一种用于拱桥的斜拉扣挂施工方法及临时合龙装置

By hinged connection and removal of the stay cables at the arch crown segment, the problem of uneven axial force distribution in the arch ring during cable hoisting and stay cable fastening construction was solved, achieving an axial force close to the ideal design state and improving construction efficiency and structural stability.

CN120700802BActive Publication Date: 2026-07-17GUANGXI ROAD & BRIDGE ENG GRP CO LTD

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
GUANGXI ROAD & BRIDGE ENG GRP CO LTD
Filing Date
2025-08-13
Publication Date
2026-07-17

AI Technical Summary

Technical Problem

The existing cable hoisting and inclined cable-stayed construction method results in a large deviation between the axial force distribution of the arch ring after the bridge is completed and the ideal design state, which affects the durability of the arch ring structure.

Method used

The arch ring is temporarily closed at the top segment using a hinged connection, and the stay cables at 1/4 of the arch ring span are removed. By utilizing the characteristic that the hinged joint does not transmit bending moment, excess constraint force is released, allowing the internal forces of the arch ring to redistribute, achieving a construction effect close to that of the scaffolding method.

Benefits of technology

This reduces the influence of initial stress on each segment of the arch ring, excluding the effect of gravity, and the axial force distribution is close to the effect of the support method construction, thus improving construction efficiency and structural stability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120700802B_ABST
    Figure CN120700802B_ABST
Patent Text Reader

Abstract

本发明涉及拱桥施工技术领域,具体涉及一种用于拱桥的斜拉扣挂施工方法及临时合龙装置。所述方法包括以下步骤:依次通过缆索吊运和斜拉扣挂将拱圈的各拱肋节段逐一从拱脚安装至拱顶,所述拱圈在两个拱顶节段之间的位置处于断开状态;采用铰接方式将两个所述拱顶节段进行合龙;将1 / 4所述拱圈跨径位置处的斜拉索进行拆除;将两个所述拱顶节段进行固定连接;拆除剩余的斜拉索,完成所述拱圈的施工。该方法通过先将两个所述拱顶节段进行临时铰接合龙,利用铰接节点不传递弯矩的特性,再拆除1 / 4所述拱圈跨径位置处的斜拉索,再将两个所述拱顶节段进行永久性合龙,能达成斜拉扣挂施工的拱圈轴力接近支架法施工效果的目标。