Method and device for quickly creating WBS based on project site division

By rapidly creating a Work Breakdown Structure (WBS) based on a BIM model that divides the project into parts, the problems of low creation efficiency and difficulty in modification in existing technologies are solved. This enables WBS management that can quickly adapt to the dynamic changes of construction projects and improves construction management efficiency.

CN118822140BActive Publication Date: 2026-11-24CHINA CONSTR THIRD ENG BUREAU GRP CO LTD +1
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202410751922.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-06-12
Publication Date
2026-11-24
Estimated Expiration
2044-06-12

AI Technical Summary

Technical Problem

The existing WBS is inefficient to create and difficult to modify, and cannot adapt to the dynamic changes of construction projects, resulting in low construction management efficiency.

Method used

By dividing the project into parts, a Work Breakdown Structure (WBS) can be quickly created using a BIM model. By combining the component classification codes with the WBS system's relationship table, a WBS data system can be automatically generated, supporting flexible adjustments to the project management structure.

Benefits of technology

It enables the rapid creation of WBS within half an hour, adapting to the dynamic changes of construction projects and improving the flexibility and efficiency of construction management.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118822140B_ABST
    Figure CN118822140B_ABST
Patent Text Reader

Abstract

This invention discloses a method and apparatus for rapidly creating a Work Breakdown Structure (WBS) based on project component division. The method includes: acquiring partial or complete BIM models in different formats, selecting the required BIM models for assembly to form a model group; dividing the model group into components according to preset component division rules; creating a WBS tree based on the component division results, and automatically generating a WBS data system and attaching it to the WBS tree by combining a pre-built association table of BIM model component classification codes and sub-item libraries. This invention solves the problems of low efficiency and difficulty in modification of existing WBS creation by flexibly configuring the basic project management structure through project component division and then creating the WBS based on the component division results.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of BIM technology, specifically relating to a method and apparatus for rapidly creating a Worksheet based on project location division. Background Technology

[0002] WBS (Work Breakdown Structure) stands for Work Task, Task Breakdown, and Structured Organization. It's a tool for breaking down complex projects into actionable steps. A WBS breaks down a project into tasks, then tasks into individual work items, and finally assigns these work items to each person's daily activities, until no further breakdown is possible. In other words: Project → Task → Work → Activity. The WBS is deliverable-oriented, grouping project elements to define the entire scope of the project. Each subsequent level represents a more detailed definition of the project's work.

[0003] The application of WBS in construction projects focuses on refined management and control, assisting in lean management of project production, and using digital means to assist in dynamic analysis of project progress. Therefore, the process of creating a WBS is very important in these scenarios. During the project decomposition process, the project manager, project members, and all functional managers involved in the project must consider all aspects of the project.

[0004] Existing WBSs rely on manual creation and decomposition, generally following these steps:

[0005] ① Define the scope of the project contract, including the tender list, contract, and construction drawings.

[0006] ②Establish a project team, determine the construction process, and, based on the milestone requirements, the project production department determines the project output and key personnel / materials / machinery according to the project schedule and milestone targets in the "Project Planning Document," and determines the work breakdown method.

[0007] ③ Decompose project work, usually in spreadsheets or planning software such as Excel or Project. If there are ready-made work breakdown templates, you should make the most of them, as this part involves a lot of work.

[0008] ④ Draw a hierarchical structure diagram of the WBS based on the division, sub-division, and itemized projects.

[0009] ⑤ Break down major project deliverables into smaller, manageable components or processes. Processes must be detailed enough to allow for estimation (cost and duration), scheduling, budgeting, and assignment of responsibilities to personnel or organizational units for that work package.

[0010] ⑤ Verify the correctness of the above decomposition. If lower-level items are found to be unnecessary, modify the constituent components.

[0011] ⑥ As other planned activities proceed, the WBS is continuously updated or revised until it covers all work.

[0012] All of the above tasks require detailed breakdown of the Work Breakdown Structure (WBS) down to the process level. However, the plans, drawings, and scope of construction projects are subject to dynamic changes, and construction management is also dynamic. It cannot be executed according to the established WBS in a static manner. When changes occur in the plan, construction scheme, or drawings, the original WBS needs to be recreated. After applying BIM technology, the model and its connections need to be re-executed. Maintaining the WBS is time-consuming and labor-intensive in practical applications, often resulting in the work breakdown structure being shelved after the planning is completed. Summary of the Invention

[0013] To overcome the shortcomings of the existing technology, the present invention provides a method and apparatus for rapidly creating a Work Breakdown Structure (WBS) based on project part division. By flexibly configuring the basic project management structure through project part division, and then creating the WBS based on the part division results, the present invention solves the problems of low efficiency and difficulty in modification of existing WBS creation.

[0014] According to one aspect of the present invention, a method for rapidly creating a Work Breakdown Structure (WBS) based on project location division is provided, comprising:

[0015] Acquire partial or complete BIM models in different formats, and select the required BIM models to combine and assemble them to form a model group;

[0016] Based on the preset part division rules, the model group is divided into parts;

[0017] Based on the part division results, a WBS tree is created, and combined with the pre-built BIM model component classification code and sub-item library association table, a WBS data system is automatically generated and attached to the WBS tree.

[0018] As a further technical solution, the pre-construction of the association table between BIM model component classification coding and WBS system includes:

[0019] Obtain the BIM model and classify and encode all components under the BIM model;

[0020] Establish a table relating component classification codes to the various WBS partitioning systems within the sub-item library.

[0021] As a further technical solution, the sub-item library is established based on sub-item logic and is used to store the WBS division system of various construction projects.

[0022] As a further technical solution, the method also includes:

[0023] Create sub-items at the last-level node of the part partitioning structure tree;

[0024] The system searches the sub-item library for the WBS partitioning system corresponding to the created sub-item and automatically generates the WBS tree for that sub-item.

[0025] As a further technical solution, the method also includes: combining the association table of BIM model component classification codes and sub-item libraries, using a fuzzy matching algorithm to link the model data with the WBS tree, forming a data integration model and publishing it to various business systems.

[0026] As a further technical solution, the method also includes: acquiring business data from various business systems and transmitting it back to the WBS tree to form a data core.

[0027] As a further technical solution, after acquiring partial or complete BIM models in different formats, it also includes: parsing and storing the classification codes in the BIM model based on a lightweight engine.

[0028] As a further technical solution, the method also includes: adjusting the parent set and subset of the created WBS tree according to the construction site management requirements.

[0029] As a further technical solution, the preset part division rules include division rules for individual buildings, floors, construction stages, and flow sections.

[0030] According to one aspect of the present invention, an apparatus for rapidly creating a Worksheet based on project location division is provided, comprising:

[0031] The upload and assembly module is used to acquire partial or complete BIM models in different formats, and select the required BIM models to combine and assemble them to form a model group.

[0032] The part division module is used to divide the model group into parts according to preset part division rules;

[0033] The WBS creation module is used to create a WBS tree based on the part division results, and automatically generate a WBS data system and attach it to the WBS tree by combining the pre-built BIM model component classification code and sub-item library association table.

[0034] Compared with the prior art, the beneficial effects of the present invention are as follows:

[0035] This invention creates a Work Breakdown Structure (WBS) based on the results of part division, which supports project task allocation based on actual management dimensions. It is flexible and fast, and the basic project management structure can be flexibly configured through part division. Combined with the mapping relationship between the model and the WBS system, it can be created quickly. Compared with the traditional mode, which often takes several days to complete, the method described in this invention can be completed in half an hour. Attached Figure Description

[0036] Figure 1 This is a schematic diagram of a method for quickly creating a Worksheet based on project location division according to an embodiment of the present invention. Detailed Implementation

[0037] Most existing Work Breakdown Structures (WBS) are created based on tables, which is not only inefficient to create but also difficult to modify. Once a WBS is modified, the management of downstream projects based on it is greatly affected. To address this, this invention provides a method for rapidly creating WBSs. This method is based on the part division results and combines the mapping relationship between components and the WBS system for rapid creation. It can adapt to different project management needs and is easy to modify.

[0038] It should be noted that:

[0039] Location segmentation refers to the division of construction processes into flow segments to make full use of time and space resources, resulting in a tree-structured location segmentation. For example, a construction project department manages project work according to the segmentation dimensions of "project-specialty-zone-building-floor-flow segment", forming a tree structure for this location segmentation.

[0040] Different construction projects require different methods of dividing parts. This invention supports part division in various situations, solving different part division scenarios for users, such as dividing parts according to different categories like single building, floor, construction stage, and construction sequence.

[0041] In some of the processes described in the specification, claims, and accompanying drawings of this invention, multiple operations are included in a specific order. However, it should be clearly understood that these operations may not be performed in the order they appear herein, or may be performed in parallel. For example, steps 1, 2, etc., are merely used to distinguish different operations, and the sequence numbers themselves do not represent any execution order. Furthermore, these processes may include more or fewer operations, and these operations may be performed sequentially or in parallel.

[0042] The technical solutions of various embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0043] Example 1

[0044] This embodiment provides a method for quickly creating a Work Breakdown Structure (WBS) based on project location division, which enables rapid creation of the WBS and facilitates modification.

[0045] like Figure 1 As shown, the method includes:

[0046] Step 1: Obtain partial or complete BIM models in different formats, and select the required BIM models to combine and assemble them to form a model group.

[0047] Before step 1, the following steps are also included: user login and management. A user management module is used, where users register themselves or are invited by relevant parties involved in the model exchange to manage user permissions, ensuring that each relevant party participating in the collaborative meeting has the corresponding permissions; after logging in, users can select BIM files that have been uploaded by the user or upload new BIM files.

[0048] After uploading the BIM file, the process also includes BIM model data management.

[0049] Specifically, after the model data is uploaded, the BIM cloud rendering platform converts the model data, temporarily stores it, and manages access permissions. Within the cloud rendering platform, users can view model descriptions, delete models, and download model data according to their permissions. In other words, after the model data is uploaded, a lightweight engine converts the original model data format into a lightweight data format, while simultaneously reading all the attribute information carried by the model and storing it in a structured format.

[0050] After uploading the model and reading all the attribute information carried by the model, the process also includes: reading and storing the classification code of each component in the model, so as to realize the mapping from the model to the WBS system based on the component classification code.

[0051] After BIM model conversion, the system also includes: assembly management of multiple model types, merging different models into model groups, and viewing and managing these model groups.

[0052] Furthermore, BIM models in various formats (such as IFC, RVT, GTJ, P3D, etc.) that were originally not allowed to be freely combined and assembled within the same software can now be assembled and viewed as a whole within this platform after parsing and lightweighting. They can also be freely packaged into multiple assembly model groups for storage, which can be used for combining and viewing models of different disciplines and formats, and for the assembly verification of single-discipline models, among other practical applications.

[0053] It should be noted that the uploaded BIM model can be a complete model, or a partial BIM model of a floor or a basement. Using a smaller, more granular BIM model facilitates model assembly. During assembly, you can select the necessary models based on your professional needs. For example, when assembling a civil engineering model, only select the civil engineering-related BIM model, without assembling models from other disciplines. Alternatively, you can select the necessary models based on the actual project requirements. For instance, when assembling a first-floor model, only select the first-floor-related BIM model, without assembling models from other floors.

[0054] Step 2: Divide the model group into parts according to the preset part division rules.

[0055] After the model is assembled, the following steps can be taken based on the actual needs of the project for part division: obtain the project management structure, and select the appropriate part division method according to different project management routes and management requirements.

[0056] The preset location division rules include rules for dividing individual buildings, floors, construction stages, and construction sequence sections. Here, construction stages can be understood as construction specialties, such as civil engineering, mechanical and electrical engineering, and other construction specialties.

[0057] Specifically, the project's division of areas is set according to management needs. For example, Project A divides the project into four zones (A / B / C / D) based on size, assigning zone leaders. Within each zone, construction is further divided into specialties such as civil engineering, mechanical and electrical engineering, and interior decoration. Each specialty is then managed and documented according to floor levels (1st, 2nd, 3rd, etc.). Project B, on the other hand, manages construction according to specialty, building, floor, and construction sequence. Different types, sizes, or regions of construction projects have different needs for area division and management. Generally, the division is set according to requirements. The "appropriate" area division method depends on the actual needs of the project, and this example allows for flexible configuration.

[0058] The result of the part division can be regarded as a tree structure of part division. After obtaining the tree structure, it also includes: using the BIM data engine to associate and link the structured model data and the business data used in production, and storing the associated data.

[0059] Association rules, also known as mapping rules, include mapping rules between tree-structured data and mapping rules between tree-structured data and ordinary data.

[0060] The mapping rules are used to perform fuzzy matching on structured data and structured component division data such as individual building floor flow section information in the model. For example, the model-parsed "building or building number" can be matched with the component division "individual building", and the model-parsed data such as elevation and floor can be matched with the component division "floor", etc. It should be noted that a construction project includes multiple individual buildings, and each individual building is further divided into floors, components, and items to be completed.

[0061] It should be noted that fuzzy matching can be implemented using existing fuzzy matching algorithms, which will not be elaborated upon in this embodiment.

[0062] The association rules in this embodiment have simple requirements for modelers; the model file only needs to have its file name, professional name, and other data entered correctly.

[0063] Step 3: Create a WBS tree based on the part division results, and automatically generate a WBS data system and attach it to the WBS tree by combining the pre-built BIM model component classification code and sub-item library association table.

[0064] The pre-construction of the correlation table between BIM model component classification codes and WBS system includes: obtaining the BIM model and classifying and coding all components under the BIM model; and establishing a correlation table between component classification codes and each WBS division system in the sub-item library.

[0065] Furthermore, the sub-item library is established based on sub-item logic and is used to store the WBS (Work Breakdown Structure) classification system for various construction projects. The WBS classification system for various construction projects can be obtained statistically based on the company's construction experience.

[0066] Optionally, the method further includes:

[0067] Create sub-items at the last-level node of the part partitioning structure tree;

[0068] The system searches for the WBS partitioning system corresponding to the created sub-item in the sub-item library and automatically generates the WBS tree for that sub-item.

[0069] By combining the BIM model component classification codes with the association table of sub-item libraries, a fuzzy matching algorithm is used to link the model data with the WBS tree, forming a data integration model, which is then published to various business systems of the DDE platform.

[0070] The system acquires business data from various business systems and uploads it back to the WBS structure tree to form the data core. These business systems include systems such as process databases, efficiency databases, and planning and scheduling systems.

[0071] In one implementation, the method further includes: adjusting the parent and subset sets of the created WBS tree according to the construction site management requirements. A sub-item hierarchy conversion function is provided here, which can quickly and in batches adjust the WBS hierarchy to suit the application standards of the construction project.

[0072] This embodiment summarizes various construction project WBS partitioning methods, establishes rapid attachment algorithm rules, provides default configuration rules for construction units, establishes a matching method between rules and models through a data engine, quickly establishes the association between the master data of sub-item engineering parts, so that it conforms to the partitioning standards of most construction projects, and provides a sub-item level conversion function, which can quickly adjust the WBS level in batches and make it suitable for the application standards of construction projects.

[0073] Example 2

[0074] Based on the same inventive concept as Embodiment 1, this embodiment provides an apparatus for rapidly creating a Worksheet based on project location division, comprising:

[0075] The upload and assembly module is used to acquire partial or complete BIM models in different formats, and select the required BIM models to combine and assemble them to form a model group.

[0076] The part division module is used to divide the model group into parts according to preset part division rules;

[0077] The WBS creation module is used to create a WBS tree based on the part division results, and automatically generate a WBS data system and attach it to the WBS tree by combining the pre-built BIM model component classification code and sub-item library association table.

[0078] The above modules can be implemented in accordance with the method embodiments, and will not be elaborated here. It should be noted that:

[0079] The system also includes a pre-built module for executing the following instructions: acquiring the BIM model and classifying and coding all components under the BIM model; and establishing a correlation table between the component classification codes and the WBS partitioning systems in the sub-item library.

[0080] The WBS creation module is also used to execute the following instructions:

[0081] Create sub-items at the last-level node of the part partitioning structure tree;

[0082] The system searches for the WBS partitioning system corresponding to the created sub-item in the sub-item library and automatically generates the WBS tree for that sub-item.

[0083] By combining the BIM model component classification codes with the association table of sub-item libraries, a fuzzy matching algorithm is used to link the model data with the WBS tree, forming a data integration model, which is then published to various business systems of the DDE platform.

[0084] It should be noted that the solution provided by this device is similar to the solution described in the above method. Therefore, the specific limitations of the implementation of each module can be found in the limitations of the method for quickly creating WBS based on project part division described above, and will not be repeated here.

[0085] In summary, the present invention achieves the following technical effects through the above embodiments:

[0086] This invention provides a method for rapidly creating a Work Breakdown Structure (WBS), combined with automatically generated part divisions from a BIM model. This allows users to quickly get started with BIM model management tools, enabling the BIM model to be rapidly linked to production data, quickly forming a BIM-data integration model, and establishing a BIM application platform for construction projects. Compared to past BIM application methods, it is easier to adapt to various changes such as drawings, schedules, and plans, improving the originally cumbersome process of BIM technology application. This is conducive to the promotion of BIM technology in building construction projects, and makes this tool a favorable condition for the application of BIM throughout the entire life cycle of building projects.

[0087] Those skilled in the art will understand that embodiments of the present invention can be provided as methods, systems, or computer program products. Therefore, the present invention can take the form of a completely hardware embodiment, a completely software embodiment, or an embodiment combining software and hardware aspects. Furthermore, the present invention can take the form of a computer program product embodied on one or more computer-usable storage media (including, but not limited to, disk storage, CD-ROM, optical storage, etc.) containing computer-usable program code.

[0088] This invention is described with reference to flowchart illustrations and / or block diagrams of methods, apparatus (systems), and computer program products according to embodiments of the invention. It will be understood that each block of the flowchart illustrations and / or block diagrams, and combinations of blocks in the flowchart illustrations and / or block diagrams, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, special-purpose computer, embedded processor, or other programmable data processing apparatus to produce a machine, such that the instructions, which execute via the processor of the computer or other programmable data processing apparatus, generate instructions for implementing the flowchart illustrations and / or block diagrams. Figure 1 One or more processes and / or boxes Figure 1 A device that provides the functions specified in one or more boxes.

[0089] These computer program instructions may also be stored in a computer-readable storage medium that can direct a computer or other programmable data processing device to function in a particular manner, such that the instructions stored in the computer-readable storage medium produce an article of manufacture including instruction means, which are implemented in a process Figure 1 One or more processes and / or boxes Figure 1 The function specified in one or more boxes.

[0090] These computer program instructions may also be loaded onto a computer or other programmable data processing equipment to cause a series of operational steps to be performed on the computer or other programmable equipment to produce a computer-implemented process, thereby providing instructions that execute on the computer or other programmable equipment for implementing the process. Figure 1 One or more processes and / or boxes Figure 1 The steps of the function specified in one or more boxes.

[0091] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, and not to limit them; although the present invention has been described in detail with reference to the foregoing embodiments, those skilled in the art should understand that modifications can still be made to the technical solutions described in the foregoing embodiments, or equivalent substitutions can be made to some or all of the technical features therein; and these modifications or substitutions do not cause the essence of the corresponding technical solutions to deviate from the technical solutions of the embodiments of the present invention.

Claims

1. A method for rapidly creating a Work Breakdown Structure (WBS) based on project location division, characterized in that: include: Acquire partial or complete BIM models in different formats, and select the required BIM models to combine and assemble them to form a model group; The model is divided into sections based on the needs of construction site management; the section division includes the division of individual buildings, floors, construction stages, and flow sections. Based on the part division results, a WBS tree is created, and combined with the pre-built BIM model component classification code and sub-item library association table, a WBS data system is automatically generated and attached to the WBS tree; The pre-construction of the association table between the BIM model component classification codes and the WBS system includes: acquiring the BIM model and classifying and coding all components under the BIM model; establishing an association table between the component classification codes and the WBS division systems in the sub-item library; wherein, the sub-item library is established according to the sub-item logic and is used to store the WBS division systems of various construction projects. The method further includes: Create sub-items at the last-level node of the part partitioning structure tree; The system searches for the WBS partitioning system corresponding to the created sub-item in the sub-item library and automatically generates the WBS tree for that sub-item. By combining the BIM model component classification codes with the association table of sub-item libraries, a fuzzy matching algorithm is used to link the model data with the WBS tree, forming a data integration model, which is then published to various business systems.

2. The method for rapidly creating a Worksheet based on project location division according to claim 1, characterized in that, The method also includes: acquiring business data from each business system and transmitting it back to the WBS tree to form a data core.

3. The method for rapidly creating a Worksheet based on project location division according to claim 1, characterized in that, After acquiring partial or complete BIM models in different formats, the process also includes parsing and storing the classification codes in the BIM model based on a lightweight engine.

4. The method for rapidly creating a Worksheet based on project location division according to claim 1, characterized in that, The method also includes: adjusting the parent set and subset of the created WBS tree according to the construction site management needs.

5. An apparatus for rapidly creating a Worksheet based on project location division, used to implement the method described in any one of claims 1-4, characterized in that, include: The upload and assembly module is used to acquire partial or complete BIM models in different formats, and select the required BIM models to combine and assemble them to form a model group. The part division module is used to divide the model group into parts according to preset part division rules; The WBS creation module is used to create a WBS tree based on the part division results, and automatically generate a WBS data system and attach it to the WBS tree by combining the pre-built BIM model component classification code and sub-item library association table.

Citation Information

Patent Citations

  • A highway engineering project management system and method based on combination of BIM and WBS

    CN109409840A

  • Construction planning method based on building information model

    CN113449360A

  • BIM and business system association method and system based on fuzzy matching

    CN115712842A

  • Project management system and method based on BIM + WBS and readable storage medium

    CN116934243A