A replacement device suitable for slope-free embankment construction and a construction method thereof

By combining foamed concrete retaining walls and lightweight replacement technology with vertical wall construction methods, the problem of insufficient foundation bearing capacity in deep, ultra-soft soil areas has been solved, resulting in reduced construction costs and time, and improved road stability and environmental friendliness.

CN119531206BActive Publication Date: 2026-11-24ANHUI HIGHWAY BRIDGE ENG CO LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202411880757.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-12-19
Publication Date
2026-11-24
Estimated Expiration
2044-12-19

AI Technical Summary

Technical Problem

In existing embankment construction projects without slopes, the foundation bearing capacity in deep, ultra-soft soil areas is poor, and the area of ​​non-renewable land resources used is too large, resulting in high construction costs, long construction periods, and serious environmental damage.

Method used

By employing foamed concrete retaining walls and lightweight replacement technology, combined with the straight-wall construction method, the use of foamed concrete retaining walls reduces the bearing capacity requirements of the foundation. By replacing soft soil with lightweight materials, the subgrade and top layer of steel wire mesh are laid simultaneously, achieving synchronous construction and reducing construction costs and time.

Benefits of technology

It effectively solved the problem of differential settlement of roadbed in soft soil sections, improved the service life and overall stability of the road, reduced construction costs, met the requirements of environmental protection and sustainable development, shortened the construction period, and made reasonable use of land resources.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119531206B_ABST
    Figure CN119531206B_ABST
Patent Text Reader

Abstract

This invention discloses a replacement device and its construction method suitable for slope-free embankment construction, belonging to the field of replacement technology for slope-free embankment construction. The method includes the following steps: S1, preloading of the original embankment; S2, excavation of the slope and foamed concrete stepped trench; S3, construction of concrete protective panels; S4, angle steel connection; S5, foamed concrete construction; S6, installation of pavement structure layers and accessories. This invention employs lightweight replacement technology and a straight-wall retaining wall design, effectively solving the problems of differential settlement of the subgrade in soft soil sections and the large land area occupied by road slopes, thereby improving the service life of the road and reducing construction costs. Simultaneously, the arrangement of wire mesh in the subgrade and top layer improves the overall stability of the subgrade. The foamed concrete can be precast or cast-in-place, and the side wall protective panels are constructed simultaneously with the foamed concrete. The pavement structure and replacement layer can also be constructed simultaneously, significantly improving construction efficiency and enabling rapid and efficient treatment of soft soil subgrades, resulting in good economic benefits.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of backfilling technology for slopeless embankment construction, and particularly to a backfilling device and its construction method suitable for slopeless embankment construction. Background Technology

[0002] The slopeless embankment construction replacement technology refers to the process of excavating a certain range of soft soil layers not too deep below the foundation in the construction of a slopeless embankment, and then filling it in layers with a hard, high-strength, stable, and erosion-resistant material. At the same time, manual or mechanical methods are used to compact, tam, and vibrate the layers to achieve the required density, thereby forming a good artificial foundation.

[0003] However, existing embankment replacement construction in soft soil areas suffers from frequent retaining wall collapses due to the low bearing capacity of the subgrade. Furthermore, it's difficult to meet the bearing capacity requirements of conventional gravity masonry retaining walls during construction. If reinforced concrete retaining walls are used, preloading is required before construction, which not only prevents synchronization with subgrade filling but also introduces numerous problems, incurs new costs, and extends the construction period. Moreover, given the current scarcity of land resources, conventional embankment construction using slope excavation inevitably occupies a large amount of farmland. Simultaneously, slope excavation damages the original vegetation cover, leading to extensive secondary bare land and severe soil erosion. Furthermore, soft soil areas are characterized by dense water networks, which may prevent meeting the required slope due to site limitations.

[0004] There are already relevant invention patents concerning the replacement of roadbed construction, as detailed below: Chinese Patent Application No. CN109322224B, entitled "A Construction Method for Roadbed Replacement," discloses a construction method for roadbed replacement comprising the following steps: S1, milling the old road, obtaining asphalt mixture and waste material containing lime and fly ash mixture after milling; the asphalt mixture is discarded, and the lime and fly ash mixture is used as filler material for optimum moisture content testing, and then transported to the roadbed to be replaced; S2, paving, spreading the filler material obtained in step S1 in layers on the soil roadbed; after the lower layer is paved, the surface of the lower layer is moistened with water before the upper layer is paved; S3, compaction, compaction proceeding from both sides to the center until no obvious wheel tracks are visible and the compaction degree meets the requirements; S4, inspection, measuring the compaction coefficient and subgrade coefficient K30 of the compacted roadbed to check the pass rate. The advantage of this invention is that it can reuse the waste material after milling the old road, achieving environmental protection, energy saving, and reduced investment costs.

[0005] However, while the aforementioned existing patents can achieve the effects of environmental protection, energy conservation, and reduced investment costs, they still have the problems of poor foundation bearing capacity in deep, ultra-soft soil areas and excessive use of non-renewable land resources. Summary of the Invention

[0006] The purpose of this application is to provide a replacement device and its construction method suitable for embankment construction without slope, in order to solve the problems of poor foundation bearing capacity in existing deep and soft soil areas and excessive use of non-renewable land resources.

[0007] This invention utilizes foamed concrete retaining walls, effectively reducing the requirements on foundation bearing capacity. It also replaces traditional slope construction with straight-wall construction, making rational use of land and lowering costs. This addresses the issue of poor foundation bearing capacity in deep, soft soil areas while conserving non-renewable land resources, promoting sustainable development, rationally utilizing land, reducing costs, and balancing the short-term needs and long-term development of highway construction with the production and daily lives of people along the route, thus achieving resource conservation. Based on engineering projects and focusing on the technology, a slope-free embankment replacement construction technology has been developed in conjunction with specific construction projects.

[0008] To achieve the above objectives, the present invention adopts the following technical solution: A replacement device suitable for embankment construction without slope includes a control box and a storage box. A T-shaped telescopic rod is fixedly connected to the control box near the storage box. Both ends of the T-shaped telescopic rod away from the control box are slidably connected to driving rods. A bidirectional motor is fixedly connected to the driving rods on their closest sides. A connecting wire is fixedly connected to the bidirectional motor near the control box, and the connecting wire is electrically connected to the inside of the control box on its side away from the bidirectional motor. A shovel frame is fixedly connected to the end of each driving rod away from the control box. Two storage boxes are provided, each fixedly connected to the top of one of the two shovel frames. This allows for the removal of the original soil layer.

[0009] As a further improvement of the present invention, each storage box has a sliding groove inside its top, and a sliding plate is slidably connected inside each sliding groove. A handle is fixedly connected to the top of each sliding plate. Each storage box has an inner frame inside, and a fixing tube is fixedly connected to the inner wall of each inner frame. A spring is fixedly connected inside each fixing tube. A pressing block is fixedly connected to the side of each spring near its outer edge. A pulling line is fixedly connected to the side of each pressing block. The pulling line is positioned in a groove in the storage box that completely fits the pulling line. A baffle plate is fixedly connected to the bottom end of each pulling line. A discharge port is provided through the storage box near the baffle plate. Replacement materials can be filled in this way.

[0010] A construction method applicable to slope-free embankment construction, specifically including: S1, preloading of the original embankment; S2, excavation of slope and foamed concrete stepped trench; S3, Concrete Protective Panel Construction: Includes the foundation construction of the concrete protective panel and the construction of the concrete protective panel; S4, Angle steel connection: This includes the installation of angle steel and the connection between the angle steel and the protective panel; S5, Foamed Concrete Construction: First, lay the bottom layer of wire mesh, then pour the foamed concrete in layers. After pouring, lay the top layer of wire mesh, and finally cure the foamed concrete. S6, Road surface structure layer and accessory installation: First, grout is injected into the pre-drilled holes in the concrete protective panel, then the guardrail base is made, and finally the guardrail is installed.

[0011] As a further improvement of the present invention, the original embankment preloading is carried out using a road roller with a vibration pressure of 40t or more. During the compaction process, water is sprinkled to keep the soil moist. If the soil becomes too wet and springy, it is dug up, dried, and replaced with new soil or treated to improve the condition. This can prevent the replacement soil from being too dry or too wet.

[0012] As a further improvement of the present invention, in step S2, the stepped trench is excavated layer by layer from the upper opening line according to the slope ratio shown in the drawing. Every 5m of excavation is measured and verified using a GPS instrument. This ensures the accuracy of the slope ratio and avoids fluctuations in the slope ratio.

[0013] As a further improvement of the present invention, the construction of the concrete protective panel foundation involves constructing a concrete base, which is plain concrete. The construction process includes removing silt and debris from the foundation soil, and incorporating waterproofing and drainage measures. A groove for the concrete protective panel is pre-reserved in the base during concrete pouring. A crushed stone leveling layer is constructed on the inner side of the base. Short reinforcing bars are pre-reserved at the ends of the protective panel. A grouting hole is located at the top of the concrete protective panel, and two embedded rings are symmetrically arranged outside the grouting hole, with connecting reinforcing bars on the two embedded rings. This ensures that the concrete meets the design drawings and quality standards.

[0014] As a further improvement of the present invention, the angle steel is pressed into the soil, and a fixing rod is bent and hung on the connecting steel bar. The fixing rod is connected to the angle steel in a V-shape, and the connection between the fixing rod and the angle steel is welded. The weld height is flush with the steel plate, and the weld length and interval are uniform when intermittent welding is used. This ensures the stability and consistency of welding quality, reduces the amount of cutting and splicing work on the construction site, and further improves construction efficiency.

[0015] As a further improvement of the present invention, the cast-in-place concrete formwork is installed according to the design requirements. Before pouring the aerated concrete, pre-drilled holes for tie rods are arranged. The surface of the tubular material is coated with a release agent and passed through the pre-drilled holes to the cast-in-place concrete formwork. After passing through, the aerated concrete is poured. After pouring one layer, a bottom layer of wire mesh is placed and the elevation is set. After the elevation is set, another bottom layer of wire mesh is laid. After laying, the foamed concrete continues to be poured. The layer thickness of the foamed concrete is controlled between 300mm and 800mm. After the foamed concrete has initially set, it is directly covered on the surface of the concrete. After covering, water curing is carried out. After the pouring operation reaches the elevation for placing the top layer of wire mesh, the top layer of wire mesh is laid. The foamed concrete is poured to the design elevation. After the top surface of the foamed concrete is poured to the design height, an impermeable geomembrane is laid. The impermeable geomembrane is used to moisturize and cure the foamed concrete. This can reduce the evaporation of water from the concrete, keep the concrete moist, and help improve the strength and durability of the concrete.

[0016] As a further improvement of the present invention, after the foamed concrete is poured, cement mortar is injected into the reserved holes of the concrete protective panel. The guardrail base is fabricated by pre-embedding rods in the road structure layer. A guardrail base template is erected on the upper part of the pre-embedding rods. The bottom of the template is fixed to the concrete protective panel. The template is fixed to the middle vertical template with tie rods. The middle template is fixed to the end templates with struts. Columns are set inside the guardrail sleeve. The columns are all embedded vertically according to the drawings and alignment. A water-blocking strip is set on the upper part of the guardrail base. Anti-blocking blocks are installed at the ends of the columns. The connecting bolts are used to install and fix the corrugated beam. The guardrail bolts are installed on the columns. This fills the reserved holes, enhances the adhesion between the concrete protective panel and the foamed concrete, thereby improving the stability and durability of the overall structure.

[0017] Compared with the prior art, the beneficial effects of this invention are as follows: This invention employs lightweight replacement technology and a straight retaining wall design, effectively solving the problems of differential settlement in soft soil sections and the large land area occupied by road slopes, thereby extending the service life of the road and reducing construction costs. Simultaneously, the placement of wire mesh in the subgrade and top layer enhances the overall stability of the subgrade. Foamed concrete can be precast or cast-in-place, and the sidewall protection panels are constructed simultaneously with the foamed concrete. The pavement structure and replacement layer can also be constructed concurrently, significantly improving construction efficiency and saving approximately 12% to 16% in overall cost. This allows for rapid and efficient treatment of soft soil subgrades, offering significant economic benefits. The lightweight replacement technology effectively reduces subgrade compression deformation by replacing soft soil with lightweight materials, thus solving the problem of differential settlement in soft soil sections. The simultaneous construction of wire mesh, foamed concrete, and sidewall protection panels further improves construction efficiency and reduces costs.

[0018] This invention proposes a method for lightweight replacement of soft soil subgrades. After preloading, the slope is excavated to form a stepped contact surface with the quarry subgrade, and then replaced with foamed concrete to form a lightweight retaining wall. The density of the foamed concrete does not exceed 450 kg / m³. 3 When the compressive strength is not less than 200 kPa, there is no significant differential settlement in the soft soil subgrade. Angle steel is pre-embedded inside the foamed concrete, and it is fixed to the protective panel on the outside of the retaining wall by tie rods and V-shaped welded connections of the angle steel, forming a straight retaining wall. This eliminates the need for slope protection, making efficient use of land and reducing costs. Wire mesh is arranged in the subgrade and top layer to improve the overall stability of the subgrade. Foamed concrete can be precast or cast-in-place; the side wall protective panels are constructed simultaneously with the foamed concrete, and the pavement structure and replacement layer can also be constructed simultaneously, significantly improving construction efficiency and shortening the construction period. Using foamed concrete with a density not exceeding 450 kg / m³ and a compressive strength not less than 200 kPa for replacement can significantly reduce differential settlement in the soft soil subgrade, ensuring the stability and safety of the subgrade. Furthermore, arranging wire mesh in the subgrade and top layer can significantly improve the overall stability and deformation resistance of the subgrade, further ensuring the safety and durability of the road. As a lightweight, high-strength material, foamed concrete has a relatively small environmental impact during its production process and is easily recyclable, meeting the requirements of environmental protection and sustainable development.

[0019] The system, consisting of a drive rod, a bidirectional motor, storage boxes, and a discharge port, is controlled by a control box via a series connection to start the bidirectional motor. This motor drives the drive rod to move left and right, causing its top to contact the shovel frame and move the storage boxes left and right. When the two storage boxes approach each other, the extrusion block moves inward, preventing the baffle from obstructing the discharge port. This allows the pre-stored concrete in the storage boxes to flow out of the discharge port, achieving the effect of simultaneously removing the original soil and replacing it with concrete. This continuous operation means that the two steps of removing the original soil and replacing the concrete are closely linked, eliminating the need to wait for the previous step to be completely completed before proceeding to the next. This significantly shortens the construction cycle and improves overall construction efficiency. Continuous operation also reduces repetitive work caused by discontinuous construction steps. Furthermore, continuous operation allows for more accurate calculation of the required quantity and specifications of concrete, avoiding material waste. Simultaneously, the closely linked construction steps reduce additional costs associated with material transportation and storage. Continuous operation also helps reduce the emission of pollutants such as dust, noise, and wastewater during construction. By rationally arranging construction steps and adopting environmentally friendly measures, the environmental impact of construction can be further reduced. Attached Figure Description

[0020] To more clearly illustrate the technical solutions in the embodiments of this application or the prior art, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of this application. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.

[0021] Figure 1 This is a partial three-dimensional structural diagram of the replacement device of the present invention.

[0022] Figure 2 For the present invention Figure 1 A three-dimensional structural diagram from another angle.

[0023] Figure 3 This is a cross-sectional structural diagram of the control box and the T-shaped telescopic rod in this invention.

[0024] Figure 4 This is a cross-sectional structural diagram of the storage box in this invention.

[0025] Figure 5 This is a flowchart of the steps of the present invention.

[0026] Figure 6 This is a cross-sectional view of the lightweight replacement fill after preloading of the deep soft soil subgrade according to the present invention.

[0027] Figure 7 This is a formwork diagram of the concrete protective panel of the present invention.

[0028] Figure 8 This is a schematic diagram of the connection between the angle steel and the concrete protective panel of the present invention.

[0029] Figure 9 Cross-sectional view of the angle steel and concrete protective panel for invention.

[0030] Figure 10 A schematic diagram of the formwork for the base of the guardrail.

[0031] In the diagram: 101, Control box; 102, T-shaped telescopic rod; 103, Driving rod; 104, Fitting shovel frame; 105, Connecting line; 106, Bidirectional motor; 201, Storage box; 202, Sliding groove; 203, Sliding plate; 204, Handle; 205, Fixing tube; 206, Inner frame; 207, Spring; 208, Extrusion block; 209, Pulling line; 210, Baffle plate; 211, Discharge port. Detailed Implementation

[0032] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0033] like Figure 1-4 As shown, the present invention provides a technical solution: a replacement device suitable for embankment construction without slope, comprising a control box 101 and a storage box 201. A T-shaped telescopic rod 102 is fixedly connected to the side of the control box 101 near the storage box 201. Both ends of the T-shaped telescopic rod 102 away from the control box 101 are slidably connected to driving rods 103. A bidirectional motor 106 is fixedly connected to the side of the driving rods 103 close to each other. A connecting line 105 is fixedly connected to the side of the bidirectional motor 106 near the control box 101. The side of the connecting line 105 away from the bidirectional motor 106 is electrically connected to the inside of the control box 101. A fitting shovel frame 104 is fixedly connected to the end of the driving rod 103 away from the control box 101. Two storage boxes 201 are provided, and the two storage boxes 201 are respectively fixedly connected to the top of the two fitting shovel frames 104. Each storage box 201 has a sliding groove 202 inside its top. Each sliding groove 202 has a sliding plate 203 slidably connected inside its sliding plate 203. Each sliding plate 203 has a handle 204 fixedly connected to its top. Each storage box 201 has an inner frame 206 inside its interior. Each inner frame 206 has a fixed tube 205 fixedly connected to its inner wall. Each fixed tube 205 has a spring 207 fixedly connected inside its interior. Each spring 207 has a pressing block 208 fixedly connected to its outer side. Each pressing block 208 has a pulling line 209 fixedly connected to its side. The pulling line 209 is set in a groove in the storage box 201 that is completely fitted with the pulling line 209. Each pulling line 209 has a baffle plate 210 fixedly connected to its bottom end. Each storage box 201 has a discharge port 211 through its side near the baffle plate 210. This allows for the simultaneous removal of the original soil and replacement with concrete. The continuous operation means that the two steps of removing the original soil and replacing the concrete are closely linked, eliminating the need to wait for the previous step to be completely finished before proceeding to the next. This significantly shortens the construction cycle and improves overall construction efficiency. Continuous operation also reduces the problem of repetitive work caused by disjointed construction steps.

[0034] This invention also provides a construction method suitable for embankment construction without slope, such as... Figure 5 As shown, it includes the following steps: S1, Pre-compacting of the original embankment. The earthwork subgrade is filled in layers with controlled elevation. Each layer is spread using a bulldozer and leveled with a grader. The earthwork embankment is compacted using a vibratory roller with a pressure of 40t or more. If the soil is found to be too dry and loose during compaction, appropriate watering is applied; if the soil is too wet and exhibits a "springy" phenomenon, it is excavated for drying, replaced, or treated to improve the condition. The compaction sequence is from both sides towards the center.

[0035] S2, excavation of slope and foamed concrete stepped trenches. The original embankment was sloped and pre-compacted according to design requirements and then excavated to the design position, while simultaneously excavating foamed concrete stepped trenches. Excavation began from the upper opening line and proceeded layer by layer downwards, following the slope ratio shown in the drawings. To ensure the accuracy of the slope ratio and avoid inconsistent slope ratios that could result in varying roadbed widths and affect the aesthetic appearance, GPS measurements were taken and calibrated every 5 meters of excavation.

[0036] like Figure 7 As shown, S3, Concrete Protective Panel Construction: This includes the construction of the concrete protective panel foundation and the construction of the concrete protective panel. The concrete protective panel foundation construction involves constructing a plain concrete base. Silt and debris are removed from the foundation soil, and waterproofing and drainage measures should be in place. Garbage inside the formwork should be cleaned, and the formwork should be moistened with water. Then, concrete is poured, and grooves for the concrete protective panel are reserved in the base. At the same time, a crushed stone leveling layer is constructed on the inner side of the base.

[0037] Short reinforcing bars are pre-installed at the ends of the concrete protective panel. Grouting holes are provided on the concrete protective panel, with symmetrically placed embedded rings on the outer side of each hole. Connecting reinforcing bars are installed at the ends of the two embedded rings. The protective panel can be precast or cast-in-place. If precast: the concrete protective panel is hoisted into the cup-shaped opening of the concrete base. After adjusting its position, the concrete protective panel is fixed to the concrete base with bolts, and then mortar is poured into the cup-shaped opening. If cast-in-place: concrete protective panel templates are erected on both sides of the groove in the concrete base, and template tie bolts are installed, followed by concrete pouring. For cast-in-place installation, the combined steel template is assembled from flat templates, internal and external corner templates. All U-shaped clips, pins, and other accessories used for splicing the longitudinal and transverse ribs must be complete, secure, and not loose or missing. After the template installation is completed, its cross-sectional dimensions and elevation, tie bolts, and connecting rod supports should be pre-inspected.

[0038] like Figures 8-9 As shown, S4, Angle Steel Connection: This includes the installation of angle steel and its connection to the protective panel. According to the design requirements, the angle steel is pressed into the soil. Connecting reinforcing bars are inserted into the adjacent embedded rings on the concrete protective panel. The ends of the tie rods or fixing rods are bent and hung on the connecting reinforcing bars, forming a V-shaped connection with the angle steel. The connection is achieved by welding. The weld must be smooth and free of porosity, slag inclusions, or other welding defects; any defects found must be repaired promptly. The weld height is generally close to that of the steel plate. When using intermittent welding, the weld length and intervals should be uniform.

[0039] S5, Foamed Concrete Construction: First, lay the bottom layer of wire mesh, then pour foamed concrete in layers. After pouring, lay the top layer of wire mesh, and finally cure the foamed concrete. Laying the bottom layer of wire mesh involves installing the cast-in-place concrete formwork according to design requirements. Before pouring the foamed concrete, pre-drilled holes for tie rods are laid. The surface of the tubular material is coated with a release agent and passed through the pre-drilled holes for tie rods on the prefabricated retaining wall to the cast-in-place concrete formwork. Then, the foamed concrete is poured. After pouring one layer, the bottom layer of wire mesh is laid after setting the elevation, and then the foamed concrete is poured.

[0040] Layered pouring of foamed concrete involves on-site mechanized pumping and pouring, combined with rapid construction methods. During pouring, all equipment is concentrated on one side of the bridge abutment for rapid pouring, stopping when the planned elevation is reached in one go. Mechanical compaction is then used; for areas without compaction, small vibratory compactors can be used for individual compaction. After compaction, the concrete surface is leveled. After a period of time, once the foamed concrete has reached its initial strength, the next layer is poured. Before pouring, formwork is erected to the required height for the next layer. Foamed concrete is poured in horizontal layers, with each layer typically controlled between 300mm and 800mm. Too thin a layer compromises the integrity of the single layer, while too thick a layer can cause air bubbles in the lower layer to compress, affecting the density and complicating construction. Overall pouring is carried out in layers, staggered in time, until the designed total filling elevation is reached. To ensure that air bubbles are independently and evenly distributed in the lightweight soil mixture, defoaming and material segregation are minimized. A certain vibration speed is maintained during construction, avoiding excessive vibration. During the pouring process, pour directly using the tip of the hose, ensuring the outlet is embedded in or as close as possible to the surface of the foamed concrete. The entire filling process should be carried out in horizontal layers, with each layer poured at least once a day. Attention should be paid to the maximum and minimum thicknesses for each pour. After the foamed concrete has initially set, cover it directly onto the concrete surface and then promptly water it for curing. This isolates the concrete structure from the air, preventing excessive moisture loss and shrinkage cracks. Furthermore, if rain occurs during construction, cover the aerated lightweight soil mixture afterward to prevent rain damage and ensure adequate curing to avoid cracking.

[0041] The top layer of wire mesh is installed after the pouring operation reaches the designated elevation, followed by the pouring of foamed concrete to the design elevation. Curing involves promptly laying an impermeable geomembrane after the foamed concrete has reached the design elevation to maintain moisture. Once the foamed concrete has initially set, it is directly covered onto the concrete surface, and water is sprayed promptly to isolate the concrete structure from the air and prevent excessive moisture loss, which could cause shrinkage cracks. Furthermore, if rain occurs during construction, the aerated lightweight soil mixture must be covered after construction to prevent rain damage and ensure that insufficient curing does not lead to cracking.

[0042] like Figure 10 As shown, S6, pavement structure layer and accessory installation: First, grout is injected into the pre-drilled holes in the concrete protective panel, then the guardrail base is fabricated, and finally the guardrail is installed. Grouting of the pre-drilled holes in the concrete protective panel involves filling the pre-drilled holes with cement mortar after the foamed concrete is poured. During compaction grouting, the grouting pipe should first perform low-pressure grouting on the outer layer, with the grouting pressure determined by on-site test drilling to form a sealed grout, before extending to the designed position for high-pressure grouting.

[0043] The base of the construction guardrail can be either cast-in-place or precast. For cast-in-place construction, embedded rods are pre-installed in the road structure layer. Then, a guardrail base formwork is erected on top of these embedded rods. The bottom of the inclined formwork is fixed to the concrete protective panel. The inclined formwork is fixed to the central vertical formwork using tie rods, and the central vertical formwork is fixed to the end vertical formwork using struts. Concrete is then poured, with angle steel extending into the guardrail base. A guardrail sleeve is pre-installed on the base, and a gravel blind drain is constructed inside the base. For precast construction, the precast guardrail base is simply lifted and installed. When installing the guardrail, the posts are first placed inside the guardrail sleeves. All posts should be vertically embedded according to the drawings and alignment. A water-blocking strip is installed on the top of the reinforced concrete guardrail base. Anti-blocking blocks are installed at the ends of the posts, and then the corrugated beams are installed and fixed using connecting bolts. The guardrail is installed according to the drawings and bolted to the posts; the metal mesh should be stretched taut, and the entire structure should not be twisted.

[0044] Finally, it should be noted that the above are merely preferred embodiments of the present invention and are not intended to limit the present invention. Although the present invention has been described in detail with reference to the foregoing embodiments, those skilled in the art can still modify the technical solutions described in the foregoing embodiments or make equivalent substitutions for some of the technical features. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the protection scope of the present invention.

Claims

1. A replacement device suitable for embankment construction without slope, comprising a control box (101) and a storage box (201), characterized in that, A T-shaped telescopic rod (102) is fixedly connected to the side of the control box (101) near the storage box (201). Both ends of the T-shaped telescopic rod (102) away from the control box (101) are slidably connected to driving rods (103). A bidirectional motor (106) is fixedly connected to the side of the driving rods (103) close to each other. A connecting wire (105) is fixedly connected to the side of the bidirectional motor (106) near the control box (101). The side of the connecting wire (105) away from the bidirectional motor (106) is electrically connected to the inside of the control box (101). A fitting shovel frame (104) is fixedly connected to the end of each driving rod (103) away from the control box (101). Two storage boxes (201) are provided, each fixedly connected to the top of one of the two fitting shovel frames (104). A sliding groove is provided inside the top of each storage box (201). 202), the sliding groove (202) is slidably connected to the inside of the sliding plate (203), the top of the sliding plate (203) is fixedly connected to the handle (204), the storage box (201) is provided with an inner frame (206), the inner wall of the inner frame (206) is fixedly connected to the fixing tube (205), the inside of the fixing tube (205) is fixedly connected to the spring (207), the spring (207) is fixedly connected to the pressing block (208) on the side near the outside, the pressing block (208) is fixedly connected to the side of the pulling line (209), the pulling line (209) is set in the groove opened in the storage box (201) that is completely in contact with the pulling line (209), the bottom end of the pulling line (209) is fixedly connected to the baffle plate (210), and the storage box (201) is provided with a discharge port (211) through the side near the baffle plate (210).

Citation Information

Patent Citations

  • A construction method for roadbed replacement

    CN109322224B

  • Foam concrete light retaining wall constructed in deep ultra-soft soil layer sequentially through pre-compaction and excavation and construction method of foam concrete light retaining wall

    CN107386317A

  • Shallow soft soil foundation foam light soil embankment structure and construction method

    CN113186766A