A steam heating power generation system and power system

By using a steam-heated power generation system in adjacent units to preheat the first unit in two stages, the problem of low start-up and shutdown efficiency of thermal power units has been solved, achieving efficient consumption of new energy sources and stable operation of the power system, while reducing fuel consumption and environmental pollution.

CN120120085BActive Publication Date: 2026-11-24NORTH CHINA ELECTRIC POWER UNIV
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202510308584.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2025-03-17
Publication Date
2026-11-24
Estimated Expiration
2045-03-17

AI Technical Summary

Technical Problem

Existing adjacent-unit heating technology cannot effectively cope with the volatility of renewable energy generation, resulting in low start-up and shutdown efficiency of thermal power generating units, insufficient renewable energy consumption ratio, and energy waste and environmental pollution problems.

Method used

The adjacent unit steam heating power generation system is adopted. The second steam path of the second unit heats the first return water path of the first unit, forming a two-stage heating process. This preheats the first boiler to a temperature close to that required for hot flushing, shortens the start-up time, and improves start-up and shutdown efficiency.

Benefits of technology

It improves the start-up and shutdown efficiency of thermal power units, reduces fuel and coal consumption, lowers costs, increases the proportion of new energy consumption, optimizes the energy structure, improves air quality, enhances the stability and reliability of the power system, and extends equipment life.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120120085B_ABST
    Figure CN120120085B_ABST
Patent Text Reader

Abstract

This invention discloses a steam-heated power generation system and power system for adjacent units, belonging to the fields of unit energy saving and rapid start-up and shutdown, new energy consumption, and deep peak shaving technology for thermal power units. It includes a first unit, a second unit, a first coupling pipeline, and a second coupling pipeline. The first unit includes a first steam path and a first return water path; the second unit includes a second steam path and a second return water path; the inlet and outlet of the first coupling pipeline are respectively connected to a first branch port and a first preheating position; the inlet and outlet of the second coupling pipeline are respectively connected to a second branch port and a second preheating position; the first branch port is located upstream of the second branch port, and the first preheating position is located upstream of the second preheating position. In this invention, the first boiler is preheated to near the temperature required for hot flushing by steam from the second boiler before ignition, effectively shortening the start-up time of the first boiler and enabling it to be put into operation more quickly, thereby improving the start-up and shutdown efficiency of the power plant.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the fields of energy saving and rapid start-up and shutdown of generating units, new energy consumption, and deep peak shaving of thermal power units. In particular, it relates to a steam heating power generation system for adjacent units and a power system, or a two-stage adjacent unit boiler steam heating system for deep peak shaving shift start-up and shutdown units that combines new energy consumption. Background Technology

[0002] The inherent characteristics of new energy power generation have brought unprecedented challenges to the stable operation of the power system. Wind power generation, as an important component of new energy power generation, is highly susceptible to the influence of natural wind conditions. In complex and variable wind environments, the power output of wind power generation may fluctuate dramatically by more than 50% in a short period of time. This high degree of uncertainty makes accurate prediction and effective management of wind power generation extremely difficult.

[0003] Similarly, solar power generation faces similar challenges. Its power generation efficiency is strictly limited by sunlight conditions; the alternation of day and night and changes in weather conditions cause solar power generation to exhibit significant intermittent characteristics. During cloudy or rainy weather, the power output of solar power generation may drop to less than 10% of that on sunny days. Such large power fluctuations pose a severe test to the frequency stability, voltage control, and supply-demand balance of the power system, easily causing grid fluctuations, affecting the reliability and stability of power supply, and consequently adversely impacting the quality of electricity used for production and daily life.

[0004] Against this backdrop, traditional thermal power generating units, as an important means of regulating the power system, lack an effective coordination mechanism between their inherent operating mode and the real-time output of renewable energy generation. When renewable energy generation surges, thermal power generating units fail to adjust their load flexibly and in a timely manner, leading to serious energy waste. In some regions, excess thermal power generation even accounts for 10% to 15% of total power generation. Conversely, when renewable energy output drops sharply, thermal power generating units struggle to quickly increase their power output to fill the power gap, requiring several hours to start up to full load, which is far from meeting the rapidly changing demands of electricity.

[0005] Existing adjacent unit heating technology is significantly insufficient in improving the start-up and shutdown efficiency of thermal power generating units and cannot effectively address the challenges posed by the volatility of new energy power generation.

[0006] Therefore, improving the start-up and shutdown efficiency of thermal power generating units and increasing the proportion of renewable energy consumption have become urgent technical challenges. Summary of the Invention

[0007] The purpose of this invention is to provide a steam-heated power generation system and power system for adjacent units to solve the problems existing in the prior art. The system utilizes the second steam path of the second unit to heat the first return water path of the first unit, forming a two-stage heating process. Before ignition, the first boiler is preheated to near the temperature required for hot flushing by the steam from the second boiler, which effectively shortens the start-up time of the first boiler and enables it to be put into operation more quickly, thereby improving the start-up and shutdown efficiency of the power plant.

[0008] To achieve the above objectives, the present invention provides the following solution: This invention provides a steam-heated power generation system for adjacent units, including a first unit, a second unit, a first coupling pipeline, and a second coupling pipeline. The first unit includes a first steam path and a first return water path. The inlet of the first steam path is connected to the outlet of a first boiler, and the outlet of the first steam path is connected to the inlet of a first condenser. The inlet of the first return water path is connected to the outlet of the first condenser, and the outlet of the first return water path is connected to the inlet of the first boiler. The second unit includes a second steam path and a second return water path. The inlet of the second steam path is connected to the outlet of the second boiler, and the outlet of the second steam path is connected to the inlet of the second condenser. The inlet of the second return water path is connected to the outlet of the second condenser, and the outlet of the second return water path is connected to the inlet of the second boiler. The inlet of the first coupling pipeline is connected to a first branch of the second steam path, and the outlet of the first coupling pipeline is connected to a first preheating position of the first return water path. The inlet of the second coupling pipeline is connected to a second branch of the second steam path, and the outlet of the second coupling pipeline is connected to a second preheating position of the second return water path. The first branch is located upstream of the second branch, and the first preheating position is located upstream of the second preheating position.

[0009] In one embodiment, the second steam path includes a second high-pressure cylinder, a second intermediate-pressure cylinder, and a second low-pressure cylinder of a steam turbine arranged in sequence. The first branch port is connected to the outlet of the second boiler, and the second branch port is connected to the outlet of the second high-pressure cylinder of the steam turbine.

[0010] In one embodiment, the second boiler is provided with a second reheater, the outlet of the high-pressure cylinder of the second steam turbine is connected to the inlet of the second reheater, the outlet of the second reheater is connected to the inlet of the intermediate-pressure cylinder of the second steam turbine, the outlet of the intermediate-pressure cylinder of the second steam turbine is connected to the inlet of the low-pressure cylinder of the second steam turbine, and the outlet of the low-pressure cylinder of the second steam turbine is connected to the inlet of the second condenser.

[0011] In one embodiment, the first return water path includes a first condensate pump, a first low-pressure heater, a first deaerator, a first feed water pump, and a first high-pressure heater arranged in sequence, with the first preheating position being the first deaerator and the second preheating position being the first high-pressure heater.

[0012] In one embodiment, the condensate from the first high-pressure heater flows by gravity to the first deaerator, and the condensate from the first low-pressure heater flows by gravity to the first condenser.

[0013] In one embodiment, the first steam path includes a first high-pressure cylinder, a first intermediate-pressure cylinder, and a first low-pressure cylinder of a steam turbine arranged sequentially; the first boiler is equipped with a first reheater, the outlet of the first high-pressure cylinder of the steam turbine is connected to the inlet of the first reheater, the outlet of the first reheater is connected to the inlet of the first intermediate-pressure cylinder of the steam turbine, the outlet of the first intermediate-pressure cylinder of the steam turbine is connected to the inlet of the first low-pressure cylinder of the steam turbine, and the outlet of the first low-pressure cylinder of the steam turbine is connected to the inlet of the first condenser.

[0014] In one embodiment, the inlet of the first deaerator is connected to the outlet of the first low-pressure heater, the extraction steam outlet of the first turbine intermediate-pressure cylinder, and the outlet of the second boiler, respectively, and the outlet of the first deaerator is connected to the first high-pressure heater.

[0015] In one embodiment, the inlet of the first high-pressure heater is connected to the outlet of the first deaerator, the exhaust outlet of the first high-pressure cylinder of the steam turbine, and the outlet of the second high-pressure cylinder of the steam turbine, and the outlet of the first high-pressure heater is connected to the inlet of the first boiler.

[0016] In one embodiment, the second return water path includes a second condensate pump, a second low-pressure heater, a second deaerator, a second feed water pump, and a second high-pressure heater arranged in sequence. The condensate from the second high-pressure heater flows by gravity to the second deaerator, and the condensate from the second low-pressure heater flows by gravity to the second condenser.

[0017] This invention provides a power system, including a power generation system and a control system. The power generation system includes a neighboring steam heating power generation system and a new energy power generation system as described above. The control system includes a central control system, a power plant real-time monitoring system, and a new energy access and monitoring system. The neighboring steam heating power generation system transmits electricity to the power grid through the power plant real-time monitoring system. The new energy power generation system transmits electricity to the power grid through the new energy access and monitoring system. The power grid transmits electricity to users through the central control system. The central control system is connected to the power plant real-time monitoring system and the new energy access and monitoring system respectively through negative feedback regulation.

[0018] The present invention achieves the following technical effects compared to the prior art: This invention utilizes the second steam path of the second unit to heat the first return water path of the first unit, forming a two-stage heating system. On one hand, it leverages the auxiliary steam from the adjacent boiler (second boiler) for preheating, reducing the heat input required by the first boiler during startup, lowering fuel oil and coal consumption, and reducing power consumption of major auxiliary equipment. This further reduces the overall startup cost of the first boiler while improving the energy efficiency and rapid start-up / shutdown performance of the first unit. On the other hand, it allows for more efficient utilization of the heat from the adjacent boiler, improving the overall system efficiency. Thus, the first boiler is preheated to near the temperature required for hot flushing by the steam from the second boiler before ignition, effectively shortening its startup time and enabling it to operate more quickly. This significantly reduces fuel oil consumption during the initial ignition phase, directly lowering fuel oil costs and improving the power plant's start-up / shutdown efficiency.

[0019] Other technical solutions included in this invention can also achieve the following technical effects: Based on improving the start-up and shutdown efficiency of thermal power generating units, the power system of this invention precisely matches the peak generation time of new energy power generation with the shutdown time of coal-fired power units. During the peak generation time of new energy power generation, it assists in regulating the load of thermal power, taps the potential to help grid-connect and consume new energy, optimizes the energy efficiency of the power system, significantly increases the proportion of new energy consumption, promotes green and low-carbon power supply, optimizes the energy structure, and reduces carbon emissions. At the same time, the shift start-up and shutdown strategy optimizes the operation of coal-fired power units, avoids the energy consumption and wear and tear of long-term continuous operation, extends the life of the units, and reduces operating costs.

[0020] In the power system, in order to meet the demand for the consumption of new energy sources, the present invention adopts a relatively frequent start-up and shutdown method for thermal power generator sets. However, by adopting the adjacent steam heating power generation system of the present invention, the emission of harmful gases and particulate matter generated during boiler start-up is reduced by reducing fuel consumption, which helps to improve air quality, reduce environmental pollution, and conforms to the environmental protection concept of sustainable development.

[0021] This invention enables thermal power to respond quickly to fluctuations in new energy sources by flexibly adjusting the start-up and shutdown of the first unit, while increasing the peak-shaving depth to ensure the stability and reliability of power supply, thereby enhancing the peak-shaving capacity of the power system and ensuring the stable operation of power supply.

[0022] This invention enables the cascade utilization of heat, recovers waste heat to reduce costs, rationally utilizes steam heating from adjacent boilers, reduces the start-up energy consumption of the boiler itself, improves the unit's energy efficiency and start-up and shutdown performance, and can also reduce thermal stress and extend equipment life, thus contributing to the sustainable development of the power industry and having high application and promotion value.

[0023] This invention avoids thermal shock to the boiler heating surface caused by sudden changes in water temperature by precisely controlling the feedwater temperature. It reduces the risk of equipment damage caused by excessive thermal stress, reduces thermal shock and temperature fluctuations, extends the service life of the boiler and its auxiliary equipment, reduces long-term operation and maintenance costs, and shortens the boiler start-up time so that the unit can be put into operation more quickly, thereby improving the production efficiency of the power plant. Attached Figure Description

[0024] To more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the drawings used in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.

[0025] Figure 1 This is a schematic diagram of the power system in an embodiment of the present invention; Figure 2 This is a daily load curve diagram in an embodiment of the present invention; Figure 3 This is a power generation curve diagram in an embodiment of the present invention; Figure 4 This is a daily load curve diagram after renewable energy consumption in an embodiment of the present invention; Among them, 1. First boiler; 2. First high-pressure cylinder of first steam turbine; 3. First intermediate-pressure cylinder of first steam turbine; 4. First low-pressure cylinder of first steam turbine; 5. First generator; 6. First condenser; 7. First condensate pump; 8. First low-pressure heater; 9. First deaerator; 10. First feedwater pump; 11. First high-pressure heater; 12. Second boiler; 13. Second steam turbine high-pressure cylinder; 14. Second steam turbine intermediate-pressure cylinder; 15. Second steam turbine low-pressure cylinder; 16. Second generator; 17. Second condenser; 18. Second condensate pump; 19. Second low-pressure heater; 20. Second deaerator; 21. Second feedwater pump; 22. Second high-pressure heater; 23. Wind power generation system; 24. Photovoltaic power generation system; 25. Power grid; 26. Electricity user; 27. Power plant real-time monitoring system; 28. New energy access and monitoring system; 29. ​​Central control system; 100, First coupling pipeline; 200, Second coupling pipeline. Detailed Implementation

[0026] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0027] The purpose of this invention is to provide a steam-heated power generation system and power system for adjacent units to solve the problems existing in the prior art. The system utilizes the second steam path of the second unit to heat the first return water path of the first unit, forming a two-stage heating system. Before ignition, the first boiler is preheated to a temperature close to that required for hot flushing by the steam from the second boiler, which effectively shortens the start-up time of the first boiler and enables it to be put into operation more quickly, thereby improving the start-up and shutdown efficiency of the power plant.

[0028] To make the above-mentioned objects, features and advantages of the present invention more apparent and understandable, the present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments.

[0029] like Figure 1 As shown, this invention provides a neighboring unit steam heating power generation system, including a first unit, a second unit, a first coupling pipeline 100, and a second coupling pipeline 200. The first unit and the second unit are both thermal power generating units, such as air-cooled coal-fired generating units, each equipped with key equipment such as a coal-fired boiler and a steam turbine. The first coupling pipeline 100 and the second coupling pipeline 200 use high-temperature and high-pressure resistant pipes, connecting the first unit and the second unit to form a neighboring unit heating network.

[0030] The first unit includes a first steam path and a first return water path. The first steam path is mainly the path for the operation and work of superheated steam, while the first return water path is mainly the path for the return and reheat of condensate. The inlet of the first steam path is connected to the outlet of the first boiler 1, and the outlet of the first steam path is connected to the inlet of the first condenser 6. The superheated steam generated by the first boiler 1 is condensed into condensate in the first condenser 6 after doing work. The inlet of the first return water path is connected to the outlet of the first condenser 6, and the outlet of the first return water path is connected to the inlet of the first boiler 1. The condensate from the first condenser 6 is preheated before entering the first boiler 1.

[0031] The second unit includes a second steam path and a second return water path. The second steam path is mainly for the operation and work of superheated steam, while the second return water path is mainly for the return and reheat of condensate. The inlet of the second steam path is connected to the outlet of the second boiler 12, and the outlet of the second steam path is connected to the inlet of the second condenser 17. The superheated steam generated by the second boiler 12 is condensed into condensate in the second condenser 17 after performing work. The inlet of the second return water path is connected to the outlet of the second condenser 17, and the outlet of the second return water path is connected to the inlet of the second boiler 12. The condensate from the second condenser 17 is preheated before entering the second boiler 12.

[0032] The inlet of the first coupling pipe 100 is connected to the first branch of the second steam path, and the outlet of the first coupling pipe 100 is connected to the first preheating position of the first return water path. The inlet of the second coupling pipe 200 is connected to the second branch of the second steam path, and the outlet of the second coupling pipe 200 is connected to the second preheating position of the second return water path. Thus, the first return water path of the first unit can utilize steam from the second steam path of the second unit for preheating, forming a two-stage preheating process. The first branch is located upstream of the second branch, and the first preheating position is located upstream of the second preheating position. In other words, during the two-stage preheating process, high-temperature steam is used for the first-stage preheating of low-temperature water, and then the cooled steam is used for the second-stage preheating of the heated water, thus forming a gradient preheating method and improving the heating efficiency of the adjacent unit's steam preheating.

[0033] It should be noted that the configuration mode for the first and second units can be one-to-one, many-to-one, or one-to-many. That is, the first unit can be connected to one or more second units, and multiple first units can be connected to one second unit, thus forming various start-up and shutdown strategies and achieving rational and effective utilization of steam. Different configuration modes can be adjusted by changing the number of the first coupling pipe 100 and the second coupling pipe 200.

[0034] This invention utilizes the second steam path of the second unit to heat the first return water path of the first unit, forming a two-stage heating system. On one hand, it utilizes the auxiliary steam from the adjacent boiler (second boiler 12) for preheating, reducing the heat input required by the main boiler (first boiler 1) during startup, lowering fuel oil and coal consumption, and reducing power consumption of major auxiliary equipment. This further reduces the overall startup cost of the first boiler 1 while improving the energy efficiency and rapid start-up / shutdown performance of the first unit. On the other hand, it allows for more efficient utilization of the heat from the adjacent boiler, improving the overall system efficiency. Thus, the first boiler 1 is preheated to near the temperature required for hot flushing by the steam from the second boiler 12 before ignition, effectively shortening its startup time and enabling it to operate more quickly. This significantly reduces fuel oil consumption during the initial ignition phase, directly lowering fuel oil costs and improving the power plant's start-up / shutdown efficiency.

[0035] The adjacent-unit steam heating power generation system of this invention, as a thermal power unit, can be organically coupled with diversified new energy power generation systems such as wind power system 23 and photovoltaic power generation system 24. It is connected to the power grid 25 for power supply through a dynamic monitoring system (power plant real-time monitoring system 27 and new energy access and monitoring system 28). At night, when new energy output is low, both units operate simultaneously to ensure basic electricity supply for users 26. During the day, when new energy resources are abundant, one unit is shut down to expand the absorption of new energy and enhance the peak-shaving depth of the thermal power unit. At this time, the peak power generation of new energy lasts for about 8 hours. During this period, the shut-down shift unit is in a hot-start state and can achieve rapid startup by relying on the adjacent-unit steam heating power generation system.

[0036] In one embodiment, the second steam path includes a second turbine high-pressure cylinder 13, a second turbine intermediate-pressure cylinder 14, and a second turbine low-pressure cylinder 15 arranged sequentially. These three cylinders are coaxially connected and drive a second generator 16 to generate electricity. A first branch port connects to the outlet of the second boiler 12, and a second branch port connects to the outlet of the second turbine high-pressure cylinder 13. That is, the steam at the first branch port is superheated steam generated by the second boiler 12, while the steam at the second branch port is steam after work has been done by the second turbine high-pressure cylinder 13. The steam at the first and second branch ports has different temperatures, heating different locations in the first return water path to achieve a gradient heating method.

[0037] In one embodiment, the second boiler 12 is equipped with a second reheater. The outlet of the high-pressure cylinder 13 of the second steam turbine is connected to the inlet of the second reheater, the outlet of the second reheater is connected to the inlet of the intermediate-pressure cylinder 14 of the second steam turbine, the outlet of the intermediate-pressure cylinder 14 is connected to the inlet of the low-pressure cylinder 15 of the second steam turbine, and the outlet of the low-pressure cylinder 15 is connected to the inlet of the second condenser 17. In the second unit, the superheated steam generated by the second boiler 12 first enters the high-pressure cylinder 13 of the second steam turbine, then enters the second reheater for reheating, and then sequentially enters the intermediate-pressure cylinder 14 and the low-pressure cylinder 15 of the second steam turbine, finally entering the second condenser 17 for condensation. This fully utilizes the energy of the steam and ensures the power generation efficiency of the second unit.

[0038] In one embodiment, the first return water path includes a first condensate pump 7, a first low-pressure heater 8, a first deaerator 9, a first feedwater pump 10, and a first high-pressure heater 11 arranged sequentially. In the first unit, the condensate from the first condenser 6, pumped by the first condensate pump 7, first enters the first low-pressure heater 8 for preheating, then enters the first deaerator 9 for deoxygenation and other treatments, and then enters the first high-pressure heater 11 for reheating under the action of the first feedwater pump 10, finally entering the first boiler 1. The first preheating location is the first deaerator 9, that is, the steam from the second steam path heats the return water in the first deaerator 9, realizing multiple possible heat transfer paths, enabling the system to flexibly adjust the heat distribution according to actual needs, improving the system's adaptability and flexibility; the second preheating location is the first high-pressure heater 11, that is, the steam from the second steam path heats the return water in the first high-pressure heater 11, realizing more efficient utilization of the heat from the adjacent boiler, while improving the system's stability and reliability, forming a highly efficient two-stage adjacent boiler steam heating power generation system.

[0039] The outlet of the second boiler 12 is connected to the inlet of the first deaerator 9, enabling the boiler (the first boiler 1 of the first unit) to use auxiliary steam from the adjacent boiler (the second boiler 12 of the second unit) for primary heating and preheating. This reduces the heat input required by the boiler during startup, thereby lowering fuel oil and coal consumption, and also reducing the power consumption of the main auxiliary equipment. The outlet of the high-pressure cylinder 13 of the second turbine is connected to the inlet of the first high-pressure heater 11, enabling the boiler to use auxiliary steam from the adjacent boiler for secondary heating. This further reduces the overall startup cost of the boiler, while improving the unit's energy efficiency and rapid start-up / shutdown performance. Through secondary heating, the heat from the adjacent boiler can be utilized more fully, improving the overall system efficiency.

[0040] In one embodiment, the condensate from the first high-pressure heater 11 flows by gravity to the first deaerator 9, and the condensate from the first low-pressure heater 8 flows by gravity to the first condenser 6.

[0041] In one embodiment, the first steam path includes a first turbine high-pressure cylinder 2, a first turbine intermediate-pressure cylinder 3, and a first turbine low-pressure cylinder 4 arranged sequentially. These three are coaxially connected and drive a first generator 5 to generate electricity. The first boiler 1 is equipped with a first reheater. The outlet of the first turbine high-pressure cylinder 2 is connected to the inlet of the first reheater, the outlet of the first reheater is connected to the inlet of the first turbine intermediate-pressure cylinder 3, the outlet of the first turbine intermediate-pressure cylinder 3 is connected to the inlet of the first turbine low-pressure cylinder 4, and the outlet of the first turbine low-pressure cylinder 4 is connected to the inlet of the first condenser 6. In the first unit, the superheated steam generated by the first boiler 1 first enters the first turbine high-pressure cylinder 2, then enters the first reheater for heating, then sequentially enters the first turbine intermediate-pressure cylinder 3 and the first turbine low-pressure cylinder 4, and finally enters the first condenser 6 for condensation, fully utilizing the energy of the steam and ensuring the power generation efficiency of the first unit.

[0042] In the first unit, the outlet of the first condenser 6 is connected to the inlet of the first condensate pump 7, the outlet of the first condensate pump 7 is connected to the inlet of the first low-pressure heater 8, the outlet of the first low-pressure heater 8, the extraction steam outlet of the first turbine intermediate-pressure cylinder 3, the condensate outlet of the first high-pressure heater 11, and the outlet of the second boiler 12 are all connected to the inlet of the first deaerator 9, the outlet of the first deaerator 9 is connected to the inlet of the first feedwater pump 10, the outlet of the first feedwater pump 10, the extraction steam outlet of the first turbine high-pressure cylinder 2, and the outlet of the second turbine high-pressure cylinder 13 are all connected to the inlet of the first high-pressure heater 11, and the outlet of the first high-pressure heater 11 is connected to the inlet of the first boiler 1. This realizes multiple heat transfer paths and efficient heat utilization methods within the system, optimizes heat distribution and circulation, improves heat utilization rate and overall system energy efficiency, enhances the system's adaptability, flexibility, stability, and reliability to different operating conditions and load demands, and reduces operating costs.

[0043] In one embodiment, the inlet of the first deaerator 9 is connected to the outlet of the first low-pressure heater 8, the extraction steam outlet of the first turbine intermediate-pressure cylinder 3, and the outlet of the second boiler 12. The outlet of the first deaerator 9 is connected to the first high-pressure heater 11. Within the first deaerator 9, the system can be heated by both the extraction steam from the first turbine intermediate-pressure cylinder 3 and the steam from the second boiler 12, thereby improving the primary preheating capacity and achieving diverse heat transfer capabilities. This allows the system to better adapt to different operating conditions and load requirements.

[0044] In one embodiment, the inlet of the first high-pressure heater 11 is connected to the outlet of the first deaerator 9, the exhaust outlet of the first high-pressure cylinder 2 of the steam turbine, and the outlet of the second high-pressure cylinder 13 of the steam turbine. The outlet of the first high-pressure heater 11 is connected to the inlet of the first boiler 1. The first high-pressure heater 11 can be heated by both the exhaust gas from the first high-pressure cylinder 2 and the steam from the second high-pressure cylinder 13, improving the secondary preheating capacity, optimizing the heat transfer path of the system, increasing heat utilization, and reducing the system's operating costs.

[0045] The outlet of the second boiler 12 is connected to the inlet of the first deaerator 9, the outlet of the first deaerator 9 is connected to the inlet of the first feedwater pump 10, the outlet of the first feedwater pump 10 is connected to the inlet of the first high-pressure heater 11, and the outlet of the first high-pressure heater 11 is connected to the inlet of the first boiler 1. This heat transfer method realizes a coupled heat circulation system between the first and second units, enabling more efficient heat utilization and improving the overall energy efficiency of the system. The outlet of the second boiler 12 is connected to the inlet of the high-pressure cylinder 13 of the second turbine, the outlet of the high-pressure cylinder 13 of the second turbine is connected to the inlet of the first high-pressure heater 11, and the outlet of the first high-pressure heater 11 is connected to the inlet of the first boiler 1. This heat transfer method realizes another efficient heat utilization method coupling the first and second units, not only enabling more efficient heat utilization and improving overall energy efficiency, but also allowing for flexible adoption of various operating strategies according to actual conditions, improving the system's flexibility and adaptability.

[0046] In one embodiment, the second return water path includes a second condensate pump 18, a second low-pressure heater 19, a second deaerator 20, a second feedwater pump 21, and a second high-pressure heater 22 arranged sequentially. In the second unit, the condensate from the second condenser 17, pumped by the second condensate pump 18, first enters the second low-pressure heater 19 for preheating, then enters the second deaerator 20 for deoxygenation and other treatments, and then enters the second high-pressure heater 22 for reheating under the action of the second feedwater pump 21, finally entering the second boiler 12. The condensate from the second high-pressure heater 22 flows by gravity to the second deaerator 20, and the condensate from the second low-pressure heater 19 flows by gravity to the second condenser 17.

[0047] like Figure 1As shown, this invention provides a power system including a power generation system and a control system. The power generation system includes a steam-heated power generation system with adjacent turbines as described above and a new energy power generation system. The new energy power generation system may include a photovoltaic power generation system 24 and a wind power generation system 23. The control system includes a central control system 29, a power plant real-time monitoring system 27, and a new energy access and monitoring system 28. The steam-heated power generation system with adjacent turbines transmits electricity to the power grid 25 through the power plant real-time monitoring system 27. The new energy power generation system transmits electricity to the power grid 25 through the new energy access and monitoring system 28. The power grid 25 transmits electricity to users 26 through the central control system 29. The central control system 29 is connected to the power plant real-time monitoring system 27 and the new energy access and monitoring system 28 respectively through negative feedback regulation.

[0048] In one embodiment, in the adjacent steam heating power generation system, both the first and second units are air-cooled coal-fired generator sets. The high-pressure cylinder 2, intermediate-pressure cylinder 3, and low-pressure cylinder 4 of the first turbine are coaxially connected, driving the first generator 5 to generate electricity. The superheated steam outlet of the first boiler 1 is connected to the inlet of the high-pressure cylinder 2 of the first turbine. The outlet of the high-pressure cylinder 2 is connected to the reheater of the first boiler 1. The outlet of the reheater of the first boiler 1 is connected to the intermediate-pressure cylinder 3 of the first turbine. The intermediate-pressure cylinder 3, low-pressure cylinder 4, and first condenser 6 are sequentially connected. The outlet pipe of the water tank of the first condenser 6 is sequentially connected to the first condensate pump 7, the first low-pressure heater 8, the first deaerator 9, the first feedwater pump 10, and the first high-pressure heater 11. The first low-pressure heater 8 uses the extracted steam from the low-pressure cylinder 4 of the first steam turbine as its heat source; the first deaerator 9 uses the extracted steam from the intermediate-pressure cylinder 3 of the first steam turbine and the steam from the second boiler 12 as its heat source; and the first high-pressure heater 11 uses the extracted steam from the high-pressure cylinder 2 of the first steam turbine and the reheat cold-end steam from the second boiler 12 as its heat source. The condensate from the first high-pressure heater 11 and the first low-pressure heater 8 flows by gravity in stages, collecting in the water tanks of the first deaerator 9 and the first condenser 6, respectively. The high-pressure cylinder 13, intermediate-pressure cylinder 14, and low-pressure cylinder 15 of the second steam turbine are coaxially connected, driving the second generator 16 to generate electricity. The superheated steam outlet of the second boiler 12 is connected to the high-pressure cylinder 13 of the second steam turbine and the inlet of the first deaerator 9. The outlet of the high-pressure cylinder 13 of the second steam turbine is connected to the reheater of the second boiler 12 and the first high-pressure heater 11. The outlet of the reheater of the second boiler 12 is connected to the intermediate-pressure cylinder 14 of the second steam turbine. The intermediate-pressure cylinder 14, low-pressure cylinder 15, and second condenser 17 are connected sequentially. The outlet pipe of the water tank of the second condenser 17 is sequentially connected to the second condensate pump 18, the second low-pressure heater 19, the second deaerator 20, the second feedwater pump 21, and the second high-pressure heater 22. The second high-pressure heater 22, the second deaerator 20, and the second low-pressure heater 19 each use extracted steam with a pressure matched to the steam turbine as their heat source. The condensate from the second high-pressure heater 22 and the second low-pressure heater 19 flows by gravity in stages and is collected in the second deaerator 20 and the second condenser 17, respectively.

[0049] This invention enables precise control of thermal power units to adapt to the characteristics of new energy sources, significantly improving the absorption of new energy, optimizing the energy structure, and reducing carbon emissions. Thermal power can quickly respond to fluctuations in new energy sources while increasing peak-shaving depth to ensure power supply stability and reliability. The adjacent unit heating and power generation system enables cascade utilization of heat, recovering waste heat to reduce costs. The rational use of steam heating from adjacent unit boilers reduces the energy consumption of the unit's boiler startup, improves unit energy efficiency and start-up / shutdown performance, reduces thermal stress, and extends equipment lifespan, contributing to the sustainable development of the power industry and demonstrating high application and promotion value.

[0050] With the rapid development of new energy power generation, especially in areas rich in new energy resources, new energy power generation (such as photovoltaic power generation and wind power generation) can supply a large amount of electricity during certain periods of the day, while its power generation capacity is weak at other times. Due to the instability of new energy power supply, it is difficult to supply new energy power to the grid, resulting in insufficient absorption of new energy power and waste. By adopting the power system of this invention, an operation strategy of rotating the start-up and shutdown of at least two sets of units in the adjacent steam-heated power generation system can be adopted, which can make full use of new energy power while ensuring the stability and economy of power supply. This strategy aims to improve the operating efficiency of the entire power system by rationally arranging the start-up and shutdown of coal-fired power units to form a good complement to new energy power generation.

[0051] In one implementation, such as Figures 1-4 As shown, the present invention provides an application example of a power system as follows: A certain location is selected as a typical application scenario, and its daily load curve is shown below. Figure 2 As shown, the characteristics are obvious. Specifically, during a period of approximately 8 hours during the daytime, due to abundant sunshine and strong winds, photovoltaic and wind power generation perform exceptionally well, with their renewable energy generation reaching [a certain level]. Figure 3 As shown, the power generation from new energy sources has increased significantly. To fully utilize this advantageous resource, the power system of this invention reduces the output of coal-fired power units during this period, shutting down one of the two air-cooled coal-fired power units, thereby increasing the proportion of new energy consumption and achieving a green and low-carbon power supply. In the afternoon, the output of new energy remains basically unchanged, but the electricity demand of user 26 decreases, and activating a single unit can further increase the peak-shaving depth. During the nighttime period, due to the smaller amount of new energy power generation, coal-fired power units must undertake the main power generation task to ensure a stable power supply. Due to the presence of the adjacent unit steam heating power generation system, the units that are started and stopped in shifts can be preheated to near the temperature required for hot flushing by the steam from the adjacent unit boiler before boiler ignition, significantly reducing fuel consumption in the initial stage of ignition and directly reducing fuel costs. Meanwhile, by precisely controlling the feedwater temperature, the problem of thermal shock to the boiler heating surface caused by sudden changes in water temperature is avoided, the risk of equipment damage caused by excessive thermal stress is reduced, thermal shock and temperature fluctuations are reduced, the service life of the boiler and its auxiliary equipment is extended, long-term operation and maintenance costs are reduced, and the boiler start-up time is shortened so that the unit can be put into operation more quickly, thereby improving the power plant's production efficiency.

[0052] During normal operation of the power system, the new energy access and monitoring system 28 continuously collects power output data from new energy sources and meteorological information. The central control system 29 updates and analyzes the data at regular intervals, and determines whether to issue instructions to the power plant real-time monitoring system 27 to perform shift start-up and shutdown operations of the generating units based on preset algorithms and strategies.

[0053] When the central control system 29 determines that the unit's operating status needs adjustment, it first sends instructions to the power plant's real-time monitoring system 27 to gradually adjust the unit's load and operating parameters in preparation for shutdown or startup. Simultaneously, the adjacent unit's steam heating and power generation system initiates the corresponding heating program, adjusting the flow rate and temperature of the heating medium to ensure the shutdown unit (e.g., ...) is kept running. Figure 1 The temperature of the unit (with the first unit shut down and the second unit running) is kept stable within a suitable range and can quickly reach the predetermined temperature conditions upon startup.

[0054] Throughout the operation, the power plant's real-time monitoring system 27 monitors the operating status of each unit and the operation of the adjacent unit's steam heating and power generation system, while the new energy access and monitoring system 28 monitors changes in the output of new energy sources. Operators can manually intervene and adjust both systems through the central control system 29 according to actual conditions, such as pausing or starting a device in an emergency or modifying control parameters. However, such manual operations require strict authorization authentication and operation records to ensure the system's safety and stability.

[0055] When the system detects abnormal fluctuations in the output of new energy sources (such as a sudden and significant drop or rise), a malfunction in the unit operation (such as equipment tripping, abnormal parameters, etc.), or a malfunction in the steam heating and power generation system of an adjacent unit (such as pipeline leakage, pump failure, etc.), the central control system 29 immediately initiates the corresponding abnormal situation handling procedure.

[0056] Taking a 660MW supercritical unit as an example, this invention further illustrates the shift-based start-up and shutdown strategy. Under hot-start conditions, the corresponding downtime for this unit is 1 to 10 hours, which closely matches the peak duration of renewable energy generation. Therefore, this invention proposes a highly efficient peak-shaving scheme for shift-based start-up and shutdown of multiple units: during the daytime of peak renewable energy generation, by timely shutting down some of these units, power output is flexibly adjusted to maximize the utilization of renewable energy and further increase the amount of renewable energy absorbed. Taking the daily load after renewable energy absorption in a certain area as an example, its curve is as follows... Figure 4As shown. This simultaneously improves the operational economy of coal-fired power units, reducing energy consumption and wear caused by prolonged continuous operation. When the output of new energy sources weakens, other units are gradually started to ensure the stability and reliability of power supply. This strategy is not only applicable to single-unit operation scenarios. In a 4×660MW power plant, by shutting down one or two units, the peak-shaving depth can be reduced to 15% and 10% of the plant's rated load, respectively, significantly improving peak-shaving capacity and enabling it to cope with the volatility and uncertainty of new energy power generation, ensuring stable operation and efficient power supply of the power system. For a 4×660MW power plant, under the condition of maintaining the total output of the power plant, after adopting a shift-based peak-shaving strategy, compared to all four units operating at minimum load, the critical times for shutting down one and two units are 4.81 hours and 6.57 hours, respectively, with total coal savings of 184.84t and 270.49t, and cost savings of approximately RMB 70,600 and RMB 46,300. Therefore, it can be seen that the present invention has significant advantages in increasing the proportion of new energy consumption, enhancing the peak shaving depth of thermal power units, and realizing the feasibility and practicality of unit shift start-up and shutdown.

[0057] Specific examples have been used to illustrate the principles and implementation methods of this invention. The descriptions of the above embodiments are only for the purpose of helping to understand the method and core ideas of this invention. Furthermore, those skilled in the art will recognize that, based on the ideas of this invention, there will be changes in the specific implementation methods and application scope. Therefore, the content of this specification should not be construed as a limitation of this invention.

Claims

1. A power system, characterized in that, include: The power generation system includes an adjacent steam heating power generation system and a new energy power generation system; The adjacent steam heating power generation system includes: The first unit includes a first steam path and a first return water path. The inlet of the first steam path is connected to the outlet of the first boiler (1). The outlet of the first steam path is connected to the inlet of the first condenser (6). The inlet of the first return water path is connected to the outlet of the first condenser (6). The outlet of the first return water path is connected to the inlet of the first boiler (1). The second unit includes a second steam path and a second return water path. The inlet of the second steam path is connected to the outlet of the second boiler (12), the outlet of the second steam path is connected to the inlet of the second condenser (17), the inlet of the second return water path is connected to the outlet of the second condenser (17), and the outlet of the second return water path is connected to the inlet of the second boiler (12). The first coupling pipeline has its inlet connected to the first branch port of the second steam path and its outlet connected to the first preheating position of the first return water path. The second coupling pipeline has its inlet connected to the second branch of the second steam path and its outlet connected to the second preheating position of the first return water path. The first branch is located upstream of the second branch and the first preheating position is located upstream of the second preheating position. The second steam path includes a second high-pressure cylinder (13), a second intermediate-pressure cylinder (14), and a second low-pressure cylinder (15) of a steam turbine arranged in sequence. The first branch is connected to the outlet of the second boiler (12) and the second branch is connected to the outlet of the second high-pressure cylinder (13). The first return water path includes a first condensate pump (7), a first low-pressure heater (8), a first deaerator (9), a first feedwater pump (10), and a first high-pressure heater (11) arranged in sequence. The first preheating position is the first deaerator (9) and the second preheating position is the first high-pressure heater (11). The system includes a central control system (29), a power plant real-time monitoring system (27), and a new energy access and monitoring system (28). The adjacent steam heating power generation system transmits electricity to the power grid (25) through the power plant real-time monitoring system (27). The new energy power generation system transmits electricity to the power grid (25) through the new energy access and monitoring system (28). The power grid (25) transmits electricity to the electricity user (26) through the central control system (29). The central control system (29) is connected to the power plant real-time monitoring system (27) and the new energy access and monitoring system (28) respectively through negative feedback regulation. The power plant real-time monitoring system (27) monitors the operating status of the adjacent steam heating power generation system in real time, and the new energy access and monitoring system (28) monitors the output changes of the new energy. The central control system (29) is configured to control the second unit to operate normally and the first unit to shut down during the daytime when the power generation performance of the new energy power generation system is excellent, and to start the first unit when the power generation of the new energy power generation system is low during the nighttime.

2. The power system according to claim 1, characterized in that: The second boiler (12) is equipped with a second reheater. The outlet of the second high-pressure cylinder (13) of the second steam turbine is connected to the inlet of the second reheater. The outlet of the second reheater is connected to the inlet of the intermediate-pressure cylinder (14) of the second steam turbine. The outlet of the intermediate-pressure cylinder (14) of the second steam turbine is connected to the inlet of the low-pressure cylinder (15) of the second steam turbine. The outlet of the low-pressure cylinder (15) of the second steam turbine is connected to the inlet of the second condenser (17).

3. The power system according to claim 1, characterized in that: The condensate from the first high-pressure heater (11) flows by gravity to the first deaerator (9), and the condensate from the first low-pressure heater (8) flows by gravity to the first condenser (6).

4. The power system according to claim 1, characterized in that: The first steam path includes a first high-pressure cylinder (2), a first intermediate-pressure cylinder (3), and a first low-pressure cylinder (4) of a steam turbine arranged in sequence; the first boiler (1) is equipped with a first reheater, the outlet of the first high-pressure cylinder (2) of the steam turbine is connected to the inlet of the first reheater, the outlet of the first reheater is connected to the inlet of the first intermediate-pressure cylinder (3) of the steam turbine, the outlet of the first intermediate-pressure cylinder (3) of the steam turbine is connected to the inlet of the first low-pressure cylinder (4) of the steam turbine, and the outlet of the first low-pressure cylinder (4) of the steam turbine is connected to the inlet of the first condenser (6).

5. The power system according to claim 4, characterized in that: The inlet of the first deaerator (9) is connected to the outlet of the first low-pressure heater (8), the extraction steam outlet of the first steam turbine intermediate-pressure cylinder (3), and the outlet of the second boiler (12), respectively. The outlet of the first deaerator (9) is connected to the first high-pressure heater (11).

6. The power system according to claim 5, characterized in that: The inlet of the first high-pressure heater (11) is connected to the outlet of the first deaerator (9), the exhaust outlet of the first high-pressure cylinder (2) of the steam turbine, and the outlet of the second high-pressure cylinder (13) of the steam turbine. The outlet of the first high-pressure heater (11) is connected to the inlet of the first boiler (1).

7. The power system according to claim 5, characterized in that: The second return water path includes a second condensate pump (18), a second low-pressure heater (19), a second deaerator (20), a second feed water pump (21), and a second high-pressure heater (22) arranged in sequence. The condensate from the second high-pressure heater (22) flows by gravity to the second deaerator (20), and the condensate from the second low-pressure heater (19) flows by gravity to the second condenser (17).

Citation Information

Patent Citations

  • System for increasing boiler feed water temperature during pipe blowing period and using method thereof

    CN112944321A

  • Novel thermal power flexibility transformation peak regulation system based on high-temperature heat storage facility

    CN113452084A

  • System and method for improving operation efficiency of power station unit

    CN118517688A