A lifeline pre-buried part burying point optimization method, medium and system

By optimizing the location of the embedded points for the lifeline, the problems of restricted worker movement and material waste caused by unreasonable embedded point placement were solved, thus improving construction efficiency and safety.

CN118774427BActive Publication Date: 2026-11-20CHINA CONSTR SECOND ENG BUREAU LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410910105.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-07-09
Publication Date
2026-11-20
Estimated Expiration
2044-07-09

AI Technical Summary

Technical Problem

The existing lifeline pre-embedded parts are not set up properly, which restricts the range of movement of construction personnel, affects work efficiency and safety, or increases material waste.

Method used

By constructing a building structure model, a three-dimensional construction flow line for the exterior wall is generated, the anchorage point location is calculated and optimized, and interference points are eliminated by combining the safety belt length and facility flow line, thereby optimizing the number and location of embedded parts.

Benefits of technology

This achieves complete coverage of the construction area while reducing the number of embedded parts, thus improving construction efficiency and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118774427B_ABST
    Figure CN118774427B_ABST
Patent Text Reader

Abstract

The application discloses a life rope pre-embedded part burying point optimization method, medium and system, relates to the technical field of building construction, and comprises the following steps: constructing a structure model of a building based on construction drawings and generating a three-dimensional construction dynamic line of an outer wall according to a construction scheme, calculating a primary anchoring burying point position by using the three-dimensional construction dynamic line of the outer wall, obtaining a primary anchoring burying point set, performing coverage calculation on the anchoring burying point position in combination with a standard length of a safety belt, obtaining a secondary anchoring burying point set capable of completely covering a construction area of the outer wall, performing cross calculation on the secondary anchoring burying point set, removing anchoring burying points that do not reduce the coverage range, and obtaining a final anchoring burying point set. After the three-dimensional construction dynamic line of the outer wall is obtained, the position of the pre-embedded part burying point is calculated and optimized, the number of the pre-embedded part burying points can be reduced as much as possible while ensuring that the construction area is completely covered, the effect of optimizing the position and the number of the pre-embedded part burying points is achieved, and the construction efficiency and the construction safety are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of building construction technology, specifically to a method, medium, and system for optimizing the embedding points of lifeline pre-embedded parts. Background Technology

[0002] When dismantling scaffolding on building exteriors or performing other high-altitude operations, lifelines, also known as safety ropes, must be installed in the work area to ensure the safety of construction workers. These lifelines are typically made of high-strength fiber or metal materials and are characterized by high load-bearing capacity, wear resistance, and high tensile strength. They are fixed to embedded parts within the wall structure, allowing workers to connect their safety harnesses to the lifelines via safety hooks, thus ensuring their safety and preventing falls due to accidents. The placement of these embedded lifeline points is a crucial measure for ensuring the safety of construction workers working at heights. Currently, there are some shortcomings in the current methods of installing these lifeline embedded points.

[0003] In some construction sites, the placement of embedded parts is not reasonable, which restricts the area where construction workers can move around. This means that the workers' range of movement cannot fully cover the construction area, making it inconvenient to carry out their work. For example, if there are not enough embedded parts or the placement is inappropriate, construction workers may need to frequently adjust the connection with the lifeline, affecting work efficiency and safety. On the other hand, setting too many embedded parts leads to material waste and additional steps in formwork installation, thereby increasing and reducing construction efficiency. Summary of the Invention

[0004] This invention provides a method, medium, and system for optimizing the embedding points of lifeline pre-embedded components to solve the above-mentioned problems.

[0005] A method for optimizing the embedding points of lifeline pre-embedded components includes:

[0006] A structural model of the building was constructed based on the construction drawings;

[0007] Based on the construction plan and the above-mentioned building structure model, a three-dimensional construction flow line for the exterior wall is generated, which includes personnel flow line and facility flow line.

[0008] The location of the primary anchorage point is calculated using the three-dimensional construction path of the exterior wall obtained above, and the set of primary anchorage points is obtained.

[0009] Based on the anchorage location and the standard length of the safety belt, a set of secondary anchorage points that can completely cover the construction area of ​​the building's exterior wall is obtained through coverage calculation.

[0010] Cross-calculation is performed on the secondary anchorage point set, and anchorage points that do not reduce the coverage area are removed to obtain the final anchorage point set.

[0011] Furthermore, the specific steps for generating the 3D construction flow line of the exterior wall are as follows:

[0012] The construction plan is identified, and the set of construction areas for the building's exterior walls is obtained based on the building's structural model;

[0013] Based on the construction process in the construction plan, the facility activity range is obtained by simulating the above-mentioned building exterior wall construction area, and the facility movement line is obtained by fitting all the facility activity ranges.

[0014] Based on the construction process, the activity range of personnel is obtained by simulating the construction area of ​​the building's exterior walls, and the movement lines of personnel are obtained by fitting the activity range of all personnel.

[0015] Furthermore, the calculation process for the primary anchorage point includes:

[0016] Based on the personnel movement line, the entire area within the personnel movement line range is designated as the first anchoring point preset area;

[0017] Using facility circulation as a variable, identify the overlapping areas between facility circulation and personnel circulation;

[0018] A feasibility analysis of anchorage point locations is conducted in the overlapping area. Locations that cannot be used as anchorage points are deleted from the first anchorage point preset area to obtain the second anchorage point preset area.

[0019] Further feasibility analysis of anchorage point locations was conducted using the building structure model. Points that could not be used as anchorage points were removed from the second anchorage point preset area to obtain the third anchorage point preset area.

[0020] All locations in the third anchorage point preset area are used as primary anchorage points, forming a primary anchorage point set.

[0021] Furthermore, the process of performing coverage calculations includes the following steps:

[0022] Calculate the area that the standard length of the seat belt can cover;

[0023] Based on the location of the construction area and the aforementioned coverable area, several primary anchoring points were selected from the primary anchoring points.

[0024] The set of secondary anchor points is output after verifying all the primary anchor points that have been extracted and can cover the entire construction area.

[0025] Furthermore, calculating the coverage area of ​​a standard seatbelt length includes the following steps:

[0026] The minimum value among the standard lengths of the seat belt is taken as the benchmark for calculating the coverable area;

[0027] The coverage radius is defined as half the length of the seat belt.

[0028] Calculate the area that the standard length of the seat belt can cover using the aforementioned coverage radius.

[0029] Furthermore, the steps for performing cross-calculation include:

[0030] List the coverage radius of all secondary anchorage points;

[0031] Calculate the distance between anchorage points;

[0032] Check the coverage relationship between anchor points, set a distance threshold, and while maintaining the coverage range, remove other anchor points within the distance threshold range within the coverage range of the anchor points;

[0033] The remaining anchor points are output as the final anchor point set.

[0034] Furthermore, the above process includes:

[0035] The remaining anchor points are verified, and if the coverage area is not reduced, the remaining anchor points are output as the final anchor point set.

[0036] When the coverage area decreases, some anchor points are restored for the reduced area until the coverage area of ​​the remaining anchor points does not decrease. The remaining anchor points are then output as the final anchor point set.

[0037] A computer-readable storage medium storing program instructions, which, when executed, are used to implement the above-described method for optimizing the embedding points of lifeline pre-embedded components.

[0038] A lifeline pre-embedded component embedding point optimization system includes the aforementioned computer-readable storage medium.

[0039] The beneficial effects of the above-mentioned technical solutions provided by the embodiments of the present invention include at least the following: after obtaining the three-dimensional construction flow line of the exterior wall, the present invention calculates and optimizes the position of the embedded parts, while ensuring complete coverage of the construction area, it can also minimize the number of embedded parts, thereby achieving the effect of optimizing the position and number of embedded parts, and improving construction efficiency and construction safety.

[0040] Other features and advantages of the invention will be set forth in the description which follows, and will be apparent in part from the description, or may be learned by practicing the invention. The objects and other advantages of the invention may be realized and obtained by means of the structures particularly pointed out in the written description, claims, and drawings.

[0041] The technical solution of the present invention will be further described in detail below with reference to the accompanying drawings and embodiments. Attached Figure Description

[0042] The accompanying drawings are provided to further illustrate the invention and form part of the specification. They are used in conjunction with embodiments of the invention to explain the invention and do not constitute a limitation thereof. In the drawings:

[0043] Figure 1 This is a flowchart illustrating the method for optimizing the embedding points of lifeline pre-embedded parts disclosed in an embodiment of the present invention. Detailed Implementation

[0044] Exemplary embodiments of the present disclosure will now be described in more detail with reference to the accompanying drawings. While exemplary embodiments of the present disclosure are shown in the drawings, it should be understood that the present disclosure may be implemented in various forms and should not be limited to the embodiments set forth herein. Rather, these embodiments are provided so that this disclosure will be thorough and complete, and will fully convey the scope of the disclosure to those skilled in the art.

[0045] In existing technologies, to ensure safety, construction workers must use lifelines when performing high-altitude operations. During the design phase, corresponding embedded parts and their embedding points are set for different building structures and construction areas.

[0046] When pouring concrete for the wall, the embedded parts are connected to the steel bars inside the wall for pouring. Therefore, the formwork needs to be processed accordingly at the location where the embedded parts are set (such as making holes).

[0047] Too many embedded parts will not only increase the amount of construction work, but also increase the risk of grout leakage from the formwork. However, too few embedded parts or unreasonable placement of them will lead to an unreasonable reduction in the activity area of ​​construction workers, requiring them to increase the adjustment range of their safety belts. This will not only increase safety risks, but also reduce construction efficiency. In order to optimize the location and number of embedded parts, this application proposes the following solution to address the above-mentioned problems.

[0048] Figure 1 The flowchart of the lifeline pre-embedded component embedding point optimization method disclosed in an embodiment of the present invention is shown, including the following steps:

[0049] like Figure 1 As shown, S1 is a structural model of the building constructed based on the construction drawings.

[0050] As an example, BIM software can be used to construct the structural model of a building;

[0051] This includes importing the building's CAD drawings into BIM software and then setting up components such as columns, beams, slabs, and walls to construct the building's structural model.

[0052] like Figure 1 As shown in Figure S2, a three-dimensional construction flow line for the exterior wall is generated based on the construction plan and the above-mentioned building structure model. The three-dimensional construction flow line for the exterior wall includes personnel flow line and facility flow line.

[0053] According to the embodiments of this disclosure, the three-dimensional construction movement line of the exterior wall is defined as follows: based on the building structure model, the virtual trajectory set on the exterior wall of the building structure model is obtained by simulation. The personnel movement line is the virtual movement trajectory of personnel in the construction area during the construction process. The facility movement line is the virtual movement trajectory of the facility during the construction process. If the position of the facility changes, the trajectory is fitted according to the position change.

[0054] According to embodiments of this disclosure, the three-dimensional construction flow line of the exterior wall is used to reflect the activity range of construction personnel and the changes in the location of facilities during the entire construction process of the construction plan, so as to identify the areas where lifeline pre-embedded parts can be installed, avoid interference with facilities, and facilitate the installation of lifelines and their use by construction personnel.

[0055] According to embodiments of this disclosure, generating a three-dimensional construction route for the exterior wall based on the construction plan includes:

[0056] The construction plan is identified, and the set of construction areas for the building's exterior walls is obtained based on the building's structural model.

[0057] Based on the construction process in the construction plan, the facility activity range is obtained by simulating the above-mentioned building exterior wall construction area, and the facility movement line is obtained by fitting all the facility activity ranges.

[0058] Based on the construction process, the activity range of personnel is obtained by simulating the construction area of ​​the building's exterior walls, and the movement lines of personnel are obtained by fitting the activity range of all personnel.

[0059] The building structure model and the three-dimensional construction route of the exterior wall obtained above can be displayed in the form of images on display devices, such as monitors, which can be easily viewed and corrected.

[0060] like Figure 1 As shown in Figure S3, the location of the primary anchorage point is calculated using the three-dimensional construction line of the exterior wall obtained above, thus obtaining the set of primary anchorage points.

[0061] According to embodiments of this disclosure, the calculation process for the primary anchorage point includes:

[0062] Based on the personnel movement line (since the construction area is fixed and the personnel's activity range is consistent with the construction area, the personnel movement line is taken as a constant, i.e., the benchmark), the entire area within the personnel movement line is taken as the preset area of ​​the first anchoring point (the entire area within the personnel movement line can be taken as the setting point of the first anchoring point).

[0063] Using facility movement as a variable (facilities under construction may have non-fixed positions due to changes in location; therefore, it is necessary to determine the location of the primary anchorage point based on the location of the facility to avoid interference between the facility and the primary anchorage point), identify the overlapping area between facility movement and personnel movement.

[0064] A feasibility analysis of anchorage point locations is conducted in the overlapping area. Locations that cannot be used as anchorage points are deleted from the first anchorage point preset area to obtain the second anchorage point preset area.

[0065] According to embodiments of this disclosure, the above feasibility analysis includes:

[0066] Determine whether there is any interference between the location of the overlapping area facilities and the location of the primary anchorage point under the construction process of the construction plan;

[0067] If interference exists, it is determined that the location cannot be used as a primary anchorage point.

[0068] If there is no interference, it can be determined as a primary anchorage location.

[0069] The aforementioned interference means that the primary anchorage point comes into contact with the facility, rendering the primary anchorage point or facility unusable.

[0070] Among them, the anchorage point refers to the embedding point of the lifeline pre-embedded part.

[0071] Further feasibility analysis of anchorage point locations was conducted using the building structure model. Points that were identified as unsuitable for anchorage were removed from the second anchorage point preset area, resulting in the third anchorage point preset area.

[0072] According to embodiments of this disclosure, the above feasibility analysis includes:

[0073] The openings in the wall, the connection between beams and columns, and the corner areas are identified as the first deletion area; the bearing capacity of the structure in the preset area of ​​the second anchor point is calculated, and the area below the set bearing capacity threshold is identified as the second deletion area;

[0074] The first and second deletion areas are deleted from the second anchoring point preset area to obtain the third anchoring point preset area.

[0075] All locations in the third anchorage point preset area are used as primary anchorage points, forming a primary anchorage point set.

[0076] like Figure 1 As shown in Figure S4, the secondary anchorage point set that can completely cover the construction area of ​​the building exterior wall is obtained by calculating the coverage based on the anchorage point location and the standard length of the safety belt.

[0077] According to embodiments of this disclosure, the process of performing coverage calculation includes the following steps:

[0078] Calculate the area that the standard length of the seat belt can cover;

[0079] Based on the location of the construction area and the aforementioned coverable area, several primary anchoring points were selected from the primary anchoring points.

[0080] The set of secondary anchor points is output after verifying all the primary anchor points that have been extracted and can cover the entire construction area.

[0081] According to the embodiments of this disclosure, virtual lifelines are set in a plurality of primary anchoring points, and the coverage area of ​​the plurality of primary anchoring points and the standard length of the safety belt is calculated based on the coverage area of ​​the standard length of the safety belt.

[0082] The standard for calculating the overall coverage area is the area that can be covered during construction.

[0083] According to embodiments of this disclosure, in order to improve the safety of construction workers while ensuring that their activity area covers the construction area, and to calculate the coverable area of ​​the standard length of the safety belt, the following steps are included:

[0084] The minimum value among the standard lengths of the seat belt is taken as the benchmark for calculating the coverable area;

[0085] The coverage radius is defined as half the length of the seat belt.

[0086] Calculate the area that the standard length of the seat belt can cover using the aforementioned coverage radius.

[0087] According to embodiments of this disclosure, calculating the coverage area of ​​a standard seat belt includes the following steps:

[0088] The minimum value among the standard lengths of the seat belt is taken as the benchmark for calculating the coverable area;

[0089] The coverage radius is defined as two-thirds of the seatbelt length.

[0090] Calculate the area that the standard length of the seat belt can cover using the aforementioned coverage radius.

[0091] According to embodiments of this disclosure, calculating the coverage area of ​​a standard seat belt includes the following steps:

[0092] The minimum value among the standard lengths of the seat belt is taken as the benchmark for calculating the coverable area;

[0093] The coverage radius is defined as three-quarters of the seatbelt length.

[0094] Calculate the area that the standard length of the seat belt can cover using the aforementioned coverage radius.

[0095] It should be noted that the preferred coverage radius is half the length of the safety belt. Using half the length of the safety belt can ensure the range of movement of construction workers while also covering the construction area.

[0096] like Figure 1 As shown in Figure S5, cross-calculation is performed on the secondary anchorage point set to remove anchorage points that do not reduce the coverage area, thus obtaining the final anchorage point set.

[0097] According to embodiments of this disclosure, the steps for performing cross-calculation include:

[0098] List the coverage radius of all secondary anchorage points;

[0099] Calculate the distance between anchorage points;

[0100] Check the coverage relationship between anchor points, set a distance threshold, and while maintaining the coverage range, remove other anchor points within the distance threshold range within the coverage range of the anchor points;

[0101] In the above embodiments, when both adjacent anchor points can be eliminated, the elimination is simulated. Specifically, after eliminating one anchor point, the overall coverage area is calculated. If the coverage area is not affected, the current elimination result is output. If the coverage area shrinks after eliminating one anchor point, the eliminated anchor point is restored and the other anchor point is eliminated. If the coverage area is not affected after elimination, the current elimination result is output. If eliminating either one results in a shrinkage of the coverage area, the current two anchor points are retained.

[0102] The remaining anchor points are output as the final anchor point set.

[0103] The above process includes:

[0104] The remaining anchor points are verified, and if the coverage area is not reduced, the remaining anchor points are output as the final anchor point set.

[0105] When the coverage area decreases, some anchor points are restored for the reduced area until the coverage area of ​​the remaining anchor points does not decrease. The remaining anchor points are then output as the final anchor point set.

[0106] A computer-readable storage medium storing program instructions, which, when executed, are used to implement the above-described method for optimizing the embedding points of lifeline pre-embedded components.

[0107] A lifeline pre-embedded component embedding point optimization system includes the aforementioned computer-readable storage medium.

[0108] After obtaining the three-dimensional construction route of the exterior wall, the embodiments of the present invention calculate and optimize the position of the embedded parts. While ensuring complete coverage of the construction area, the number of embedded parts can be reduced as much as possible, thereby optimizing the position and number of embedded parts and improving construction efficiency and safety.

[0109] It should be understood that the specific order or hierarchy of steps in the disclosed process is an example of an exemplary method. Based on design preferences, it should be understood that the specific order or hierarchy of steps in the process may be rearranged without departing from the scope of this disclosure. The appended method claims provide elements of various steps in an exemplary order and are not intended to limit the scope to the specific order or hierarchy described.

[0110] In the detailed description above, various features are combined together in a single embodiment to simplify this disclosure. This approach to disclosure should not be construed as reflecting an intention that embodiments of the claimed subject matter require more features than are explicitly stated in each claim. Rather, as reflected in the appended claims, the invention is presented with fewer features than all of the features in a single disclosed embodiment. Therefore, the appended claims are hereby explicitly incorporated into the detailed description, with each claim representing a separate preferred embodiment of the invention.

[0111] Those skilled in the art will also understand that the various illustrative logic blocks, modules, circuits, and algorithm steps described in conjunction with the embodiments herein can be implemented as electronic hardware, computer software, or a combination thereof. To clearly illustrate the interchangeability between hardware and software, the various illustrative components, blocks, modules, circuits, and steps described above are generally described in terms of their functionality. Whether such functionality is implemented as hardware or software depends on the specific application and the design constraints imposed on the overall system. Those skilled in the art can implement the described functionality in alternative ways for each specific application; however, such implementation decisions should not be construed as departing from the scope of this disclosure.

[0112] The steps of the methods or algorithms described in conjunction with the embodiments herein can be directly embodied in hardware, software modules executed by a processor, or a combination thereof. The software modules can reside in RAM memory, flash memory, ROM memory, EPROM memory, EEPROM memory, registers, hard disks, removable disks, CD-ROMs, or any other form of storage medium well known in the art. An exemplary storage medium is connected to the processor, enabling the processor to read information from and write information to the storage medium. Of course, the storage medium can also be a component of the processor. The processor and storage medium can reside in an ASIC. The ASIC can reside in a user terminal. Alternatively, the processor and storage medium can exist as discrete components in the user terminal.

[0113] For software implementation, the techniques described in this application can be implemented using modules (e.g., procedures, functions, etc.) that perform the functions described in this application. This software code can be stored in memory units and executed by a processor. The memory units can be implemented within the processor or outside the processor; in the latter case, they are communicatively coupled to the processor via various means, as is well known in the art.

[0114] The foregoing description includes examples of one or more embodiments. It is certainly impossible to describe all possible combinations of components or methods in order to describe the above embodiments, but those skilled in the art will recognize that the various embodiments can be further combined and arranged. Therefore, the embodiments described herein are intended to cover all such changes, modifications, and variations that fall within the scope of the appended claims. Furthermore, the term "comprising" as used in the specification or claims is interpreted in a manner similar to the term "including," as interpreted when used as a conjunction in the claims. Additionally, the use of any term "or" in the specification of the claims is intended to mean "non-exclusive or."

Claims

1. A method for optimizing the embedding points of lifeline pre-embedded components, characterized in that, include: A structural model of the building was constructed based on the construction drawings; Based on the construction plan and the above-mentioned building structure model, a three-dimensional construction flow line for the exterior wall is generated, which includes personnel flow line and facility flow line. The locations of primary anchorage points are calculated using the three-dimensional construction flow lines of the exterior wall obtained above, resulting in a set of primary anchorage points. The calculation process for primary anchorage points includes: using personnel flow lines as a reference, the entire area within the personnel flow lines is designated as the first anchorage point preset area; using facility flow lines as variables, the overlapping areas of facility flow lines and personnel flow lines are identified; a feasibility analysis of anchorage point locations is performed on the overlapping areas, and locations that cannot be used as anchorage points are deleted from the first anchorage point preset area to obtain the second anchorage point preset area; a further feasibility analysis of anchorage point locations is performed using the building structure model, and locations that cannot be used as anchorage points are deleted from the second anchorage point preset area to obtain the third anchorage point preset area; all locations in the third anchorage point preset area are designated as primary anchorage points, forming a set of primary anchorage points. Based on the location of the primary anchorage points and the standard length of the safety belt, a set of secondary anchorage points that can completely cover the construction area of ​​the building's exterior wall is obtained through coverage calculation. Cross-calculation is performed on the secondary anchorage point set, and anchorage points that do not reduce the coverage area are removed to obtain the final anchorage point set.

2. The method for optimizing the embedding points of lifeline pre-embedded parts as described in claim 1, characterized in that, The specific steps for generating the 3D construction route of the exterior wall are as follows: The construction plan is identified, and the set of construction areas for the building's exterior walls is obtained based on the building's structural model; Based on the construction process in the construction plan, the facility activity range is obtained by simulating the above-mentioned building exterior wall construction area, and the facility movement line is obtained by fitting all the facility activity ranges. Based on the construction process, the activity range of personnel is obtained by simulating the construction area of ​​the building's exterior walls, and the movement lines of personnel are obtained by fitting the activity range of all personnel.

3. The method for optimizing the embedding points of lifeline pre-embedded parts as described in claim 1, characterized in that, The process of performing coverage calculations includes the following steps: Calculate the area that the standard length of the seat belt can cover; Based on the location of the construction area and the aforementioned coverable area, several primary anchoring points were selected from the primary anchoring points. The set of secondary anchor points is output after verifying all the primary anchor points that have been extracted and can cover the entire construction area.

4. The method for optimizing the embedding points of lifeline pre-embedded parts as described in claim 3, characterized in that, Calculating the coverage area of ​​a standard seatbelt length involves the following steps: The minimum value among the standard lengths of the seat belt is taken as the benchmark for calculating the coverable area; The coverage radius is defined as half the length of the seat belt. Calculate the area that the standard length of the seat belt can cover using the aforementioned coverage radius.

5. The method for optimizing the embedding points of lifeline pre-embedded parts as described in claim 1, characterized in that, The steps for performing cross-calculation include: List the coverage radius of all secondary anchorage points; Calculate the distance between anchorage points; Check the coverage relationship between anchor points, set a distance threshold, and while maintaining the coverage range, remove other anchor points within the distance threshold range within the coverage range of the anchor points; The remaining anchor points are output as the final anchor point set.

6. The method for optimizing the embedding points of lifeline pre-embedded parts as described in claim 5, characterized in that, The above process includes: The remaining anchor points are verified, and if the coverage area is not reduced, the remaining anchor points are output as the final anchor point set. When the coverage area decreases, some anchor points are restored for the reduced area until the coverage area of ​​the remaining anchor points does not decrease. The remaining anchor points are then output as the final anchor point set.

7. A computer-readable storage medium, characterized in that, The computer-readable storage medium stores program instructions, which, when executed, are used to implement the lifeline pre-embedded component embedding point optimization method according to any one of claims 1 to 6.

8. A system for optimizing the embedding points of lifeline pre-embedded components, characterized in that, Includes the computer-readable storage medium as described in claim 7.