to each other, and a web perpendicular to the upper flange and the lower flange, wherein fixing holes are opened on the upper flange and the lower flange of the C-shaped connector; the fixing member passes through the fixing hole on the lower flange of the C-shaped connector and fixes the C-shaped connector to the concrete layer; a dry-hardened cement mortar layer is poured on the concrete layer, and the thickness of the dry-hardened cement mortar layer is at the elevation of the upper flange of the C-shaped connector; the patterned steel plate is fixed on the upper flange of the C-shaped connector.

[0008] The drainage pipe is installed in the gap between adjacent patterned steel plates. One end of the drainage pipe is equipped with a floor drain, and the other end is pre-buried in the foundation soil and extends to the main drainage pipe. Gravel is laid in the gap between adjacent patterned steel plates.

[0009] Preferably, steel strips are vertically installed along the edge of the patterned steel plate to form a boundary with other paving materials; L-shaped connectors are provided where steel strips are required, and the bottom surface of the L-shaped connectors is fixed to the concrete layer by expansion bolts, while the vertical surface of the L-shaped connectors is used to fix the steel strips.

[0010] Furthermore, the L-shaped connector is made of hot-dip galvanized angle steel.

[0011] Preferably, the C-type connector is made of hot-dip galvanized channel steel; the distance between the upper flange and the lower flange of the C-type connector is 30-50mm.

[0012] Preferably, the fastener is an expansion bolt.

[0013] Preferably, the thickness of both the crushed stone layer and the concrete layer is 150 mm.

[0014] Preferably, the slope around the floor drain on the concrete layer is 0.3% to 0.5%.

[0015] Preferably, the patterned steel plate has a size of 2440mm × 1220mm, and the gap between adjacent patterned steel plates is set to 80-120mm.

[0016] Preferably, the ratio of cement to sand used in the dry-hardened cement mortar layer is 1:3.

[0017] Secondly, the present invention provides a construction method for the steel plate wet-dry combined laying structure described in the first aspect, the specific steps of which are as follows:

[0018] S1: The arrangement of the patterned steel plates is further refined according to the area to be covered by the patterned steel plates;

[0019] S2: Compact and level the foundation soil, locate the foundation according to the detailed drawings in step S1, and pre-bury drainage pipes in the foundation soil. One end of the drainage pipe is connected to the main drainage pipe and the rainwater collection tank in sequence; the upper elevation of the drainage pipe must exceed the finished ground surface.

[0020] S3: Lay a layer of crushed stone on the foundation soil; pour concrete on the crushed stone layer to form a concrete layer, wherein the concrete is poured and smoothed as it is poured, with the lowest point being the location where the floor drain needs to be installed, and the slope around the floor drain is 0.3% to 0.5%.

[0021] S4: After the concrete layer has hardened, C-type connectors need to be installed on its surface for marking and positioning, and the elevation needs to be measured.

[0022] S5: Fix the lower flange of the C-type connector to the concrete layer after the chalk line positioning is completed using expansion bolts;

[0023] S6: Mix cement and sand with a small amount of water in a 1:3 ratio to obtain dry-hard cement mortar; spread the dry-hard cement mortar evenly on the concrete layer, level the dry-hard cement mortar with the horizontal elevation of the upper flange of the C-type connector, and form a dry-hard cement mortar layer after hardening.

[0024] S7: Place the patterned steel plate on the upper flange of the C-type connector, with the side of the patterned steel plate flush with the web of the C-type connector, and clean the dry hardened cement mortar between the gaps of two adjacent patterned steel plates.

[0025] S8: Spot weld the side of the patterned steel plate to the web of the C-shaped connector; then set an L-shaped connector at the boundary of the patterned steel plate laying area. The bottom of the L-shaped connector is fixed to the concrete layer with expansion bolts, and the vertical surface of the L-shaped connector is fixed with steel strips by spot welding to enhance the stability of the overall structure; after completion, cut the drain pipe to make it flush with the concrete layer and install a floor drain; lay gravel in the gap between the adjacent patterned steel plates. The gravel above the floor drain can prevent foreign objects from clogging the drain pipe.

[0026] Compared with the prior art, the present invention has the following advantages:

[0027] (1) This invention changes the traditional application scenario of patterned steel plates, applying them to non-temporary structures. Through a construction method combining dry and wet work, C-shaped connectors create an overhead connection between the patterned steel plate and the concrete floor. Dry-hardened cement mortar is then used to fill the space beneath the patterned steel plate and connect it to the concrete floor, significantly reducing the noise generated by foot traffic. This method both extends the service life of the patterned steel plate and improves the user's walking experience.

[0028] (2) The steel plate dry and wet combined laying structure provided by the present invention has a pre-embedded drainage pipe and a floor drain, which realizes the effective collection and summarization of rainwater on the outdoor ground, thereby realizing the reuse of rainwater and improving the efficiency of resource utilization. Attached Figure Description

[0029] Figure 1 This is a cross-sectional view of the laying structure provided in this embodiment;

[0030] Figure 2 for Figure 1 Enlarged view of a portion of the C-shaped connector;

[0031] Figure 3 This is a top view of the laying structure provided in this embodiment;

[0032] Figure 4 for Figure 3 A magnified view of a portion of the image;

[0033] In the diagram: 1. Foundation soil; 2. Crushed stone layer; 3. Concrete layer; 4. C-type connector; 5. L-type connector; 6. Steel bar; 7. Dry-hardened cement mortar layer; 8. Patterned steel plate; 9. Gravel; 10. Drainage pipe; and 11. Floor drain. Detailed Implementation

[0034] To make the above-mentioned objects, features, and advantages of the present invention more apparent and understandable, the specific embodiments of the present invention will be described in detail below with reference to the accompanying drawings. Many specific details are set forth in the following description to provide a thorough understanding of the present invention. However, the present invention can be practiced in many other ways different from those described herein, and those skilled in the art can make similar modifications without departing from the spirit of the present invention. Therefore, the present invention is not limited to the specific embodiments disclosed below. Technical features in the various embodiments of the present invention can be combined accordingly without mutual conflict.

[0035] As a preferred embodiment of the present invention, this embodiment provides a steel plate wet-dry combined laying structure with rainwater harvesting function, as shown in the cross-sectional view. Figure 1 As shown. The steel plate dry and wet combined laying structure includes a crushed stone layer 2, a concrete layer 3, C-type connectors 4, a dry hardened cement mortar layer 7, a patterned steel plate 8, a drainage pipe 10, and a floor drain 11.

[0036] In the structure provided by this invention, the crushed stone layer 2 is laid on the compacted and leveled foundation soil 1. The concrete layer 3 is poured on top of the crushed stone layer 2. Generally, the thickness of both the crushed stone layer 2 and the concrete layer 3 is 150mm.

[0037] The C-type connector 4 used in the structure provided by this invention is specifically as follows: Figure 2 The C-type connector 4 includes an upper flange and a lower flange that are parallel to each other, and a web perpendicular to the upper flange and the lower flange. Fixing holes are provided on both the upper flange and the lower flange of the C-type connector 4.

[0038] In this embodiment, the C-type connector 4 is made of hot-dip galvanized channel steel, and the distance between the upper and lower flanges of the C-type connector 4 is 30mm, that is, the height of the web is 30mm. It should be noted that those skilled in the art can choose a C-type connector 4 with a distance of 30-50mm between the upper and lower flanges. However, if the distance between the upper and lower flanges exceeds 50mm, it is recommended to reinforce the C-type connector.

[0039] C-shaped connectors 4 are fixed at intervals on the concrete layer 3. At least four C-shaped connectors 4 are installed under each patterned steel plate 8 to be laid, supporting the four corners of the plate. In this embodiment, standard patterned steel plates are used, with dimensions of 2440mm × 1220mm, and a gap of 80mm between adjacent plates. Of course, those skilled in the art can select appropriate plate sizes and gap settings based on actual working conditions.

[0040] In this embodiment, expansion bolts pass through fixing holes on the lower flange of the C-shaped connector 4 to fix the C-shaped connector 4 to the concrete layer 3. Six C-shaped connectors 4 are installed under each patterned steel plate 8 to be laid, four of which are used to support the four corners of the patterned steel plate 8, and the other two are located on the central axis of the long side of the patterned steel plate 8. The upper flange of the C-shaped connector 4 is used to support the patterned steel plate 8.

[0041] In the structure provided by the present invention, a dry-hardened cement mortar layer 7 is poured on the concrete layer 3, and the thickness of the dry-hardened cement mortar layer 7 is based on the upper flange of the C-shaped connector 4.

[0042] To enable the paving structure to also collect rainwater, drainage pipes 10 are pre-embedded in the gaps between adjacent patterned steel plates 8. The drainage pipes 10 are pre-embedded in the foundation soil 1, the gravel layer 2, and the concrete layer 3, with geotextile fabric at the ends to prevent soil clogging. A drain 11 is installed at one end of the drainage pipe 10 located in the concrete layer 3, and the other end of the drainage pipe 10 extends to the main drainage pipe. Figure 3 and Figure 4 As shown, gravel is laid in the gaps between adjacent patterned steel plates 8. The gravel 9 above the drain 11 helps prevent foreign objects from clogging the drain pipe 10.

[0043] In this embodiment, to improve the overall stability of the area where the patterned steel plate 8 is laid, steel strips 6 are vertically installed at the edge of the laid patterned steel plate 8 to form a boundary with other paving materials. L-shaped connectors 5 are provided where the steel strips 6 are installed. The bottom surface of the L-shaped connectors 5 is fixed to the concrete layer 3 by expansion bolts, and the vertical surface of the L-shaped connectors 5 is used to fix the steel strips 6. The L-shaped connectors 5 can be made of hot-dip galvanized angle steel.

[0044] The following is a construction method for the above-mentioned patterned steel plate wet and dry combined laying structure, with the specific steps as follows:

[0045] Step 1: Detailing the layout of the drawings.

[0046] The arrangement of the patterned steel plates (8) is refined according to the required area. The standard size of the patterned steel plates is 2440mm × 1220mm, and the gap between adjacent patterned steel plates is 80mm. The principle is to prioritize the symmetrical arrangement of standard plates along the center, and the locations of rainwater drains are marked on the drawings. Each rainwater drain is controlled to be approximately 50m². 2 Left and right, that is, the area within 50m of a single floor drain. 2 They all looked for a slope towards this drain.

[0047] Step 2: Leveling the foundation soil and laying drainage pipes.

[0048] After compacting and leveling the foundation soil 1, and positioning it according to the detailed drawings, pre-embed drainage pipes 10 in the foundation soil 1. One end of the drainage pipe 10 is connected to the main drainage pipe and the rainwater collection tank in sequence. The upper elevation of the drainage pipe 10 must exceed the finished ground surface. After completion, use rags to seal the pipe opening to prevent foreign objects from entering.

[0049] Step 3: Laying graded crushed stone layer and pouring concrete layer.

[0050] A layer of crushed stone 2 is laid on the foundation soil 1. Concrete 3 is then poured on the crushed stone layer 2, with the concrete being poured and smoothed as it is poured, with the lowest point being the location where the drain 11 is to be installed. The slope around the drain 11 is 0.3%. The thickness of both the crushed stone layer 2 and the concrete layer 3 is 150mm.

[0051] Step 4: Position the connectors by marking lines and measure the elevation.

[0052] After the concrete layer 3 has hardened, C-type connectors 4 need to be installed on its surface for positioning by marking lines. The lines are drawn with the size of a single patterned steel plate as the boundary, and the positions of each patterned steel plate are marked. The standard height of the C-type connector is 30mm. However, since the ground elevation is not uniform, the elevation needs to be measured and checked to make the finished surface the same height. For some positions with large differences, the connectors need to be processed and manufactured.

[0053] Step 5: Secure the connectors.

[0054] Six C-shaped connectors 4 are installed at the bottom of a patterned steel plate 8, one C-shaped connector is installed at each of the four sides, and one C-shaped connector is installed in the middle of the two long sides of the patterned steel plate. L-shaped connectors are installed at the boundary positions. All connectors are fixed to the concrete ground with expansion bolts.

[0055] Step 6: Mix and lay dry-hardened cement mortar.

[0056] Cement and sand are mixed with a small amount of water in a 1:3 ratio to obtain dry-hardened cement mortar. The dry-hardened cement mortar is spread evenly on the concrete layer 3, and leveled with the horizontal plane of the upper flange of the C-type connector 4. After hardening, it forms a dry-hardened cement mortar layer 7.

[0057] Step 7: Place the patterned steel plate and clean the gaps.

[0058] Place the patterned steel plate 8 on the upper flange of the C-shaped connector 4, with the side of the patterned steel plate 8 flush with the web of the C-shaped connector 4. Clean the dry, hardened cement mortar between adjacent patterned steel plates 8. The cleaning standard is that the sides of the patterned steel plate and the side of the connector are exposed, and the bottom surface is exposed to the concrete floor.

[0059] Step 8: Welding connection, floor drain installation, and gravel filling.

[0060] The side of the patterned steel plate 8 is spot-welded to the web of the C-shaped connector 4. Then, L-shaped connectors 5 are installed at the boundary of the area where the patterned steel plate 8 is laid. The bottom of the L-shaped connector 5 is fixed to the concrete layer 3 with expansion bolts, and the vertical surface of the L-shaped connector 5 is spot-welded with steel strips 6 to enhance the stability of the overall structure. After completion, the drain pipe 10 is cut to be flush with the concrete layer 3, and a floor drain 11 is installed. Gravel is laid in the gaps between adjacent patterned steel plates 8 until it is flush with the surface of the patterned steel plate, ensuring a smooth and aesthetically pleasing overall appearance. The gravel 9 above the floor drain 11 prevents foreign objects from clogging the drain pipe 10.

[0061] The present invention provides a connection between the patterned steel plate and the concrete layer through a combination of dry and wet operations: the patterned steel plate and the concrete ground are connected by a C-shaped connector, and the bottom of the patterned steel plate is filled with dry hard cement mortar to connect it to the concrete ground, which greatly reduces the abnormal noise caused by stepping on the steel plate.

[0062] Drainage pipes and rainwater collection drains are buried in the foundation soil and concrete layers respectively. The drains are installed in the gaps between the checkered steel plates, and gravel is laid on top of the drains to reduce the possibility of blockage by foreign objects. Rainwater can flow from the drains and drainage pipes all the way to the rainwater collection tank, thus achieving the function of rainwater collection.

[0063] The embodiments described above are merely preferred embodiments of the present invention and are not intended to limit the invention. Those skilled in the art can make various changes and modifications without departing from the spirit and scope of the invention. Therefore, all technical solutions obtained through equivalent substitution or transformation fall within the protection scope of the present invention.

Claims

1. A steel plate dry-wet combined laying structure with rainwater harvesting function, characterized in that, It includes a crushed stone layer (2), a concrete layer (3), a C-type connector (4), a dry-hardened cement mortar layer (7), a patterned steel plate (8), a drainage pipe (10), and a floor drain (11); The crushed stone layer (2) is laid on the compacted and leveled foundation soil (1); the concrete layer (3) is poured on the crushed stone layer (2); several C-shaped connectors (4) for placing patterned steel plates (8) are fixed at intervals on the concrete layer (3); the C-shaped connector (4) includes an upper flange and a lower flange that are parallel to each other and a web perpendicular to the upper flange and the lower flange, wherein fixing holes are opened on the upper flange and the lower flange of the C-shaped connector (4); the fixing member passes through the fixing hole on the lower flange of the C-shaped connector (4) and fixes the C-shaped connector (4) on the concrete layer (3); a dry hard cement mortar layer (7) is poured on the concrete layer (3), the thickness of the dry hard cement mortar layer (7) is at the elevation of the upper flange of the C-shaped connector (4); the patterned steel plate (8) is fixed on the upper flange of the C-shaped connector (4); The drainage pipe (10) is set in the gap between adjacent patterned steel plates (8). One end of the drainage pipe (10) is provided with a floor drain (11), and the other end is pre-buried in the foundation soil (1) and extends to the main drainage pipe. Gravel (9) is laid in the gap between adjacent patterned steel plates (8).

2. The steel plate wet-dry combined laying structure according to claim 1, characterized in that, The patterned steel plate (8) is laid with steel strips (6) vertically arranged on the edge to form a boundary with other paving materials; L-shaped connectors (5) are provided where steel strips (6) need to be set. The bottom surface of the L-shaped connectors (5) is fixed to the concrete layer (3) by expansion bolts. The vertical surface of the L-shaped connectors (5) is used to fix the steel strips (6).

3. The steel plate wet-dry combined laying structure according to claim 2, characterized in that, The L-shaped connector (5) is made of hot-dip galvanized angle steel.

4. The steel plate wet-dry combined laying structure according to claim 1, characterized in that, The C-type connector (4) is made of hot-dip galvanized channel steel; the distance between the upper flange and the lower flange of the C-type connector (4) is 30-50mm.

5. The steel plate wet-dry combined laying structure according to claim 1, characterized in that, The fastener is an expansion bolt.

6. The steel plate wet-dry combined laying structure according to claim 1, characterized in that, The thickness of both the crushed stone layer (2) and the concrete layer (3) is 150 mm.

7. The steel plate wet-dry combined laying structure according to claim 1, characterized in that, The slope around the floor drain (11) on the concrete layer (3) is 0.3% to 0.5%.

8. The steel plate wet-dry combined laying structure according to claim 1, characterized in that, The patterned steel plate (8) has a size of 2440mm×1220mm, and the gap between adjacent patterned steel plates (8) is set to 80~120mm.

9. The steel plate wet-dry combined laying structure according to claim 1, characterized in that, The ratio of cement to sand used in the dry-hardened cement mortar layer (7) is 1:

3.

10. A construction method for a steel plate dry-wet combined laying structure as described in any one of claims 1 to 9, characterized in that, The specific steps are as follows: S1: The arrangement of the patterned steel plate (8) is further refined according to the area of ​​the patterned steel plate to be laid; S2: Compact and level the foundation soil (1), and according to the detailed drawings in step S1, pre-bury drainage pipes (10) in the foundation soil (1). One end of the drainage pipe (10) is connected to the main drainage pipe and the rainwater collection tank in sequence; the upper elevation of the drainage pipe (10) must exceed the finished ground surface; S3: Lay a layer of crushed stone (2) on the foundation soil (1); pour concrete on the crushed stone layer (2) to form a concrete layer (3), wherein the concrete is poured and smoothed as it is poured, with the lowest point being the location where the drain (11) needs to be installed, and the slope around the drain (11) is 0.3% to 0.5%. S4: After the concrete layer (3) has hardened, a C-type connector (4) needs to be installed on its surface for marking and positioning, and the elevation needs to be measured. S5: Fix the lower flange of the C-type connector (4) to the concrete layer (3) after the chalk line positioning is completed by expansion bolts; S6: Mix cement and sand with a small amount of water in a ratio of 1:3 to obtain dry hard cement mortar; spread the dry hard cement mortar on the concrete layer (3), level the dry hard cement mortar with the horizontal elevation of the upper flange of the C-type connector (4), and form a dry hard cement mortar layer (7) after hardening. S7: Place the patterned steel plate (8) on the upper flange of the C-type connector (4), with the side of the patterned steel plate (8) flush with the web of the C-type connector (4), and clean the dry hard cement mortar between the gaps of two adjacent patterned steel plates (8). S8: Spot weld the side of the patterned steel plate (8) to the web of the C-type connector (4); then set an L-type connector (5) at the boundary of the area where the patterned steel plate (8) is laid. The bottom surface of the L-type connector (5) is fixed to the concrete layer (3) by expansion bolts. The vertical surface of the L-type connector (5) is fixed with steel strips (6) by spot welding to enhance the stability of the overall structure. After completion, cut the drain pipe (10) so that it is flush with the concrete layer (3) and set a floor drain (11). Lay gravel (9) in the gap between the adjacent patterned steel plates (8). The gravel (9) above the floor drain (11) can prevent foreign objects from clogging the drain pipe (10).