Optimization design method for clean energy direct current transmission project sending end system
By combining the power grid and electricity consumption analysis, the DC transmission and transmission curve and solution are determined, and the problems of low power balance and clean energy utilization in the DC transmission project transmission end system design are solved, and the optimization balance of power and energy are achieved. Efficient use.
Patent Information
- Application Number
- CN202410446877.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-15
- Publication Date
- 2024-12-06
Smart Images

Figure CN119093454A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of power grids, and in particular relates to a method for optimizing the design of a sending-end system of a clean energy direct current transmission project. Background Art
[0002] At present, relevant research on the sending-end system of DC transmission projects has been initially carried out in China, but it mainly focuses on various optimization scheduling methods of DC transmission projects.
[0003] Reference [1] proposed a multi-source coordinated frequency regulation strategy for a HVDC transmission system with large-scale wind power. The regional control deviation constraint of HVDC transmission was considered on a long time scale to ensure the rationality of the spinning reserve capacity setting of wind turbines and thermal power units.
[0004] Reference [2] proposed an optimal control strategy for a flexible DC transmission system with modular multi-level S converters under asymmetric conditions, which enhanced the fault ride-through capability of the flexible DC transmission system.
[0005] Patent [3] discloses a method for optimizing the grid connection mode of a local power grid and a DC sending-end system of an energy base based on multi-attribute decision making. By establishing a comprehensive evaluation index system for the grid connection mode and setting the combined weights of the evaluation indexes, a method for optimizing the grid connection mode based on multi-attribute decision making is proposed.
[0006] Patent [4] discloses an optimization control method for a multi-terminal flexible direct current transmission system based on optimal power flow. The method optimizes and calculates the VSC-MTDC system containing wind power forecast data, and uses the optimization result as a reference value for the entire multi-terminal flexible direct current transmission system to perform a multi-objective optimization control method.
[0007] Reference [5] proposed a technical solution for active blocking of DC to ensure that the DC sending-end units can deliver during the dry season, while also meeting the safety and stability requirements of the Jinzhong DC in both interconnected and islanded operation modes, and enhancing the flexibility of the DC and sending-end unit operation mode arrangements.
[0008] Patent [6] discloses a method and system for assessing the risk of cascading failures of new energy sources in a DC sending-end system, which meets the accuracy of cascading failure analysis dominated by power electronic switching control and adaptability to multi-time scale fault characteristics, while also improving the rapidity of risk assessment;
[0009] Reference [7] proposed an overvoltage suppression strategy with coordinated control of multiple devices to reduce the steady-state overvoltage risk caused by large-scale withdrawal of DC blocking power flow at the weak-transmitting end of the UHV DC grid, support DC transmission capacity and promote the consumption of new energy.
[0010] Patent [8] discloses a DC power transmission sending-end system, a voltage control method, a device and a DC power transmission system. When an overvoltage occurs in the sending-end power grid due to a DC commutation failure, a lockout or a restart of the DC power transmission system, a static voltage support device or a dynamic reactive power compensation device is controlled to provide a support current to absorb excess reactive power from the sending-end power grid, thereby avoiding transient overvoltage and ensuring that the voltage is kept within a relatively stable range to the greatest extent possible, thereby improving the stability of the DC power transmission sending-end system and the sending-end power grid.
[0011] Patent [9] discloses a method for optimizing the capacity of the supporting power sources of the hydropower, wind power and solar power systems at the sending end taking into account resource constraints, wherein a method for formulating two DC transmission curves based on the needs of the sending and receiving end systems is designed;
[0012] Reference
[10] proposed a method for optimizing the design of the sending-end system to adjust the DC sending-end system access scheme and control the startup mode of the sending-end units, which improved the system stability of the DC transmission project.
[0013] The above-mentioned documents and patents [1-4] basically focus on the operation side of DC transmission, focusing on the optimization control of the sending-end system; documents and patents [5-8] focus on the fault conditions of DC transmission, focusing on DC locking, overvoltage and other issues; although documents and patents [9-10] involve the design of the sending-end system of DC transmission projects, they mainly focus on some of the contents that need to be considered in the design, lacking systematic analysis and design, and no research on the long-term design level of DC transmission projects, lacking the establishment of appropriate design solutions. Summary of the invention
[0014] In order to achieve the above-mentioned purpose, the present invention specifically adopts the following technical solutions:
[0015] The optimization design method of the sending-end system of the clean energy DC transmission project combines the current status of the sending-end system power grid and social electricity consumption and development planning to analyze the annual power balance requirements of the planning level, and determines the DC transmission curve based on the clean energy output characteristics, and then determines the transmission mode, transmission capacity and recommended plan for the DC transmission project.
[0016] The analysis of power balance according to the current status and development plan of the power grid source and grid load of the sending-end system specifically includes the following steps (S1-S12):
[0017] S1: According to the production plan, determine the design research level year; the present invention preliminarily determines 2025 and 2030 as the design level years.
[0018] S2: Source: Analyze the current status of the power supply structure of the sending end system;
[0019] S3: Network: Analyze the current status of the power grid at the sending end;
[0020] S4: Load: Analyze the current status of electricity consumption in the entire society of the sending end system;
[0021] S5: Source: Analyze the power development plan of each planning level year of the sending end system;
[0022] S6: Network: Analyze the power grid development plan for each planning level year of the sending end system;
[0023] S7: Load: Analyze the annual power demand forecast of each planning level of the sending end system;
[0024] Due to the limited coal transportation capacity and environmental protection factors, the development of thermal power in Region A is limited. The primary energy is mainly hydropower resources, and a multi-energy complementary power supply pattern is formed with many independent power sources such as solar photovoltaic power stations. Analyze the power supply planning, power transmission and reception planning and power grid planning of each planning level of the sending end system to provide data support for the subsequent power supply organization plan and power balance.
[0025] S8: Analyze the power supply organization plan of the sending end system;
[0026] S9: Analyze the output characteristics of each hydropower station in the sending end system when operating independently in each planned dry year and normal year;
[0027] S10: Analyze the output characteristics of the sending end system in each planned dry year and normal year when each hydropower station is in joint operation;
[0028] S11: Conduct power balance analysis at the sending end;
[0029] S12: Analyze the power retention plan at the sending end;
[0030] According to the results of power balance, the overall power supply and demand situation of each planning level is estimated, and the long-term support capacity of various adjustment methods for the power supply and demand balance of the sending-end system is taken into account. The power retention work at the sending end is done well, and the local power demand is given priority. Combined with the supply and demand situation of the sending-end system and the power demand of the receiving end, the power retention plan of the sending-end power is determined with reference to the existing retention experience.
[0031] The determination of the transmission mode, transmission capacity and recommended scheme of DC transmission project specifically includes the following steps (S13-S24):
[0032] S13: Do you want to bundle the water and light into a bundle and send it out? If yes, go to the next step; if no, go to S16;
[0033] S14: Analyze the output characteristics of new energy power sources in the sending-end system;
[0034] S15: Analyze the water-light complementary characteristics;
[0035] S16: Analyze the DC power transmission curve and utilization hours;
[0036] S17: Determine the transmission method and transmission capacity;
[0037] S18: DC voltage level selection;
[0038] S19: Technical comparison and selection of DC design schemes for sending-end converter stations;
[0039] S20: Preliminary selection of DC conductor cross section;
[0040] S21: Conductor current carrying capacity verification;
[0041] S22: Analyze and calculate transmission losses;
[0042] S23: Comparative analysis of DC conductor technologies;
[0043] S24: Provide recommended DC conductor solutions.
[0044] The beneficial effects of the present invention are as follows:
[0045] 1. In the present invention, the method for optimizing the design of the sending-end system of a clean energy DC transmission project determines the DC transmission curve in combination with the clean energy output characteristics, and further determines the transmission mode, transmission capacity and recommended scheme of the DC transmission project.
[0046] 2. In the present invention, the optimization design method of the sending-end system of the clean energy direct current transmission project evaluates the planning scheme of the sending channel according to the analysis results of the power balance of the power grid source and network load status and development plan of the sending-end system, and estimates the overall power supply and demand situation of each planning level year according to the power balance results, taking into account the long-term support capacity of various adjustment methods for the power supply and demand balance of the sending-end system, and doing a good job in retaining power at the sending end, giving priority to ensuring local electricity demand.
[0047] 3. The present invention carries out targeted optimization in both the grid planning stage and the system operation stage, thereby reducing water abandonment to a greater extent and improving the utilization rate of clean energy. BRIEF DESCRIPTION OF THE DRAWINGS
[0048] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the following briefly introduces the drawings required for use in the embodiments. It should be understood that the following drawings only illustrate certain embodiments of the present invention and should not be regarded as limiting the scope. For those skilled in the art, other related drawings can be obtained based on these drawings without creative work, among which:
[0049] Figure 1 It is a flow chart of the present invention;
[0050] Figure 2 This is the independent operation curve of the Jinshang cascade power station in the average water year of 2025;
[0051] Figure 3 This is the joint operation curve of the Jinshang cascade power station in the average water year of 2030;
[0052] Figure 4 This is the typical daily power transmission curve of 4 million PV bundles in 2030 (August);
[0053] Figure 5 This is the typical daily power transmission curve of 7 million PV bundles in 2030 (August);
[0054] Figure 6 This is an output characteristic analysis diagram of wind power output and photovoltaic output of the present invention; DETAILED DESCRIPTION
[0055] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments.
[0056] The components of the embodiments of the present invention generally described and illustrated in the figures herein may be arranged and designed in a wide variety of different configurations.
[0057] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by the skilled person in the art without making creative efforts are within the scope of protection of the present invention.
[0058] The features and performance of the present invention are further described in detail below in conjunction with the embodiments.
[0059] Embodiment 1:
[0060] like Figure 1 The flowchart of a method for optimizing the design of a sending-end system of a clean energy DC transmission project shown in FIG. specifically includes the following steps:
[0061] S1: According to the plan for the start of operation and full operation of the power supply in area A, 2025 and 2030 are selected as the design level years.
[0062] S2: Region A includes three provinces, B, C and D. Limited by the transportation capacity of electric coal and environmental protection factors, the development of thermal power in provinces C and D is limited. The primary conventional energy is mainly hydropower resources in Province B, and forms a multi-energy complementary power supply pattern with many independent power sources in Region A. As of the end of 2020, the total installed capacity of Region A was 131.3 million kW, of which hydropower installed capacity accounted for 67.8% of the total capacity, thermal power accounted for 25.2%, and the rest were wind power and photovoltaic power, etc. It is expected that hydropower resources will remain the most important primary energy source for a long period of time thereafter; the total installed capacity of Province B was 101.05 million kW, of which hydropower accounted for 78.92 million kW, accounting for 78.1% of the total capacity, with good transmission potential.
[0063] S3: The power grid in Region A is interconnected with power grids outside the region through “five horizontal and two vertical” lines, and is internally interconnected through AC and DC lines. As of 2020, there are 5 DC converter stations, 71 substations, and a total 500kV line length of 22,313km, which has a certain external transmission capacity. As an important part of the power grid in Region A, Province B has built a number of centralized hydropower transmission channels by the end of 2020, forming a “four direct and eight alternating” interconnection pattern with power grids outside the province.
[0064] S4: The economic situation in Region A is improving, and the electricity demand of the whole society is growing rapidly, with a growth rate higher than the national average. In terms of electricity consumption, the total electricity consumption of Region A in 2020 was 413.5 billion kWh, with an average annual growth rate of 7.3% in the preset historical period corresponding to 2020; in terms of electricity load, the maximum load of the power grid in Region A in 2020 was 79.3 million kW, with an average annual growth rate of 7.3% in the preset historical period corresponding to 2020. Among them, the electricity consumption and load of provinces B and C account for the vast majority of the power grid in Region A, and the growth rate is basically the same as that of the power grid in Region A; the power grid in Province D is growing faster, but the volume is smaller.
[0065] S5: As the main sending-end system in Region A, Province B, considering only the approved thermal power projects under construction, will have a total installed capacity of about 152.96 million kW by 2025 and about 193.80 million kW by 2030. The total installed capacity of Province D is relatively small, with a total installed capacity of about 8.31 million kW by 2025 and about 12.81 million kW by 2030.
[0066] S6: In the first preset forecast period corresponding to 2025, the power grid in region A will add 4 UHV DC projects, build a UHV AC channel for hydropower transmission between two places in province B, promote the integration of the power grids in provinces B and C, optimize the power grid structure in province B, promote the construction of gas turbines in province D, develop "photovoltaic + energy storage", build a 500kV second channel between provinces B and D, and expand the second phase of inter-provincial mutual assistance DC in due course. At the provincial main grid level, the power grid in province B will disperse the DC transmission channel, optimize the grid structure, and reduce safety risks; the power grid in province C will improve the main grid structure of the central urban area and improve the power supply level of the load center in combination with the access of Hami North to province C UHV DC; the power grid in province D plans to expand the second phase of inter-provincial mutual assistance DC to 1.2 million kW (increasing the transmission capacity by 600,000 kW) in the first preset forecast period corresponding to 2025, and plan to build a new provincial power grid reinforcement project to ensure the power supply demand of the power grid in province D in the first preset forecast period corresponding to 2025.
[0067] S7: The power demand forecast results of region A in the first preset forecast period corresponding to 2025 and the second preset forecast period corresponding to 2030 are shown in Table 1. Based on this result, data support can be provided for subsequent power supply organization plans and power and electricity balance.
[0068] Table 1 (Unit: 100 million kWh, 10,000 kW)
[0069]
[0070] S8: The planned river section of the upper reaches of the Jinsha River is about 518 km long, with a natural drop of 979 m and a basin area of 1.0459 million km2. It is rich in hydropower resources and has good development conditions. A total of 8 power stations are planned to be developed with a total installed capacity of 9.436 million kW. According to the power supply planning, the progress of the early stage of the project and the environmental protection constraints, the present invention is aimed at studying 7 power stations, with a total installed capacity of 9.136 million kW. The expected production sequence of the 7-level power station is shown in Table 2.
[0071] Table 2 (Unit: 10,000 kW)
[0072]
[0073] S9: According to the development plan of the sending end system, by 2025, the Jinshang section G3, G5 and G6 power stations will be completed, and one unit of the G4 power station will be put into operation. The total installed capacity of the Jinshang cascade power stations will reach 5.516 million kW. The output characteristics of each hydropower station when operating independently are shown in Table 3. The independent operation curve in a normal water year in 2025 is as follows: Figure 2 As shown; According to the development plan of the sending-end system, all 7-level power stations in the Jinshang section will be put into operation in 2030, with a total installed capacity of 9.136 million kW. The output characteristics of each hydropower station when operating independently are shown in Table 4.
[0074] Table 3 (Unit: 100 million kWh, 10,000 kW)
[0075]
[0076] Table 4 (Unit: 10,000 kW)
[0077]
[0078] S10: After all 7-level power stations in the upper section of Jin are put into operation in 2030, the output characteristics of the hydropower stations during joint operation are shown in Tables 5 and 6. The joint operation curve in a normal water year in 2030 is as follows: Figure 3 shown.
[0079] Table 5 (Unit: 100 million kWh, 10,000 kW)
[0080]
[0081] Table 6 (Unit: 10,000 kW)
[0082]
[0083]
[0084] S11: According to the design level year, the present invention determines 2025 and 2030 as the calculation level year. According to the load characteristics, power supply structure and supply and demand balance characteristics, the power balance is performed month by month throughout the year. The representative months of the wet and dry seasons are selected as August and December respectively. Among them, Province B selects the dry year for power balance and the normal year for power balance. Province D selects the dry year as the level year. In the first preset prediction cycle corresponding to 2025, the reserve rate of Province B is 12%, and the reserve rate of Province D is 15%. Hydropower, wind power and photovoltaic power participate in the balance analysis in accordance with relevant requirements. Due to the full commissioning of the external direct current and the continuous increase in local load, Province B has a large power shortage in 2025 and 2030. Therefore, the power guarantee plan is adopted, the new units are added and the direct current transmission is reduced. The power and power balance results are shown in Tables 7 and 8. The power grid of Province D mainly presents abundant and dry shortages in 2025 and 2030, and the power and power balance results are shown in Tables 9 and 10.
[0085] Table 7 (Unit: 10,000 kW)
[0086]
[0087] Table 8 (Unit: 100 million kWh)
[0088]
[0089]
[0090] Table 9 (Unit: 10,000 kW)
[0091]
[0092] Table 10 (Unit: 100 million kWh)
[0093]
[0094] S12: According to the results of power and electricity balance, in the first preset forecast period corresponding to 2025, neither Province B nor Province D has the ability to organize additional power transmission for Jinshang DC, and Jinshang DC should mainly transmit power from power stations; in the second preset forecast period corresponding to 2030, the hydropower development of Province B will be basically completed, and it will face a supply and demand situation of "shortage in both wet and dry seasons" in the medium and long term. Province D will face severe power shortage problems during the dry season in the first preset forecast period corresponding to 2025 and the second preset forecast period corresponding to 2030, and it should consider retaining a certain amount of local power and electricity from Jinshang Hydropower. Combined with the power supply and demand situation of the power grids in Provinces B and D and the power demand of the receiving end, and referring to the retention of the existing Jiehe Power Station, it is temporarily considered to retain 30% of the power retained by Jinshang Hydropower during the dry season, and the two provinces are allocated at a ratio of 1:1.
[0095] S13: Do you want to bundle the water and light into a bundle and send it out? If yes, go to the next step; if no, go to S16;
[0096] Determine whether the power supply organization scheme includes photovoltaics. If yes, go to the next step. If not, go to S16.
[0097] S14: Analyze the output characteristics of new energy power sources in the sending-end system;
[0098] According to the new energy output curve, as shown in the attached figure Figure 6 , wind power output has intraday anti-peak characteristics, and photovoltaic output is consistent with the peak load characteristics of the noon peak, but does not have the peak capacity of the evening peak.
[0099] S15: Analyze the water-light complementary characteristics;
[0100] In 2030: With 9.136 million kW of hydropower and 4 million kW of photovoltaic power, the total power generation will be 45.76 billion kWh, the maximum operating power of DC will be 8 million kW, and the annual DC power transmission will be 44.62 billion kWh, of which hydropower will be 39.46 billion kWh and photovoltaic power will be 5.16 billion kWh. The power transmission during the peak season (May to November) will account for 75.3%; the abandoned power will be about 1.14 billion kWh, and the overall abandonment rate will be 2.5%.
[0101] Jinshang DC transmission curve in 2030 (hydropower 9.136 million kW, photovoltaic 4 million kW)
[0102] Table 11 Units: 10,000 kW, 100 million kWh
[0103]
[0104] 2025: With a total hydropower station capacity of 5.516 million kW and supporting photovoltaic power of 3 million kW, the maximum operating power of DC will be 6 million kW, with no abandoned power. The annual DC power transmission will be 27.31 billion kWh, of which hydropower will be 22.58 billion kWh and photovoltaic power will be 4.72 billion kWh. The power transmission during the peak season (May to November) will account for 82.9%.
[0105] Jinshang DC transmission curve in 2025 (hydropower 5.516 million kW, photovoltaic 3 million kW)
[0106] Table 12 Units: 10,000 kW, 100 million kWh
[0107]
[0108]
[0109] (4) Impact of peak load regulation of Jinshang Hydropower Station on power abandonment rate
[0110] According to the analysis, if the grid strengthening scheme is recommended, the maximum transmission capacity of Jinshang's surplus power through the Sichuan-Tibet AC interconnection channel is 1.6 million kW. Considering that Jinshang Hydropower Station is in peak operation for Sichuan power grid from July to September, the maximum transmission capacity of 1.6 million kW is considered during the peak hours of 10-12 noon and 18-20 evening. Figure 4 , by 2030, the bundled 4 million kW photovoltaic power transmission capacity will be about 81 million kWh, and the power abandonment rate will be reduced to 2.3%; Figure Figure 5 In 2030, the bundled 7 million kW PV transmission capacity will be about 88 million kWh, and the power abandonment rate will be reduced to 3.8%. The annual DC utilization hours will be reduced by about 10 hours, which has a small impact.
[0111] S16: The present invention is based on the principle of DC curve formulation, taking into account the power supply characteristics of the sending end and the load characteristics of the receiving end, and making full use of the hydropower regulation capacity. The photovoltaic power is bundled according to the power abandonment rate not exceeding 5%, and the power transmission capacity of the DC channel is fully utilized. Considering that the utilization hours of thermal power at the receiving end meet the reasonable level and the space for supporting photovoltaic power, combined with the actual utilization hours of the three major DC hydropower transmission in Province B in recent years, the DC utilization hours should not be too high or too low. The Jinshang DC utilization hours are initially planned to be 50,000-6,000 hours. The proposed analysis is shown in Table 13.
[0112] Table 13 (unit: h)
[0113]
[0114] In order to meet the needs of the receiving end as much as possible and take into account a certain number of hours of DC utilization, the present invention proposes an annual DC power transmission curve based on supporting hydropower and photovoltaic power of different scales to promote the full consumption of clean energy, no abandonment of electricity in the dry season, and less abandonment of water in the abundant season. When the final scale of hydropower complementarity is 7 million kW of supporting photovoltaic power, 400kW and 700kW of supporting photovoltaic power and Jinshang Hydropower Station will be selected in 2025 and 2030 respectively for the DC power transmission curve formulation. Combined with the above-mentioned 2025 hydropower station built 5.516 million kW, DC operation 6 million kW, with supporting photovoltaic 4 million kW, the maximum DC operating power is 6 million kW, no abandonment, and the annual DC power transmission is 28.86 billion kWh, of which hydropower power is 22.58 billion kWh, photovoltaic power is 6.28 billion kWh, and the power transmission in the abundant season (May to November) accounts for 81.4%. The Jinshang DC power transmission curve is shown in Table 14. By 2030, all hydropower stations will have a total capacity of 9.136 million kW, with supporting photovoltaic power generation of about 7 million kW, totaling 50.50 billion kWh of electricity generation. The maximum operating power of DC will be 8 million kW. By optimizing the system and curtailing power in small amounts, the annual DC transmission capacity will be 48.41 billion kWh. The transmission capacity during the peak season (May to November) will account for 78.6%, with about 2.01 billion kWh of curtailed power and an overall curtailment rate of 4.0%. The Jinshang DC transmission curve is shown in Table 15.
[0115] Table 14 (Unit: 10,000 kW, 100 million kWh)
[0116]
[0117] Table 15 (Unit: 10,000 kW, 100 million kWh)
[0118]
[0119] When the final scale of hydro-photovoltaic complementarity is 4 million kW of supporting photovoltaic power, 300kW and 400kW of supporting photovoltaic power and Jinshang Hydropower Station will be selected in 2025 and 2030 respectively for DC transmission curve formulation. Combined with the above-mentioned 2025 hydropower station built with 5.516 million kW and supporting photovoltaic power of 3 million kW, the maximum operating power of DC is 6 million kW, there is no abandoned power, and the annual DC transmission capacity is 27.31 billion kWh, of which hydropower power is 22.58 billion kWh and photovoltaic power is 4.72 billion kWh. The transmission capacity in the peak season (May to November) accounts for 82.9%. The Jinshang DC transmission curve is shown in Table 16. By 2030, when all hydropower stations are completed with a capacity of 9.136 million kW and 4 million kW of photovoltaic power, the total power generation will be 45.76 billion kWh, the maximum DC operating power will be 8 million kW, and the annual DC power transmission will be 44.62 billion kWh, of which hydropower will be 39.46 billion kWh and photovoltaic power will be 5.16 billion kWh. The power transmission during the peak season (May to November) will account for 75.3%, and the abandoned power will be about 1.14 billion kWh. The overall abandonment rate is 2.5%. The Jinshang DC transmission curve is shown in Table 17.
[0120] Table 16 (Unit: 10,000 kW, 100 million kWh)
[0121]
[0122]
[0123] Table 17 (Unit: 10,000 kW, 100 million kWh)
[0124]
[0125] S17: According to the planning requirements of the total installed capacity of Jinshang Hydropower Station in 2030 of 9.136 million kW, combined with the output characteristics of the power station, before the G1 power station was put into operation, the maximum average output of Jinshang Power Station in normal water years was 8.368 million kW when it was operated alone, and after the G1 power station was put into operation, the maximum average output of Jinshang Power Station in normal water years was 8.104 million kW when it was jointly operated. In order to ensure the reliable transmission of hydropower, the DC transmission capacity is selected to be 8 million kW. In order to meet the long-distance and large-capacity power transmission needs of Jinshang Hydropower Station and Province E, reduce line losses, and improve transmission efficiency and benefits, it is recommended to use DC transmission to transmit power from the power station.
[0126] S18: So far, the domestic power transmission engineering technology at the two voltage levels of ±500kV and ±800kV has been relatively mature and can be used as two voltage levels in the DC transmission voltage sequence. Among them, the DC system using a single 12-pulse valve group wiring module at a voltage level of ±500kV is suitable for projects with a load of about 3 million kW and a distance of less than 1,000km; the DC system using a double 12-pulse valve group series wiring module at a voltage level of ±800kV is suitable for projects with a capacity of about 8 million kW and a distance of 1,400-2,000km. Considering that the Jinshang Hydropower Base is about 1,800 to 1,900km away from Province E, with a power transmission capacity of 8 million kW, a long transmission distance, and a high power transmission capacity, it is suitable to choose a DC voltage of a high voltage level of ±800kV.
[0127] S19: The single-end scheme of the present invention recommends the use of a dual 12-pulsator series structure, and builds a ±800kV converter station in Province B or Province D with a transmission capacity of 8 million kW. The multi-end scheme of the sending end builds a converter station in Province B and Province D with a transmission capacity of 4 million kW. The two converter stations are connected in series (parallel) and sent out through a ±800kV DC line. Compared with the single-end scheme, although the total investment of the multi-end scheme is higher than that of the single-end scheme, it has the following outstanding advantages: (1) A single converter station occupies a small area and has a large range of options, which is conducive to reducing the altitude of the converter station and using mature equipment; (2) It is conducive to respectively bringing together the two north and south hydropower groups centered on the G3 and G6 hydropower stations, reducing the scale and construction difficulty of the AC supporting project. Comprehensive technical and economic comparisons recommend the multi-end scheme. Considering that the installed capacity of the supporting hydropower source at the sending end of the present invention reaches 9.136 million kW, after being respectively collected through two converter stations, the length of the line connecting the main hydropower station to the converter station is relatively short, and the system strength can meet the ±800kV, 8 million kW DC operation requirements. Therefore, the sending end system does not consider the use of flexible DC, and it is recommended to use conventional DC.
[0128] Combined with the comparison of technical solutions (Table 18), the main advantage of the parallel solution over the cascade solution is that the DC power of the two stations can be freely adjusted within the range of minimum power to rated power, with high flexibility, and the disadvantage is poor economic efficiency. However, after the hydropower is fully put into production, the power capacity of the two stations is basically the same. Under the condition of cascade hydropower joint dispatching operation, it is not easy to have a large difference in the power transmission of the two stations. Therefore, considering the comprehensive technical and economic benefits, the cascade solution is recommended.
[0129] Table 168
[0130]
[0131] S20: The current density of the domestic ±800kV DC transmission lines that have been built and are under construction is about 0.625-1.06A / mm2, and the current density of other ultra-high voltage DC transmission lines is about 0.77-1.33A / mm2. The conductors to be selected in the present invention are listed in Table 19.
[0132] Table 19
[0133]
[0134]
[0135] S21: According to the "±800kV DC Overhead Transmission Line Design Specification", the long-term overload capacity of the system can be considered as 1.1 times the rated current. The transmission capacity from Jinshang to E Province is 8 million kW, the rated current of each pole is 5000A, and the overload current of each pole is 1.1 times the rated current, that is, 5500A. The maximum allowable current carrying capacity of each pole of the conductor scheme is calculated. Under overload conditions, the maximum allowable temperature of the conductor current carrying capacity is 70℃, the ambient temperature is 40℃, the solar radiation power density is 0.1W / cm2, and the wind speed is 0.5m / s, and the conductor temperature is checked. The detailed results are shown in Table 20. It can be seen that except for the 6×800mm2 conductor, the current carrying capacity of all other conductors in the preliminary selection can meet the DC 1.1 times overload capacity requirements.
[0136] Table 20
[0137]
[0138] S22: The various losses of DC transmission lines with different cross-sections under rated transmission scale are listed in Table 21. Since the conductor corona loss is small, the resistance loss is the main part of the power loss. For the same DC scale and transmission distance, the larger the conductor cross-section, the smaller the line resistance, and the lower the voltage loss and power loss of the DC line.
[0139] Table 21
[0140]
[0141] Note: 1. The average altitude is about 4000m; 2. The length is temporarily compared as 1842km; 3. The loss comparison does not include the losses of the converter stations at both ends.
[0142] S23: The calculation parameters adopted in the present invention are: the economic service life of the project is 30 years, and the discount rate is 8%; the equipment operation and maintenance rate is 1.7%; the loss hours are 2500h, 3000h, 3500h, 4000h, 4500h, and 5000h respectively; the electricity consumption price is 0.35 yuan / kWh, 0.4 yuan / kWh, 0.45 yuan / kWh, 0.5 yuan / kWh, 0.55 yuan / kWh, and 0.6 yuan / kWh respectively.
[0143] S24: The present invention takes into account hydropower and bundled photovoltaic power, and the utilization hours are considered to be 5000-5500 hours, and the corresponding loss hours are 3560h-4460h. The current carrying capacity of 6×JL1 / G2A-1250 conductor can meet the requirements, the annual cost is optimal, and it has good adaptability.
Claims
1. A clean energy DC transmission sending-end system optimization design method, characterized by: Preliminary analysis of the power balance of the power grid source-grid-load status and development plan of the sending-end system. The analysis of power balance according to the current status and development plan of the power grid source-grid-load of the sending-end system specifically includes the following steps (S1-S12): S1: According to the production plan, determine the design research level year; the present invention preliminarily determines 2025 and 2030 as the design level years. S2: Source: Analyze the current status of the power supply structure of the sending end system; S3: Network: Analyze the current status of the power grid at the sending end; S4: Load: Analyze the current status of electricity consumption in the entire society of the sending end system; S5: Source: Analyze the power development plan of each planning level year of the sending end system; S6: Network: Analyze the power grid development plan for each planning level year of the sending end system; S7: Load: Analyze the annual power demand forecast of each planning level of the sending end system; Due to the limited coal transportation capacity and environmental protection factors, the development of thermal power in Region A is limited. The primary energy is mainly hydropower resources, and a multi-energy complementary power supply pattern is formed with many independent power sources such as solar photovoltaic power stations. Analyze the power supply planning, power transmission and reception planning and power grid planning of each planning level of the sending end system to provide data support for the subsequent power supply organization plan and power balance. S8: Analyze the power supply organization plan of the sending end system; S9: Analyze the output characteristics of each hydropower station in the sending end system when operating independently in each planned dry year and normal year; S10: Analyze the output characteristics of the sending end system in each planned dry year and normal year when each hydropower station is in joint operation; S11: Conduct power balance analysis at the sending end; S12: Analyze the power retention plan at the sending end; According to the results of power balance, the overall power supply and demand situation of each planning level is estimated, and the long-term support capacity of various adjustment methods for the power supply and demand balance of the sending-end system is taken into account. The power retention work at the sending end is done well, and the local power demand is given priority. Combined with the supply and demand situation of the sending-end system and the power demand of the receiving end, the power retention plan of the sending-end power is determined with reference to the existing retention experience. The determination of the transmission mode, transmission capacity and recommended scheme of DC transmission project specifically includes the following steps (S13-S24): S13: Do you want to bundle the water and light into a bundle and send it out? If yes, go to the next step; if no, go to S16; S14: Analyze the output characteristics of new energy power sources in the sending-end system; S15: Analyze the water-light complementary characteristics; S16: Analyze the DC power transmission curve and utilization hours; S17: Determine the transmission method and transmission capacity; S18: DC voltage level selection; S19: Technical comparison and selection of DC design schemes for sending-end converter stations; S20: Preliminary selection of DC conductor cross section; S21: Conductor current carrying capacity verification; S22: Analyze and calculate transmission losses; S23: Comparative analysis of DC conductor technologies; S24: Provide recommended DC conductor solutions.