Dynamic risk prediction and optimization decision-making method and system for deep foundation pit construction process
By combining numerical simulation and the Transformer algorithm, real-time risk prediction and optimization decision-making in the deep foundation pit construction process were realized, which solved the problems of insufficient real-time performance and accuracy in the construction process in the existing technology, and improved the safety and efficiency of construction.
Patent Information
- Application Number
- CN202511064164.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-07-31
- Publication Date
- 2025-11-18
AI Technical Summary
Existing methods for predicting and optimizing risks in deep foundation pit construction cannot meet the real-time, accurate, and efficient requirements of the construction process, especially in complex construction environments where there is a lack of intelligent technologies that can dynamically respond to and adjust construction plans.
By combining numerical simulation and the Transformer algorithm, and by integrating real-time monitoring data with advanced algorithms, we can achieve accurate risk prediction and dynamic optimization of construction plans during the construction process. We use a deep foundation pit numerical simulation model to simulate the mechanical behavior of the soil and the response of the support system, and combine the Transformer algorithm to perform time-series modeling analysis, identify abnormal deformation signals, and dynamically adjust the construction plan based on the real-time risk prediction results.
It enables accurate risk prediction and dynamic optimization of construction schemes during deep foundation pit construction, improving the safety, efficiency, and economy of construction. It can adapt to different construction environments and working conditions, provide real-time decision support, and ensure the safety and stability of construction.
Smart Images

Figure CN120974895A_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The present application relates to the technical field of deep foundation pit construction, in particular to a deep foundation pit construction process dynamic risk prediction and optimization decision method and system. BACKGROUND
[0002] In the deep foundation pit construction process, the safety evaluation and prevention and control of the foundation pit are the key to ensure the smooth progress of the project, and the whole process involves multiple links such as the analysis of the mechanical behavior of the soil body, the design optimization of the support system, and the control of the construction progress. At present, the safety evaluation and prevention and control decision of deep foundation pit construction mainly relies on traditional static analysis methods and experience judgment. These methods cannot provide timely and accurate risk warning and effective construction optimization suggestions when facing complex construction environment and changing working conditions. The existing foundation pit construction risk prediction and prevention and control mainly have the following several kinds:
[0003] 1. Based on engineering experience judgment: The traditional foundation pit construction risk prediction mainly relies on the engineering experience of construction personnel and historical data. Although this method can provide risk warning information to a certain extent, it is prone to lead to lagged prediction results due to the lack of real-time data support, and cannot cope with complex construction environment and working condition changes.
[0004] 2. Based on numerical model calculation: Existing researchers often use numerical simulation methods (such as PLAXIS finite element analysis) to calculate and analyze the soil deformation, settlement and other aspects in the foundation pit construction process. However, traditional numerical simulation is static, lacks dynamic response to real-time data, and its accuracy is seriously dependent on the setting of initial conditions and the selection of model parameters, which is difficult to adapt to the changes in the construction process.
[0005] 3. Based on monitoring data analysis: The foundation pit construction process monitors the soil displacement, support system stress and other data through sensors, and conducts risk assessment through simple data statistics or rule-based analysis model. These methods have great limitations in dealing with complex time series data and high-dimensional data, and are difficult to provide real-time decision support.
[0006] Therefore, the existing foundation pit construction risk prediction and optimization decision method cannot fully meet the real-time, accuracy and efficiency requirements in the construction process, especially in complex construction environment, lacking intelligent technology that can dynamically respond and adjust the construction scheme. SUMMARY
[0007] The present application provides a deep foundation pit construction process dynamic risk prediction and optimization decision method and system to solve the above problems in the prior art.
[0008] According to one aspect of the present application, a deep foundation pit construction process dynamic risk prediction and optimization decision method is provided, comprising:
[0009] establish a deep foundation pit numerical simulation model, simulate the mechanical behavior of soil and the response parameters of the support system during the construction process by using the deep foundation pit numerical simulation model, and obtain numerical simulation results;
[0010] obtain multi-dimensional real-time monitoring data of the foundation pit, compare the real-time monitoring data with the numerical simulation results, and calibrate the parameters of the deep foundation pit numerical simulation model according to the comparison results;
[0011] The Transformer algorithm is used to perform time series modeling analysis on the real-time monitoring data, identify abnormal deformation signals that may exist during the construction of the foundation pit, and obtain real-time risk prediction results.
[0012] The numerical simulation results are introduced as a reference to compare and analyze the abnormal deformation signals predicted by the Transformer algorithm, and identify potential risk sources that cause prediction deviation and abnormal deformation behavior.
[0013] According to the real-time risk prediction results and the risk source identification results, the construction scheme is dynamically adjusted to complete decision optimization.
[0014] According to another aspect of the present application, a deep foundation pit construction process dynamic risk prediction and optimization decision system is provided, comprising:
[0015] The numerical simulation module is used to establish a deep foundation pit numerical simulation model, simulate the mechanical behavior of soil and the response parameters of the support system during the construction process by using the deep foundation pit numerical simulation model, and obtain numerical simulation results.
[0016] The real-time monitoring module is used to obtain multi-dimensional real-time monitoring data of the foundation pit, compare the real-time monitoring data with the numerical simulation results, and calibrate the parameters of the deep foundation pit numerical simulation model according to the comparison results.
[0017] The Transformer algorithm module uses the Transformer algorithm to perform time series modeling analysis on the real-time monitoring data, identifies abnormal deformation signals that may exist during the construction of the foundation pit, and obtains real-time risk prediction results. The numerical simulation results are introduced as a reference to compare and analyze the abnormal deformation signals predicted by the Transformer algorithm, and identify potential risk sources that cause prediction deviation and abnormal deformation behavior.
[0018] The decision optimization module is used to dynamically adjust the construction scheme according to the real-time risk prediction results and the risk source identification results, and complete decision optimization.
[0019] Compared with the prior art, the present application has the following at least one beneficial effect:
[0020] The deep foundation pit construction process dynamic risk prediction and optimization decision method and system provided by the application combines numerical simulation and Transformer algorithm, realizes accurate risk prediction and dynamic construction scheme optimization through real-time monitoring data and advanced algorithm combination, and improves the safety, efficiency and economy of foundation pit construction.
[0021] The deep foundation pit construction process dynamic risk prediction and optimization decision method and system provided by the application can capture potential risks in the deep foundation pit construction process in real time, accurately predict dynamic risks, and provide real-time optimized construction schemes, realize a data-driven intelligent risk prediction and optimization decision technology, improve the safety and efficiency of construction, and have wide application prospect and practical value.
[0022] The deep foundation pit construction process dynamic risk prediction and optimization decision method and system provided by the application automatically recommends construction adjustment schemes through optimization algorithm, provides real-time decision support to construction personnel, forms real-time feedback and closed-loop control, and ensures the safety and stability of the construction scheme.
[0023] The deep foundation pit construction process dynamic risk prediction and optimization decision method and system provided by the application periodically evaluates the construction, continuously collects new monitoring data and compares it with existing numerical simulation results, updates and optimizes the numerical simulation model and Transformer algorithm, so that the system can adapt to different construction environments and working conditions, and ensure that the system has high prediction accuracy and adaptability.
[0024] The deep foundation pit construction process dynamic risk prediction and optimization decision method and system provided by the application can analyze the changes of soil, support and surrounding environment according to the real-time changing data in the construction process, provide risk warning and dynamic adjustment suggestions under different working conditions, and ensure the safety and efficiency of construction under complex construction conditions. BRIEF DESCRIPTION OF DRAWINGS
[0025] Other features, objects and advantages of the application will become more apparent through reading the following detailed description of non-limiting embodiments with reference to the accompanying drawings:
[0026] Figure 1 The workflow diagram of the deep foundation pit construction process dynamic risk prediction and optimization decision method in a preferred embodiment of the application.
[0027] Figure 2 The composition module schematic diagram of the deep foundation pit construction process dynamic risk prediction and optimization decision system in a preferred embodiment of the application.
[0028] Figure 3A workflow diagram of the deep foundation pit construction process dynamic risk prediction and optimization decision method in a specific application example of the present application.
[0029] Figure 4 A structure and module relationship diagram of the deep foundation pit construction process dynamic risk prediction and optimization decision system in a specific application example of the present application.
[0030] Figure 5 A data real-time acquisition and processing flowchart in a specific application example of the present application.
[0031] Figure 6 A Transformer algorithm principle diagram in a specific application example of the present application.
[0032] Figure 7 A foundation pit construction process risk assessment and optimization decision case diagram in a specific application example of the present application. DETAILED DESCRIPTION
[0033] The embodiments of the present application will be described in detail below: The present embodiment is implemented on the premise of the technical scheme of the present application, and detailed implementation modes and specific operation processes are given. It should be pointed out that, for ordinary skilled persons in the art, without departing from the concept of the present application, a number of modifications and improvements can be made, which are all within the protection scope of the present application.
[0034] The existing foundation pit construction risk prediction and optimization decision method cannot fully meet the real-time, accuracy and efficiency requirements in the construction process, especially in complex construction environment, there is a lack of intelligent technology that can dynamically respond and adjust the construction scheme. In view of the above problems, an embodiment of the present application provides a deep foundation pit construction process dynamic risk prediction and optimization decision method, which combines numerical simulation and Transformer algorithm, realizes accurate risk prediction and dynamic construction scheme optimization of the construction process through the combination of real-time monitoring data and advanced algorithm, and improves the safety, efficiency and economy of the foundation pit construction.
[0035] Specifically, as shown in Figure 1 The deep foundation pit construction process dynamic risk prediction and optimization decision method provided by the embodiment can include:
[0036] S1, a deep foundation pit numerical simulation model is established, the deep foundation pit numerical simulation model is used to simulate the soil mechanical behavior and support system response parameters in the construction process, and numerical simulation results are obtained;
[0037] S2, multi-dimensional real-time monitoring data of the foundation pit are acquired, the real-time monitoring data are compared with the numerical simulation results, and the parameters of the deep foundation pit numerical simulation model are calibrated according to the comparison results;
[0038] S3, using the Transformer algorithm to analyze the time series modeling of the real-time monitoring data, identifying the abnormal deformation signals that may exist in the foundation pit construction, and obtaining the real-time risk prediction results;
[0039] S4, introducing the numerical simulation results as a reference benchmark to compare and analyze the abnormal deformation signals predicted by the Transformer algorithm, identifying the potential risk sources causing the prediction deviation and abnormal deformation behavior;
[0040] S5, dynamically adjusting the construction scheme according to the real-time risk prediction results and risk source identification results, and completing decision optimization.
[0041] The above-mentioned technical solutions provided by the embodiments of the application will be further described in detail in combination with preferred embodiments.
[0042] In some preferred embodiments, S1, the deep foundation pit numerical simulation model is established, the mechanical behavior of the soil and the response parameters of the support system during construction are simulated using the deep foundation pit numerical simulation model, and the numerical simulation results are obtained, which can further include:
[0043] S11, a deep foundation pit numerical simulation model is established using the PLAXIS finite element method;
[0044] S12, the parameters of the deep foundation pit numerical simulation model are adjusted to simulate the stress and deformation response of the foundation pit, and key parameters are obtained, including soil stress, strain and support stiffness parameters, and the numerical simulation results are obtained.
[0045] In some preferred embodiments, S2, the multi-dimensional real-time monitoring data of the foundation pit is obtained, the real-time monitoring data is compared with the numerical simulation results, and the parameters of the deep foundation pit numerical simulation model are calibrated according to the comparison results, which can further include:
[0046] S21, using sensors to collect multi-dimensional real-time monitoring data of the foundation pit, including foundation pit wall and ground subsidence data, support system stress data and groundwater change data;
[0047] S22, comparing the real-time monitoring data with the numerical simulation results to obtain the error value between them; further, including the wall inclinometer, support axial force and ground subsidence time series data of each monitoring section, identifying the differences in response amplitude, change trend and key moments between the two;
[0048] S23, according to the comparison result, the soil mechanical behavior parameters of the deep foundation numerical simulation model and the support system response parameters are calibrated; further, including: taking the error of the measured data and the numerical simulation as the target value, establishing a parameter inversion model based on genetic algorithm (GA), constantly updating the soil mechanical parameters (such as elastic modulus, cohesion, internal friction angle) and support structure parameters in the model, and re-running the finite element calculation in each iteration until the simulation result and the measured data error converge to the preset accuracy range, so as to realize the dynamic correction of the model and the synchronous matching of the site working condition.
[0049] In some preferred embodiments, S3 above uses the Transformer algorithm to perform time series modeling analysis on real-time monitoring data, identifies abnormal deformation signals that may exist in foundation pit construction, obtains real-time risk prediction results, and can further include:
[0050] S31, a pre-trained Transformer algorithm model is constructed, the Transformer algorithm model performs time series data modeling and analysis on real-time monitoring data through a self-attention mechanism, extracts trends and features of real-time monitoring data, captures dynamic laws of foundation pit deformation development, and predicts abnormal deformation signals that may exist in foundation pit construction;
[0051] S32, the abnormal deformation signal predicted by the Transformer algorithm model is analyzed, and when the abnormal deformation signal value exceeds the set risk threshold, the current foundation pit deformation behavior is defined as an abnormal risk state.
[0052] In some preferred embodiments, S31 above performs time series data modeling and analysis on real-time monitoring data, extracts trends and features of real-time monitoring data, captures dynamic laws of foundation pit deformation development, and predicts abnormal deformation signals that may exist in foundation pit construction, and can further include:
[0053] The monitoring data of the historical construction stage and the current construction monitoring data of the corresponding stage are jointly constructed as multi-dimensional time sequence features as the input of the Transformer algorithm model, the Transformer algorithm model performs deep time series modeling through a self-attention mechanism, extracts foundation pit deformation evolution trends and features, obtains long-term data dependency relationships, captures dynamic laws of foundation pit deformation development, dynamically perceives and trends extrapolates current real-time monitoring data, and deeply learns uncertain factors in foundation pit construction, automatically identifies key factors closely related to construction safety, and predicts abnormal deformation signals that may occur in foundation pit construction; wherein:
[0054] The uncertain factors include: spatial variability of soil parameters, uncertainty of the construction process, and uncertainty of adjacent construction interference;
[0055] Key factors include: support stiffness reduction, abnormal precipitation, foundation pit over-excavation and construction disturbance;
[0056] In some preferred embodiments, S32, the abnormal deformation signal predicted by the Transformer algorithm model is analyzed, and when the abnormal deformation signal value exceeds the set risk threshold value, the current foundation pit deformation behavior is defined as an abnormal risk state, which can further include:
[0057] A pre-trained risk prediction model is constructed, and after the risk prediction model predicts the abnormal deformation signal based on the Transformer algorithm model, a scoring method based on the set foundation pit deformation risk threshold rule is used to output the corresponding foundation pit construction risk level, i.e. the corresponding abnormal risk state is obtained.
[0058] In some preferred embodiments, S4, the numerical simulation results are introduced as reference benchmarks for comparative analysis of the Transformer algorithm prediction output to identify potential risk sources causing prediction deviation and deformation abnormal behavior, which can further include:
[0059] Based on the abnormal deformation signal predicted by the Transformer algorithm and compared with the numerical simulation results, the causes of the deviation between the two are analyzed, and the corresponding construction conditions are obtained to obtain the potential risk sources causing the prediction deviation and the deformation abnormal behavior.
[0060] In some preferred embodiments, S5, the construction scheme is dynamically adjusted according to the real-time risk prediction results, which can further include:
[0061] According to the real-time risk prediction results, the construction adjustment scheme is automatically recommended by the optimization algorithm, and real-time decision support is provided to form real-time feedback and closed-loop control; wherein:
[0062] S51, the construction adjustment scheme includes: automatically optimizing the earthwork excavation rhythm, dynamically adjusting the support system installation interval and prestress according to the real-time monitoring data and numerical simulation feedback;
[0063] S52, the construction adjustment scheme is automatically recommended by the optimization algorithm, which includes: combining the risk sources identified based on monitoring prediction and numerical simulation results, automatically identifying the key control factors of the support system in the current construction stage, generating adjustment recommendation scheme of steel support, and realizing intelligent control of assembly installation, position movement and prestress application of steel support through servo system; when deformation anomaly or risk rising trend occurs, the system can actively optimize the support interval and axial force configuration, thereby dynamically adjusting the support stiffness and stress state to effectively control the foundation pit side wall deformation and overall risk level.
[0064] In some preferred embodiments, the method described above can further comprise:
[0065] S6, periodically evaluate the construction process, continuously collect new monitoring data and compare with existing numerical simulation results, update and optimize the deep foundation numerical simulation model and the Transformer algorithm.
[0066] Based on the same inventive concept, an embodiment of the present application also provides a deep foundation construction process dynamic risk prediction and optimization decision system.
[0067] Specifically, as shown in Figure 2 The deep foundation construction process dynamic risk prediction and optimization decision system provided by this embodiment can include:
[0068] A numerical simulation module for establishing a deep foundation numerical simulation model, simulating the mechanical behavior of the soil and the response parameters of the support system during the construction process using the deep foundation numerical simulation model, and obtaining numerical simulation results;
[0069] A real-time monitoring module for obtaining multi-dimensional real-time monitoring data of the foundation pit, comparing the real-time monitoring data with the numerical simulation results, and calibrating the parameters of the deep foundation numerical simulation model according to the comparison results;
[0070] A Transformer algorithm module for performing time series modeling analysis on the real-time monitoring data using the Transformer algorithm, identifying possible abnormal deformation signals in the foundation pit construction, obtaining real-time risk prediction results, and comparing the abnormal deformation signals predicted by the Transformer algorithm with the numerical simulation results as a reference benchmark to identify potential risk sources causing prediction deviation and abnormal deformation behavior;
[0071] A decision optimization module for dynamically adjusting the construction scheme according to the real-time risk prediction results and the risk source identification results to complete decision optimization.
[0072] The implementation of each functional module of the system provided by the above embodiments of the present application will be described in further detail below in conjunction with preferred embodiments.
[0073] In this preferred embodiment, the system provided by the above embodiments of the present application includes:
[0074] A numerical simulation module for establishing a deep foundation PLAXIS numerical simulation model, simulating the mechanical behavior of the soil and the response parameters of the support system during the construction process, including the stress, strain of the soil and the stress of the support, and analyzing the interaction between the soil and the support structure to provide a mechanical data basis for the foundation pit construction process;
[0075] A real-time monitoring module collects multi-dimensional monitoring data of the foundation pit in real time through sensors installed at various locations of the foundation pit, including wall displacement, ground settlement, support axial force, underground water level, etc., and compares and calibrates these real-time monitoring data with the numerical simulation results to ensure that the numerical model is consistent with the actual situation on site;
[0076] A Transformer algorithm module inputs the real-time monitoring data into the Transformer algorithm module, uses the Transformer algorithm to model and analyze the time series data through the self-attention mechanism, captures the long-term dependency relationship in the construction process, identifies potential risk patterns such as soil instability and excessive settlement of the foundation pit based on the analysis of the Transformer algorithm and the feedback results of the numerical simulation, and predicts the risk state of the foundation pit construction;
[0077] A decision optimization module dynamically adjusts the construction scheme through the optimization decision module based on the real-time risk prediction results, including adjusting the earth excavation sequence, optimizing the support system configuration, adjusting the construction progress, etc., to minimize the risks that may occur during the construction process and improve the construction efficiency.
[0078] In some preferred embodiments, the numerical simulation module is established based on the PLAXIS finite element analysis method, which can simulate the stress, strain, displacement of the soil body and the interaction between the soil body and the support system, and dynamically adjust the model parameters according to the real-time data to improve the adaptability of the model to the actual working conditions.
[0079] In some preferred embodiments, the real-time monitoring module collects data in real time through various sensors to ensure real-time monitoring of changes in soil and support conditions, and the data collected by the sensors is transmitted to the central processing system through a wireless network to ensure the real-time and accuracy of the data.
[0080] In some preferred embodiments, the Transformer algorithm module analyzes the time series monitoring data through the self-attention mechanism, which can learn the potential risk patterns and time-dependent relationships between different construction stages, analyze and predict risks such as soil deformation and support system failure, and update the risk state in real time during the construction process. The real-time risk prediction results can be displayed to the construction personnel through a visual interface, and the construction personnel can view the construction state of different risk levels through the interface and take appropriate construction measures based on the prediction results, such as adjusting the earth excavation sequence, optimizing the support system or reinforcement measures, etc.
[0081] In some preferred embodiments, the optimization decision module automatically optimizes the construction scheme through a deep learning algorithm, and the construction personnel can dynamically adjust it according to the real-time feedback to ensure the progress and safety of the entire construction process.
[0082] The dynamic risk prediction and optimization decision-making method and system for deep foundation pit construction provided in the above embodiments of the present invention, by combining numerical simulation and the Transformer algorithm, can capture potential risks in the deep foundation pit construction process in real time, perform accurate dynamic risk prediction, and provide real-time optimized construction solutions. This data-driven intelligent risk prediction and optimization decision-making method improves the safety and efficiency of construction and has broad application prospects and practical value.
[0083] It should be noted that the steps in the method provided by the present invention can be implemented using the corresponding components in the system. Those skilled in the art can refer to the technical solution of the system to implement the steps of the method, and can also refer to the technical solution of the method to implement the composition of the system. That is, the embodiments in the system and the embodiments in the method can be understood as preferred examples of each other, which will not be elaborated here.
[0084] The technical solution provided by the above embodiments of the present invention will be further described in detail below with reference to a specific application example.
[0085] like Figure 3 As shown, the dynamic risk prediction and optimization decision-making method for deep foundation pit construction involved in this specific application example includes the following steps:
[0086] Step S1: Establish a numerical simulation model for the deep foundation pit to simulate the soil mechanical behavior and support system response parameters during the construction process;
[0087] Step S2: Collect multi-dimensional real-time monitoring data of the foundation pit, including wall displacement, ground settlement, and support axial force, and compare and calibrate the monitoring data with the numerical simulation results;
[0088] Step S3: Input the real-time monitoring data into the Transformer algorithm module, use the Transformer algorithm to model and analyze the time series data, capture possible risk patterns during construction, and identify potential risk signals in the data;
[0089] Step S4: Based on the analysis of the Transformer algorithm and the feedback results of numerical simulation, predict the risk status of foundation pit construction in real time.
[0090] Step S5: Based on the real-time risk prediction results, dynamically adjust the construction plan through the optimization decision module, including the earthwork excavation sequence and support system configuration.
[0091] like Figure 4 As shown, the dynamic risk prediction and optimization decision-making system for deep foundation pit construction involved in this specific application example includes: a numerical simulation module, a real-time monitoring module, a Transformer algorithm module, and an optimization decision-making module.
[0092] In this specific application example, each module of the system works closely together to complete the dynamic risk prediction and optimization decision of the construction process through data flow and mutual feedback. In actual engineering, the numerical simulation module provides the basic mechanical data of the soil and support system, the real-time monitoring module is responsible for collecting key data during the foundation pit construction process and transmitting it to the central processing system through wireless transmission, the Transformer algorithm module analyzes the deviation between real-time data and numerical model through deep learning, and provides real-time risk assessment and early warning for the risk prediction and optimization decision module.
[0093] As shown in Figure 5 , the real-time monitoring module collects data during the foundation pit construction process in real time through sensors, including wall displacement, ground settlement, support axial force, etc., and transmits these monitoring data to the central processing system through wireless network. At this time, the numerical simulation data is combined with the real-time monitoring data for subsequent analysis.
[0094] In this specific application example, during the foundation pit construction process, the wall displacement, ground settlement, support axial force, etc. data are obtained through intelligent acquisition equipment and transmitted to the central processing system through wireless network. Users can read and download through HTTP GET, providing a data basis for subsequent foundation pit construction risk prediction.
[0095] As shown in Figure 6 , the real-time monitoring data and numerical simulation results are analyzed through the Transformer algorithm module. The Transformer algorithm models the input time series data through self-attention mechanism, captures the long-term dependence relationship in the data, identifies potential risk patterns (such as soil instability, support failure, etc.), and makes real-time prediction of risks during the construction process.
[0096] In this specific application example, Transformer is combined with reinforcement learning. In the dynamic construction process, reinforcement learning is used to continuously optimize prediction accuracy and decision-making strategy; at the same time, real-time monitoring data and simulation data are processed using Transformer to dynamically adjust the construction plan and prevent potential risks.
[0097] As shown in Figure 7 , the real-time prediction of the risk during the foundation pit excavation process is combined with actual cases. In the later stage of excavation, the wall deformation is too large, and there is a large risk. The risk of the foundation pit is controlled by dynamically adjusting the support spacing.
[0098] In this specific application example, through continuous analysis of real-time monitoring data during the foundation pit construction process, the system identifies that the wall deformation is large in the later stage of excavation, and there is a certain risk. The optimization decision module automatically adjusts the support system spacing according to the warning result, and takes reinforcement measures to ensure the stability of the foundation pit. This adjustment effectively avoids further deformation of the foundation pit wall, thereby ensuring the smooth progress and construction efficiency of the construction.
[0099] Through the cooperation between the numerical simulation module, the real-time monitoring module, the Transformer algorithm module and the optimization decision module of the above specific application examples, the corresponding methods are implemented, and the dynamic risk prediction and construction scheme optimization in the deep foundation pit construction process are realized. The interaction and data transmission between each module form a closed loop feedback system, which can effectively improve the safety, stability and efficiency of the construction.
[0100] The details not described in the above embodiments of the present application are known in the art.
[0101] The specific embodiments of the present application are described above. It should be understood that the present application is not limited to the above specific embodiments, and various modifications or changes can be made by those skilled in the art within the scope of the claims, which does not affect the essential content of the present application.
Claims
1. A method for dynamic risk prediction and optimization decision in deep foundation pit construction process, characterized in that, The method comprises the following steps: a deep foundation pit numerical simulation model is established, the mechanical behavior of soil and the response parameters of the support system during construction are simulated by using the deep foundation pit numerical simulation model, and numerical simulation results are obtained; multi-dimensional real-time monitoring data of the foundation pit are obtained, the real-time monitoring data are compared with the numerical simulation results, and the parameters of the deep foundation pit numerical simulation model are calibrated according to the comparison results; a time series modeling analysis is performed on the real-time monitoring data by using a Transformer algorithm, abnormal deformation signals possibly existing in the foundation pit construction are identified, and real-time risk prediction results are obtained; the numerical simulation results are introduced as a reference benchmark, the abnormal deformation signals predicted by the Transformer algorithm are compared and analyzed, and potential risk sources causing the prediction deviation and abnormal deformation behavior are identified; according to the real-time risk prediction results and the risk source identification results, a construction scheme is dynamically adjusted, and decision optimization is completed.
2. The method of claim 1, wherein, The deep foundation pit numerical simulation model is established, the mechanical behavior of soil and the response parameters of the support system during construction are simulated by using the deep foundation pit numerical simulation model, and numerical simulation results are obtained, which comprises the following steps: a deep foundation pit numerical simulation model is established by using a PLAXIS finite element method; parameters of the deep foundation pit numerical simulation model are adjusted, the stress and deformation response of the foundation pit is simulated, key parameters including soil stress, strain and support stiffness parameters are obtained, and numerical simulation results are obtained.
3. The method of claim 1, wherein, The multi-dimensional real-time monitoring data of the foundation pit are obtained, the real-time monitoring data are compared with the numerical simulation results, and the parameters of the deep foundation pit numerical simulation model are calibrated according to the comparison results, which comprises the following steps: multi-dimensional real-time monitoring data of the foundation pit are collected by using sensors, including foundation pit wall and ground settlement data, support system stress data and underground water change data; the real-time monitoring data are compared with the numerical simulation results, and error values between the two are obtained; according to the comparison results, the mechanical behavior parameters of soil and the response parameters of the support system of the deep foundation pit numerical simulation model are calibrated.
4. The method of claim 1, wherein, The real-time monitoring data are time series modeled and analyzed by using the Transformer algorithm, abnormal deformation signals possibly existing in the foundation pit construction are identified, and real-time risk prediction results are obtained, which comprises the following steps: a pre-trained Transformer algorithm model is constructed, the Transformer algorithm model performs time series data modeling and analysis on the real-time monitoring data by using a self-attention mechanism, extracts trends and features of the real-time monitoring data, captures dynamic laws of the deformation development of the foundation pit, and predicts abnormal deformation signals possibly existing in the foundation pit construction; the abnormal deformation signals predicted by the Transformer algorithm model are analyzed, and when the abnormal deformation signal value exceeds a set risk threshold, the current foundation pit deformation behavior is defined as an abnormal risk state.
5. The method of claim 4, wherein, The real-time monitoring data are time series modeled and analyzed, trends and features of the real-time monitoring data are extracted, dynamic laws of the deformation development of the foundation pit are captured, and abnormal deformation signals possibly existing in the foundation pit construction are predicted, which comprises the following steps: The monitoring data of the historical construction stage and the current construction monitoring data of the corresponding stage are jointly constructed as multi-dimensional time sequence features as inputs of a Transformer algorithm model, the Transformer algorithm model performs deep time sequence modeling through a self-attention mechanism, extracts the deformation evolution trend and features of the foundation pit, obtains the long-term dependence relationship of the data, captures the dynamic law of the deformation development of the foundation pit, dynamically perceives the real-time monitoring data and trend extrapolation, and deeply learns the uncertainty factors in the construction of the foundation pit, automatically identifies the key factors closely related to the construction safety, and predicts the abnormal deformation signals that may occur in the construction process of the foundation pit; wherein: The uncertainty factors include spatial variability of soil parameters, uncertainty of the construction process and uncertainty of the adjacent construction interference; The key factors include reduced support stiffness, abnormal dewatering, over-excavation of the foundation pit and construction disturbance; The abnormal deformation signals predicted by the Transformer algorithm model are analyzed, and when the abnormal deformation signal value exceeds the set risk threshold, the current deformation behavior of the foundation pit is defined as an abnormal risk state, including: A pre-trained risk prediction model is constructed, which, based on the abnormal deformation signals predicted by the Transformer algorithm model, adopts a scoring method based on the set foundation pit deformation risk threshold rule to output the corresponding foundation pit construction risk level, i.e. to obtain the corresponding abnormal risk state.
6. The method of claim 1, wherein, The numerical simulation results are introduced as reference benchmarks to compare and analyze the abnormal deformation signals predicted by the Transformer algorithm, to identify the potential risk sources causing the prediction deviation and deformation abnormal behavior, including: Based on the abnormal deformation signals predicted by the Transformer algorithm and compared with the numerical simulation results, combining data-driven and mechanism feedback, the reasons for the deviation between the two are analyzed, and the corresponding construction conditions are obtained, to obtain the potential risk sources causing the prediction deviation and deformation abnormal behavior.
7. The method of claim 1, wherein, According to the real-time risk prediction results and the risk source identification results, the construction scheme is dynamically adjusted to complete decision optimization, including: According to the real-time risk prediction results, the construction adjustment scheme is automatically recommended by an optimization algorithm, and real-time decision support is provided to form real-time feedback and closed-loop control; wherein: The construction adjustment scheme includes automatically optimizing the earthwork excavation rhythm, dynamically adjusting the support system installation spacing and prestress according to real-time monitoring data and numerical simulation feedback; The construction adjustment scheme is automatically recommended by an optimization algorithm, including automatically identifying the key control factors of the support system in the current construction stage based on the risk sources identified based on monitoring prediction and numerical simulation results, generating adjustment recommendation schemes for steel supports, and realizing intelligent control of assembly installation, position movement and prestress application of steel supports through a servo system; when deformation abnormalities or risk rising trends occur, the system actively optimizes the support spacing and axial force configuration, thereby dynamically adjusting the support stiffness and stress state to control the deformation of the foundation pit side wall and the overall risk level.
8. The method of claim 1-7, wherein, Further comprising: Periodically evaluate the construction process, continuously collect new monitoring data and compare with existing numerical simulation results, update and optimize the deep foundation numerical simulation model and Transformer algorithm.
9. A deep foundation pit construction process dynamic risk prediction and optimization decision system, characterized in that, Comprise: a numerical simulation module, which is used to establish a deep foundation numerical simulation model, simulate the mechanical behavior of soil and the response parameters of the support system during construction by using the deep foundation numerical simulation model, and obtain numerical simulation results; a real-time monitoring module, which is used to obtain multi-dimensional real-time monitoring data of the foundation pit, compare the real-time monitoring data with the numerical simulation results, and calibrate the parameters of the deep foundation numerical simulation model according to the comparison results; a Transformer algorithm module, which is used to analyze the time series of the real-time monitoring data by using the Transformer algorithm, identify abnormal deformation signals that may exist in the foundation pit construction, and obtain real-time risk prediction results; introduce the numerical simulation results as a reference benchmark, compare and analyze the abnormal deformation signals predicted by the Transformer algorithm, and identify potential risk sources that cause prediction deviation and abnormal deformation behavior; a decision optimization module, which is used to dynamically adjust the construction scheme according to the real-time risk prediction results and risk source identification results, and complete decision optimization.
10. The deep foundation pit construction process dynamic risk prediction and optimization decision system according to claim 9, characterized in that, Also include: an intelligent acquisition box, the intelligent acquisition box comprising: a displacement sensor for monitoring changes in foundation pit wall and ground settlement; a stress sensor for measuring the stress of the support system; a groundwater level monitor for real-time monitoring of changes in groundwater level.
Citation Information
Patent Citations
Foundation pit construction risk assessment method and system based on digital twin simulation platform
CN115936437A
Foundation pit deformation prediction method based on transformer model
CN118940911A
Intelligent monitoring and early warning method and system for deep foundation pit
CN119843726A
Foundation pit deformation real-time monitoring method, device and system based on BIM technology
CN120026669A
Cited By
Intelligent control method, device and equipment for micro-disturbance construction of temporary iron deep foundation pit
CN121721994A
Foundation pit dewatering and reinforcing intelligent control method for tunnel protection
CN121832680A
Intelligent control method for foundation pit dewatering and reinforcement under tunnel protection
CN121832680B