Underground structure construction method

By using a pipe jacking method with a reinforced concrete closed frame in the construction of underground road structures, the problems of settlement and collapse in densely populated areas of existing buildings and structures were solved, improving construction safety and environmental protection.

CN120444030BActive Publication Date: 2026-11-24BEIJING GENERAL MUNICIPAL ENG DESIGN & RES INST +1
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202510640456.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2025-05-19
Publication Date
2026-11-24
Estimated Expiration
2045-05-19

AI Technical Summary

Technical Problem

Existing underground road construction methods are prone to causing settlement and collapse in areas with dense existing buildings and structures, affecting the normal operation of the upper road traffic infrastructure and adjacent buildings and structures.

Method used

The method involves arranging pipe curtain tools in the cross-sectional structure of the proposed underground road, and jacking in the first and second batches of pipe curtain combined section steel pipes along the longitudinal axis to form a closed curtain. The prefabricated reinforced concrete closed frame structure is then used to replace the pipe curtain steel pipes to complete the construction of the underground road structure.

Benefits of technology

It improved construction safety, avoided disturbance and settlement risks to the surrounding environment, ensured the normal operation of the upper road and adjacent buildings and structures, and achieved low-impact construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120444030B_ABST
    Figure CN120444030B_ABST
Patent Text Reader

Abstract

This invention discloses a method for constructing underground structures. The method includes: arranging pipe jacking tools at the centerline of the cross-sectional structure of the proposed underground road; jacking in the first batch of pipe jacking tools along the longitudinal axis of the proposed underground road; jacking in the first batch of pipe jacking composite section steel pipes to replace the first batch of pipe jacking tools; jacking in the gaps between the first batch of pipe jacking composite section steel pipes; jacking in the second batch of pipe jacking composite section steel pipes to replace the second batch of pipe jacking tools; and fixing the adjacent portions of the first batch of pipe jacking composite section steel pipes and the adjacent second batch of pipe jacking composite section steel pipes with first fasteners to form an overall frame of composite section steel pipes. This invention improves the safety of underground construction.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of underground engineering construction technology, and more specifically to a method for constructing underground structures. Background Technology

[0002] With rapid economic development and the continued acceleration of urbanization, large and mega-cities are exhibiting a strong siphon effect on population and social resources. At the same time, traffic congestion has become the biggest obstacle to urban development, and the contradiction between traffic demand and spatial resources is becoming increasingly acute. Traditional surface road systems can no longer meet the ever-increasing traffic flow and the needs of urban functional expansion. Constructing underground road systems is an effective way to solve urban traffic congestion and optimize urban spatial layout.

[0003] The demand for densifying road traffic infrastructure networks, constructing integrated above-ground and underground transportation systems, and fully developing and utilizing three-dimensional space resources is growing. It is common for newly constructed underground roads to pass under existing surface roads, railway lines, rail transit lines, or other buildings and structures.

[0004] The construction of new underground roads faces the dual challenges of complex geological conditions and the protection of surrounding environmental risks. It requires that the construction of new underground roads, while ensuring safety, should minimize the demolition and alteration of adjacent buildings or pipelines, minimize the impact on existing traffic, minimize the disturbance to the surrounding environment, ensure construction safety and environmental safety, and achieve low-impact construction.

[0005] In related technologies, the main methods used in the construction of underground road structures include open-cut method, mining method (cut-and-cover method), and shield tunneling method. In areas with dense existing buildings and structures, a combined construction method of "advanced pipe jacking + integral jacking box culvert" is often adopted. This method can form an advanced support structure in the stratum without affecting the normal traffic on the surface road, providing conditions for subsequent excavation and structural jacking. However, existing technical methods have many shortcomings: such as high precision requirements for pipe jacking layout, long construction period, and significant disturbance to the surrounding stratum during jacking construction, which can easily lead to settlement or even collapse of the upper road or adjacent buildings and structures. Summary of the Invention

[0006] The present invention aims to provide a construction method for underground road structures, which can solve the problem in related technologies that the construction of underground road structures causes the collapse and settlement of the upper road traffic infrastructure and existing buildings (structures), thereby affecting normal operation.

[0007] According to one aspect of the present invention, a method for constructing an underground structure is provided, comprising: arranging pipe jacking tool pipes at the centerline of the cross-sectional structure of the proposed underground road; jacking in a first batch of pipe jacking tool pipes along the longitudinal axis of the proposed underground road, wherein the first batch of pipe jacking tool pipes are arranged at intervals and constructed using a skip-hole jacking method; jacking in a first batch of pipe jacking composite section steel pipes along the longitudinal axis of the proposed underground road to replace the first batch of pipe jacking tool pipes, wherein the outer diameter of the first batch of pipe jacking composite section steel pipes is equal to the outer diameter of the first batch of pipe jacking tool pipes; jacking in a second batch of pipe jacking tool pipes through the gaps between the first batch of composite section steel pipes; jacking in a second batch of pipe jacking composite section steel pipes to replace the second batch of pipe jacking tool pipes, wherein the outer diameter of the second batch of pipe jacking composite section steel pipes is equal to the outer diameter of the second batch of pipe jacking tool pipes, and the first batch of pipe jacking composite section steel pipes and the second batch of pipe jacking tool pipes... The combined cross-section steel pipes form a closed curtain; the adjacent portions of the first batch of combined cross-section steel pipes and the adjacent second batch of combined cross-section steel pipes are fixed by the first fastener to form an overall frame of combined cross-section steel pipes; the reinforced concrete closed frame structure of the proposed underground road is prefabricated; the second fasteners of the first batch of combined cross-section steel pipes and the third fasteners of the second batch of combined cross-section steel pipes are removed; the reinforced concrete closed frame structure of the proposed underground road is jacked in as a whole, replacing the first replacement portion in the overall frame of the first batch of combined cross-section steel pipes and the second replacement portion in the overall frame of the second batch of combined cross-section steel pipes, thus completing the replacement of the proposed underground road structure; the soil inside the reinforced concrete closed frame structure of the proposed underground road is excavated to form the space required for underground passage, thus completing the construction of the underground road structure.

[0008] Preferably, the first batch of pipe jacking tool tubes includes: the first batch of pipe jacking tool tubes is divided into multiple segments along the longitudinal axis of the proposed underground road, the multiple segments are connected end to end and run through the entire length of the proposed underground road, wherein the cross-section of the first batch of pipe jacking tool tubes is circular, and the internal space of the first batch of pipe jacking tool tubes is used to discharge excavated soil during the jacking construction of the first batch of pipe jacking tool tubes.

[0009] Preferably, the first batch of pipe-jacking composite section steel pipes, replacing the first batch of pipe-jacking tool pipes, includes: the first batch of pipe-jacking composite section steel pipes includes: a first steel component part and a plain concrete part; wherein, the first steel component part includes a first retention part, a first replacement part, and a first demolition part, the interiors of the first retention part, the first replacement part, and the first demolition part are welded together as a whole, and the contact surfaces between the first retention part, the first replacement part, and the first demolition part are connected by a second fastener; the first batch of pipe-jacking composite section steel pipes are divided into multiple segments along the longitudinal axis of the proposed underground road, the multiple segments are connected end to end, and run through the entire length of the proposed underground road.

[0010] Preferably, the type of the first pipe curtain composite section steel pipe includes at least one of the following: L-type, type I, and type T;

[0011] The L-shaped section is located at the connection between the side wall and the top slab, and the connection between the side wall and the bottom slab of the cross section of the proposed underground road structure; the I-shaped section is located at the position of the top slab and the bottom slab of the cross section of the proposed underground road structure; and the T-shaped section is located at the connection between the middle wall and the top slab, and the connection between the middle wall and the bottom slab of the cross section of the proposed underground road structure.

[0012] Preferably, jacking a second batch of pipe jacking tool pipes through the gaps in the first batch of pipe jacking composite section steel pipes includes: cutting the plain concrete portion of the first batch of pipe jacking tool pipes during the jacking construction of the second batch of pipe jacking tool pipes; wherein the second batch of pipe jacking tool pipes is divided into multiple segments along the longitudinal axis of the proposed underground road, the multiple segments being connected end to end and running through the entire length of the proposed underground road, wherein the cross-section of the second batch of pipe jacking tool pipes is circular, and the internal space of the second batch of pipe jacking tool pipes is used for discharging excavated soil during the jacking construction of the second batch of pipe jacking tool pipes.

[0013] Preferably, the process of jacking in the second batch of pipe jacking composite section steel pipes and replacing the second batch of pipe jacking tool pipes includes: the second batch of pipe jacking composite section steel pipes includes a second steel component portion, wherein the second steel component portion includes: a second retention portion, a second replacement portion, and a second dismantling portion, the interiors of the second retention portion, the second replacement portion, and the second dismantling portion are welded together as a whole, and the contact surfaces between the second retention portion, the second replacement portion, and the second dismantling portion are connected by a third fastener; the second batch of pipe jacking composite section steel pipes are divided into multiple segments along the longitudinal axis of the proposed underground road, the multiple segments are connected end to end, and run through the entire passage of the proposed underground road; the first batch of pipe jacking composite section steel pipes and the second batch of pipe jacking composite section steel pipes are structurally interlocked to form a closed composite section steel pipe overall frame.

[0014] Preferably, the first batch of pipe-jacking composite section steel pipes and the adjacent portion of the second batch of pipe-jacking composite section steel pipes are fixed with a first fastener to form an overall frame of composite section steel pipes. This includes: recombining the first batch of pipe-jacking composite section steel pipes and the second batch of pipe-jacking composite section steel pipes by dismantling and connecting them through the following steps: connecting the first replacement portion and the second replacement portion of the first batch of pipe-jacking composite section steel pipes and the second batch of pipe-jacking composite section steel pipes into a whole; removing the second fastener between the following components: between the first retained portion and the first replacement portion; between the first replacement portion and the first dismantled portion; removing the third fastener between the following components: between the second retained portion and the second replacement portion; between the second replacement portion and the second dismantled portion; the first replacement portion and the second replacement portion are fixed with the first fastener; wherein, the first replacement portion and the first retained portion are separated, the first replacement portion and the first dismantled portion are separated, the second replacement portion and the second retained portion are separated, and the second replacement portion and the second dismantled portion are separated.

[0015] Preferably, after the reinforced concrete closed frame structure of the proposed underground road is jacked up as a whole, replacing the first replacement part in the first batch of pipe-jacking composite section steel pipe overall frame and the second replacement part in the second batch of pipe-jacking composite section steel pipe overall frame, and the structural replacement of the proposed underground road is completed, the method further includes: excavating the interior of the reinforced concrete closed frame structure of the proposed underground road after it has been jacked up and placed in place, and removing the first removal part and the second removal part.

[0016] Preferably, it further includes: pouring self-compacting concrete to fill the gaps inside the first and second retained portions; constructing a haunch structure, wherein the haunch structure is located in the following positions of the main body of the reinforced concrete closed frame: between the side wall and the top slab, between the side wall and the bottom slab, between the middle wall and the top slab, and between the middle wall and the bottom slab.

[0017] This invention provides a construction method for underground road structures, comprising: arranging pipe jacking tool pipes at the centerline of the cross-sectional structure of the proposed underground road; jacking in a first batch of pipe jacking tool pipes along the longitudinal axis of the proposed underground road, wherein the first batch of pipe jacking tool pipes are arranged at intervals and constructed using a skip-hole jacking method; jacking in a first batch of pipe jacking composite section steel pipes along the longitudinal axis of the proposed underground road to replace the first batch of pipe jacking tool pipes, wherein the outer diameter of the first batch of pipe jacking composite section steel pipes is equal to the outer diameter of the first batch of pipe jacking tool pipes; jacking in a second batch of pipe jacking tool pipes through the gaps between the first batch of composite section steel pipes; jacking in a second batch of pipe jacking composite section steel pipes to replace the second batch of pipe jacking tool pipes, wherein the outer diameter of the second batch of pipe jacking composite section steel pipes is equal to the outer diameter of the second batch of pipe jacking tool pipes, and the first batch of pipe jacking composite section steel pipes and the second batch of pipe jacking tool pipes... A first batch of composite steel pipes forms a closed curtain; the adjacent portions of the first batch of composite steel pipes and the adjacent second batch of composite steel pipes are fixed with first fasteners to form an overall frame of composite steel pipes; the reinforced concrete closed frame structure of the proposed underground road is prefabricated; the second fasteners of the first batch of composite steel pipes and the third fasteners of the second batch of composite steel pipes are removed; the reinforced concrete closed frame structure of the proposed underground road is jacked in as a whole, replacing the first replacement portion in the overall frame of the first batch of composite steel pipes and the second replacement portion in the overall frame of the second batch of composite steel pipes, completing the structural replacement of the proposed underground road; the soil inside the reinforced concrete closed frame structure of the proposed underground road is excavated to form the space required for underground passage, completing the construction of the underground road structure. The method described in this application involves constructing a horizontally advanced interlocking pipe jacking along the centerline of the cross-sectional structure of the proposed underground road. The pipe jacking consists of steel-concrete composite components and steel composite sections. After the pipe jacking runs through the entire length of the underground road and forms a closed structure, the prefabricated main structure of the underground road closed frame is pushed in using the overall jacking method, replacing a portion of the advanced pipe jacking composite section. After the main structure is in place, the soil is excavated to construct the underground structure and form the tunnel functional space. This construction method solves the problem in related technologies where underground structure construction in densely populated areas of existing buildings and structures can easily lead to settlement and collapse, affecting the normal operation of the superstructure or road traffic facilities, and improves the safety of underground engineering construction. Attached Figure Description

[0018] The accompanying drawings, which are included to provide a further understanding of the invention and form part of this application, illustrate exemplary embodiments of the invention and, together with their description, serve to explain the invention and do not constitute an undue limitation thereof. In the drawings: Figure 1 This is a flowchart of an underground structure construction method according to an embodiment of the present invention; Figure 2 This is a schematic diagram of the first batch of tube curtain tool tubes according to an embodiment of the present invention; Figure 3 This is a schematic diagram of the first batch of composite cross-section steel pipes for jacking up according to an embodiment of the present invention; Figure 4(a) is an exploded view of the "L"-shaped steel pipe in the first batch of pipe-jacking composite section steel pipes according to an embodiment of the present invention; Figure 4(b) is an exploded view of the "I" type steel pipe in the first batch of pipe jacking composite section steel pipes according to an embodiment of the present invention; Figure 4(c) is an exploded view of the "T"-shaped steel pipe in the first batch of pipe-jacking composite section steel pipes according to an embodiment of the present invention; Figure 5(a) is a schematic diagram of the "L"-shaped steel pipe combination connection in the first batch of pipe jacking composite section steel pipes according to an embodiment of the present invention; Figure 5(b) is a schematic diagram of the "I" type steel pipe combination connection in the first batch of pipe jacking composite section steel pipes according to an embodiment of the present invention; Figure 5(c) is a schematic diagram of the combined connection of the "T"-shaped steel pipes in the first batch of pipe jacking composite section steel pipes according to an embodiment of the present invention; Figure 6 This is a schematic diagram of the second batch of tube curtain tool tubes according to an embodiment of the present invention; Figure 7 This is an enlarged schematic diagram of the combined connection of the first batch of pipe jacking cross-section steel pipes during the jacking of the second batch of pipe jacking tool pipes according to an embodiment of the present invention. Figure 8 This is a schematic diagram of the second batch of pipe jacking composite section steel pipes replacing the second batch of pipe jacking tool pipes according to an embodiment of the present invention; Figure 9 This is an exploded view of the second batch of advanced pipe curtain composite section steel pipes according to an embodiment of the present invention; Figure 10 This is a schematic diagram of the internal connections of the steel components of the first batch of pipe-jacking composite section steel pipes and the steel components of the second batch of pipe-jacking composite section steel pipes according to an embodiment of the present invention. Figure 11 This is a partially enlarged schematic diagram showing the reassembly of the steel components of the first batch of pipe-jacking composite section steel pipes and the steel components of the second batch of pipe-jacking composite section steel pipes according to an embodiment of the present invention, through a process of disassembly and reconnection. Figure 12 This is an overall schematic diagram of the replacement portion in the steel pipe of the replacement pipe curtain composite section of the main structure of the reinforced concrete closed frame according to an embodiment of the present invention. Figure 13 This is a partially enlarged schematic diagram of the replacement portion in the steel pipe of the replacement pipe curtain composite section of the main structure of the reinforced concrete closed frame according to an embodiment of the present invention; Figure 14This is a schematic diagram of the excavation of the soil inside the reinforced concrete closed frame structure of the underground road according to an embodiment of the present invention, while simultaneously removing the demolished portion of the steel pipe in the pipe jacking composite section. Figure 15 This is a schematic diagram of materials such as self-compacting concrete filling voids according to an embodiment of the present invention; Figure 16 This is a schematic diagram of the axillary angle structure according to an embodiment of the present invention. Detailed Implementation

[0019] It should be noted that, unless otherwise specified, the embodiments and features described in this application can be combined with each other. The present invention will now be described in detail with reference to the accompanying drawings and embodiments.

[0020] This embodiment provides a method for constructing underground structures. Figure 1 This is a flowchart of an underground structure construction method according to an embodiment of the present invention, such as... Figure 1 As shown, the method includes the following steps S101 to S109.

[0021] Step S101: Arrange the pipe jacking tool pipe at the centerline of the cross-sectional structure of the proposed underground road; jack the first batch of pipe jacking tool pipes 11 along the longitudinal axis of the proposed underground road. The first batch of pipe jacking tool pipes 11 are arranged at intervals and constructed using a skip-hole jacking method.

[0022] Step S102: The first batch of pipe curtain composite section steel pipes 21 are pushed in to replace the first batch of pipe curtain tool pipes 11. The outer diameter of the first batch of pipe curtain composite section steel pipes 21 is equal to the outer diameter of the first batch of pipe curtain tool pipes 11.

[0023] Step S103: Insert the second batch of pipe curtain tool pipes 12 into the gap between the first batch of pipe curtain composite section steel pipes 21.

[0024] Step S104: The second batch of pipe curtain composite section steel pipes 22 are pushed in to replace the second batch of pipe curtain tool pipes 12. The outer diameter of the second batch of pipe curtain composite section steel pipes 22 is equal to the outer diameter of the second batch of pipe curtain tool pipes 12, and the first batch of pipe curtain composite section steel pipes 21 and the second batch of pipe curtain composite section steel pipes 22 form a closed curtain.

[0025] In step S105, the adjacent portions of the first batch of pipe curtain composite section steel pipes 21 and the adjacent second batch of pipe curtain composite section steel pipes 22 are fixed by the first fastener to form an overall frame of composite section steel pipes.

[0026] Step S106: Prefabricate the reinforced concrete closed frame structure of the proposed underground road.

[0027] Step S107: Remove the second fastener of the first batch of pipe jacking composite section steel pipe 21 and the third fastener 43 of the second batch of pipe jacking composite section steel pipe 22.

[0028] Step S108: The reinforced concrete closed frame structure 51 of the proposed underground road is jacked up as a whole, replacing the first replacement part 212 in the overall frame of the first batch of composite section steel pipes 21 and the second replacement part 222 in the overall frame of the second batch of composite section steel pipes 22, thus completing the replacement of the proposed underground road structure.

[0029] Step S109: Excavate the soil inside the reinforced concrete closed frame structure of the proposed underground road to form the space required for underground passage and complete the construction of the underground road structure.

[0030] In this embodiment, a horizontally advanced interlocking pipe curtain is constructed along the centerline of the cross-sectional structure of the proposed underground road. The pipe curtain steel pipe is a combination of steel-concrete components and steel components. After the pipe curtain steel pipe runs through the entire length of the underground road and forms a closed structure, the prefabricated underground road closed frame main structure is pushed in using the overall jacking method, replacing a part of the advanced pipe curtain steel pipe combination section. After the main structure is in place, the soil is excavated to construct the underground structure and form the tunnel functional space. This construction method solves the problem in related technologies that underground structure construction in areas with dense existing buildings (structures) is prone to settlement and collapse, affecting the normal operation of the superstructure (structures) or road traffic facilities, and improves the safety of underground engineering construction.

[0031] During implementation, the first batch of pipe curtain tool tubes 11 being pushed in during step S101 can be carried out in the following manner:

[0032] The first batch of pipe jacking tool pipes 11, along the longitudinal axis of the proposed underground road, is divided into multiple segments. These segments are connected end-to-end, running the entire length of the proposed underground road. The first batch of pipe jacking tool pipes 11 has a circular cross-section, and its internal space is used for discharging excavated soil during the jacking operation. In this embodiment, the first batch of pipe jacking tool pipes is jacked up end-to-end.

[0033] As a preferred embodiment, step S102 can be carried out in the following manner:

[0034] The first batch of pipe-jacking composite section steel pipes 21 includes: a first steel component part and a plain concrete part 31. Preferably, the plain concrete part 31 and the first steel component part are connected by a material that can be cut by the pipe jacking machine's cutter, which can be glass fiber reinforcement. The first steel component part includes a first retention part 211, a first replacement part 212, and a first removal part 213. The interiors of the first retention part 211, the first replacement part 212, and the first removal part 213 are welded together. The contact surfaces between the first retention part 211, the first replacement part 212, and the first removal part 213 are connected by a second fastener 41.

[0035] The first batch of composite cross-section steel pipes 21 are divided into multiple segments along the longitudinal axis of the proposed underground road. These segments are connected end to end and run through the entire length of the proposed underground road.

[0036] This preferred embodiment enables the jacking of the first batch of pipe-jacking composite section steel pipes. The first batch of pipe-jacking composite section steel pipes 21 includes a first steel component part and plain concrete. The first steel component part is then divided into a first retention part, a first replacement part, and a first demolition part, which respectively form an integral frame in subsequent operations.

[0037] Preferably, the type of steel pipe in the first pipe jacking composite section includes at least one of the following: L-shaped, type I, and T-shaped (see Figures 4 and 5 for details). For example, L-shaped pipes are installed at the connection points between the side walls and the top slab, and between the side walls and the bottom slab of the cross section of the proposed underground road structure; type I pipes are installed at the positions of the top slab and the bottom slab of the cross section of the proposed underground road structure; and T-shaped pipes are installed at the connection points between the middle wall and the top slab, and between the middle wall and the bottom slab of the cross section of the proposed underground road.

[0038] This preferred embodiment realizes multiple types of steel pipes with combined cross sections for the first pipe curtain. The three different types can achieve adjacent interlocking laying of the cross section steel pipes in the subsequent process, which has better water-stopping performance, which is conducive to improving the working environment during jacking construction. At the same time, it is also conducive to controlling the erosion of soil and water in the surrounding strata and reducing the risk of excessive settlement or deformation of the surrounding environmental risk sources during construction.

[0039] In practice, step S103 can be performed in the following manner:

[0040] During the jacking construction of the second batch of pipe jacking tool pipe 12, the plain concrete portion 31 of the first batch of pipe jacking composite section steel pipe 21 was cut;

[0041] The second batch of pipe jacking tool pipes 12 are divided into multiple segments along the longitudinal axis of the proposed underground road. These segments are connected end to end and run through the entire length of the proposed underground road. The cross-section of the second batch of pipe jacking tool pipes 12 is circular, and the internal space of the second batch of pipe jacking tool pipes 12 is used to discharge excavated soil during the jacking construction of the second batch of pipe jacking tool pipes 12.

[0042] As a preferred embodiment, step S104 can be implemented in the following manner:

[0043] The second batch of pipe jacking composite section steel pipes 22 includes the second steel component part, such as... Figure 9 As shown, the second steel component includes: a second retention portion 221, a second replacement portion 222, and a second removal portion 223. The interiors of the second retention portion 221, the second replacement portion 222, and the second removal portion 223 are welded together as a whole. The contact surfaces between the second retention portion 221, the second replacement portion 222, and the second removal portion 223 are connected by a third fastener 43 (e.g., ...). Figure 10 (As shown).

[0044] The second batch of composite cross-section steel pipes 22 are divided into multiple segments along the longitudinal axis of the proposed underground road. These segments are connected end to end and run through the entire length of the proposed underground road.

[0045] The first batch of pipe curtain composite section steel pipes 21 and the second batch of pipe curtain composite section steel pipes 22 interlock structurally to form a closed curtain.

[0046] In practice, step S105 can be performed in the following manner:

[0047] The adjacent portions of the first batch of pipe-jacking composite section steel pipes 21 and the adjacent second batch of pipe-jacking composite section steel pipes 22 are fixed by the first fastener 42 (e.g., Figure 11 As shown), the composite section steel pipe integral frame includes:

[0048] The first batch of pipe-jacking composite section steel pipes 21 and the second batch of pipe-jacking composite section steel pipes 22 are reassembled by dismantling and connecting them through the following steps, connecting the first replacement portion 212 and the second replacement portion 222 of the first batch of pipe-jacking composite section steel pipes 21 and the second batch of pipe-jacking composite section steel pipes 22 into a whole. (See...) Figure 10 and Figure 11 )

[0049] Remove the second fastener 41 between the following components: between the first retained portion 211 and the first replacement portion 212; between the first replacement portion 212 and the first removed portion 21;

[0050] Remove the third fastener 43 between the following components: between the second retained portion 221 and the second replacement portion 222; between the second replacement portion 222 and the second removed portion 223;

[0051] The first replacement part 212 and the second replacement part 222 are fixed together by the first fastener 42;

[0052] Specifically, the first replacement portion 212 and the first retention portion 211 are separated, and the first replacement portion 212 and the first dismantling portion 213 are separated; the second replacement portion 222 and the second retention portion 221 are separated, and the second replacement portion 222 and the second dismantling portion 221 are separated.

[0053] Through this preferred embodiment, the adjacent portions of the first batch of pipe jacking composite section steel pipes 21 and the adjacent second batch of pipe jacking composite section steel pipes 22 are fixed by the first fastener 42 to form an overall frame of composite section steel pipes. This has better water-stopping performance, which is conducive to improving the working environment during jacking construction. It is also conducive to controlling the loss of soil and water in the surrounding strata and reducing the risk of excessive settlement or deformation of the surrounding environmental risk sources during construction.

[0054] In implementation, step S108 can be carried out as follows: After the reinforced concrete closed frame structure of the proposed underground road is jacked up as a whole, replacing the first replacement part in the first batch of pipe-jacking composite section steel pipe 21 overall frame and the second replacement part in the second batch of pipe-jacking composite section steel pipe overall frame, and completing the structural replacement of the proposed underground road, the following steps are also included: dismantling the first dismantling part 21 and the second dismantling part 223. In this preferred embodiment, by dismantling the dismantling parts, the composite section steel pipe overall frame is better realized.

[0055] During the construction of the underground structure, the process may also include: pouring self-compacting concrete 32 to fill the voids inside the first reserved portion 211 and the second reserved portion 221; constructing the haunch structure 52 (see details). Figure 16 The axle structure 52 can be located in the following positions of the reinforced concrete closed frame main structure: between the side wall and the top slab, between the side wall and the bottom slab, between the middle wall and the top slab, and between the middle wall and the bottom slab. This preferred embodiment can further ensure the waterproofing quality of the underground road structure.

[0056] This embodiment provides a construction method for an underground road structure. The method may include: constructing an interlocking pipe curtain along the centerline of the cross-sectional structure of the proposed underground road. The pipe curtain steel pipes (the first batch of pipe curtain combined steel pipes and the second batch of pipe curtain combined steel pipes) are steel-concrete components and steel component composite sections. After the pipe curtain steel pipes run through the entire length of the underground road and form a closed structure, the prefabricated underground road closed frame main structure is pushed in using the overall jacking method, replacing part of the first batch and the second batch of pipe curtain steel pipe composite sections. After the main structure is in place, the soil is excavated to construct the underground structure and form a tunnel functional space.

[0057] To better illustrate this, the specific implementation steps are explained in detail below.

[0058] Step 1: Preparation and construction of the working well.

[0059] The main tasks in this step include site preparation, material and equipment preparation, surveying and setting out, and construction of the working shaft structure. The working shaft is located at both ends of the section where the proposed underground road crosses existing buildings and structures, with one end being the starting end and the other end being the receiving end.

[0060] Step 2: Push in the first batch of horizontal advanced tube curtain tool tubes.

[0061] In this step, the pipe jacking tool tubes are installed in two batches using the jacking method. The first batch of pipe jacking tool tubes 11 are arranged at intervals, that is, the first batch of pipe jacking tool tubes 11 are installed in the stratum using a skip-hole jacking method, such as... Figure 2 As shown. The tool pipe is a circular cross-section steel pipe, and its internal space can be used to discharge excavated soil during the jacking construction. If necessary, grouting and other ground reinforcement operations can be carried out from inside the first batch of pipe jacking tool pipes 11. The first batch of pipe jacking tool pipes 11 is manufactured in several segments along the longitudinal direction, with each segment connected end to end, and its total length runs through the entire length of the proposed underground road structure.

[0062] Step 3: Push in the first batch of pipe jacking composite section steel pipes 21, replacing the first batch of pipe jacking tool steel pipes 11, as follows. Figure 3 As shown.

[0063] In this step, the first batch of pipe curtain composite section steel pipe 21 is a composite section member with the same outer diameter as the first batch of pipe curtain tool steel pipe 11, as shown in Figures 4(a)(b)(c), 5(a), (b)(c).

[0064] The first batch of pipe jacking composite section steel pipes 21 are composed of steel components and plain concrete components 31. The plain concrete components 31 and the steel components of the composite section steel pipes 21 are connected by materials and structures that can be cut by the pipe jacking machine (such as fiberglass reinforcement).

[0065] The steel components of the first batch of pipe-jacking composite section steel pipes 21 consist of three parts: the first retention part 211, the first replacement part 212, and the first dismantling part 213. The interior of these three parts is welded together with steel plates, and the contact surfaces between the three parts are connected by bolts (second fasteners 41).

[0066] The first batch of composite cross-section steel pipes 21 are divided into three types according to their location. Among them, the "L" type is suitable for the connection between the side wall and the top and bottom slabs of the cross section of the proposed underground road, as shown in Figure 4(a) and Figure 5(a); the "I" type is suitable for the top and bottom slabs, as shown in Figure 4(b) and Figure 5(b); and the "T" type is suitable for the connection between the middle wall and the top and bottom slabs, as shown in Figure 4(c) and Figure 5(c).

[0067] Figures 4 and 5 show only one example of the combination of "L", "I", and "T" shaped steel pipe sections. Depending on the specific location of the top slab, bottom slab, side wall, and middle wall, those skilled in the art can arrange them in a mirror or rotation manner according to the actual construction needs.

[0068] The first batch of composite cross-section steel pipes 21 were manufactured in several segments along the longitudinal direction, with each segment connected end to end, and their total length running through the entire length of the proposed underground road structure.

[0069] Step 4: Push in the second batch of pipe jacking tool steel pipes 12, as follows... Figure 6 , Figure 7 As shown.

[0070] A second batch of pipe-jacking tool pipes 12 is installed in the middle of the first batch of composite cross-section steel pipes 21. During the jacking excavation, the plain concrete portion 31 of the first batch of composite cross-section pipes 21 is cut. The tool pipes can be circular cross-section steel pipes, and their internal space can be used to discharge excavated soil during the jacking construction. Grouting and other ground reinforcement operations can be carried out from inside the tool pipes as needed. The tool pipes are manufactured in several segments along the longitudinal direction, with each segment connected end to end, and their total length runs through the entire length of the proposed underground road structure.

[0071] Step 5: Push in the second batch of pipe jacking composite section pipes 22, replacing the second batch of pipe jacking tool steel pipes 12, as follows. Figure 8 As shown.

[0072] The second batch of pipe jacking composite section steel pipes 22 are composite section members with the same outer diameter as the second batch of pipe jacking tool pipes 12, such as... Figure 9 , Figure 10 As shown.

[0073] The second batch of pipe jacking composite section steel pipes 22 are composed of the second steel components.

[0074] The second batch of combined cross-section steel pipes 22 consists of three parts: the second retained part 221, the second replacement part 222, and the second dismantled part 223. These three parts are internally welded together using steel plates, and the contact surfaces between them are connected by a third fastener 43 (e.g., ...). Figure 10 (As shown).

[0075] The second batch of pipe-jacking composite section steel pipes 22 are manufactured in several segments along the longitudinal direction, with each segment connected end to end, and their total length runs through the entire length of the proposed underground road structure.

[0076] The second batch of composite section steel pipes 22 and the first batch of composite section steel pipes 21 are interlocked, forming a closed curtain in the stratum to be excavated.

[0077] Step 6: Remove the connecting bolts (second fasteners 41) between the retained portion (first retained portion 211) and the replacement portion (first replacement portion 212) of the first batch of pipe-jacking composite section steel pipes 21, and between the replacement portion (first replacement portion 212) and the dismantled portion (first dismantled portion 213); remove the connecting bolts (third fasteners 43) between the retained portion (second retained portion 221) and the replacement portion (second replacement portion 222) of the second batch of pipe-jacking composite section steel pipes 22, and between the replacement portion (second replacement portion 222) and the dismantled portion (second dismantled portion 223). The replacement portion of the first batch of pipe-jacking composite section steel pipes 21 and the adjacent replacement portion of the second batch of pipe-jacking composite section steel pipes 22 are connected by bolts (first fasteners 42). The steel components of the first batch of cross-section steel pipes and the steel components of the second batch of cross-section steel pipes are recombined by disassembly and reconnection, so that the replacement portions of each composite section steel pipe are connected into a whole, and the replacement portions are separated from the retained portions and the dismantled portions, such as... Figure 11 As shown.

[0078] Step 7: Precast the underground road reinforced concrete closed frame structure 51 until it reaches the design strength, and at the same time carry out preparatory work such as sliding plate, backrest, jacking equipment and measurement.

[0079] Step 8: Starting from the launching shaft, the precast reinforced concrete closed frame structure 51 is jacked in as a whole. Simultaneously, within the receiving shaft, the replacement portions 212 and 222 of the advanced pipe-jacking composite section steel pipes 21 and 22 are pulled. The steel components exposed within the receiving shaft are segmented and cut off, thus replacing the replacement portions 212 and 222 of the pipe-jacking composite section steel pipes 21 and 22 with the main reinforced concrete closed frame structure 51. Figure 12 , Figure 13 As shown.

[0080] Step 9: After the underground road reinforced concrete closed frame structure 51 is jacked into place, the internal soil 6 is excavated, and simultaneously, the demolished portions 213 and 223 of the advanced pipe jacking composite section steel pipes 21 and 22 are removed, such as... Figure 14 As shown.

[0081] Step 10: Use self-compacting concrete or similar materials to fill and compact the gaps 32 in the remaining portions 211 and 221 of the first batch of pipe-jacking composite section steel pipes 21 and the second batch of pipe-jacking composite section steel pipes 22, such as... Figure 15 As shown.

[0082] Step 11: Construct the haunch-angle structure 52 between the side walls and top and bottom slabs, and between the central wall and top and bottom slabs of the underground road reinforced concrete closed frame main structure, as well as the roadbed, pavement, roadside curbs, drainage, and other ancillary facilities, such as... Figure 16 As shown.

[0083] This embodiment and its preferred embodiments provide a method for constructing underground road structures, which can achieve the following technical effects:

[0084] (1) The pipe curtain steel pipe adopts innovative steel-concrete components and steel component combination sections, which can meet the needs of different construction stages, and its cross section has high flexibility and applicability.

[0085] (2) The use of steel pipes for pipe draping provides a larger operating space, making the disconnection and reconnection of each part of the combined section more feasible for construction.

[0086] (3) Pipe jacking uses steel pipes for laying, which has greater structural rigidity and stronger support capacity, and can achieve more reliable advanced stratum reinforcement and protection effects. While improving its own support capacity, it can carry out stratum reinforcement operations such as grouting from inside the steel pipe, further strengthening stratum stability and environmental risk source protection.

[0087] (4) The pipe jacking is constructed in batches according to the sequence of the jump holes. The technology is mature and reliable, which can effectively reduce the overall disturbance to the surrounding strata and control the construction risks.

[0088] (5) The adjacent steel pipes of the advanced pipe curtain are laid in an interlocking manner, which has better water-stopping performance, which is conducive to improving the working environment during jacking construction. At the same time, it is also conducive to controlling the loss of soil and water in the surrounding strata and reducing the risk of excessive settlement or deformation of the surrounding environment during construction.

[0089] (6) After the overall closed frame structure is jacked into place, the internal gaps of the advanced pipe curtain steel pipe are filled with self-compacting concrete, which can further ensure the waterproof quality of the underground road structure.

[0090] (7) The overall construction plan proceeds in the order of first constructing the pipe curtain, then jacking the closed frame structure into place, and finally excavating the earthwork. This allows the main structure of the underground road to be excavated before the earthwork, which fundamentally avoids the risks of face instability caused by the traditional construction plan of excavating the earthwork first and then constructing the structure, as well as the risks of collapse and subsidence of the upper road or adjacent buildings that are crossed and cannot interrupt traffic. This greatly improves the safety of construction.

[0091] (8) Since the reinforced concrete closed frame structure is jacked inside the steel pipe of the advanced pipe curtain composite section, and a part of the steel pipe composite section is "replaced" at the same time as jacking, its outer contour does not directly contact the surrounding soil. While reducing the overall jacking friction, it isolates the surrounding soil from the jacking construction of the closed frame structure, thereby ensuring the normal use of the upper road, adjacent buildings (structures) or underground pipelines, and realizing low-disturbance construction.

[0092] (9) Since the layout of the advanced pipe curtain steel pipe does not require the use of space outside the main structure of the underground road, the underground space can be used efficiently as a limited resource, especially when the newly built underground road and the existing transportation infrastructure need to be arranged close to each other in the vertical direction.

[0093] (10) Because the advanced pipe curtain adopts a combined cross-section structure, some of the steel components are replaced by the overall jacking closed frame structure or removed during the internal soil excavation, which can realize the recycling and reuse of steel.

[0094] This invention relates to the field of underground engineering construction technology, specifically to a construction method for tunneling under existing roads or other buildings using the cut-and-cover method. This method involves first constructing a horizontal pre-constructed pipe jacking in the strata. The pipe jacking consists of steel-concrete composite components and steel components with combined cross-sections. Then, a portion of the pre-constructed pipe jacking is replaced using a precast reinforced concrete closed frame structure integral jacking method. Finally, the soil is excavated to construct the underground structure and form a functional space. Specifically, a horizontal pre-constructed interlocking pipe jacking is constructed along the centerline of the cross-section of the proposed underground road. The pipe jacking consists of steel-concrete composite components and steel components with combined cross-sections. The pipe jacking runs the entire length of the underground road and forms a closed structure. Then, the precast underground road closed frame main structure is pushed in using an integral jacking method, replacing a portion of the pre-constructed pipe jacking composite cross-section. After the main structure is in place, the soil is excavated to construct the underground structure and form a tunnel functional space.

[0095] The above description is merely a preferred embodiment of the present invention and is not intended to limit the invention. Various modifications and variations can be made to the present invention by those skilled in the art. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the scope of protection of the present invention.

Claims

1. A method for constructing underground structures, characterized in that, include: Pipe jacking tool pipes are arranged at the centerline of the cross-sectional structure of the proposed underground road; the first batch of pipe jacking tool pipes are jacked in along the longitudinal axis of the proposed underground road. The first batch of pipe jacking tool pipes are arranged at intervals and are constructed using a skip-hole jacking method. The first batch of pipe jacking composite section steel pipes is pushed in to replace the first batch of pipe jacking tool pipes, wherein the outer diameter of the first batch of pipe jacking composite section steel pipes is equal to the outer diameter of the first batch of pipe jacking tool pipes; The second batch of pipe jacking tool pipes is inserted into the gap between the first batch of pipe jacking composite section steel pipes; The second batch of pipe curtain composite section steel pipes is pushed in to replace the second batch of pipe curtain tool pipes. The outer diameter of the second batch of pipe curtain composite section steel pipes is equal to the outer diameter of the second batch of pipe curtain tool pipes, and the first batch of pipe curtain composite section steel pipes and the second batch of pipe curtain composite section steel pipes form a closed curtain. The first batch of pipe curtain composite section steel pipes and the adjacent second batch of pipe curtain composite section steel pipes are fixed by the first fastener to form an overall frame of composite section steel pipes. Prefabricate the reinforced concrete closed frame structure of the proposed underground road; Remove the second fasteners of the first batch of pipe jacking composite section steel pipes and the third fasteners of the second batch of pipe jacking composite section steel pipes; The reinforced concrete closed frame structure of the proposed underground road is jacked in as a whole, replacing the first replacement part in the first batch of pipe jacking composite section steel pipe overall frame and the second replacement part in the second batch of pipe jacking composite section steel pipe overall frame, thus completing the replacement of the proposed underground road structure. The soil inside the reinforced concrete closed frame structure of the proposed underground road is excavated to form the space required for underground passage, thus completing the construction of the underground road structure.

2. The method according to claim 1, characterized in that, The first batch of pipe-jacking tools includes: The first batch of pipe jacking tools is divided into multiple segments along the longitudinal axis of the proposed underground road. These segments are connected end to end and run through the entire length of the proposed underground road. The cross-section of the first batch of pipe jacking tools is circular, and the internal space of the first batch of pipe jacking tools is used to discharge excavated soil during the jacking construction of the first batch of pipe jacking tools.

3. The method according to claim 1, characterized in that, The first batch of pipe jacking composite section steel pipes is driven in, replacing the first batch of pipe jacking tool pipes, including: The first batch of pipe jacking composite section steel pipes includes: a first steel component part and a plain concrete part; The first steel component includes a first retention part, a first replacement part, and a first removal part. The interiors of the first retention part, the first replacement part, and the first removal part are welded together as a whole. The contact surfaces between the first retention part, the first replacement part, and the first removal part are connected by a second fastener. The first batch of pipe-jacking composite section steel pipes are divided into multiple segments along the longitudinal axis of the proposed underground road. These multiple segments are connected end to end and run through the entire length of the proposed underground road.

4. The method according to claim 3, characterized in that, The first batch of composite cross-section steel pipes for pipe jacking includes at least one of the following types: L-type, Type I, and T-type; The L-shaped section is located at the connection between the side wall and the top slab, and the side wall and the bottom slab of the cross section of the proposed underground road structure; the I-shaped section is located at the position of the top slab and the bottom slab of the cross section of the proposed underground road structure; and the T-shaped section is located at the connection between the middle wall and the top slab, and the middle wall and the bottom slab of the cross section of the proposed underground road.

5. The method according to claim 3, characterized in that, The second batch of pipe-jacking tool pipes is inserted into the gaps between the first batch of pipe-jacking composite section steel pipes, including: During the jacking construction of the second batch of pipe jacking tool pipes, the plain concrete portion of the first batch of pipe jacking composite section steel pipes is cut; The second batch of pipe jacking tools is divided into multiple segments along the longitudinal axis of the proposed underground road. These segments are connected end to end and run through the entire length of the proposed underground road. The cross-section of the second batch of pipe jacking tools is circular, and the internal space of the second batch of pipe jacking tools is used to discharge excavated soil during the jacking construction of the second batch of pipe jacking tools.

6. The method according to claim 5, characterized in that, The second batch of pipe jacking composite section steel pipes, replacing the second batch of pipe jacking tool pipes, includes: The second batch of pipe jacking composite section steel pipes includes a second steel component part, wherein the second steel component part includes: a second retention part, a second replacement part and a second removal part, the interiors of the second retention part, the second replacement part and the second removal part are welded together as a whole, and the contact surfaces between the second retention part, the second replacement part and the second removal part are connected by a third fastener; The second batch of pipe-jacking composite section steel pipes are divided into multiple segments along the longitudinal axis of the proposed underground road. These multiple segments are connected end to end and run through the entire length of the proposed underground road. The first batch of pipe curtain composite section steel pipes and the second batch of pipe curtain composite section steel pipes are interlocked structurally to form a closed curtain.

7. The method according to claim 6, characterized in that, The first batch of pipe-jacking composite section steel pipes and the adjacent second batch of pipe-jacking composite section steel pipes are fixed together by a first fastener to form an overall frame of composite section steel pipes, including: The first batch of pipe-jacking composite section steel pipes and the second batch of pipe-jacking composite section steel pipes are recombined by dismantling and connecting them through the following steps, connecting the first replacement portion and the second replacement portion of the first batch of pipe-jacking composite section steel pipes and the second batch of pipe-jacking composite section steel pipes into a whole: Remove the second fastener between the following components: between the first retained portion and the first replacement portion; between the first replacement portion and the first removed portion; Remove the third fastener between the following components: between the second retained portion and the second replacement portion; between the second replacement portion and the second removed portion; The first replacement portion and the second replacement portion are fixed together by the first fastener; Specifically, the first replacement portion and the first retention portion are separated, and the first replacement portion and the first dismantling portion are separated; the second replacement portion and the second retention portion are separated, and the second replacement portion and the second dismantling portion are separated.

8. The method according to claim 6 or 7, characterized in that, After the reinforced concrete closed frame structure of the proposed underground road is jacked up as a whole, replacing the first replacement portion in the first batch of pipe-jacking composite section steel pipe overall frame and the second replacement portion in the second batch of pipe-jacking composite section steel pipe overall frame, and the structural replacement of the proposed underground road is completed, the following steps are also included: Remove the first and second removal sections.

9. The method according to claim 6 or 7, characterized in that, Also includes: Pour self-compacting concrete to fill the voids inside the first and second retained portions; Construct a haunch structure, wherein the haunch structure is located in the following positions of the main reinforced concrete closed frame structure: between the side wall and the top slab, between the side wall and the bottom slab, between the middle wall and the top slab, and between the middle wall and the bottom slab.

Citation Information

Patent Citations

  • Method for construction of large underground space in soft formations

    CN108930544A

  • Pipe roof jacking construction method and device

    CN117780359A