Device for preventing the falling of the sealant strip of shield tunnel segment and construction method thereof
By installing a main structure and snap-fit components inside the joints of shield tunnel segments, the problem of sealing strip detachment was solved, the sealing strip was firmly fixed, and the safety of the tunnel was improved.
Patent Information
- Application Number
- CN202410958728.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-17
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2044-07-17
AI Technical Summary
The sealing strips used for caulking tunnel segments are prone to falling off during train operation, posing a safety hazard and affecting train operation safety.
The main structure is installed inside the joint of the shield tunnel segments. Components such as screws, transmission blocks and connecting blocks are used to ensure that the sealing strip is tightly attached to the inner wall of the joint, and the snap-fit components are used to prevent the sealing strip from falling off.
It effectively prevents the sealing strip from falling off under vibration and dynamic load conditions, increases the tightness between the sealing strip and the caulking, and ensures the safety of train operation.
Smart Images

Figure CN118774876B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of shield tunnel segment technology, and in particular to a device and its construction method for preventing the detachment of the sealing strip for shield tunnel segments. Background Technology
[0002] During operation, the sealing strips between the tunnel segments inside a shield tunnel often detach due to dynamic loads from train operation, piston wind pressure, and vibration. This poses a risk of lapsing onto the overhead contact line and causing short circuits, affecting train operation and creating significant safety risks to the railway line. Surveys of shield tunnels on operating urban rail lines in several Chinese cities, including Nanchang, Hangzhou, and Wuxi, all employ sealant caulking in their segment waterproofing design, yet the detachment of these sealant strips is also a common problem. Summary of the Invention
[0003] To address the aforementioned problems, this invention aims to provide a device and construction method for preventing the detachment of sealing strips used in shield tunnel segments.
[0004] To achieve the above objectives, the technical solution of the present invention is as follows: a device for preventing the detachment of sealing strips in shield tunnel segment caulking, comprising a sealing strip and a main body, wherein the sealing strip is disposed inside the anti-shield tunnel segment caulking joint, the main body is disposed inside the anti-shield tunnel segment caulking joint, and a fixing structure is disposed inside the main body, the fixing structure comprising:
[0005] Assembly cavity, two moving blocks, screw, threaded sleeve, connecting seat, transmission block, two telescopic rods, plug-in block, snap-fit assembly, two connecting blocks and two sliders;
[0006] The assembly cavity is located inside the main body. Two sliders are mounted on the bottom of two movable blocks. The two sliders are slidably connected to the inner walls on both sides of the bottom of the assembly cavity. One end of the screw passes through the bottom of the main body and extends into the assembly cavity. The screw is threadedly connected to the through-hole. One end of the threaded sleeve is threadedly connected to one end of the screw. The connecting seat is connected to the other end of the threaded sleeve. The transmission block is mounted on the top of the connecting seat. Both ends of the telescopic rod are connected to the bottom of the connecting seat and the inner wall of the bottom of the assembly cavity, respectively. The insertion block is mounted on the top of the transmission block. The snap-fit components are respectively located on the top of the insertion block and the bottom of the inner wall of the top of the assembly cavity. One end of each of the two connecting blocks passes through both sides of the main body and is inserted into one side of each of the two movable blocks.
[0007] Preferably, the snap-fit assembly includes: a support base, two sliding frames, two first L-shaped blocks, a strip block, two spring rods, two second L-shaped blocks, and a first limiting hole;
[0008] The support seat is installed on the top inner wall of the assembly cavity. The interior of the support seat is hollow. The two sliding frames are slidably connected to both sides of the support seat. The two first L-shaped blocks pass through the support seat and are connected to the two sliding frames. The strip block is installed at the bottom of the support seat. The two spring rods are respectively installed on both sides of the bottom of the support seat. One end of the two spring rods is connected to the outside of the two first L-shaped blocks. The two second L-shaped blocks are respectively disposed on both sides of the top of the insertion block. The first limiting hole is opened at the top of the insertion block.
[0009] Preferably, a rotating block is installed at the other end of the screw, and a groove is provided at one end of the screw where it passes through the main body, the groove matching the rotating block.
[0010] Preferably, the transmission block is configured as an isosceles trapezoid, the moving block is configured as a trapezoid, and the two sides of the transmission block are in close contact with the inner side of the moving block.
[0011] Preferably, the moving block is provided with a limiting groove on its inner side, and the transmission block is provided with limiting sliders on both sides, and the limiting groove is slidably connected to the sliders.
[0012] Preferably, two reset springs are embedded on both sides of the limiting hole, one end of each reset spring is connected to two horizontal blocks, and a second limiting hole is provided on the lower side of the strip block corresponding to the horizontal block.
[0013] Preferably, the outer side of the connecting block is inclined, and the inclination degree matches the inclination degree of the inner wall of the anti-shield tunnel segment joint.
[0014] Preferably, the outer side of the connecting block is provided with a rough rubber layer.
[0015] Preferably, a reinforcing block is provided between the spring rod and the first L-shaped block.
[0016] Meanwhile, this invention also discloses a construction method for preventing the detachment of sealant strips used for sealing joints in shield tunnel segments, comprising the following steps:
[0017] Step S1: First, clean the inside of the joints of the shield tunnel segments to remove floating dust and other impurities.
[0018] Step S2: Place the main body inside the caulking joint and rotate the screw to push the two connecting blocks out from both sides of the main body, so that the outer sides of the two connecting blocks are in close contact with the inner wall of the caulking joint, and fix the main body inside the caulking joint.
[0019] Step S3: Apply the joint sealant. After the sealant hardens, it forms a whole with the main body. By fitting the main body, the sealant strip can be firmly fixed inside the joint, preventing the sealant strip from falling off.
[0020] The beneficial effects of this invention are as follows: By setting the main body inside the caulking joint of the shield tunnel segments, and using a screw in conjunction with a transmission block, a moving block, and a connecting block, the outer side of the connecting block can be tightly attached to the inner wall of the caulking joint, so that the main body is firmly fixed inside the caulking joint. At the same time, the plug-in block, in conjunction with the snap-fit assembly, can prevent the connecting block from retracting back into the inner wall of the main body when the tunnel segments vibrate inside. After the adhesive solidifies, it will form a whole with the main body. Even if there is a situation where the adhesive is not tightly attached to the caulking joint of the segments, or the filling is not full, the mechanical force between the connecting blocks on both sides of the main body and the segments can effectively prevent the sealing strip from falling off, and increase the tightness between the sealing strip and the caulking joint. Attached Figure Description
[0021] Figure 1 This is the front view of the present invention.
[0022] Figure 2 This is a schematic diagram of the main shrinkage structure of the present invention.
[0023] Figure 3 This is a schematic diagram of the main body unfolded structure of the present invention.
[0024] Figure 4 This is a top view of the loading seat of the present invention.
[0025] Figure 5 This is a side view of the loading seat of the present invention.
[0026] Figure 6 for Figure 2 A magnified view of a portion of the image.
[0027] Figure 7 This is a three-dimensional structural diagram of the moving block and the transmission block in this invention.
[0028] In the diagram: 1. Sealing strip, 2. Main body, 3. Assembly cavity, 4. Moving block, 5. Screw, 6. Threaded sleeve, 7. Connecting seat, 8. Transmission block, 9. Telescopic rod, 10. Insertion block, 11. Connecting block, 12. Slider, 13. Bearing seat, 14. Sliding frame, 15. First L-shaped block, 16. Strip block, 17. Spring rod, 18. Second L-shaped block, 19. First limiting hole, 20. Rotating block, 21. Limiting groove, 22. Limiting slider, 23. Return spring, 24. Horizontal block, 25. Second limiting hole, 26. Rubber rough layer, 27. Reinforcing block. Detailed Implementation
[0029] The present invention will now be described in detail with reference to the accompanying drawings, such as... Figure 1-7As shown, a device for preventing the sealing strip of the shield tunnel segment caulking joint from falling off includes a sealing strip 1 and a main body 2. The sealing strip 1 is disposed inside the anti-shield tunnel segment caulking joint, and the main body 2 is disposed inside the anti-shield tunnel segment caulking joint. A fixing structure is disposed inside the main body 2.
[0030] The fixed structure mainly consists of an assembly cavity 3, two moving blocks 4, a screw 5, a threaded sleeve 6, a connecting seat 7, a transmission block 8, two telescopic rods 9, a plug-in block 10, a snap-fit assembly, two connecting blocks 11, and two sliders 12.
[0031] Assembly cavity 3 is located inside main body 2. Two sliders 12 are installed at the bottom of two moving blocks 4. The two sliders 12 are slidably connected to the inner walls of the bottom two sides of assembly cavity 3. One end of screw 5 passes through the bottom of main body 2 and extends into assembly cavity 3. Screw 5 is threadedly connected to the through point. One end of threaded sleeve 6 is threadedly connected to one end of screw 5. Connecting seat 7 is connected to the other end of threaded sleeve 6. Transmission block 8 is installed on top of connecting seat 7. Both ends of telescopic rod 9 are connected to the bottom of connecting seat 7 and the inner wall of bottom of assembly cavity 3, respectively. Insertion block 10 is installed on top of transmission block 8. Snap-fit components are respectively set on the top of insertion block 10 and the bottom of the inner wall of top of assembly cavity 3. One end of two connecting blocks 11 passes through both sides of main body 2 and is inserted into one side of two moving blocks 4, respectively.
[0032] The snap-fit assembly mainly consists of a bearing seat 13, two sliding frames 14, two first L-shaped blocks 15, a strip block 16, two spring rods 17, two second L-shaped blocks 18, and a first limiting hole 19.
[0033] The support seat 13 is installed on the top inner wall of the assembly cavity 3. The inside of the support seat 13 is hollow. Two sliding frames 14 are slidably connected to the two sides of the support seat 13. Two first L-shaped blocks 15 pass through the support seat 13 and are connected to the two sliding frames 14. A strip block 16 is installed at the bottom of the support seat 13. Two spring rods 17 are respectively installed on the bottom sides of the support seat 13. One end of the two spring rods 17 is connected to the outside of the two first L-shaped blocks. Two second L-shaped blocks are respectively set on the top sides of the plug-in block 10. The first limiting hole 19 is opened at the top of the plug-in block 10.
[0034] Before filling the joint with the sealing strip 1 of the shield tunnel segment, the dust inside the joint needs to be cleaned first. Then, the main body 2 is placed inside the joint. The screw 5 is rotated by the rotating block. At this time, the screw 5 will cooperate with the threaded sleeve 6 to drive the connecting seat 7 and the transmission block 8 to rise. As the transmission block 8 rises, it will push the two moving blocks 4 outward, pushing the two connecting blocks 11 to extend from both sides of the main body 2, so that the rubber rough layer 26 on the outside of the two connecting blocks 11 is in close contact with the inner wall of the joint. The two connecting blocks 11 cooperate to fix the main body 2 as a whole. The transmission block 8 is designed as an isosceles trapezoid, and the moving block 4 is designed as a trapezoid. The two sides of the transmission block 8 are in close contact with the inner side of the moving block 4. At the same time, the inner side of the moving block 4 is provided with a limiting groove 21, and the two sides of the transmission block 8 are provided with limiting sliders 22. The limiting groove 21 and the limiting slider 22 are slidably connected, which can limit the position of the moving block 4 and increase the smoothness of the relative movement between the transmission block 8 and the moving block 4.
[0035] During the upward movement of the transmission block 8, the first limiting hole 19 in the middle of the top of the insertion block 10 will be inserted into the bottom of the strip block 16. At this time, the two second L-shaped blocks will push the two first L-shaped blocks 15 outward, so that the two first L-shaped blocks 15 will move to both sides of the mounting base through the two sliding frames 14. After the first limiting hole 19 is fully inserted into the strip block 16, the two spring rods 17 will push the two first L-shaped blocks 15 to reset, so that the first L-shaped blocks 15 and the second L-shaped blocks can be staggered. At the same time, the second limiting hole 25 located on the lower side of the strip block 16 will be inserted into the two horizontal blocks 24 to complete the connection between the transmission block 8 and the loading base. The reinforcing block 27 is used to increase the overall strength of the first L-shaped block 15. The above components are combined to keep the connecting block 11 in the extended state through mechanical connection, which can continuously fix the main body 2.
[0036] After the main body 2 is fixed, the sealing strip 1 can be filled. After the adhesive solidifies, it will form a whole with the main body 2, which can firmly fix the sealing strip 1 to the anti-shield tunnel segment caulking. Even if there is a situation where the adhesive is not tightly adhered to the segment caulking, or the filling is not full, the mechanical force between the connecting blocks 11 on both sides of the main body 2 and the segment can effectively prevent the sealing strip 1 from falling off, and increase the tightness between the sealing strip 1 and the caulking.
[0037] A construction method for preventing the detachment of sealant strips used for sealing joints in shield tunnel segments includes the following steps:
[0038] Step S1: First, clean the inside of the joints in the shield tunnel segments to remove any floating dust or other impurities.
[0039] Step S2: Place the main body 2 inside the caulking joint and rotate the screw 5 so that the transmission block 8 pushes the two connecting blocks 11 out from both sides of the main body 2, and makes the outer sides of the two connecting blocks 11 fit tightly against the inner wall of the caulking joint, and fixes the main body 2 inside the caulking joint.
[0040] Step S3: Apply caulking sealant. After the sealant hardens, it forms a whole with the main body 2. By cooperating with the main body 2, the sealant strip 1 can be firmly fixed inside the caulking joint, preventing the sealant strip 1 from falling off.
[0041] The above technical solutions only embody the preferred technical solutions of the present invention. Any modifications that may be made by those skilled in the art to certain parts thereof embody the principles of the present invention and fall within the protection scope of the present invention.
Claims
1. A construction method for preventing the detachment of sealant strips in shield tunnel segments, comprising a device for preventing the detachment of sealant strips in shield tunnel segments, the device comprising a sealant strip (1) and a main body (2), characterized in that, The sealing strip (1) is installed inside the anti-shield tunnel segment joint, and the main body (2) is installed inside the anti-shield tunnel segment joint. The main body (2) has a fixing structure inside, which includes: assembly cavity (3), two moving blocks (4), screw (5), threaded sleeve (6), connecting seat (7), transmission block (8), two telescopic rods (9), plug-in block (10), snap-fit assembly, two connecting blocks (11), and two sliders (12). Assembly cavity (3) is opened inside the main body (2). Two sliders (12) are respectively installed at the bottom of two moving blocks (4). The two sliders (12) are slidably connected to the inner walls on both sides of the bottom of the assembly cavity (3). One end of the screw (5) passes through the bottom of the main body (2) and extends into the assembly cavity (3). The plug block (10) is installed on the top of the transmission block (8). The snap-fit components are respectively set on the top of the plug block (10) and the bottom of the inner wall of the top of the assembly cavity (3). One end of the two connecting blocks (11) passes through both sides of the main body (2) and is plugged into one side of the two moving blocks (4). The snap-fit assembly includes: a support base (13), two sliding frames (14), two first L-shaped blocks (15), a strip block (16), two spring rods (17), two second L-shaped blocks (18), and a first limiting hole (19); The support seat (13) is installed on the top inner wall of the assembly cavity (3). The inside of the support seat (13) is hollow. Two sliding frames (14) are slidably connected to the two sides of the support seat (13). Two first L-shaped blocks (15) pass through the support seat (13) and are connected to the two sliding frames (14). A strip block (16) is installed at the bottom of the support seat (13). Two spring rods (17) are respectively installed on the bottom sides of the support seat (13). One end of the two spring rods (17) is connected to the outside of the two first L-shaped blocks. Two second L-shaped blocks are respectively set on the top sides of the plug-in block (10). The first limiting hole (19) is opened at the top of the plug-in block (10). The construction method includes the following steps: Step S1: First, clean the inside of the joints of the shield tunnel segments to remove floating dust and other impurities. Step S2: Place the main body (2) inside the caulking joint and rotate the screw (5) so that the transmission block (8) pushes the two connecting blocks (11) out from both sides of the main body (2) and makes the outer side of the two connecting blocks (11) fit tightly against the inner wall of the caulking joint, and fixes the main body (2) inside the caulking joint. Step S3: Apply caulking sealant. After the sealant hardens, it forms a whole with the main body (2). By cooperating with the main body (2), the sealant strip (1) can be firmly fixed inside the caulking joint, preventing the sealant strip (1) from falling off.
2. The construction method for preventing the detachment of the sealing strip in the joints of shield tunnel segments according to claim 1, characterized in that, The screw (5) is threaded to the bottom of the main body (2), one end of the threaded sleeve (6) is threaded to one end of the screw (5), the connecting seat (7) is connected to the other end of the threaded sleeve (6), the transmission block (8) is installed on the top of the connecting seat (7), and both ends of the telescopic rod (9) are respectively connected to the bottom of the connecting seat (7) and the bottom inner wall of the assembly cavity (3).
3. The construction method for preventing the detachment of the sealing strip in the joints of shield tunnel segments according to claim 2, characterized in that, A rotating block (20) is installed at the other end of the screw (5). A groove is provided at one end of the screw (5) where it passes through the main body (2), and the groove matches the rotating block (20).
4. The construction method for preventing the detachment of the sealing strip in the joints of shield tunnel segments according to claim 3, characterized in that, The transmission block (8) is designed as an isosceles trapezoid, the moving block (4) is designed as a trapezoid, and the two sides of the transmission block (8) are in close contact with the inner side of the moving block (4).
5. The construction method for preventing the detachment of the sealing strip in the joints of shield tunnel segments according to claim 4, characterized in that, The moving block (4) has a limiting groove (21) on its inner side, and the transmission block (8) has limiting sliders (22) on both sides. The limiting groove (21) and the limiting sliders (22) are slidably connected.
6. The construction method for preventing the detachment of the sealing strip in the joints of shield tunnel segments according to claim 5, characterized in that, Two reset springs (23) are embedded on both sides of the limiting hole. One end of the reset spring (23) is connected to two horizontal blocks (24). A second limiting hole (25) is provided on the lower side of the strip block (16) corresponding to the horizontal block (24).
7. The construction method for preventing the detachment of the sealing strip in the joints of shield tunnel segments according to claim 6, characterized in that, The outer side of the connecting block (11) is inclined, and the inclination degree matches the inclination degree of the inner wall of the anti-shield tunnel segment caulking.
8. The construction method for preventing the detachment of the sealing strip in the joints of shield tunnel segments according to claim 7, characterized in that, A rough rubber layer (26) is provided on the outside of the connecting block (11).
9. A construction method for preventing the detachment of sealant strips used for sealing joints in shield tunnel segments according to claim 8, characterized in that, A reinforcing block (27) is provided between the spring rod (17) and the first L-shaped block (15).
Citation Information
Patent Citations
Connection structure of wooden furniture landing leg and crossbeam
CN208381071U
Disclosed are feeding farm room and auxiliary fixing device
CN212545039U