High-strength stainless steel stranded wire net-ECC local enhanced grouting sleeve connection prefabricated column-foundation joint and construction method

By using local reinforcement technology of high-strength stainless steel strand mesh and ECC materials in the column foundation nodes of prefabricated concrete structures, combined with grouting sleeve connection method, the problems of poor ductility, low tensile strength and durability of prefabricated concrete structures are solved. , improves seismic resistance and durability, and is suitable for building structures in high load and earthquake-prone areas.

CN118933190APending Publication Date: 2024-11-12ZHENGZHOU UNIV
View PDF 0 Cites 4 Cited by

Patent Information

Application Number
CN202411221542.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-02
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

The application of prefabricated concrete structures in high intensity zones is limited by the problems of poor ductility, low tensile strength, poor durability and insufficient seismic performance, especially at node connections, cracks and durability problems are prone to occur.

Method used

The local reinforcement technology of high-strength stainless steel strand mesh and ECC material is adopted. By setting up high-strength stainless steel strand mesh and ECC segments in the prefabricated column foundation nodes, combined with the grouting sleeve connection method, the tensile resistance and durability of the node are improved.

Benefits of technology

It significantly improves the seismic resistance and durability of the prefabricated column foundation nodes, solves the problem of insufficient performance at the node connections, and is suitable for high-load environments and earthquake-prone areas, and is simple and efficient in construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933190A_ABST
    Figure CN118933190A_ABST
Patent Text Reader

Abstract

The invention discloses a high-strength stainless steel stranded wire net-ECC local enhanced grouting sleeve connection prefabricated column-foundation joint and a construction method, and belongs to the technical field of building structure engineering. The prefabricated column-foundation joint comprises a prefabricated column and a prefabricated foundation which are vertically connected, the prefabricated column and the prefabricated foundation are connected through a grouting sleeve, the prefabricated column is divided into a prefabricated concrete section and a prefabricated ECC section, and the prefabricated ECC section is formed by pouring ECC at the lower bottom of a steel reinforcement framework in the prefabricated column; a high-strength stainless steel stranded wire net is further arranged between the outer wall of the prefabricated ECC section and the steel reinforcement framework, one end of the high-strength stainless steel stranded wire net is anchored in the ECC at the column bottom of the prefabricated ECC section, and the other end of the high-strength stainless steel stranded wire net extends and is anchored in common concrete of the prefabricated concrete section. The prefabricated ECC sections are formed by replacing common concrete with ECC, the bearing capacity and durability of the node in the early stage are improved, meanwhile, the tensile capacity of the joint of the column foundation node is improved through the high-strength stainless steel stranded wires, and the shock resistance of the node is greatly improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to a prefabricated column-foundation node for assembled buildings and bridges, and in particular to a high-strength stainless steel stranded wire mesh-ECC locally reinforced grouting sleeve connected prefabricated column-foundation node and a construction method, belonging to the technical field of building structure engineering. Background Art

[0002] Prefabricated frame nodes have the following advantages: high production efficiency, short construction period, good product quality, low environmental impact and low labor consumption. In prefabricated concrete frame structures, the connection between columns, beams and floor slabs, especially the connection between column foundation nodes and other load-bearing components, is the key core part that affects the overall performance and seismic performance of the structure.

[0003] However, due to the characteristics of concrete materials, concrete structures generally have the following problems: 1) poor ductility, which is not conducive to structural earthquake resistance; 2) low tensile strength and easy to crack; 3) poor durability and easy corrosion of steel bars. Due to the existence of joints in prefabricated components, their integrity, durability and seismic performance are even worse than those of integral cast-in-place components. Under the action of earthquake loads, the concrete in the plastic hinge area of ​​the columns in the building structure peels off and crushes, the residual displacement of the structure is too large, and post-earthquake repair is extremely difficult. These problems have, to a certain extent, limited and restricted the promotion and application of prefabricated concrete structures in complex and harsh engineering environments such as medium and high intensity.

[0004] In order to promote the application and development of prefabricated concrete structures in high-intensity areas, my country has explored prefabricated pier-column nodes with different connection forms in recent years. High-strength stainless steel stranded wire mesh and ECC materials have been widely used to enhance the seismic performance of concrete structures. Existing literature shows that by introducing high-strength stainless steel stranded wire mesh into concrete structures, the tensile strength and ductility of the structure can be significantly improved. Although these technologies have achieved certain results, there are still some problems in practical applications. For example, ECC materials are prone to stress concentration at the junction with traditional concrete, which may lead to local failure; in addition, existing node reinforcement technologies are mostly focused on the overall reinforcement of components, but fail to effectively solve the local seismic performance and durability problems of the nodes.

[0005] Therefore, there is an urgent need for a local reinforcement technology that can effectively integrate the advantages of high-strength stainless steel stranded wire mesh and ECC materials to further improve the seismic performance and durability of assembled integral column foundation nodes. Summary of the invention

[0006] The purpose of the present invention is to solve the problems of poor ductility, easy cracking, poor durability and insufficient seismic performance of existing prefabricated concrete structural components, and to provide a high-strength stainless steel stranded wire mesh-ECC locally reinforced grouting sleeve connected prefabricated column-foundation node and construction method. ECC is used to replace ordinary concrete to form a prefabricated ECC segment, which improves the early bearing capacity and durability of the node. At the same time, by arranging high-strength stainless steel strands at the joint and pouring them at the same time, the tensile capacity of the column foundation node connection is increased, which greatly improves the seismic resistance of the node.

[0007] To achieve the above-mentioned purpose, the present invention adopts the following technical scheme: a high-strength stainless steel stranded wire mesh-ECC partially reinforced grouting sleeve connected prefabricated column-foundation node, including a vertically connected prefabricated column and a prefabricated foundation, the prefabricated column and the prefabricated foundation are connected by a grouting sleeve, wherein the prefabricated column is divided into a prefabricated concrete segment and a prefabricated ECC segment, the prefabricated concrete segment is composed of ordinary concrete poured on the upper part of the steel skeleton in the prefabricated column, and the prefabricated ECC segment is composed of ECC poured on the bottom of the steel skeleton in the prefabricated column; The steel skeleton is composed of a plurality of uniformly distributed precast column longitudinal bars and precast column double-leg stirrups vertically tied and connected to form a cage-shaped frame, wherein the bottom end of the precast column longitudinal bar is fixedly connected to the top of the grouting sleeve, and the upper end extends to the top end surface of the precast column; A high-strength stainless steel stranded wire mesh is also arranged between the outer wall of the prefabricated ECC segment and the steel skeleton, one end of the high-strength stainless steel stranded wire mesh is anchored in the ECC at the bottom of the column of the prefabricated ECC segment, and the other end extends and anchored in the ordinary concrete of the prefabricated concrete segment.

[0008] Furthermore, the prefabricated ECC segment is a semi-cast ECC sandwich column structure or a fully cast ECC full-section column structure, wherein the semi-cast ECC sandwich column structure consists of an ECC outer shell and a concrete cast inner core, and the height of the concrete cast inner core is lower than the height of the prefabricated ECC segment.

[0009] Furthermore, the column section of the prefabricated column in the semi-cast ECC sandwich column structure is 400-800 mm, and the thickness of the ECC shell is not less than 80 mm and not greater than 1 / 4 of the width of the column section.

[0010] Furthermore, the high-strength stainless steel strand mesh is composed of a plurality of evenly distributed transverse steel strands and vertical steel strands that are vertically tied and connected to each other. The transverse steel strands are arranged between the double-legged stirrups of the precast column, and the transverse steel strands are closed loops, and their two ends are overlapped and anchored by aluminum buckles; the upper ends of the longitudinal steel strands are anchored in the ordinary concrete of the precast concrete segment by aluminum buckles and ties, and the lower ends are anchored to the double-legged stirrups of the precast column by aluminum buckles and ties.

[0011] Furthermore, the diameter of the steel strands in the high-strength stainless steel stranded wire mesh is 3.6 mm to 6 mm, the spacing between the steel strands is 60 to 100 mm, and the anchoring length of the longitudinal steel strands is 20 times the diameter of the steel strands and is not less than 100 mm.

[0012] Furthermore, the spacing between the upper and lower ends of the prefabricated column is increased by using double-legged stirrups of the prefabricated column.

[0013] Furthermore, the inner diameter of the grouting sleeve is not less than 1.5 times the diameter of the transversely extended steel bar, and its length is 2 to 4 times the diameter of the longitudinally extended steel bar; and the lower part of the grouting sleeve is provided with a first prefabricated column double-legged stirrup and is 30 mm away from the bottom of the sleeve, and the lower end of the connection between the top of the grouting sleeve and the prefabricated column longitudinal reinforcement is also provided with a prefabricated column double-legged stirrup.

[0014] Furthermore, a joint is provided between the prefabricated column and the prefabricated foundation, and the joint is a high-strength non-shrinkage mortar layer with a thickness of 20 to 30 mm.

[0015] The present invention also discloses a construction method for connecting a prefabricated column-foundation node with a high-strength stainless steel stranded wire mesh-ECC locally reinforced grouting sleeve, comprising the following steps: S1. Before pouring the precast columns, arrange the steel skeleton and high-strength stainless steel stranded wire mesh: Tie up the steel skeleton and connect the grouting sleeve at the bottom, arrange high-strength stainless steel stranded wire mesh within 100~150mm below the precast ECC segment and the precast concrete segment outside the steel skeleton, one end of the high-strength stainless steel stranded wire mesh is anchored to the double-legged stirrups of the precast column at the bottom of the precast ECC segment, and the other end is extended and anchored to the double-legged stirrups of the precast column of the precast concrete segment; S2. Casting of precast concrete segments on the upper part of precast columns: After the steel skeleton and the high-strength stainless steel stranded wire mesh are tied and connected in the above step S1, a template is set outside the precast concrete segment, and a temporary baffle is set at the casting interface of the precast concrete segment and the precast ECC segment, and then ordinary concrete is used to cast the precast concrete segment; S3. Casting of precast ECC segments at the bottom of precast columns: The precast ECC segment is divided into a semi-cast ECC sandwich column structure and a fully cast ECC full-section column structure; the casting process of the semi-cast ECC sandwich column structure includes: removing the temporary baffle before the initial setting of the ordinary concrete of the precast concrete segment in the above step S2, fixing the inflatable core mold at the middle position of the precast ECC segment, casting the ECC to the top of the inflatable core mold, completing the casting of three sides of the ECC shell, taking out the inflatable core mold before the initial setting of the ECC and immediately casting ordinary concrete to the top surface of the ECC, completing the casting of the concrete casting inner core, and immediately casting the ECC to the interface with the precast concrete segment after the casting of the concrete casting inner core is completed; The casting process of the fully cast ECC full-section column structure includes: removing the temporary baffle before the initial setting of the ordinary concrete of the precast concrete segment in the above step S2, casting the ECC to the interface with the precast concrete segment, and completing the casting of the precast ECC segment; S4. Pre-treatment of prefabricated column assembly construction: First, clean the sides of the prefabricated column. When making the prefabricated column, roughen the bottom surface of the column and clean it to expose the coarse concrete aggregate at the bottom of the column. The roughness of the bottom surface of the column is not less than 4mm as measured by the sand pile method. S5. Carry out the hoisting construction of prefabricated columns: The prefabricated column and the prefabricated foundation are connected by a grouting sleeve. The gap between the prefabricated column and the prefabricated foundation is less than 20mm. The prefabricated column is slowly lifted up so that the gap between the prefabricated column and the prefabricated foundation is 150mm~250mm, leaving space for the construction of the seat grouting layer; S6. Construction of the mortar layer at the bottom of the prefabricated column: Use square wood strips with a height of 40~60mm as templates to make the templates for the base mortar layer at the bottom of the prefabricated column, and then fix them on the prefabricated foundation; mix the base mortar with water as required and pour it into the template with a thickness of 20~30mm, and then use a crane to slowly drop the prefabricated column from top to bottom, so that the distance between the prefabricated column and the prefabricated foundation is 20~30mm. The base mortar is densely filled between the two prefabricated components. The base mortar is an early-strength mortar. When the strength meets the self-weight requirements of the prefabricated column, the crane will be removed; S7. Inject grouting material into the grouting sleeve: After the compressive strength of the mortar of the base layer meets the requirements, the pre-mixed grouting material is poured into the corrugated pipe through a manual grouting pump. The grouting material is made by high-speed stirring with an electric stirrer for 5 minutes to obtain good fluidity, and the grouting of the stirred grouting material is completed once within 1 hour. The grouting operation is stopped after the grouting material overflows from the upper grouting hole of the grouting sleeve. After the grouting is completed, the hose connected to the lower grouting hole of the grouting sleeve is closed, while the hose connected to the upper grouting hole remains open until the grouting material solidifies and hardens.

[0016] The beneficial effects of the present invention are: 1) The node structure of the present invention can effectively solve the problems of poor ductility, easy cracking, poor durability, and insufficient seismic performance of prefabricated concrete structures and ordinary concrete pier and column components, and is suitable for prefabricated piers in frame and bridge structures or prefabricated columns in building structures; ECC is used to replace ordinary concrete to form prefabricated ECC segments, which improves the early bearing capacity and durability of the node. At the same time, by arranging high-strength stainless steel strands at the joints and pouring them at the same time, the tensile strength of the column foundation node connection is increased, which greatly improves the seismic resistance of the node.

[0017] 2) The node of the present invention adopts a structure combining high-strength stainless steel stranded wire mesh and ECC, which can solve the shortcomings of poor performance and easy cracking of the assembled integral column-foundation node at the splicing part of the prefabricated components, improve the early stiffness and stress performance of the assembled integral column foundation node, and at the same time, it is convenient to construct, simple in structure, good in crack resistance and high in economic benefits.

[0018] 3) The ECC in the present invention can be used only in key parts of the structure, while the design of using ordinary concrete in other parts has good economic benefits and is conducive to the promotion and large-scale application of this composite structure.

[0019] 4) The node structure of the present invention has high bearing capacity: the bearing capacity of the node is improved by the combination of the grouting sleeve and the high-strength stainless steel stranded wire mesh, and it is suitable for high-load environments; excellent seismic performance: the use of ECC materials significantly enhances the seismic performance of the node, and it is suitable for earthquake-prone areas; durability: the combination of ECC materials and high-strength grouting materials improves the durability of the node and reduces maintenance costs; convenient construction: the combined connection method of the grouting sleeve and the high-strength stainless steel stranded wire mesh is adopted, and the construction process is simple and efficient, which meets the requirements of rapid construction of prefabricated buildings. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 This is a schematic diagram of a node structure of Embodiment 1 of the present invention; Figure 2 This is a schematic diagram of a node structure of Embodiment 2 of the present invention; Figure 3 for Figure 1 Layout diagram of medium and high strength stainless steel stranded wire mesh; Figure 4 for Figure 1 Sectional view at AA in the middle; Figure 5 for Figure 1 Sectional view at the middle BB; Figure 6 for Figure 1 Sectional view at CC; Figure 7 for Figure 1 Sectional view at DD in the middle; Figure 8 It is a casting flow chart of the node structure of the present invention; Fig. 9 for Figure 8 Arrangement diagram of the steel bar skeleton, high-strength stainless steel stranded wire mesh, temporary baffles and inflatable mandrel; Fig.10 for Figure 8 Schematic diagram of the three-dimensional structure of the middle inflatable core mold; Fig.11 for Figure 8 Front view of the temporary baffle.

[0021] In the figure, 1-precast column, 2-precast foundation, 3-ECC, 4-ordinary concrete, 5-precast column longitudinal reinforcement, 6-precast column double-leg stirrups, 7-grouting sleeve, 8-high-strength stainless steel stranded wire mesh, 9-aluminum buckle, 10-inflatable core mold, 11-temporary baffle. DETAILED DESCRIPTION

[0022] The present invention is further explained below in conjunction with the accompanying drawings and specific embodiments.

[0023] Example 1: Figure 1 As shown, the present invention provides a high-strength stainless steel stranded wire mesh-ECC locally reinforced grouting sleeve connected prefabricated column-foundation node, including a vertically connected prefabricated column 1 and a prefabricated foundation 2, the prefabricated column 1 and the prefabricated foundation 2 are connected by a grouting sleeve 7, wherein the prefabricated column 1 is divided into a prefabricated concrete segment and a prefabricated ECC segment, the prefabricated concrete segment is composed of ordinary concrete 4 poured on the upper part of the steel skeleton in the prefabricated column 1, and the prefabricated ECC segment is composed of ECC 3 poured on the bottom of the steel skeleton in the prefabricated column 1.

[0024] The steel skeleton is composed of a plurality of evenly distributed precast column longitudinal bars 5 and precast column double-leg stirrups 6 which are vertically tied together to form a cage-shaped frame, wherein the bottom end of the precast column longitudinal bar 5 is fixedly connected to the top of the grouting sleeve 7, and the upper end extends to the top end face of the precast column 1.

[0025] like Figure 3 As shown, a high-strength stainless steel stranded wire mesh 8 is arranged between the outer wall of the precast ECC segment and the steel skeleton, one end of the high-strength stainless steel stranded wire mesh 8 is anchored in the ECC 3 at the bottom of the column of the precast ECC segment, and the other end extends and is anchored in the ordinary concrete 4 of the precast concrete segment.

[0026] The high-strength stainless steel strand mesh 8 is composed of a plurality of evenly distributed transverse steel strands and vertical steel strands that are vertically tied and connected to each other. The transverse steel strands are arranged between the double-legged stirrups 6 of the precast column, and the transverse steel strands are closed loops, and their two ends are overlapped and anchored by aluminum buckles 9; the upper ends of the longitudinal steel strands are anchored in the ordinary concrete 4 of the precast concrete segment by aluminum buckles 9 and tying wires, and the lower ends are anchored to the double-legged stirrups 6 of the precast column by aluminum buckles 9 and tying wires.

[0027] The diameter of the steel strands in the high-strength stainless steel strand mesh 8 is 3.6mm~6mm, the spacing between the steel strands is 60~100mm, and the anchoring length of the longitudinal steel strands is 20 times the diameter of the steel strands and is not less than 100mm.

[0028] like Figure 1 and 3 As shown, according to the economic cost, the prefabricated ECC segment selects a semi-cast ECC sandwich column structure, which consists of an ECC shell and a concrete cast inner core, and the height of the concrete cast inner core is lower than the height of the prefabricated ECC segment.

[0029] The column section of the precast column 1 in the semi-cast ECC sandwich column structure is 400~800mm, and the thickness of the ECC shell is not less than 80mm and not more than 1 / 4 of the column section width; if the cross-sectional size is too small, it is not practical and difficult to manufacture; if the cross-sectional size is too large, the use of the ECC shell has limited effect on improving the node performance.

[0030] The grouting sleeve 7 of the prefabricated column is arranged at the bottom of the column. The size of the grouting sleeve 7 is determined according to the diameter of the steel bars inserted into the prefabricated column 1 and the prefabricated foundation 2. The inner diameter of the grouting sleeve should be at least 1.5 times the diameter of the connected longitudinal steel bars to ensure that the steel bars can be inserted smoothly and leave enough grouting space, thereby ensuring the full filling and density of the grouting material, that is, the inner diameter of the grouting sleeve 7 is not less than 1.5 times the diameter of the transversely inserted steel bars; in addition, in order to provide sufficient anchoring length, its length should be designed to be 2 to 4 times the diameter of the longitudinally extending steel bars.

[0031] The lower part of the grouting sleeve 7 is provided with the first precast column double-leg stirrup 6 and is 30 mm away from the bottom of the sleeve. The lower end of the connection between the top of the grouting sleeve 7 and the precast column longitudinal reinforcement 5 is also provided with a precast column double-leg stirrup 6. The grouting sleeve 7 and the stirrups should be firmly tied to avoid the position change of the grouting sleeve 7 during the concrete pouring process, which may cause difficulties in the later assembly construction.

[0032] The upper and lower ends of the precast column 1 are both provided with precast column double-leg stirrups 6 to increase the spacing.

[0033] A joint is provided between the prefabricated column 1 and the prefabricated foundation 2, and the joint is a high-strength non-shrinkage mortar layer with a thickness of 20 to 30 mm.

[0034] like Figure 4~Figure 7 As shown, Figure 4 for Figure 1 The cross-sectional view of the middle AA section shows that the outermost layer of the section is ECC 3. The ECC area includes precast column longitudinal reinforcement 5, precast column double-leg stirrups 6 and high-strength stainless steel stranded wire mesh 8. The center of the section is the inner core of the concrete pouring.

[0035] Figure 5 for Figure 1 The cross-sectional view of the middle BB section shows that the full cross section is ECC 3. The ECC area includes precast column longitudinal reinforcement 5, precast column double-leg stirrups 6, and high-strength stainless steel stranded wire mesh 8.

[0036] Figure 6 for Figure 1 The cross-sectional view of the middle CC section shows that the entire cross-section is ordinary concrete 4, and the ordinary concrete area includes precast column longitudinal reinforcement 5, precast column double-leg stirrups 6, and high-strength stainless steel stranded wire mesh 8.

[0037] Figure 7 for Figure 1 The cross-sectional view of the middle DD section shows that the entire cross-section is ordinary concrete 4, and the ordinary concrete area includes precast column longitudinal reinforcement 5 and precast column double-leg stirrups 6.

[0038] Example 2: Figure 2 As shown, the difference from Example 1 is that: According to the seismic requirements, the precast ECC segment selects a fully cast ECC full-section column structure, that is, the full-section ECC 3 is cast within the height range of the precast ECC segment.

[0039] like Figure 8 As shown, the present invention also provides a construction method for connecting a prefabricated column-foundation node with a high-strength stainless steel stranded wire mesh-ECC locally reinforced grouting sleeve, comprising the following steps: S1. Before pouring the precast column 1, arrange the steel skeleton and high-strength stainless steel stranded wire mesh 8: Tie up the steel skeleton and connect the grouting sleeve 7 at the bottom, arrange the high-strength stainless steel stranded wire mesh 8 within the range of 100-150mm below the precast ECC segment outside the steel skeleton and the precast concrete segment, one end of the high-strength stainless steel stranded wire mesh 8 is anchored to the double-legged stirrups 6 of the precast column at the bottom of the precast ECC segment, and the other end is extended and anchored to the double-legged stirrups 6 of the precast column of the precast concrete segment.

[0040] S2. Casting of precast concrete segments on the upper part of precast column 1: After the steel skeleton and the high-strength stainless steel stranded wire mesh 8 are tied and connected in the above step S1, a template is set on the outside of the precast concrete segment, and a temporary baffle 11 is set at the casting interface between the precast concrete segment and the precast ECC segment, and then ordinary concrete 4 is used to cast the precast concrete segment.

[0041] S3. Casting of precast ECC segments at the bottom of precast column 1: Precast ECC segments select different structural forms according to economic cost and seismic requirements, and are divided into semi-cast ECC sandwich column structures and fully cast ECC full-section column structures; the casting process of the semi-cast ECC sandwich column structure includes: removing the temporary baffle 11 before the initial setting of the ordinary concrete 4 of the precast concrete segment in the above step S2, fixing the inflatable core mold 10 at the middle position of the precast ECC segment, casting ECC 3 to the top of the inflatable core mold, completing the casting of three sides of the ECC shell, taking out the inflatable core mold 10 before the initial setting of ECC 3 and immediately casting ordinary concrete 4 to the top surface of ECC 3 to complete the casting of the concrete casting inner core, and immediately casting ECC 3 to the interface with the precast concrete segment after the casting of the concrete casting inner core is completed.

[0042] like Fig. 9 As shown, it is a structural diagram of the arrangement of the temporary baffle 11, the inflatable core mold 10, and the high-strength stainless steel stranded wire mesh 8 in the node. Fig.10 The inflatable core mold 10 is a structural diagram of the inflatable core mold 10, which is used to separate the ECC 3 and the ordinary concrete 4. The inflatable core mold serves as a temporary partition to prevent the ECC 3 from flowing into the middle ordinary concrete pouring interval; Fig.11 It is a structural diagram of the temporary baffle 11.

[0043] like Figure 2 As shown, the casting process of the fully cast ECC full-section column structure includes: removing the temporary baffle 11 before the ordinary concrete 4 of the precast concrete segment in the above step S2 initially sets, casting the ECC 3 to the interface with the precast concrete segment, and completing the casting of the precast ECC segment.

[0044] S4. Treatment before assembly of prefabricated column 1: First, clean the side of the prefabricated column 1. When the prefabricated column 1 is manufactured, the bottom surface of the column is roughened and cleaned to expose the coarse aggregate of concrete at the bottom of the column. The roughness of the bottom surface of the column is not less than 4 mm as measured by the sand pile method.

[0045] S5. Perform hoisting construction of prefabricated column 1: The prefabricated column 1 and the prefabricated foundation 2 are connected by a grouting sleeve 7. The gap between the prefabricated column 1 and the prefabricated foundation 2 is less than 20 mm. The prefabricated column 1 is slowly lifted so that the gap between the prefabricated column 1 and the prefabricated foundation 2 is 150 mm to 250 mm, leaving space for the construction of the seat mortar layer.

[0046] S6. Construction of the mortar layer at the bottom of prefabricated column 1: Use square wooden strips with a height of 40~60mm as templates to make the template of the lower seat slurry layer of prefabricated column 1, and then fix it on the prefabricated foundation 2; mix the seat slurry with water as required and pour it into the template with a thickness of 20~30mm, and then use a crane to slowly drop the prefabricated column 1 from top to bottom, so that the distance between the prefabricated column 1 and the prefabricated foundation 2 is 20~30mm, and the two prefabricated components are densely filled with the seat slurry, which is an early-strength mortar. After the strength meets the self-weight requirement of the prefabricated column 1, the crane will be removed.

[0047] S7, inject grouting material into the grouting sleeve 7: After the compressive strength of the mortar of the seat slurry layer reaches the requirement, the pre-mixed grouting material is poured into the corrugated pipe through a manual grouting pump. The grouting material is made by high-speed stirring with an electric stirrer for 5 minutes to obtain good fluidity, and the grouting of the stirred grouting material is completed once within 1 hour until the grouting material overflows from the upper grouting hole of the grouting sleeve 7 and the grouting operation is stopped. After the grouting is completed, the hose connected to the lower grouting hole of the grouting sleeve 7 is closed, while the hose connected to the upper grouting hole remains open until the grouting material solidifies and hardens.

[0048] The node structure of the present invention can effectively solve the problems of poor ductility, easy cracking, poor durability, insufficient seismic performance, etc. of prefabricated concrete structures and ordinary concrete pier and column components, and is suitable for prefabricated piers in frame and bridge structures or prefabricated columns in building structures; ECC is used to replace ordinary concrete to form prefabricated ECC segments, which improves the early bearing capacity and durability of the node. At the same time, by arranging high-strength stainless steel strands at the joints and pouring them at the same time, the tensile strength of the column foundation node connection is increased, which greatly improves the seismic resistance of the node.

[0049] The above description is only used to illustrate the technical solution of the present invention rather than to limit it. Other modifications or equivalent substitutions made to the technical solution of the present invention by ordinary technicians in this field should be included in the scope of the claims of the present invention as long as they do not depart from the spirit and scope of the technical solution of the present invention.

Claims

1. A high-strength stainless steel stranded wire mesh-ECC locally reinforced grouting sleeve connecting prefabricated column-foundation node, characterized in that: The invention comprises a precast column (1) and a precast foundation (2) connected vertically, wherein the precast column (1) and the precast foundation (2) are connected via a grouting sleeve (7), wherein the precast column (1) is divided into a precast concrete segment and a precast ECC segment, wherein the precast concrete segment is formed by pouring ordinary concrete (4) on the upper part of a steel frame in the precast column (1), and the precast ECC segment is formed by pouring ECC (3) on the lower part of a steel frame in the precast column (1); The steel frame is composed of a plurality of evenly distributed precast column longitudinal bars (5) and precast column double-leg stirrups (6) which are vertically tied and connected to form a cage-shaped frame, wherein the bottom end of the precast column longitudinal bar (5) is fixedly connected to the top of the grouting sleeve (7), and the upper end extends to the top end surface of the precast column (1); A high-strength stainless steel stranded wire mesh (8) is also provided between the outer wall of the prefabricated ECC segment and the steel skeleton, one end of the high-strength stainless steel stranded wire mesh (8) is anchored in the ECC (3) at the column bottom of the prefabricated ECC segment, and the other end extends and is anchored in the ordinary concrete (4) of the prefabricated concrete segment.

2. According to claim 1, a high-strength stainless steel stranded wire mesh-ECC locally reinforced grouting sleeve connected prefabricated column-foundation node is characterized by: The prefabricated ECC segment is a semi-cast ECC sandwich column structure or a fully cast ECC full-section column structure, wherein the semi-cast ECC sandwich column structure consists of an ECC outer shell and a concrete cast inner core, and the height of the concrete cast inner core is lower than the height of the prefabricated ECC segment.

3. According to claim 2, a high-strength stainless steel stranded wire mesh-ECC locally reinforced grouting sleeve connected prefabricated column-foundation node is characterized by: The column cross section of the prefabricated column (1) in the semi-cast ECC sandwich column structure is 400-800 mm, and the thickness of the ECC shell is not less than 80 mm and not greater than 1 / 4 of the width of the column cross section.

4. According to claim 1, a high-strength stainless steel stranded wire mesh-ECC locally reinforced grouting sleeve connected prefabricated column-foundation node is characterized by: The high-strength stainless steel strand mesh (8) is composed of a plurality of evenly distributed transverse steel strands and vertical steel strands that are tied and connected perpendicularly to each other. The transverse steel strands are arranged between the double-legged stirrups (6) of the precast column, and the transverse steel strands are closed loops, with both ends thereof being overlapped and anchored by aluminum buckles (9). The upper ends of the longitudinal steel strands are anchored in the ordinary concrete (4) of the precast concrete segment by aluminum buckles (9) and tie wires, and the lower ends are anchored on the double-legged stirrups (6) of the precast column by aluminum buckles (9) and tie wires.

5. According to claim 4, a high-strength stainless steel stranded wire mesh-ECC locally reinforced grouting sleeve connected prefabricated column-foundation node is characterized by: The diameter of the steel strands in the high-strength stainless steel strand mesh (8) is 3.6 mm to 6 mm, the spacing between the steel strands is 60 to 100 mm, and the anchoring length of the longitudinal steel strands is 20 times the diameter of the steel strands and is not less than 100 mm.

6. According to claim 1, a high-strength stainless steel stranded wire mesh-ECC locally reinforced grouting sleeve connected prefabricated column-foundation node is characterized by: The upper and lower ends of the prefabricated column (1) are both provided with prefabricated column double-leg stirrups (6) to increase the spacing.

7. According to claim 1, a high-strength stainless steel stranded wire mesh-ECC locally reinforced grouting sleeve connected prefabricated column-foundation node is characterized by: The inner diameter of the grouting sleeve (7) is not less than 1.5 times the diameter of the steel bar extending in the transverse direction, and its length is 2 to 4 times the diameter of the steel bar extending in the longitudinal direction; and a first prefabricated column double-legged stirrup (6) is provided at the lower part of the grouting sleeve (7) and is 30 mm away from the bottom of the sleeve, and a prefabricated column double-legged stirrup (6) is also provided at the lower end of the connection between the top of the grouting sleeve (7) and the prefabricated column longitudinal reinforcement (5).

8. According to claim 1, a high-strength stainless steel stranded wire mesh-ECC locally reinforced grouting sleeve connected prefabricated column-foundation node is characterized by: A joint is provided between the prefabricated column (1) and the prefabricated foundation (2), and the joint is a high-strength non-shrinkage mortar layer with a thickness of 20 to 30 mm.

9. A construction method for connecting a prefabricated column-foundation node with a high-strength stainless steel stranded wire mesh-ECC locally reinforced grouting sleeve according to any one of claims 1 to 8, characterized in that: The following steps are involved: S1. Before pouring the precast column (1), arrange the steel skeleton and high-strength stainless steel stranded wire mesh (8): The steel frame is tied and connected to the grouting sleeve (7) at the bottom, and a high-strength stainless steel stranded wire mesh (8) is arranged within a range of 100 to 150 mm below the precast ECC segment and the precast concrete segment outside the steel frame, one end of the high-strength stainless steel stranded wire mesh (8) is anchored to the precast column double-legged stirrup (6) at the column bottom of the precast ECC segment, and the other end extends and is anchored to the precast column double-legged stirrup (6) of the precast concrete segment; S2. Casting of precast concrete segments on the upper part of the precast column (1): After the steel skeleton and the high-strength stainless steel stranded wire mesh (8) are tied and connected in the above step S1, a template is set outside the precast concrete segment, and a temporary baffle (11) is set at the casting interface between the precast concrete segment and the precast ECC segment, and then ordinary concrete (4) is used to cast the precast concrete segment; S3. Casting of the precast ECC segment at the bottom of the precast column (1): Precast ECC segments are divided into semi-cast ECC sandwich column structures and fully cast ECC full-section column structures; The casting process of the semi-cast ECC sandwich column structure comprises: removing the temporary baffle (11) before the initial setting of the ordinary concrete (4) of the precast concrete segment in the above step S2, fixing the inflatable core mold (10) at the middle position of the precast ECC segment, casting the ECC (3) to the top of the inflatable core mold, completing the casting of three sides of the ECC shell, taking out the inflatable core mold (10) before the initial setting of the ECC (3) and immediately casting the ordinary concrete (4) to the top surface of the ECC (3), completing the casting of the concrete casting inner core, and immediately casting the ECC (3) to the interface with the precast concrete segment after the casting of the concrete casting inner core is completed; The casting process of the fully cast ECC full-section column structure comprises: removing the temporary baffle (11) before the ordinary concrete (4) of the precast concrete segment in the above step S2 begins to set, casting the ECC (3) to the interface with the precast concrete segment, and completing the casting of the precast ECC segment; S4. Prefabricated columns (1) Pre-assembly and construction treatment: First, the side of the prefabricated column (1) is cleaned. When the prefabricated column (1) is manufactured, the bottom surface of the column is roughened and cleaned so that the coarse concrete aggregate at the bottom of the column is exposed. The roughness of the bottom surface of the column is not less than 4 mm as measured by the sand pile method; S5. Perform hoisting construction of prefabricated columns (1): The prefabricated column (1) and the prefabricated foundation (2) are connected via a grouting sleeve (7), the gap between the prefabricated column (1) and the prefabricated foundation (2) is less than 20 mm, the prefabricated column (1) is slowly lifted so that the gap between the prefabricated column (1) and the prefabricated foundation (2) is 150 mm to 250 mm, and space is reserved for the construction of the seat grouting layer; S6. Construction of the mortar layer at the bottom of the prefabricated column (1): A square wooden strip with a height of 40 to 60 mm is used as a template to make a template for the base mortar layer at the lower part of the prefabricated column (1), and then fixed on the prefabricated foundation (2); the base mortar is mixed with water as required and poured into the template to a thickness of 20 to 30 mm, and then the prefabricated column (1) is slowly lowered from top to bottom using a crane, so that the spacing between the prefabricated column (1) and the prefabricated foundation (2) is 20 to 30 mm, and the space between the two prefabricated components is densely filled with the base mortar, which is an early-strength mortar. After the strength meets the self-weight requirement of the prefabricated column (1), the crane is removed; S7. Inject grouting material into the grouting sleeve (7): After the compressive strength of the mortar of the base grouting layer reaches the required level, the pre-mixed grouting material is poured into the corrugated pipe by a manual grouting pump. The grouting material is prepared by stirring at high speed with an electric stirrer for 5 minutes to obtain good fluidity, and the grouting of the stirred grouting material is completed once within 1 hour. The grouting operation is stopped after the grouting material overflows from the upper grouting hole of the grouting sleeve (7). After the grouting is completed, the hose connected to the lower grouting hole of the grouting sleeve (7) is closed, while the hose connected to the upper grouting hole is kept open until the grouting material solidifies and hardens.

Citation Information

Cited By

  • High-intensity area stainless steel-ECC assembly type pier column-foundation node connecting structure and construction method

    CN119507310A

  • Stainless steel-ecc assembled pier-column-foundation joint connection structure and method in high intensity area

    CN119507310B

  • Block sandwich assembly type concrete test component and construction method thereof

    CN120385546A

  • Stirrup assembly type concrete beam column structure

    CN120401652A