Method for dismantling existing steel sheet pile of wharf
By inserting cutting guide piles on the side of the steel sheet pile and cutting them into sections, and then excavating soil on the side of the steel sheet pile, the problem of insufficient lifting capacity of lifting equipment in the existing technology is solved, and safer and more efficient steel sheet pile removal is achieved .
Patent Information
- Application Number
- CN202411637597.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-15
- Publication Date
- 2025-02-07
AI Technical Summary
In the prior art, when removing steel sheet piles, the lifting capacity of the lifting equipment is required to be at least greater than the sum of the self-weight of the steel sheet pile and the transverse connection structure, as well as the sum of the steel sheet pile and the transverse connection structure and the soil side friction resistance, resulting in the lifting equipment. It is easy to damage and difficult to remove steel sheet piles with a large depth.
By inserting the cutting guide pile on the side of the steel sheet pile, the first cutting device is guided to move along the axial direction of the cutting guide pile, the steel sheet pile is cut into smaller segments, and the soil is excavated on the side of the steel sheet pile to reduce the segments and soil body. The side friction resistance between them can reduce the lifting needs of lifting equipment.
It reduces the difficulty of pulling out steel sheet piles, reduces the risk of damage to lifting equipment, and improves the removal efficiency.