Method for assembling large shuttle tanker double curvature surface in sections
By combining a cloud platform and a total station, and using reflectors to measure and adjust coordinates at key and precision control points, the problem of low efficiency and poor safety in the assembly of large-scale hyperboloid sections of shuttle tankers was solved, achieving efficient and safe segmented installation.
Patent Information
- Application Number
- CN202510059816.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2025-01-15
- Publication Date
- 2026-11-20
- Estimated Expiration
- 2045-01-15
AI Technical Summary
During the assembly of the large-scale hyperboloid sections of the shuttle tanker, the existing methods are inefficient and have poor safety, and the frequent back-and-forth between the loading site and the office by on-site operators poses a significant safety risk.
By using a cloud platform to store segment information, and combining a total station with analysis software, coordinate measurements and adjustments are made at key points and precision control points using reflectors, thus achieving precise positioning and installation of the segments.
It improved the efficiency of the segmented assembly, reduced the frequency of on-site operators' trips, lowered safety risks, and shortened the construction period.
Smart Images

Figure CN119840799B_ABST
Abstract
Description
Technical Field
[0001] This application relates to the field of shipbuilding technology, and in particular to a method for assembling a large hyperboloid section of a shuttle tanker. Background Technology
[0002] A shuttle tanker is a type of vessel specifically designed for transporting oil from offshore oil fields to land. It is primarily known for its high maneuverability and mainly operates between floating storage and offloading (FSO) vessels in offshore oil fields and ports. It can also transport crude oil in waters with complex sea conditions.
[0003] In the field of shuttle tanker repair and construction, the sections at the beginning and end are usually hyperboloids with large linear shapes. During the assembly process, since there are no measurement benchmarks in the XYZ directions, the sections are usually adjusted to the theoretical height using steel supports based on the outer plate shape value.
[0004] In existing technologies, due to the large segmented alignment of shuttle tankers and their hyperboloidal surfaces, the height difference of steel supports typically exceeds 10 meters, making on-site construction inconvenient and dangerous. Because of the hyperboloidal surface, there is no precise measurement reference for establishing the axis when assembling multiple segments together. Typically, precision control personnel use a total station to measure the overall data, which is then retrieved to an office computer for analysis. On-site workers must wait for the precision control analysis results. After the data analysis is complete, the segment precision is adjusted on-site based on deviations. This process is repeated until the precision data meets the requirements.
[0005] In summary, the existing method for assembling large-scale hyperboloid sections of shuttle tankers is inefficient, and due to the large number of equipment and complex operating conditions at the loading site, it is dangerous for on-site operators to frequently travel between the loading site and the office, resulting in low safety. Summary of the Invention
[0006] To improve the efficiency and safety of assembling large-section hyperboloid segmented assemblies for shuttle tankers, this application provides a method for assembling large-section hyperboloid segmented assemblies for shuttle tankers.
[0007] The technical solution provided in this application for a segmented assembly method of a large-scale hyperboloidal surface for a shuttle tanker is as follows: A method for assembling a large-scale hyperboloid segment of a shuttle tanker mainly includes the following steps: Step S1: Establish a cloud platform to store segment information, which includes segment name, segment position in the overall group, segment 3D data, segment outer plate shape value point data, and segment assembly order; Step S2: Select the first segment, select multiple key points of the outer plate in the outer plate shape value point data of the first segment, and implant reflective sheets at the key points of the outer plate of the first segment. Set up a general assembly steel pier based on the first segment in the mounting site, and install the first segment on the general assembly steel pier. Step S3: Import the actual coordinate data of multiple key points of the outer plate on the first segment of the site into the analysis software, import the three-dimensional data model and outer plate shape value point data of the second segment into the analysis software, select two precision control points from the outer plate shape value point data of the second segment, implant reflectors on the two precision control points respectively, and obtain the on-site positioning theoretical data of the two precision control points on the second segment through the three-point movement function of the total station; Step S4: Based on the on-site positioning theoretical data, obtain the coordinate data of multiple key points on the outer plate of the first segment and the coordinate data of two precision control points on the second segment. Compare the deviation between the actual coordinate data of the second segment and the on-site positioning theoretical data, adjust the position of the second segment along the width, height and length directions, and effectively seal the first and second segments.
[0008] By adopting the above technical solution, during the process of assembling the segments into a whole, the operator can retrieve the segment information of each segment from the cloud platform, and select the first segment based on the site conditions of the mounting site, the position of each segment in the whole, and the assembly order of each segment. Based on the outer plate shape data of the first segment, the operator can set up the steel pier for mounting and supporting the whole assembly at the mounting site. After the first segment is mounted on the main assembly steel pier by a crane, the actual coordinate data of multiple key points on the outer plates of the first segment can be detected using a total station. By integrating the measured and design models of the first segment in the analysis software, the theoretical on-site positioning data of two precision control points on the second segment after its installation can be obtained. When the second segment is transported to the mounting site by crane, operators can use a total station to detect the function of multiple key points on the outer plates and the two precision control points. By adjusting the models of the first and second segments within the total station, the deviation between the measured coordinate values of the two precision control points on the second segment and the theoretical on-site positioning data can be determined. This allows relevant personnel to adjust the second segment along the length, width, and height directions based on the deviation between the measured coordinate values of the two precision control points and the theoretical on-site positioning data, until the coordinate positions of the two precision control points on the second segment match the theoretical on-site positioning data. After the placement and installation of the second segment are completed, the first and second segments are effectively sealed, thus realizing the mounting and installation of the first and second segments. By employing the aforementioned technical means, on-site operators can be spared from frequently traveling between the assembly site and the office during the assembly of the second segment, reducing the likelihood of injuries to on-site operators due to frequent travel between the assembly site and the office. This can effectively save time and effort required to adjust the position of the second segment, improve the efficiency of assembly between the second and first segments, and shorten the time required to assemble the segments into the final assembly.
[0009] Preferably, step S2 includes the following steps: Step S21: Obtain segmentation information for each segment from the cloud platform, and determine the first segment based on the segmentation information; Step S22: Obtain the three-dimensional data and outer plate shape point data of the first segment from the cloud platform, and import the three-dimensional data and outer plate shape point data of the first segment into the total station; Step S23: Select multiple outer panel key points from the outer panel shape value point data of the first segment. The number of outer panel key points is at least three, and the multiple outer panel key points include a first reference point and a second reference point. The first reference point is the point in the outer panel shape value point data of the first segment that has a negative value and the largest absolute value of the Y-axis coordinate. The Y-axis coordinate value and Z-axis coordinate value of the second reference point are the same as the Y-axis coordinate value and Z-axis coordinate value of the first reference point. Step S24: Use a crane to transport the first segment to the pre-set installation position of the first segment at the mounting site, and adjust the position of the first segment along the length, height and width directions so that the first segment is in a basically horizontal state at the key points of the outer panel as visually observed. Step S25: Set up the main assembly steel block at the mounting site, and set the main assembly steel block near the outer plate of the first reference point; Step S26: Set up the piers on the main group steel blocks to support the first segment and loosen the hooks to release the first segment.
[0010] By adopting the above technical solution, and by embedding reflective sheets at key points on the outer plates of the first segment, operators can easily adjust the first segment to a roughly horizontal position during installation. By setting up the main assembly steel pier based on the position of the first key point, since the Y-axis coordinate of the first key point is negative and has the largest absolute value, the first key point is located at the lowest point of the first segment after it is adjusted to a roughly horizontal position, allowing the height of the main assembly steel pier to be lowered. After the installation of the first segment is completed, the reflective sheets embedded at each key point on the outer plates of the first segment allow operators to easily measure the coordinate data of each key point on the outer plates of the first segment using a total station.
[0011] Preferably, step S3 includes the following steps: Step S31: Use a total station to inspect the first segment after it has been installed on site, and obtain the coordinate data of multiple key points on the outer plate of the first segment; Step S32: Import the 3D models of the first and second segments into the analysis software in the office, and hide the second segment; Step S33: Import the coordinate data of multiple key points of the outer panel on the first segment after installation into the analysis software. Move the positions of the first and second segments in the analysis software so that the coordinates of each key point of the outer panel on the design model of the first segment coincide with the coordinates of each key point of the outer panel on the installation site of the first segment. Unhide the second segment. Select two precision control points in the outer panel shape value point data of the second segment. The two precision control points are located at the bow end of the outer panel of the second segment. Export the coordinates of the two precision control points from the analysis software and calibrate them as theoretical data for on-site positioning. Step S34: Print out the on-site positioning theoretical data into a report and bring it to the installation site.
[0012] By adopting the above technical solution, by adjusting the design model of the first segment to coincide with the design model of the first segment in the analysis software, a preset model of the second segment after installation at the mounting site can be obtained. By setting and embedding two precision control points on the second segment, the position of the second segment can be easily verified at the mounting site.
[0013] Preferably, step S33 includes the following steps: Step S331: Select the first reference point and the second reference point, so that the design model of the first segment is rotated 90 degrees around the X-axis; Step S332: Using the point movement function of the analysis software, move the X-axis coordinates, Y-axis coordinates, and Z-axis coordinates of the first reference point of the design model of the first segment and the actual first reference point in the mounting site of the first segment to 0. Step S333: Select a third reference point from multiple key points of the outer plate of the first segment. Use the first reference point, second reference point and third reference point on the first segment in the installation site to form a measured reference surface. Use the first reference point, second reference point and third reference point in the design model on the first segment to form a design reference surface. Use the three-point movement function of the analysis software to move the Z-axis coordinate values of the first reference point, second reference point and third reference point to 0, so that the design reference surface of the first segment coincides with the measured reference surface. Step S334: Display the hidden second segment and select two precision control points from the outer plate shape value point data of the second segment; Step S335: Implant reflective sheets at two precision control points on the outer plate of the second segment.
[0014] By adopting the above technical solution, the design model of the first segment is rotated 90 degrees around the X-axis, and then the X-axis, Y-axis, and Z-axis coordinate values of the first reference point on the design model of the first segment and the first reference point on the first segment in the actual measurement are all moved to 0. When the design reference plane and the actual measurement reference plane coincide, the design model of the first segment and the actual measurement model of the first segment can be made to coincide. At this time, after the display status of the second segment is changed to display, the coordinates of the two precision control points on the second segment in the analysis software are the theoretical data of the field positioning.
[0015] Preferably, step S4 includes the following steps: Step S41: Use a crane to transport the second segment to the loading site, and adjust the position of the second segment along the length, width, and height directions to roughly locate the position of the second segment; Step S42: Use a total station to detect the actual coordinate data of multiple key points on the outer plate of the first segment and two precision control points on the second segment; Step S43: Compare the positions of the two precision control points on the second segment in the total station to determine the deviation between the actual position of the second segment in the mounting site and the preset installation position; Step S44: Based on the deviation between the actual position and the preset position of the second segment in the mounting site, adjust the position of the second segment along the length, width and height directions using a crane until the coordinate data of the two precision control points on the second segment in the total station are the same as those of the precision control points on the second segment in the design model. Step S45: Set up the piers on the main steel piers to support the second section, release the hooks to release the second section, and effectively seal the first and second sections.
[0016] By adopting the above technical solution, during the installation of the second segment, since reflectors are set on the two precision control points of the second segment, the measured coordinate values of the two precision control points on the second segment can be obtained by using a total station. After importing the measured coordinate values of the two precision control points into the total station, the coordinate values of the two precision control points after the three-point movement of the measured first segment and the second segment can be compared with the theoretical data of the on-site positioning. By comparing the coordinate values of the two precision control points after the three-point movement with the theoretical data of the on-site positioning, the deviation between the second segment and the preset installation position can be obtained, which makes it convenient for on-site operators to adjust the position of the second segment along the length, width and height directions according to the deviation.
[0017] Preferably, step S42 includes the following steps: Step S421: Use a total station to detect the coordinate data of the first key point, the second key point, the third key point, and the two precision control points on site; Step S422: Select the first key point, the second key point, and the third key point in the total station and move them to 0. Then, obtain the actual coordinate data of the two precision control points on the second segment.
[0018] Preferably, the height of the first reference point from the ground of the mounting site is not less than 900mm, and the height of the steel pier for the main assembly is not less than 900mm.
[0019] In summary, the method for assembling a large-scale hyperboloid segment of a shuttle tanker according to this application has at least one of the following beneficial technical effects: 1. It can eliminate the need for on-site operators to frequently travel between the assembly site and the office during the assembly of the second section, reducing the risk of injury to on-site operators due to frequent travel between the assembly site and the office. It can effectively save time and effort required to adjust the position of the second section, improve the assembly efficiency between the second section and the first section, and shorten the construction period for assembling the sections into the final assembly. 2. By embedding reflective sheets at key points on each outer panel of the first segment and at two precision control points on the second segment, it is convenient to detect the actual coordinates of the key points on each outer panel of the first segment and the precision control points on the second segment using a total station at the installation site. Attached Figure Description
[0020] Figure 1 This is a schematic diagram illustrating the main process of the method for assembling a large-scale hyperboloid section of a shuttle tanker, as described in this application embodiment.
[0021] Figure 2 This is a schematic diagram illustrating the overall structure of the first segment in an embodiment of this application.
[0022] Figure 3 This is a schematic diagram used in this application embodiment to illustrate the design models of the first segment and the second segment after coordinate transformation.
[0023] Explanation of the attached diagram labels: 1. First segment; 2. Second segment. Detailed Implementation
[0024] The following is in conjunction with the appendix Figure 1-3 This application will be described in further detail.
[0025] Example 1 This application discloses a method for assembling a large-scale hyperboloid segment of a shuttle tanker. (Refer to...) Figure 1 It mainly includes the following steps: Step S1: Establish a cloud platform to store segment information, including segment name, segment position in the overall group, segment 3D data, segment outer plate shape value point data, and segment assembly order; Step S2: Select the first segment 1, select multiple key points of the outer plate in the outer plate shape value point data of the first segment 1, and implant reflective sheets at the key points of the outer plate of the first segment 1. Set up a general assembly steel pier based on the first segment 1 in the mounting site, and install the first segment 1 on the general assembly steel pier. Step S3: Import the actual coordinate data of multiple key points of the outer plate on the first segment 1 of the site into the analysis software, import the three-dimensional data model and outer plate shape point data of the second segment 2 into the analysis software, select two precision control points from the outer plate shape point data of the second segment 2, implant reflectors on the two precision control points respectively, and obtain the on-site positioning theoretical data of the two precision control points on the second segment 2 through the three-point movement function of the total station. Step S4: Based on the on-site positioning theoretical data, obtain the coordinate data of multiple key points on the outer plate of the first segment 1 and the coordinate data of two precision control points on the second segment 2. Compare the deviation between the actual coordinate data of the second segment 2 on-site and the on-site positioning theoretical data, adjust the position of the second segment 2 along the width direction, height direction and length direction, and effectively seal the first segment 1 and the second segment 2.
[0026] During the process of assembling the segments into the main assembly, the operator can retrieve the segment information of each segment from the cloud platform, and select the first segment 1 based on the site conditions of the mounting site, the position of each segment in the main assembly, and the assembly order of each segment. Based on the outer plate shape data of the first segment 1, the operator can set up the main assembly steel pier at the mounting site to support the main assembly. After the first segment 1 is mounted on the main assembly steel pier by a crane, the actual coordinate data of multiple key points of the outer plate on the first segment 1 can be detected by a total station.
[0027] After integrating the measured model and design model of the first segment 1 within the analysis software, the theoretical data of the on-site positioning of the two precision control points on the second segment 2 after the second segment 2 is installed on-site can be obtained.
[0028] After the crane transports the second segment 2 to the installation site, the operators can use a total station to detect the function of multiple key points on the outer plate and two precision control points. By adjusting the models of the first segment 1 and the second segment 2 in the total station, the deviation between the measured coordinate values of the two precision control points on the second segment 2 and the theoretical data of the on-site positioning can be determined. This allows relevant personnel to adjust the second segment 2 along the length, width, and height directions based on the deviation between the measured coordinate values of the two precision control points and the theoretical data of the on-site positioning, until the coordinate positions of the two precision control points on the second segment 2 match the theoretical data of the on-site positioning.
[0029] After the placement and installation of the second segment 2 are completed, the first segment 1 and the second segment 2 are effectively sealed to enable the mounting and installation of the first segment 1 and the second segment 2.
[0030] By employing the aforementioned technical means, on-site operators can be spared from frequently traveling between the assembly site and the office during the assembly of the second segment 2, thereby reducing the risk of injury to on-site operators due to frequent travel between the assembly site and the office. This also effectively saves time and effort required to adjust the position of the second segment 2, improves the efficiency of the assembly between the second segment 2 and the first segment 1, and shortens the time required to assemble the segments into the final assembly.
[0031] Step S2 includes the following steps: Step S21: Obtain segmentation information for each segment from the cloud platform, and determine the first segment 1 based on the segmentation information; Step S22: Obtain the three-dimensional data and outer plate shape point data of the first segment 1 from the cloud platform, and import the three-dimensional data and outer plate shape point data of the first segment 1 into the total station; Step S23: Select multiple key points of the outer plate from the outer plate shape value point data of the first segment 1. The number of key points of the outer plate is at least three, and the multiple key points of the outer plate include a first reference point and a second reference point. The first reference point is the point in the outer plate shape value point data of the first segment 1 that has a negative value and the largest absolute value of the Y-axis coordinate. The Y-axis coordinate value and Z-axis coordinate value of the second reference point are the same as the Y-axis coordinate value and Z-axis coordinate value of the first reference point. Step S24: Use a crane to transport the first segment 1 to the pre-set installation position of the first segment 1 at the mounting site, and adjust the position of the first segment 1 along the length, height and width directions so that the first segment 1 is in a state where the outer panel is basically level at multiple key points of the outer panel as visually observed. Step S25: Set up the main assembly steel block at the mounting site, and set the main assembly steel block near the outer plate of the first reference point; Step S26: Set up the wooden blocks on the main group to support the first segment 1 and loosen the hooks to release the first segment 1.
[0032] By embedding reflective sheets at key points on the outer plates of the first segment 1, operators can easily adjust the first segment 1 to a roughly horizontal position during installation. By setting up the main assembly steel pier based on the position of the first key point, since the Y-axis coordinate of the first key point is negative and has the largest absolute value, the first key point will be located at the lowest point of the first segment 1 after the first segment 1 is adjusted to a roughly horizontal position, allowing the height of the main assembly steel pier to be lowered. After the installation of the first segment 1 is completed, the reflective sheets embedded at each key point on the outer plates of the first segment 1 allow operators to easily measure the coordinate data of each key point on the outer plates of the first segment 1 using a total station.
[0033] For example, such as Figure 2 The diagram shows the first section 1 at the bottom of the shuttle tanker. Section 1 is the first section to be assembled during the overall assembly process. Four key outer plate points are located on section 1: P1, P2, P3, and P4. P1 and P3 are located at the structural intersection at the stern end of the outer plate of section 1, while P2 and P4 are located at the structural intersection at the bow end of the outer plate of section 2.
[0034] It should be noted that in this embodiment, the height of the first reference point from the ground of the mounting site is not less than 900mm, and the height of the steel pier for the main assembly is not less than 900mm, which facilitates on-site construction by operators.
[0035] Step S3 includes the following steps: Step S31: Use a total station to inspect the first segment 1 after it has been installed on site, and obtain the coordinate data of multiple key points on the outer plate of the first segment 1; Step S32: Import the 3D models of the first segment 1 and the second segment 2 into the analysis software in the office, and hide the second segment 2; Step S33: Import the coordinate data of multiple key points of the outer panel on the first segment 1 after installation into the analysis software. Move the positions of the first segment 1 and the second segment 2 in the analysis software so that the coordinates of each key point of the outer panel on the design model of the first segment 1 coincide with the coordinates of each key point of the outer panel in the installation site of the first segment 1. Unhide the second segment 2. Select two precision control points in the outer panel shape value point data of the second segment 2. The two precision control points are located at the bow end of the outer panel of the second segment 2. Export the coordinates of the two precision control points from the analysis software and calibrate them as theoretical data for on-site positioning. Step S34: Print out the on-site positioning theoretical data into a report and bring it to the installation site.
[0036] By adjusting the design model of the first segment 1 to coincide with the design model of the first segment 1 in the analysis software, the preset model of the second segment 2 after installation at the mounting site can be obtained. By setting and embedding two precision control points on the second segment 2, the position of the second segment 2 can be easily verified at the mounting site.
[0037] Step S33 includes the following steps: Step S331: Select the first reference point and the second reference point so that the design model of the first segment 1 is rotated 90 degrees around the X-axis; Step S332: Using the point movement function of the analysis software, move the X-axis coordinates, Y-axis coordinates, and Z-axis coordinates of the first reference point of the design model of the first segment 1 and the actual first reference point in the mounting site of the first segment 1 to 0. Step S333: Select a third reference point from among the multiple key points of the outer plate of the first segment 1. Use the first reference point, second reference point and third reference point on the first segment 1 in the site to form a measured reference surface. Use the first reference point, second reference point and third reference point in the design model on the first segment 1 to form a design reference surface. Use the three-point movement function of the analysis software to move the Z-axis coordinate values of the first reference point, second reference point and third reference point to 0, so that the design reference surface of the first segment 1 coincides with the measured reference surface. Step S334: Display the hidden second segment 2 and select two precision control points from the outer plate shape value point data of the second segment 2; Step S335: Implant reflective sheets at two precision control points on the outer plate of the second segment 2.
[0038] By rotating the design model of the first segment 1 by 90 degrees around the X-axis, and then moving the X-axis, Y-axis, and Z-axis coordinates of the first reference point on the design model of the first segment 1 and the first reference point on the actual measurement site of the first segment 1 to 0; when the design reference plane and the actual measurement reference plane coincide, the design model of the first segment 1 and the actual measurement model of the first segment 1 can be made to coincide. At this time, after changing the display status of the second segment 2 to display, the coordinates of the two precision control points on the second segment 2 in the analysis software are the theoretical data of the field positioning.
[0039] Rotating the design model 90 degrees along the X-axis allows for the conversion of the Y-axis and Z-axis coordinates, ensuring that the coordinates of each precision control point in the design model correspond one-to-one with the measured Y-axis and Z-axis coordinates of each precision control point on the first segment 1 of the installation site.
[0040] After moving one point and then three points, the design reference plane on the design model of the first segment 1 can be made to coincide with the measured reference plane on the measured model, and the coordinate data of each precision control point on the design model can coincide with the coordinate data of each precision control point on the measured model. At this time, by displaying the second segment 2, two precision control points are selected on the outer plate shape value data of the second segment 2. The coordinate data of the two precision control points are the theoretical data of on-site positioning.
[0041] For example, please refer to Figure 3 In this embodiment, the coordinates of the precision control points on the transformed first segment 1 design model are P1(0, 0, 0), P2(12561, 0, 0), P3(11964, 16038, 727), and P3(2632, 16581, 0). The two precision control points selected on the transformed second segment 2 are Q1 and Q2. Both Q1 and Q2 are located at the bow end of the outer plate of the second segment 2, and the coordinate data of Q1 and Q2 are Q1(25073, -23, 1704) and Q2(21455, 15592, 2783), respectively. Then the theoretical field positioning data of the two precision control points are: Q1(25073, -23, 1704) and Q2(21455, 15592, 2783).
[0042] Step S4 includes the following steps: Step S41: Use a crane to transport the second segment 2 to the loading site, and adjust the position of the second segment 2 along the length, width and height directions to roughly locate the position of the second segment 2; Step S42: Use a total station to detect the actual coordinate data of multiple key points on the outer plate of the first segment 1 and two precision control points on the second segment 2; Step S43: Compare the positions of the two precision control points on the second segment 2 in the total station to determine the deviation between the actual position of the second segment 2 in the mounting site and the preset installation position; Step S44: Based on the deviation between the actual position and the preset position of the second segment 2 in the mounting site, adjust the position of the second segment 2 along the length, width and height directions using a crane until the coordinate data of the two precision control points on the second segment 2 in the total station are the same as those of the precision control points on the second segment 2 in the design model. Step S45: Set up a wooden block on the main steel block to support the second segment 2, release the hook to release the second segment 2, and effectively seal the first segment 1 and the second segment 2.
[0043] During the installation of the second segment 2, reflectors are installed on the two precision control points of the second segment 2. The actual coordinate values of the two precision control points on the second segment 2 can be measured using a total station. After importing the actual coordinate values of the two precision control points into the total station, the coordinate values of the two precision control points after the actual three-point movement of the first segment 1 and the second segment 2 can be compared with the theoretical data of the on-site positioning. By comparing the coordinate values of the two precision control points after the three-point movement with the theoretical data of the on-site positioning, the deviation of the second segment 2 from the preset installation position can be obtained. This allows the on-site operators to adjust the position of the second segment 2 along the length, width, and height directions based on the deviation.
[0044] Step S42 includes the following steps: Step S421: Use a total station to detect the coordinate data of the first key point, the second key point, the third key point, and two precision control points on site; Step S422: Select the first key point, the second key point, and the third key point in the total station and move them to 0. Then, obtain the actual coordinate data of the two precision control points on the second segment 2.
[0045] For example, in this embodiment, the theoretical on-site positioning data are Q1 (25073, -23, 1704) and Q2 (21455, 15592, 2783). After the total station converts the models of the first segment 1 and the second segment 2, the measured coordinate data of Q1 and Q2 can be compared with the theoretical on-site positioning data to determine the deviation between the second segment 2 and the preset installation position.
[0046] The implementation principle of the method for assembling a large-scale hyperboloid section of a shuttle tanker according to an embodiment of this application is as follows: During the assembly of sections into a complete assembly, the operator can retrieve the section information of each section from the cloud platform, and select the first section 1 based on the site conditions of the mounting site, the position of each section in the complete assembly, and the assembly order of each section. Based on the outer plate shape data of the first section 1, a steel pier for supporting the assembly is set up at the mounting site. After the first section 1 is mounted and installed on the steel pier by a crane, the actual coordinate data of multiple key points of the outer plate on the first section 1 can be detected by a total station. After integrating the measured model and design model of the first section 1 in the analysis software, the theoretical on-site positioning data of two precision control points on the second section 2 after the second section 2 is installed at the mounting site can be obtained. According to reports, after the crane transports the second segment 2 to the installation site, the operators can use a total station to detect the function of multiple key points on the outer plate and two precision control points. By adjusting the models of the first segment 1 and the second segment 2 in the total station, the deviation between the measured coordinate values of the two precision control points on the second segment 2 and the theoretical data of on-site positioning can be determined. This allows relevant personnel to adjust the second segment 2 along the length, width, and height directions based on the deviation between the measured coordinate values of the two precision control points and the theoretical data of on-site positioning, until the coordinate positions of the two precision control points on the second segment 2 match the theoretical data of on-site positioning. After the placement and installation of the second segment 2 are completed, the first segment 1 and the second segment 2 are effectively sealed, thus realizing the mounting and installation of the first segment 1 and the second segment 2. By employing the aforementioned technical means, on-site operators can be spared from frequently traveling between the assembly site and the office during the assembly of the second segment 2, thereby reducing the risk of injury to on-site operators due to frequent travel between the assembly site and the office. This also effectively saves time and effort required to adjust the position of the second segment 2, improves the efficiency of the assembly between the second segment 2 and the first segment 1, and shortens the time required to assemble the segments into the final assembly.
[0047] Example 2 In this embodiment, the first segment 1 is a semi-finished product assembly formed by assembling multiple segments. The semi-finished product assembly is regarded as a whole, and the position of the segment to be mounted can be adjusted based on the model of the semi-finished product assembly.
[0048] The above are all preferred embodiments of this application, and are not intended to limit the scope of protection of this application. Therefore, all equivalent changes made in accordance with the structure, shape and principle of this application should be covered within the scope of protection of this application.
Claims
1. A method for assembling a large-scale hyperboloid segment of a shuttle tanker, characterized in that, include: Step S1: Establish a cloud platform to store segment information, which includes segment name, segment position in the overall group, segment 3D data, segment outer plate shape value point data, and segment assembly order; Step S2: Select the first segment (1), select multiple key points of the outer plate in the outer plate type value point data of the first segment (1), and implant reflective sheets at the key points of the outer plate of the first segment (1). Set up a general assembly steel pier based on the first segment (1) in the mounting site, and install the first segment (1) on the general assembly steel pier. Step S3: Import the actual coordinate data of multiple key points of the outer plate on the first segment (1) of the site into the analysis software, import the three-dimensional data model and outer plate shape value point data of the second segment (2) into the analysis software, select two precision control points from the outer plate shape value point data of the second segment (2), implant reflectors on the two precision control points respectively, and obtain the on-site positioning theoretical data of the two precision control points on the second segment (2) through the three-point movement function of the total station; Step S4: Based on the on-site positioning theoretical data, obtain the coordinate data of multiple key points on the outer plate of the first segment (1) and the coordinate data of two precision control points on the second segment (2). Compare the deviation between the actual coordinate data of the second segment (2) and the on-site positioning theoretical data. Adjust the position of the second segment (2) along the width, height and length directions to effectively seal the first segment (1) and the second segment (2). Step S2 includes the following steps: Step S21: Obtain segmentation information of each segment from the cloud platform, and determine the first segment based on the segmentation information (1); Step S22: Obtain the three-dimensional data and outer plate type value point data of the first segment (1) from the cloud platform, and import the three-dimensional data and outer plate type value point data of the first segment (1) into the total station; Step S23: Select multiple outer plate key points from the outer plate shape value point data of the first segment (1). The number of outer plate key points is at least three, and the multiple outer plate key points include a first reference point and a second reference point. The first reference point is the point in the outer plate shape value point data of the first segment (1) with a negative value and the largest absolute value of the Y-axis coordinate. The Y-axis coordinate value and Z-axis coordinate value of the second reference point are the same as the Y-axis coordinate value and Z-axis coordinate value of the first reference point. Step S24: Use a crane to transport the first segment (1) to the pre-set installation position of the first segment (1) at the mounting site, and adjust the position of the first segment (1) along the length direction, height direction and width direction so that the first segment (1) is in a state where the outer panel at multiple key points of the outer panel is basically horizontal. Step S25: Set up the main assembly steel block at the mounting site, and set the main assembly steel block near the outer plate of the first reference point; Step S26: Set up the piers for supporting the first segment (1) on the main group using steel piers and loosen the hooks to release the first segment (1). Step S3 includes the following steps: Step S31: Use a total station to inspect the first segment (1) after it has been installed on site, and obtain the coordinate data of multiple key points of the outer plate on the first segment (1); Step S32: Import the 3D models of the first segment (1) and the second segment (2) into the analysis software in the office, and hide the second segment (2); Step S33: Import the coordinate data of multiple key points of the outer plate on the first segment (1) after installation into the analysis software. Move the positions of the first segment (1) and the second segment (2) in the analysis software so that the coordinates of each key point of the outer plate on the design model of the first segment (1) coincide with the coordinates of each key point of the outer plate in the installation site of the first segment (1). Cancel the hidden state of the second segment (2). Select two precision control points in the outer plate shape value point data of the second segment (2) and the two precision control points are located at the bow end of the outer plate of the second segment (2). Export the coordinates of the two precision control points from the analysis software and calibrate them as theoretical data for on-site positioning. Step S34: Print out the theoretical data of the on-site positioning into a report and bring it to the launch site. Step S33 includes the following steps: Step S331: Select the first reference point and the second reference point so that the design model of the first segment (1) is rotated 90 degrees around the X-axis, so that the Y-axis coordinate value and Z-axis coordinate value of the design model are transformed, so that the coordinate transformation of each precision control point in the design model corresponds one-to-one with the Y-axis coordinate and Z-axis coordinate of each precision control point on the first segment (1) at the installation site; Step S332: Using the point movement function of the analysis software, move the X-axis coordinate, Y-axis coordinate and Z-axis coordinate of the first reference point of the design model of the first segment (1) and the actual first reference point in the mounting site of the first segment (1) to 0; Step S333: Select the third reference point from the multiple key points of the outer plate of the first segment (1), and form a measured reference surface by the first reference point, the second reference point and the third reference point on the first segment (1) in the mounting site. Form a design reference surface by the first reference point, the second reference point and the third reference point in the design model on the first segment (1). Use the three-point movement function of the analysis software to move the Z-axis coordinate values of the first reference point, the second reference point and the third reference point to 0, so that the design reference surface of the first segment (1) coincides with the measured reference surface. Step S334: Display the hidden second segment (2) display status, and select two precision control points from the outer plate shape value point data of the second segment (2); Step S335: Implant reflective sheets at two precision control points on the outer plate of the second segment (2). Step S4 includes the following steps: Step S41: Transport the second segment (2) to the loading site by crane, and adjust the position of the second segment (2) along the length, width and height directions to roughly locate the position of the second segment (2); Step S42: Use a total station to detect the actual coordinate data of multiple key points on the outer plate of the first segment (1) and two precision control points on the second segment (2); Step S43: Compare the positions of the two precision control points on the second segment (2) in the total station to determine the deviation between the actual position of the second segment (2) in the mounting site and the preset installation position; Step S44: Based on the deviation between the actual position and the preset position of the second segment (2) in the mounting site, adjust the position of the second segment (2) along the length, width and height directions by using a crane until the coordinate data of the two precision control points on the second segment (2) in the total station are the same as those of the precision control points on the second segment (2) in the design model. Step S45: Set up a support block on the main steel block to support the second segment (2), release the hook to release the second segment (2), and effectively seal the first segment (1) and the second segment (2). Step S42 includes the following steps: Step S421: Use a total station to detect the coordinate data of the first key point, the second key point, the third key point, and the two precision control points on site; Step S422: Select the first key point, the second key point and the third key point in the total station and move them to three points. Move the Z-axis coordinate values of the first key point, the second key point and the third key point to 0. Obtain the actual coordinate data of the two precision control points on the second segment (2). The height of the first reference point from the ground of the mounting site is not less than 900mm, and the height of the steel pier used for the main assembly is not less than 900mm.
Citation Information
Patent Citations
Control method for ship-body section carrying accuracy based on OTS
CN107499454A
Method for unifying datum point control precision of large ship
CN116552737A