Unloading construction method of large steel structure roof
By setting monitoring points and stress monitoring points on the large steel structure roof, establishing a simulation model, and optimizing the dismantling sequence of the support frame, the problem of cracking at the branch points of the tree-shaped column was solved, and safe and reliable unloading construction was achieved.
Patent Information
- Application Number
- CN202411057311.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-02
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2044-08-02
AI Technical Summary
In the process of unloading the roof of a large steel structure building, the branch points of the tree-shaped columns are prone to cracking or breakage. Existing support dismantling methods fail to effectively consider the stress changes of the tree-shaped columns.
By setting displacement and stress monitoring points on the steel structure roof and tree-shaped columns, a simulation model was established, a dismantling sequence table for the support frame was created, and the dismantling sequence was optimized by comparing real-time monitoring data with simulation data to ensure the safety of the tree-shaped column branches.
This effectively avoids the risk of cracking and breakage of tree-shaped column branches, ensuring the safety and reliability of unloading construction.
Smart Images

Figure CN118979634B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of steel structure construction, and specifically to a method for unloading and constructing a large steel structure roof. Background Technology
[0002] With the development of large steel structure buildings in recent years, more and more construction companies are using steel structures to construct large buildings, such as large stations, sports stadiums or exhibition halls. Tree-shaped columns, as the main supporting structure, have a beautiful appearance, good support strength and effect, and can meet the complex support requirements of the top.
[0003] The roof steel structure installation employs lifting and hoisting methods, requiring numerous temporary supports and lifting scaffolds during construction. After completion, unloading is necessary, a complex process involving the interaction between the main structure and the supports, characterized by a gradual transfer and redistribution of structural forces. The supports transition from a load-bearing state to a unloaded state, while the main structure transitions from its installed state to its designed load-bearing state. Many factors influence structural safety during this process; the design of the supports, the selection of the unloading scheme, and the effective control of the unloading process all significantly impact the structure itself. The tree-shaped columns have numerous connection points with the roof, resulting in complex displacement and stress variations. Applying existing methods for dismantling and reinforcing ordinary columns and roofs directly to the dismantling of tree-shaped columns and roofs can easily lead to neglect of the stress on the branches of the tree-shaped columns, potentially causing cracking or even breakage at these branch points. Summary of the Invention
[0004] To address the aforementioned shortcomings of existing technologies, this invention provides an unloading and construction method for large steel structure roofs with tree-shaped column-connected roofs.
[0005] To achieve the above-mentioned objectives, the technical solution adopted by this invention is as follows:
[0006] A method for unloading and constructing a large steel structure roof is provided, which includes the following steps:
[0007] S1: Select displacement monitoring points on the steel structure roof and stress monitoring points on the tree-shaped columns and supporting trusses respectively;
[0008] S2: Set up simulation models of the steel structure roof and tree-shaped columns, and mark the displacement monitoring points and stress monitoring points in the simulation model;
[0009] S3: Number the support frames to be disassembled, create a disassembly sequence table for the support frames, disassemble the support frames along the number in the simulation model, and record the simulation data of displacement monitoring points and stress monitoring points when each support frame is disassembled in the simulation model.
[0010] S4: Disassemble the physical support frame according to the disassembly sequence table. After disassembling each support frame, compare the data of the displacement monitoring point and stress monitoring point with the simulation data and calculate the data offset.
[0011] S5: When the data offset is greater than the threshold, pause the dismantling of the next support frame and update the simulation model with data from the actual displacement monitoring points and stress monitoring points. Use the updated simulation model to verify and optimize the unloading sequence of the remaining support frames. Use the simulation to verify and optimize the unloading construction plan and continue the dismantling construction. Otherwise, continue the dismantling construction according to the dismantling sequence table until all support frames are dismantled.
[0012] Furthermore, the formula for calculating the data offset is:
[0013]
[0014] Where, λ i L is the distance factor; i T represents the distance between the i-th displacement monitoring point and the p-th support frame; i ′ ,p T represents the displacement change at the i-th displacement monitoring point before and after the p-th support frame is disassembled; i,p ε represents the displacement change of the i-th displacement monitoring point in the simulation model before and after the p-th support frame is disassembled; j P′ is the ratio of the distance between the j-th stress monitoring point and the nearest tree-shaped column to the stress; i,p P represents the stress change at the j-th stress monitoring point before and after the p-th support frame is disassembled; i,p denoted as , where is the stress change value of the j-th stress monitoring point in the simulation model before and after the p-th support frame is disassembled; m is the total number of displacement monitoring points; and n is the total number of stress monitoring points.
[0015] Furthermore, the displacement monitoring points are the projection points of each branch of the tree-shaped column perpendicular to the roof; the stress monitoring points are the center point of each branch of the tree-shaped column and the connection point between the supporting truss and the branch of the tree-shaped column.
[0016] Furthermore, the method for creating the support frame disassembly sequence table is as follows:
[0017] A1: Collect the distance from the p-th support frame to the center of the roof. And the distance between the support frame and the connection points of the three nearest tree-shaped columns and support trusses.
[0018] A2: Calculate the dismantling impact score of the p-th support frame according to the dismantling impact score calculation formula. The dismantling impact score calculation formula is:
[0019]
[0020] A3: Sort the disassembly order of the support frame according to the magnitude of the disassembly impact score. The smaller the disassembly impact score, the higher the ranking.
[0021] Furthermore, the specific steps for simulation verification and optimization of the support frame disassembly sequence are as follows:
[0022] B1: Based on the disassembly sequence table of the support frame, simulate the disassembly of the support frame in the simulation model and record the stress changes at the stress monitoring points;
[0023] B2: After the kth support frame in the disassembly sequence is disassembled, if the following occurs: Case 1: The stress value detected by any stress monitoring point is greater than the stress threshold of the corresponding tree-shaped column branch, proceed to step B3; if the following occurs: Case 2: The stress change detected by any stress monitoring point is greater than the change threshold, proceed to step B4; if both Case 1 and Case 2 occur simultaneously, proceed to step B3; otherwise, proceed to step B5.
[0024] B3: Rewind twice to dismantle the support frame; at this time, the (k-2)th support frame in the original dismantling sequence table has been dismantled, but the (k-1)th support frame has not been dismantled; find the symmetrical point of the connection point between the (k-1)th support frame and the roof along the center of the roof, and take the support frame that is closest to the symmetrical point and has not yet been dismantled as the (k-1)th support frame in the new dismantling sequence table, and return to B2 to continue the dismantling judgment.
[0025] B4: Rewind the support frame disassembly once; at this point, the (k-1)th support frame in the original disassembly sequence table has been disassembled, but the kth support frame has not been disassembled; take the support frame closest to the kth support frame as the kth support frame in the new disassembly sequence table, and return to B2 to continue the disassembly judgment;
[0026] B5: Once all support frames have been completely disassembled, output the optimized support frame disassembly sequence table.
[0027] Furthermore, after creating the support frame disassembly sequence table in step S3, a simulation verification and optimization are performed before proceeding to step S4.
[0028] The beneficial effects of this invention are as follows:
[0029] This invention sets displacement monitoring points on the steel structure roof and stress monitoring points on the tree-shaped columns and supporting trusses, sets a dismantling sequence table for the support frame, and compares real-time monitoring data with simulation data from a simulation model. The offset obtained from the comparison guides the actual dismantling construction, thus ensuring that the entire support unloading construction process can fully take into account the changes in the tree-shaped columns. Through the setting, verification, and optimization of the dismantling sequence, it can be ensured that the branches of the tree-shaped columns will not crack or other risks during the dismantling of the support rods. Attached Figure Description
[0030] Figure 1 This is a schematic diagram of the process of the present invention. Detailed Implementation
[0031] The specific embodiments of the present invention are described below to enable those skilled in the art to understand the present invention. However, it should be understood that the present invention is not limited to the scope of the specific embodiments. For those skilled in the art, various changes are obvious as long as they are within the spirit and scope of the present invention as defined and determined by the appended claims. All inventions utilizing the concept of the present invention are protected.
[0032] like Figure 1 As shown, a method for unloading and constructing a large steel structure roof includes the following steps:
[0033] S1: Select displacement monitoring points on the steel structure roof and stress monitoring points on the tree-shaped columns and supporting trusses respectively;
[0034] S2: Set up simulation models of the steel structure roof and tree-shaped columns, and mark the displacement monitoring points and stress monitoring points in the simulation model;
[0035] S3: Number the support frames to be disassembled, create a disassembly sequence table for the support frames, disassemble the support frames along the number in the simulation model, and record the simulation data of displacement monitoring points and stress monitoring points when each support frame is disassembled in the simulation model.
[0036] S4: Disassemble the physical support frame according to the disassembly sequence table. After disassembling each support frame, compare the data of the displacement monitoring point and stress monitoring point with the simulation data and calculate the data offset.
[0037] S5: When the data offset is greater than the threshold, pause the dismantling of the next support frame and update the simulation model with data from the actual displacement monitoring points and stress monitoring points. Use the updated simulation model to verify and optimize the unloading sequence of the remaining support frames. Use the simulation to verify and optimize the unloading construction plan and continue the dismantling construction. Otherwise, continue the dismantling construction according to the dismantling sequence table until all support frames are dismantled.
[0038] The formula for calculating data offset is:
[0039]
[0040] Where, λ i L is the distance factor; i T represents the distance between the i-th displacement monitoring point and the p-th support frame; i ′ ,p T represents the displacement change at the i-th displacement monitoring point before and after the p-th support frame is disassembled; i,pε represents the displacement change of the i-th displacement monitoring point in the simulation model before and after the p-th support frame is disassembled; j P is the ratio of the distance between the j-th stress monitoring point and the nearest tree-shaped column to the stress; i ′ ,p P represents the stress change at the j-th stress monitoring point before and after the p-th support frame is disassembled; i,p denoted as , where is the stress change value of the j-th stress monitoring point in the simulation model before and after the p-th support frame is disassembled; m is the total number of displacement monitoring points; and n is the total number of stress monitoring points.
[0041] The displacement monitoring points are the projection points of each branch of the tree-shaped column perpendicular to the roof; the stress monitoring points are the center point of each branch of the tree-shaped column and the connection points between the supporting truss and the branches of the tree-shaped column.
[0042] The method for creating the support frame disassembly sequence table is as follows:
[0043] A1: Collect the distance from the p-th support frame to the center of the roof. And the distance between the support frame and the connection points of the three nearest tree-shaped columns and support trusses.
[0044] A2: Calculate the dismantling impact score of the p-th support frame according to the dismantling impact score calculation formula. The dismantling impact score calculation formula is:
[0045]
[0046] A3: Sort the disassembly order of the support frame according to the magnitude of the disassembly impact score. The smaller the disassembly impact score, the higher the ranking.
[0047] The specific steps for simulation verification and optimization of the support frame disassembly sequence are as follows:
[0048] B1: Based on the disassembly sequence table of the support frame, simulate the disassembly of the support frame in the simulation model and record the stress changes at the stress monitoring points;
[0049] B2: After the kth support frame in the disassembly sequence is disassembled, if the following occurs: Case 1: The stress value detected by any stress monitoring point is greater than the stress threshold of the corresponding tree-shaped column branch, proceed to step B3; if the following occurs: Case 2: The stress change detected by any stress monitoring point is greater than the change threshold, proceed to step B4; if both Case 1 and Case 2 occur simultaneously, proceed to step B3; otherwise, proceed to step B5.
[0050] B3: Rewind twice to dismantle the support frame; at this time, the (k-2)th support frame in the original dismantling sequence table has been dismantled, but the (k-1)th support frame has not been dismantled; find the symmetrical point of the connection point between the (k-1)th support frame and the roof along the center of the roof, and take the support frame that is closest to the symmetrical point and has not yet been dismantled as the (k-1)th support frame in the new dismantling sequence table, and return to B2 to continue the dismantling judgment.
[0051] B4: Rewind the support frame disassembly once; at this point, the (k-1)th support frame in the original disassembly sequence table has been disassembled, but the kth support frame has not been disassembled; take the support frame closest to the kth support frame as the kth support frame in the new disassembly sequence table, and return to B2 to continue the disassembly judgment;
[0052] B5: Once all support frames have been completely disassembled, output the optimized support frame disassembly sequence table.
[0053] After creating the support frame disassembly sequence table in step S3, perform a simulation verification and optimization, and then proceed to step S4.
Claims
1. A method for unloading and constructing a large steel structure roof, characterized in that, Includes the following steps: S1: Select displacement monitoring points on the steel structure roof and stress monitoring points on the tree-shaped columns and supporting trusses respectively; S2: Set up simulation models of the steel structure roof and tree-shaped columns, and mark the displacement monitoring points and stress monitoring points in the simulation model; S3: Number the support frames to be disassembled, create a disassembly sequence table for the support frames, and disassemble the support frames along the number in the simulation model. When each support frame is disassembled in the simulation model, record the simulation data of the displacement monitoring point and the stress monitoring point. S4: Disassemble the physical support frame according to the disassembly sequence table. After disassembling each support frame, compare the data of the displacement monitoring point and stress monitoring point with the simulation data and calculate the data offset. S5: When the data offset is greater than the threshold, pause the dismantling of the next support frame, update the simulation model with the data from the actual displacement monitoring points and stress monitoring points, use the updated simulation model to verify and optimize the unloading sequence of the remaining support frames, and continue the dismantling construction using the simulation-verified and optimized unloading construction plan; otherwise, continue the dismantling construction according to the dismantling sequence table until all support frames are dismantled.
2. The unloading construction method for a large steel structure roof according to claim 1, characterized in that, The formula for calculating the data offset is: ; ; in, Distance factor; For the first The displacement monitoring point and the first The distance between the support frames; For the first Before and after the first support frame was disassembled Displacement change values at each displacement monitoring point; For the first Before and after the first support frame was disassembled Displacement change values of each displacement monitoring point in the simulation model; For the first The ratio of the distance between each stress monitoring point and the nearest tree-shaped column to the stress; For the first Before and after the first support frame was disassembled Stress change values at each stress monitoring point; For the first Before and after the first support frame was disassembled Stress change values at each stress monitoring point in the simulation model; This represents the total number of displacement monitoring points. This represents the total number of stress monitoring points.
3. The unloading construction method for a large steel structure roof according to claim 1, characterized in that, The displacement monitoring points are the projection points of each branch point of the tree-shaped column perpendicular to the roof; the stress monitoring points are each branch point of the tree-shaped column and the connection points between the supporting truss and the branches of the tree-shaped column.
4. The unloading construction method for a large steel structure roof according to claim 1, characterized in that, The method for creating the disassembly sequence table for the support frame is as follows: A1: Collect the first The distance of each support frame from the center of the roof And the distance between the support frame and the connection points of the three nearest tree-shaped columns and support trusses. , , ; A2: Calculate the first [item] based on the disassembly impact scoring formula. The disassembly impact score for each support frame is calculated using the following formula: ; A3: Sort the disassembly order of the support frame according to the magnitude of the disassembly impact score. The smaller the disassembly impact score, the higher the ranking.
5. The unloading construction method for a large steel structure roof according to claim 1, characterized in that, The specific steps for simulation verification and optimization of the support frame disassembly sequence are as follows: B1: Based on the disassembly sequence table of the support frame, simulate the disassembly of the support frame in the simulation model and record the stress changes at the stress monitoring points; B2: When the disassembly sequence is in the order table k After the support frame is disassembled, if situation 1 occurs: the stress value detected at any stress monitoring point is greater than the stress threshold of the corresponding tree-shaped column branch, proceed to step B3; if situation 2 occurs: the stress change detected at any stress monitoring point is greater than the change threshold, proceed to step B4; if both situation 1 and situation 2 occur simultaneously, proceed to step B3. Otherwise proceed to step B5; B3: Retract twice to disassemble the support frame; At this point, the original disassembly sequence number is... k -2 support frames have been disassembled. k -1 support frame was not disassembled; the first one was found. k -1. The support frame whose connection point to the roof is symmetrical about the center of the roof is selected as the first unremoved support frame in the new dismantling sequence. k -1 support frame, return to B2 to continue disassembly and assessment; B4: Retract the support frame once for disassembly; At this point, the original disassembly sequence number is... k -1 support frame has been disassembled, the first k The support frame was not disassembled; The first k The support frame closest to the new dismantling sequence is the first one in the new dismantling order. k One support frame, return to B2 to continue disassembly and assessment; B5: Once all support frames have been completely disassembled, output the optimized support frame disassembly sequence table.
6. The unloading construction method for a large steel structure roof according to claim 5, characterized in that, After creating the support frame disassembly sequence table in step S3, perform a simulation verification and optimization, and then proceed to step S4.
Citation Information
Patent Citations
Stress removing and reinforcing method used for steel construction truss
CN102890739A
Large-span steel structure support unloading monitoring method
CN109781368A