Large-span corridor and construction method thereof

By using a temporary support system and segmented construction methods in the long-span steel connecting corridor, the structural instability caused by the deflection of the steel connecting corridor was solved, thereby enhancing the stability of the steel beams and protecting the main structure.

CN119466131BActive Publication Date: 2026-11-24CHINA CONSTR EIGHT ENG DIV CORP LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202411573873.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-11-06
Publication Date
2026-11-24
Estimated Expiration
2044-11-06

AI Technical Summary

Technical Problem

Large-span steel connecting corridors in buildings may deflect due to their own stress and temperature changes, leading to tensile cracks or tilting, which can affect the stability of adjacent main structures.

Method used

A temporary support system, including vertical and horizontal jacks, was adopted to offset internal stress by supporting the steel beams, and the stability of the steel beams was enhanced by a segmented construction method.

Benefits of technology

It effectively prevents the steel connecting corridor from deflecting, avoids tilting deformation and column cracking of adjacent main structural columns, and improves the stability of the connecting corridor steel beams.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119466131B_ABST
    Figure CN119466131B_ABST
Patent Text Reader

Abstract

This invention relates to a long-span connecting corridor and its construction method. The long-span connecting corridor is located between existing structures on both sides. The corridor includes: a pair of frame beams, with the pair of frame beams respectively connected to the existing structures on both sides; at least two X-direction steel beams connected between the pair of frame beams; and Y-direction steel beams connected between adjacent X-direction steel beams. The bottom of the long-span connecting corridor is supported by several temporary support components, each including: a base installed on the road surface below the corridor; and vertical jacks installed on top of the bases for supporting the corridor. This invention uses a temporary support system equipped with hydraulic jacks to support the beams of the corridor, thereby offsetting the internal stress of the steel beams and preventing the corridor from deflecting, which could lead to tilting deformation and cracking of adjacent main structural columns.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of building construction, and specifically to a long-span connecting corridor and its construction method. Background Technology

[0002] With the rapid development of my country's economy and society, the scale of large-scale commercial complexes is increasing day by day. To meet the requirements of modern commercial functions, the connecting corridor structure in super high-rise buildings is widely used. In large-scale commercial steel structure connecting corridor projects, rigid connection is preferred to strengthen the connection between the steel corridor and the main structure on both sides and the overall connectivity. However, for large-span steel corridors with steel connections at both ends of the building, the main beam of the steel corridor often deflects due to its own stress and temperature changes, which can lead to tensile cracking or tilting. Summary of the Invention

[0003] To address the aforementioned problems, this invention provides a long-span connecting corridor and its construction method, which can prevent the steel connecting corridor from deflecting downwards, thereby preventing adjacent main structural columns from tilting, deforming, or cracking.

[0004] A long-span connecting corridor is located between existing structures on both sides. The long-span connecting corridor includes: a pair of frame beams, which are respectively connected to the existing structures on both sides; at least two X-direction steel beams connected between the pair of frame beams; and Y-direction steel beams connected between adjacent X-direction steel beams. The bottom of the long-span connecting corridor is supported by several temporary support members, which include: a base set on the road surface below the long-span connecting corridor; and a vertical jack set on top of the base for supporting the long-span connecting corridor.

[0005] A further improvement of the present invention is that the base includes: a roadbed plate disposed on the road surface; a plurality of tower crane standard sections fixed to the upper surface of the roadbed plate, the plurality of tower crane standard sections being stacked together along the height direction, and the vertical jack being disposed on the top of the uppermost tower crane standard section.

[0006] A further improvement of the present invention is that the large-span connecting corridor is a multi-layer connecting corridor structure composed of multiple large-span connecting corridor bodies spliced ​​layer by layer. Each layer of the large-span connecting corridor body includes a pair of frame beams, at least two X-direction steel beams connected between the pair of frame beams, and Y-direction steel beams connected between adjacent X-direction steel beams. Z-direction steel columns are connected between the X-direction steel beams of adjacent layers of the large-span connecting corridor bodies. The temporary support is only supported at the bottom of the X-direction steel beams of the bottom layer of the large-span connecting corridor body.

[0007] A further improvement of the present invention is that an expansion joint is provided between the frame beam on one side and the existing structure.

[0008] A further improvement of the present invention is that each of the X-direction steel beams is composed of at least two connected segments, and the bottom of the connection between each pair of adjacent X-direction steel beam segments is supported by the temporary support member.

[0009] A further improvement of the present invention is that a horizontal jack for reinforcing splicing is connected between each two adjacent X-direction steel beam segments.

[0010] A further improvement of the present invention is that it includes the following steps:

[0011] S1. Several temporary support members are installed on the road surface below the large-span connecting corridor, corresponding to the design position of the X-direction steel beam and the span of the connecting corridor;

[0012] S2. Frame beams are respectively provided on opposite sides of the existing structures on both sides, and frame columns are provided at the bottom of the frame beams to support the frame beams;

[0013] S3. Connect the two ends of each X-direction steel beam to the frame beams on both sides respectively, support the X-direction steel beams on the corresponding temporary support members, and fix the Y-direction steel beams between adjacent X-direction steel beams.

[0014] S4. After the entire long-span connecting corridor is installed and settled and stabilized, the temporary support components are removed.

[0015] A further improvement of the present invention is that the large-span connecting corridor is a multi-layer connecting corridor structure composed of multiple large-span connecting corridor bodies spliced ​​layer by layer. When constructing the multi-layer connecting corridor structure, Z-direction steel columns are constructed on each X-direction steel beam, and the second layer of the large-span connecting corridor body is constructed with the Z-direction steel columns as supports. This step is repeated until the construction of the multi-layer connecting corridor structure is completed.

[0016] A further improvement of the present invention is that, during the construction of the X-direction steel beam layer by layer, if the X-direction steel beam of the first layer deflects downwards, the vertical jack can be raised to prevent further deflection.

[0017] A further improvement of the present invention is that, in performing step S3, the X-direction steel beam is divided into multiple segments. During segmented construction, the first end of the first X-direction steel beam segment is fixed to the frame beam on one side, and the second end is connected to the first temporary support. The first end of the second X-direction steel beam segment is connected to the second end of the first X-direction steel beam segment, and the second end of the second X-direction steel beam segment is connected to the second temporary support, until the second end of the last X-direction steel beam segment is fixed to the frame beam on the other side to form the X-direction steel beam.

[0018] This invention supports the beams of the connecting corridor by setting up a temporary support system equipped with hydraulic jacks to offset the internal stress of the steel beams, thereby preventing the steel connecting corridor from deflecting and causing the adjacent main structural columns to tilt, deform, or crack. Furthermore, the stability of the steel beams of the connecting corridor is enhanced by using a segmented construction method. Attached Figure Description

[0019] Figure 1 This is a schematic diagram of the planar structure of the present invention;

[0020] Figure 2 for Figure 1 A magnified view of a section at point A in the middle;

[0021] Figure 3 This is a schematic diagram of the facade structure of a long-span connecting corridor;

[0022] Figure 4 for Figure 3 A magnified view of a section at point B in the middle;

[0023] Figure 5 for Figure 3 A magnified view of a section at point C;

[0024] Figure 6 This is a structural schematic diagram of the large-span connecting corridor during construction of the present invention;

[0025] Figure 7 This is a schematic diagram of the temporary support structure of the present invention;

[0026] Figure 8 Schematic diagram of the temporary support structure after deflection

[0027] Figure 9 This is a side view of the temporary support structure after the horizontal jack has been installed.

[0028] Figure 10 Front view of the temporary support structure after the horizontal jack has been installed;

[0029] Figure 11 This is a schematic diagram of the construction of the first X-direction steel beam in the construction of the large-span connecting corridor of the present invention;

[0030] Figure 12 This is a schematic diagram of the construction of the second X-direction steel beam in the large-span connecting corridor of the present invention;

[0031] Figure 13 This is a plan view of the connection node between the X-direction steel beam and the frame beam.

[0032] Figure 14 This is a schematic elevation view of the connection node between the X-direction steel beam and the frame beam.

[0033] In the diagram: 1. X-direction steel beam; 11. First X-direction steel beam segment; 12. Second X-direction steel beam segment; 13. Third X-direction steel beam segment; 14. Fourth X-direction steel beam segment; 2. Z-direction steel column; 3. Frame beam; 4. Y-direction steel beam; 5. Temporary support component; 51. Tower crane standard section; 52. Roadbed plate; 53. Vertical jack; 54. Support column; 55. High-strength bolt; 56. Steel structure; 57. First additional steel plate; 58. Horizontal jack; 59. Positioning plate; 510. Auxiliary steel plate; 6. Expansion joint; 7. Frame column; 8. Diagonal brace; 9. Steel column; 10. Road surface; 15. Truck crane; 16. Cantilever structure; 17. Connection node; 18. Steel beam pre-construction section; 19. Second additional steel plate. Detailed Implementation

[0034] The technical solutions of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention.

[0035] like Figures 1 to 14 As shown, the long-span connecting corridor includes: a pair of frame beams 3, and an existing structure on both sides of the pair of frame beams 3 respectively; at least two X-direction steel beams 1 connected between the pair of frame beams 3; Y-direction steel beams 4 connected between adjacent X-direction steel beams 1; the bottom of the long-span connecting corridor is supported by several temporary support members 5, the temporary support members 5 including: a base set on the road surface below the long-span connecting corridor; and a vertical jack 53 set on the top of the base for supporting the long-span connecting corridor.

[0036] like Figures 7-8 As shown, the base includes: a roadbed 52 disposed on the road surface 10; a plurality of tower crane standard sections 51 disposed on the upper surface of the roadbed 52, the plurality of tower crane standard sections 51 being stacked together along the height direction, and a vertical jack 53 being placed on the top of the uppermost tower crane standard section 51.

[0037] Better, such as Figures 7-8 As shown in this embodiment, the top of the uppermost tower crane standard section 51 is also provided with several support columns 54. The support columns 54 are located around the vertical jack 53 and together with the vertical jack 53 support the X-direction steel beam 1.

[0038] Better, such as Figures 7-8 As shown, this embodiment uses a standard tower crane section 51. The appropriate number of standard tower crane sections 51 can be selected according to the construction height of the long-span corridor. When the standard tower crane sections 51 are stacked to a height-to-width ratio > 3, anti-overturning measures need to be added, such as adding diagonal supports or steel wire rope ties.

[0039] Better, such as Figures 7-8 As shown, in this embodiment, a steel structure 56 is fixed above the standard section of the tower crane, and the vertical jack 53 and the support column 54 are located on the steel structure 56.

[0040] Better, such as Figures 7-8 As shown, the steel structure 56 is connected to the top surface of the tower crane standard section 51 by high-strength bolts 55.

[0041] like Figure 1 , Figure 3 As shown, there are multiple large-span connecting corridor bodies. The large-span connecting corridor is a multi-layer connecting corridor structure formed by splicing multiple layers of connecting corridor bodies one by one. The large-span connecting corridor bodies of adjacent layers are connected by Z-direction steel columns 2. The top of the Z-direction steel column 2 is connected to the X-direction steel beam 1 of the upper layer, and the bottom is connected to the X-direction steel beam 1 of the lower layer. The temporary support 5 is supported at the bottom of the bottom X-direction steel beam 1.

[0042] Preferably, the X-direction steel beam in this embodiment is a box girder.

[0043] Better, such as Figure 3 As shown, in this embodiment, a diagonal brace 8 connects the X-direction steel beam of the first layer and the X-direction steel beam of the second layer to further reinforce the structure.

[0044] Better, such as Figure 3 As shown, in this embodiment, the frame column 7 is supported by the frame beam 3, and a steel column 9 is fixed at the bottom of the frame column 7. The steel column 9 extends into the ground to further reinforce the frame column 7.

[0045] Better, such as Figure 1 As shown, in this embodiment, the Y-direction steel beam extends outward from the X-direction steel beam to form a cantilever structure 16.

[0046] like Figure 1 , Figure 3 As shown, an expansion joint 6 is reserved between the frame beam 3 on one side and the existing structure, and the frame beam 3 on the other side is fixedly connected to the existing structure. The frame column 7 supports the bottom of the frame beam 3.

[0047] like Figure 11 , 12 As shown, an X-direction steel beam 1 is divided into at least two segments, and the temporary support 5 is used to support the connection between two adjacent X-direction steel beam segments.

[0048] Preferably, in this embodiment, an X-direction steel beam 1 is divided into two segments: the first X-direction steel beam 1 of the first layer is divided into a first X-direction steel beam segment 11 and a second X-direction steel beam segment 12, and the second X-direction steel beam 1 of the first layer is divided into a third X-direction steel beam segment 13 and a fourth X-direction steel beam segment 14.

[0049] Preferably, the segments of the upper and lower X-direction steel beams should be staggered to improve the overall structural stability.

[0050] like Figure 9 , Figure 10As shown, at the connection of two adjacent X-direction steel beam segments, there is an outwardly cantilevered auxiliary steel plate 510. The direction of the auxiliary steel plate 510 is perpendicular to the length direction of the X-direction steel beam 1. A horizontal jack 58 is provided between the auxiliary steel plates 510 of two adjacent X-direction steel beam segments 1. By setting the horizontal jack 58, the connection of the X-direction steel beam segments is further reinforced.

[0051] Preferably, in this embodiment, the horizontal jacks 58 are installed on the top and side surfaces of the connection between adjacent X-direction steel beam segments. The horizontal jacks 58 located on the side surfaces can have anti-fall steel plates welded to the side surfaces of the X-direction steel beams 1 to prevent the jacks from falling. The distance between their end faces and the ends of the steel beams is not less than half the size of the hydraulic jacks themselves. All jacks must simultaneously provide initial prestress according to calculations. During the hoisting, welding, and temperature changes of the steel beams, pre-jacking pressure must be provided in real time to eliminate the internal stress of the steel beams themselves. For large-span steel corridor structures with three or more floors, it is only necessary to install the horizontal jacks 58 on the top and side surfaces of the steel beam segments on both sides of the connection to counteract the horizontal thrust of the X-direction steel beams 1 themselves, preventing the steel corridor from deflecting downwards and causing the adjacent main structural columns to tilt, deform, or crack. Once the steel beams of this floor are permanently fixedly connected, the horizontal jacks 58 can be removed.

[0052] Preferably, in this embodiment, both the vertical jack 53 and the horizontal jack 58 are hydraulic jacks. The hydraulic jacks are connected to an external hydraulic station (including a prestressed oil pump) to provide prestress for supplementation, thereby compensating for the deflection of the steel beam through the lifting and tensioning process, and achieving the effect of overall force balance.

[0053] Preferably, in this embodiment, the auxiliary steel plate 510 is provided with lifting holes.

[0054] Better, such as Figure 9 , Figure 10 As shown, in this embodiment, a positioning code plate 59 is welded at the connection between the two steel beam segments. One side of the positioning code plate 59 is fixed to one steel beam segment, and the other side is fixed to the other steel beam segment to reinforce the connection between adjacent steel beam segments.

[0055] Better, such as Figure 2 As shown, in this embodiment, the frame beam 3 is provided with several connection nodes 17, and the X-direction steel beam 1 is connected to the connection nodes 17.

[0056] Better, such as Figure 13 , 14 As shown, a pre-construction section 18 of steel beam is provided at the connection node 17 in the direction of X-direction steel beam 1. The two ends of X-direction steel beam 1 are connected to the pre-construction sections 18 on both sides. A second additional steel plate 19 is welded at the connection between the pre-construction section 18 and X-direction steel beam 1.

[0057] like Figures 1 to 14As shown, the present invention provides a construction method for a long-span connecting corridor, comprising the following steps:

[0058] S1. On the road surface below the long-span connecting corridor, several temporary support components 5 are set at the design position of the X-direction steel beam 1 and the span of the connecting corridor.

[0059] S2. Frame beams 3 are respectively provided on the opposite side of the existing structure on both sides, and frame columns 7 are provided at the bottom of the frame beams 3 to support the frame beams 3.

[0060] S3. Connect the two ends of at least two X-direction steel beams 1 to the frame beams 3 on both sides respectively, support the X-direction steel beams 1 on the temporary support 5, and fix several Y-direction steel beams 4 between adjacent X-direction steel beams 1.

[0061] S4. After the entire large-span connecting corridor is installed and settled and stabilized, remove the temporary support components 5.

[0062] Preferably, in this embodiment, a truck crane 15 is used for lifting and construction.

[0063] Preferably, the large-span connecting corridor is a multi-layer connecting corridor structure formed by splicing together multiple layers of large-span connecting corridor bodies. When constructing the multi-layer connecting corridor structure, several Z-direction steel columns 2 are constructed on each X-direction steel beam 1, and the second layer of large-span connecting corridor body is constructed with the Z-direction steel columns 2 as supports. This step is repeated until the construction of the multi-layer connecting corridor structure is completed.

[0064] Preferably, the multi-layer connecting corridor structure in this embodiment has multiple layers of large-span connecting corridor bodies, and each layer of large-span connecting corridor body has two X-direction steel beams 1. During construction, the truck crane 15 is moved between the two X-direction steel beams 1, and the first X-direction steel beam of the first layer is constructed first. Then, a Z-direction steel column 2 is constructed on the first X-direction steel beam, and the first X-direction steel beam of the second layer is constructed directly above the first X-direction steel beam of the first layer, using the Z-direction steel column 2 as support. This step is repeated until the first X-direction steel beam of each layer is constructed. At this point, the direction of the truck crane is turned around, and the construction of the second X-direction steel beam of each layer is repeated. The first X-direction steel beam and the second X-direction steel beam of each layer are connected by a Y-direction steel beam. Construction is carried out in this order, first completing the construction of the X-direction steel beams on one side, and then constructing the X-direction steel beams on the other side. This reduces the number of times the truck crane 15 moves and turns back and forth, and speeds up the construction progress.

[0065] like Figure 8 As shown, during the construction of the X-direction steel beam 1 layer by layer, if the X-direction steel beam 1 of the first layer deflects downwards during the process, the vertical jack 53 can be raised to prevent the deflection.

[0066] Better, such as Figure 8As shown, in this embodiment, after the vertical jack 53 is lifted, in order to ensure the supporting effect of the support column 54, a first additional steel plate 57 is placed at the bottom of the support column 54.

[0067] like Figure 11 , 12 As shown, when performing step S3, the X-direction steel beam 1 can be divided into multiple segments. In this embodiment, an X-direction steel beam 1 is divided into two segments. During segmented construction, the first end of the first X-direction steel beam segment 11 is fixed to the frame beam 3 on one side, and the second end is connected to the first temporary support 5. The first end of the second X-direction steel beam segment 12 is connected to the second end of the first X-direction steel beam segment 11, and the second end of the second X-direction steel beam segment 12 is connected to the second temporary support 5, until the second end of the last steel beam segment is fixed to the frame beam 3 on the other side to form the X-direction steel beam 1.

[0068] Preferably, in this embodiment, during construction, after the main body of the large-span connecting corridor on the first floor is hoisted, horizontal and vertical positioning calibration is carried out. After calibration, permanent welding connection is carried out. The connection between the upper and lower floors is carried out after the horizontal and vertical components of the upper floor are calibrated.

[0069] like Figures 1 to 14 As shown, when performing step S2, an expansion joint 6 is opened between the frame beam 3 on one side and the existing structure to provide space for the horizontal expansion and contraction of the large-span corridor, preventing structural cracks or damage when it expands and contracts due to climate temperature changes.

[0070] Preferably, in this embodiment, during construction, the steel connecting corridor constructed in winter or when the temperature is low should have the frame columns 7 slightly tilted toward the connecting corridor side, while those constructed in summer or when the temperature is high should be slightly tilted away from the connecting corridor side.

[0071] Preferably, in this embodiment, the connecting node 17 is securely connected to the X-direction steel beam 1 via a V-shaped weld. Considering that the X-direction steel beam 1 is rigidly connected in both directions, its own stress distribution is greater than that of hinged or sliding connections. To prevent X-direction tensile cracking at the segmented connection points of the X-direction steel beam 1, its segmented positions need to be optimized. This patent optimizes the connection method at the segmented positions of the steel box girder, optimizes and adjusts the pre-construction section 18 of the steel beam, adjusts the size of the added connecting steel plate, and welds it to the end of the X-direction steel beam 1 via a corner joint. The X-direction steel beam 1 and the pre-construction section 18 of the steel beam are directly and securely welded via a Y-shaped weld, thereby reducing one welding seam and eliminating the risk of Z-direction tensile cracking at the segmented positions.

[0072] Finally, it should be noted that the above are merely preferred embodiments of the present invention and are not intended to limit the present invention. Although the present invention has been described in detail with reference to the foregoing embodiments, those skilled in the art can still modify the technical solutions described in the foregoing embodiments or make equivalent substitutions for some of the technical features. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the protection scope of the present invention.

Claims

1. A long-span connecting corridor, situated between existing structures on both sides, characterized in that, The long-span connecting corridor includes: a pair of frame beams, existing structures on both sides of the pair of frame beams; at least two X-direction steel beams connected between the pair of frame beams; and Y-direction steel beams connected between adjacent X-direction steel beams. The bottom of the long-span connecting corridor is supported by several temporary support members, which include: a base set on the road surface below the long-span connecting corridor; and a vertical jack set on top of the base for supporting the long-span connecting corridor. Each X-direction steel beam is composed of at least two connected segments, and the bottom of the connection between each pair of adjacent X-direction steel beam segments is supported by the temporary support member. Each pair of adjacent X-direction steel beam segments is also connected by horizontal jacks for reinforcement and splicing. The horizontal jack provides initial prestress based on calculations, and provides pre-jacking pressure in real time during the steel beam hoisting, welding and temperature changes to eliminate the internal stress of the X-direction steel beam itself.

2. The long-span connecting corridor as described in claim 1, characterized in that, The base includes: a roadbed plate disposed on the road surface; a plurality of tower crane standard sections fixed to the upper surface of the roadbed plate, the plurality of tower crane standard sections being stacked together along the height direction to form a whole, and the vertical jack being disposed on the top of the uppermost tower crane standard section.

3. The long-span connecting corridor as described in claim 1, characterized in that, The large-span connecting corridor is a multi-layer connecting corridor structure composed of multiple large-span connecting corridor bodies spliced ​​layer by layer. Each layer of the large-span connecting corridor body includes a pair of frame beams, at least two X-direction steel beams connected between the pair of frame beams, and Y-direction steel beams connected between adjacent X-direction steel beams. Z-direction steel columns are connected between the X-direction steel beams of adjacent layers of the large-span connecting corridor body. The temporary support is only supported at the bottom of the X-direction steel beams of the bottom layer of the large-span connecting corridor body.

4. The long-span connecting corridor as described in claim 1, characterized in that, An expansion joint is provided between the frame beam on one side and the existing structure.

5. A construction method for a long-span connecting corridor as described in any one of claims 1 to 4, characterized in that, Includes the following steps: S1. Several temporary support members are installed on the road surface below the large-span connecting corridor, corresponding to the design position of the X-direction steel beam and the span of the connecting corridor; S2. Frame beams are respectively provided on opposite sides of the existing structures on both sides, and frame columns are provided at the bottom of the frame beams to support the frame beams; S3. Connect the two ends of each X-direction steel beam to the frame beams on both sides respectively, support the X-direction steel beams on the corresponding temporary support members, and fix the Y-direction steel beams between each adjacent X-direction steel beams. S4. After the entire long-span connecting corridor is installed and settled and stabilized, the temporary support components are removed.

6. The construction method for a long-span connecting corridor as described in claim 5, characterized in that, The large-span connecting corridor is a multi-layer connecting corridor structure composed of multiple large-span connecting corridor bodies spliced ​​layer by layer. When constructing the multi-layer connecting corridor structure, Z-direction steel columns are constructed on each X-direction steel beam, and the second layer of the large-span connecting corridor body is constructed with the Z-direction steel columns as supports. This step is repeated until the construction of the multi-layer connecting corridor structure is completed.

7. The construction method for a long-span connecting corridor as described in claim 5, characterized in that, During the construction of the X-direction steel beam layer by layer, if the X-direction steel beam of the first layer deflects downwards, the vertical jack can be raised to prevent further deflection.

8. The construction method for a long-span connecting corridor as described in claim 5, characterized in that, When performing step S3, the X-direction steel beam is divided into multiple segments. During segmented construction, the first end of the first segment of the X-direction steel beam is fixed to the frame beam on one side, and the second end is connected to the first temporary support. The first end of the second segment of the X-direction steel beam is connected to the second end of the first segment of the X-direction steel beam, and the second end of the second segment of the X-direction steel beam is connected to the second temporary support, until the second end of the last segment of the X-direction steel beam is fixed to the frame beam on the other side to form the X-direction steel beam.

Citation Information

Patent Citations

  • Fabricated corridor, corridor end connecting structure and construction method

    CN117145043A

  • Method for integral staggered lifting and horizontal sliding of corridor steel structure

    CN118167049A

  • Overweight steel truss girder supporting jig frame and construction method thereof

    CN118361138A