Water-rich sand layer large-section rectangular pipe jacking receiving construction method

By using triaxial mixing piles and freezing method to reinforce the water-rich sandy strata, combined with a ring steel plate water-stopping device and double-liquid grout sealing, the risk of water leakage during pipe jacking reception was solved, achieving safe and efficient construction results.

CN120990624BActive Publication Date: 2026-08-04THE THIRD CONSTR OF CHINA CONSTR EIGHTH ENG BUREAU
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202511176957.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2025-08-21
Publication Date
2026-08-04
Estimated Expiration
2045-08-21

AI Technical Summary

Technical Problem

When receiving pipes in water-rich sandy strata, conventional methods pose a risk of water leakage, which can easily cause the pipe jacking head to deviate from its direction, fail to receive the pipes, or even lead to ground subsidence and safety accidents.

Method used

The receiving tunnel portal was reinforced by a combination of triaxial mixing piles and vertical freezing method. A water-stopping device consisting of annular steel plates and fiber was used. The pressure inside and outside the well was balanced by backfilling with soil and water. A double-liquid grout was used to seal any leaks. The pipe sections were connected by longitudinal tensioning components to ensure stability and water-stopping effect.

Benefits of technology

It enables safe and efficient pipe jacking reception in water-rich sandy strata, reduces the risk of water leakage, ensures construction safety, avoids ground subsidence and building hazards, and provides reliable construction support.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120990624B_ABST
    Figure CN120990624B_ABST
Patent Text Reader

Abstract

The application provides a water-rich sand layer large-section rectangular pipe jacking receiving construction method, relates to the pipe jacking receiving construction technical field, and comprises the following steps: receiving preparation, receiving hole door removal, receiving frame and water stop device installation, receiving well water and soil backfilling, pipe jacking machine jacking in place, receiving well water and soil pumping and hole door plugging, receiving well water and soil pumping and hole door plugging, relay closure, pipe joint periphery slurry solidification and the like. The application can maximize the reduction of personnel injury and economic loss caused by water leakage, thereby realizing safe and efficient pipe jacking receiving of the water-rich sand layer stratum, and providing reliable technical support for similar projects.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of pipe jacking construction technology, specifically a method for receiving large-section rectangular pipes in water-rich sand layers. Background Technology

[0002] With the acceleration of urbanization, underground space development has become an important way to alleviate urban problems such as land scarcity and traffic congestion. Against this backdrop, rectangular pipe jacking technology, with its significant advantage of minimal disturbance to surface traffic and the environment, has gradually become the preferred solution for urban underground engineering construction. This technology uses jacking equipment to precisely insert rectangular cross-section pipe sections underground, utilizing soil pressure or mud pressure within the soil chamber to balance groundwater and soil pressure, thereby minimizing the impact of construction on the surrounding environment and ultimately achieving trenchless laying. Rectangular pipe jacking technology has been widely applied in various projects such as underground space development, underground pedestrian passages, integrated utility tunnels, underpasses, underground interconnections, subway station entrances and exits, and cut-and-cover stations, representing the future development direction of short-distance rectangular tunnel construction technology in cities.

[0003] Pipe jacking reception is the most challenging aspect to control during pipe jacking construction. Conventional pipe jacking reception procedures typically involve: first, reinforcing the foundation around the receiving shaft using methods such as freezing, deep well dewatering, or grouting to improve soil stability and water tightness; second, installing a steel receiving bracket inside the receiving shaft to support and guide the pipe jacking machine; then, gradually reducing the jacking speed as the machine approaches the shaft and strengthening monitoring to ensure precise entry of the machine into the receiving bracket; and finally, quickly sealing the opening after the machine enters the shaft to prevent soil erosion. However, water-rich sandy strata have large pores between sand particles, excellent groundwater connectivity, and extremely poor self-stabilization, making them highly susceptible to flow and liquefaction under construction disturbances. In such cases, conventional pipe jacking reception methods pose a significant risk of water leakage. If leakage occurs, it can range from causing the machine to deviate from its course and reception failure to triggering large-scale ground subsidence and collapse, potentially endangering surrounding buildings and personnel, resulting in serious safety accidents. Therefore, how to efficiently complete the pipe jacking reception in water-rich sandy strata while ensuring safety has become an urgent technical challenge. Summary of the Invention

[0004] In response to the aforementioned existing technologies, this invention proposes a construction method for receiving large-section rectangular pipe jacking in water-rich sandy strata. By using this method for pipe jacking reception, personnel injuries and economic losses caused by water leakage are minimized, thereby achieving safe and efficient pipe jacking reception in water-rich sandy strata and providing reliable technical support for similar projects.

[0005] This invention provides a method for receiving large-section rectangular jacking pipes in water-rich sand layers, comprising the following steps:

[0006] S1. Receiving preparation: The distance between the pipe jacking machine and the receiving well is designated as the pipe jacking receiving section, and preparation is made to start pipe jacking receiving;

[0007] S2. Receiving Tunnel Removal: After the receiving tunnel reinforcement meets the design requirements and passes the acceptance test, the retaining structure within the receiving tunnel area shall be removed. During the removal process, ensure that the retaining structure is removed while the reinforcement is in good condition.

[0008] S3. Installation of receiving frame and water-stopping device: After the receiving tunnel is excavated, the position of the receiving tunnel is measured and confirmed. The receiving frame of the pipe jacking machine is installed according to the actual elevation of the pipe jacking machine, and the water-stopping device is installed at the receiving tunnel.

[0009] S4. Backfilling of soil and water in the receiving well: After the receiving frame and water-stopping device are installed, immediately backfill the receiving well with soil and water to balance the soil and water pressure inside and outside the receiving well.

[0010] S5. Pipe jacking machine reaches the design position: After the backfilling is completed, the pipe jacking machine exits the tunnel for the second time and jacks to the design position.

[0011] S6. Pumping out water and clearing soil in the receiving well and sealing the tunnel entrance: Pumping out water in the receiving well and clearing backfill soil in layers, and sealing the receiving tunnel entrance as the clearing progresses.

[0012] S7. Separation of the pipe jacking machine from the pipe section: The pipe jacking machine is separated from the first pipe section, moved horizontally to the hoisting hole position, disassembled and hoisted out of the well;

[0013] S8. Closure of intermediate station: After the pipe jacking is completed, the intermediate station is closed and filled with concrete.

[0014] S9. Grout curing around pipe sections: Cement grout is cured using a system and pipeline for injecting thixotropic mud.

[0015] Preferably, in S1, the reinforcement of the receiving tunnel portal adopts a combination of triaxial mixing piles and vertical freezing reinforcement measures. The freezing reinforcement method is plate freezing wall soil reinforcement, with the frozen wall closely attached to the underground continuous wall of the receiving well. The actual number of active freezing days is determined based on the temperature field monitoring at the engineering site. After freezing, nine cross-shaped probe holes are drilled at the receiving tunnel portal using a water drill. The probe hole depth exceeds the underground continuous wall by 100mm, and the probe hole diameter is 50mm. Temperature measuring wires are installed in the probe holes to measure the probe hole temperature and evaluate the freezing effect of the receiving tunnel portal.

[0016] Preferably, in S2, before the diaphragm wall is broken, nine observation holes are drilled at the receiving portal. The diameter of the holes is 80mm, and the drilling depth is ensured to reach the reinforced soil. Ball valves are installed at the drilling locations, and the outside of the ball valves is sealed with quick-drying cement. Before the diaphragm wall is broken, the ball valves are opened at regular intervals to observe whether water flows out. The condition of the reinforced soil outside the receiving portal is continuously observed. After it is determined that there is basically no open water, the diaphragm wall is broken immediately.

[0017] Preferably, in S3, the receiving frame includes a receiving base and a guiding device. The receiving base includes a concrete guide platform, 32#a channel steel, and P43 guide rails. The guide platform is made of C30 concrete, and the guide platform is reinforced with Φ16 main bars and Φ8@300 stirrups. The channel steel is anchored with Φ20@400 anchor bars. The central axis of the receiving base is consistent with the tunnel design axis. Two guiding devices are set at the bottom of the receiving portal. The guiding devices are 5mm lower than the bottom of the pipe jacking machine head, and the receiving base is 5mm lower than the guiding devices.

[0018] Preferably, in S3, the water-stopping device includes two annular steel plates and a webbing wire. The height of the annular steel plates is 10-30mm higher than the outer wall of the jacking pipe section, and the thickness is 3mm. A triangular brace is set between the two annular steel plates. A 10mm high cut is made at the position corresponding to each triangular brace, and a webbing wire with a height of 25cm is inserted between the two annular steel plates. Two grouting holes are reserved on the top, bottom, left, and right of the portal steel ring as subsequent emergency grouting holes.

[0019] Preferably, in S4, the remaining frozen pipes outside the two rows of frozen pipes on the left and right sides of the pipe jacking machine are simultaneously thawed and removed by circulating hot brine. The specific method for removing the frozen pipes is as follows: the frozen holes are forcibly thawed with preheated hot brine. After thawing with hot brine for 5-8 minutes, the thawed frozen pipes are tested by using a truck crane. When the frozen pipe is heated to the point where it can be twisted appropriately, it can be pulled out. When it is pulled up 0.5m, the circulation of hot brine can be stopped, and the brine in the pipe can be discharged by compressed air to quickly pull out the frozen pipe.

[0020] Preferably, in S5, when the tip of the pipe jacking machine is 6m away from the receiving tunnel entrance, the grouting of the first pipe section is stopped, and the grouting position is gradually moved backward during the subsequent jacking process to ensure that a complete 6m soil plug is formed before the pipe enters the tunnel.

[0021] Preferably, in S5, the pipe jacking machine advances within the backfill soil of the receiving well, with the advancing speed controlled at 5-10 mm / min; it stops advancing after the first pipe section protrudes 50 cm from the receiving tunnel entrance. Supports are set at predetermined positions on the receiving frame track to prevent the pipe jacking machine from sliding forward. The rectangular pipe section body uses a first longitudinal tensioning member to prevent the pipe section from loosening. The first longitudinal tensioning member is formed by pre-embedding temporary steel plates on the top and bottom plates of the first 5 rectangular pipe sections. The tie rods are welded to the pre-embedded steel plates to prevent adjacent rectangular pipe sections from loosening after the jacking force is removed. The first longitudinal tensioning member is removed after construction is completed.

[0022] Preferably, in S8, when the pipe jacking machine begins to enter the receiving well, the top of the intermediate cylinder is fully retracted to the minimum position, so that the front and rear shell pipe openings of the intermediate chamber are connected and tightly fitted.

[0023] After the jacking construction is completed and before the jacking cylinder is removed, double-liquid cement grout is injected from high to low outward through the grouting hole of the intermediate station to replace the thixotropic mud that plays a drag-reducing role during the jacking pipe construction and fill the gap between the front and rear shells. If there is leakage, secondary grouting is performed. After the grouting is completed, the grouting hole is sealed.

[0024] The jacking equipment in the relay room is dismantled sequentially from front to back, including the relay room circuit, control system, oil pump station, oil lines, jacks, etc. The dismantling order for each relay room is: top first, then both sides, and finally bottom. The connecting plates of the front and rear shells of the relay room are welded, and the annular inner lining plate of the rear section is welded to the front shell section to completely seal the moving parts of the relay room. The oil stains on the surface of the relay room are wiped off with detergent, the steel mesh is installed, the formwork is installed, and the micro-expansion concrete is poured in three stages in the order of bottom first, then both sides, and finally bottom.

[0025] The second longitudinal tensioner is used to insert the prestressing tendons through the prestressing ducts pre-embedded inside all rectangular pipe sections, and the prestressing is carried out after the pipe sections are topped.

[0026] Preferably, in S9, after receiving the material, grouting is performed from both ends to the middle; the water-cement ratio of the cured cement grout is 0.7-0.8, the grout specific gravity is 1.26-1.28, the grouting pressure is 0.3-0.5MPa, and the grouting volume is ≥1.02m3 / section.

[0027] Compared with existing technologies, the beneficial effects of this invention are as follows: 1) For water-rich sandy geology, the receiving tunnel portal is reinforced using a combination of triaxial mixing piles and vertical freezing method. This utilizes the rapid construction and water-stopping capabilities of the mixing piles, while leveraging the high strength and stability of the freezing method, resulting in a dual reinforcement effect and effectively preventing risks such as water and sand inrush at the receiving tunnel portal. 2) For freezing reinforcement, after backfilling the receiving well with soil and water, the remaining frozen pipes outside the two rows of frozen pipes on the left and right sides of the pipe jacking machine are thawed and removed. Upon reaching the receiving well, the first to tenth pipe sections are solidified by injecting double-liquid grout through 1-inch holes, and then the two rows of frozen pipes on the left and right sides of the pipe jacking machine are removed. Through the combined measures of "staged thawing of the frozen wall + active sealing with double-liquid grout," the triple goals of safe receiving, efficient water-stopping, and soil reinforcement are achieved. 3) For water-rich environments, the receiving tunnel portal uses a combination structure of two ring steel plates and fiber reinforced wire to form a reliable water-stopping system, achieving soil and water retention and ensuring the safety of pipe jacking receiving construction. 4) To simulate the original soil working environment, the backfill in the receiving well provides necessary support and stability for the pipe jacking machine's receiving operation. By using a given formula for calculating the backfill height and the type of backfill soil, the water and soil pressure inside and outside the well is balanced, preventing groundwater from flowing into the receiving well. 5) During receiving, the pipe sections are securely connected together using the first and second longitudinal tensioning members to prevent relative displacement between the pipe sections. Attached Figure Description

[0028] Figure 1 This is a schematic diagram of the construction process for receiving large-section rectangular jacking pipes in water-rich sand layers, as described in an embodiment of the present invention.

[0029] Figure 2 This is a schematic diagram of the receiving well in an embodiment of the present invention.

[0030] Figure 3 This is a schematic diagram of the guiding device in an embodiment of the present invention.

[0031] Figure 4 This is a schematic diagram of the water-stopping device in an embodiment of the present invention.

[0032] Figure 5 This is a schematic diagram of the core sampling hole in the receiving portal of an embodiment of the present invention.

[0033] Figure 6 This is a schematic diagram of the receiving plane of the large-section rectangular jacking pipe in the water-rich sand layer in an embodiment of the present invention.

[0034] Figure 7-8 This is a schematic diagram of the receiving elevation of a large-section rectangular jacking pipe in a water-rich sand layer according to an embodiment of the present invention.

[0035] Figure 9 This is a schematic diagram of the removal of the frozen pipe after backfilling in an embodiment of the present invention.

[0036] Figure 10 This is a schematic diagram of the removal of the frozen pipe after injecting the double-liquid slurry into pipe sections 1-10 in an embodiment of the present invention.

[0037] Figure 11 This is a schematic diagram showing the location of the grouting holes in the relay station in an embodiment of the present invention.

[0038] In the diagram: 1. Core tube exterior wall; 2. Cantilever slab; 3. Construction adjustment joint; 4. Floor slab aluminum formwork; 5. Diagonal brace; 6. Floor deck connecting reinforcement; 7. Tie rod; 8. Floor deck. Detailed Implementation

[0039] To make the technical means, creative features, objectives and effects of this invention easier to understand, the invention will be further described below with reference to specific embodiments.

[0040] Example: Figure 1-11 The method for receiving large-section rectangular jacking pipes in water-rich sand layers, as shown, includes the following steps:

[0041] S1. Receiving preparation: The distance between the pipe jacking machine and the receiving well is designated as the pipe jacking receiving section, and preparation is made to start pipe jacking receiving;

[0042] The reinforcement of the receiving tunnel portal adopts a combination of triaxial mixing piles and vertical freezing reinforcement measures. The freezing reinforcement method is to reinforce the soil of the plate freezing wall. The frozen wall is closely attached to the underground continuous wall of the receiving well. The actual number of active freezing days is determined according to the temperature field monitoring at the project site. After freezing, nine cross-shaped probe holes are drilled at the receiving tunnel portal using a water drill. The probe hole depth is more than 100mm beyond the underground continuous wall and the probe hole diameter is 50mm. Temperature measuring wires are installed in the probe holes to measure the probe hole temperature and evaluate the freezing effect of the receiving tunnel portal.

[0043] As the pipe jacking machine gradually approaches the receiving well, the surveyors re-measure the attitude of the pipe jacking machine and increase the frequency and accuracy of the measurements. Based on the re-measurement results, they promptly correct any deviations to ensure that the pipe jacking machine can be accurately received. Only after ensuring that the reinforcement range, strength, and water-stopping properties of the receiving end meet the design requirements and the attitude of the pipe jacking machine are verified can the removal of the receiving tunnel entrance be completed.

[0044] S2. Receiving Tunnel Removal: After the receiving tunnel reinforcement meets the design requirements and passes the acceptance test, the retaining structure within the receiving tunnel area shall be removed. During the removal process, ensure that the retaining structure is removed while the reinforcement is in good condition.

[0045] Before breaking the diaphragm wall, nine observation holes with a diameter of 80 mm were drilled at the receiving tunnel entrance. The drilling depth was ensured to reach the reinforced soil. Ball valves were installed at the drilling locations and sealed on the outside with quick-drying cement. Before breaking the diaphragm wall, the ball valves were opened periodically to observe whether water flowed out. The condition of the reinforced soil outside the receiving tunnel entrance was continuously monitored. Once it was determined that there was basically no open water, the diaphragm wall was immediately broken.

[0046] During demolition, construction should be carried out in layers and sections, and it is not allowed to directly break through from the outer protective layer of the diaphragm wall to the reinforced body. If leakage occurs on the surface of the diaphragm wall, demolition should be stopped, the cause should be identified in time, and the reinforced body should be reinforced with grout. Demolition can only continue after the wall surface is dry or there is no leakage.

[0047] S3. Installation of receiving frame and water-stopping device: After the receiving tunnel is excavated, the position of the receiving tunnel is measured and confirmed. The receiving frame of the pipe jacking machine is installed according to the actual elevation of the pipe jacking machine, and the water-stopping device is installed at the receiving tunnel.

[0048] The receiving frame includes a receiving base and a guiding device. The receiving base includes a concrete guide platform, 32#a channel steel, and P43 guide rails. The guide platform is made of C30 concrete and is reinforced with Φ16 main bars and Φ8@300 stirrups. The channel steel is anchored with Φ20@400 anchor bars. The central axis of the receiving base is consistent with the tunnel design axis. Two guiding devices are set at the bottom of the receiving portal. The guiding devices are 5mm lower than the bottom of the pipe jacking machine head, and the receiving base is 5mm lower than the guiding devices.

[0049] The water-stopping device includes two annular steel plates and a webbing wire. The height of the annular steel plates is 10-30mm higher than the outer wall of the jacking pipe section, and the thickness is 3mm. Triangular supports are set between the two annular steel plates. A 10mm high cut is made at the position of each triangular support, and webbing wire is inserted between the two annular steel plates. The height of the webbing wire is 25cm. Two grouting holes are reserved on the top, bottom, left and right of the portal steel ring as subsequent emergency grouting holes.

[0050] S4. Backfilling of soil and water in the receiving well: After the receiving frame and water-stopping device are installed, immediately backfill the receiving well with soil and water to balance the soil and water pressure inside and outside the receiving well.

[0051] Upon completion of the tunnel portal demolition, the receiving well is immediately backfilled with soil and water, using cement-modified soil. In this embodiment, the net dimensions of the receiving well are 11.2m longitudinally, 12.87m laterally, 20.9m deep, and the bottom slab is 1.4m thick. The receiving tunnel portal is reinforced using φ850@600 triaxial mixing piles + vertical freezing reinforcement. The longitudinal length of the triaxial mixing piles is 6m, the width of the tunnel portal reinforcement is 15.1m, and the longitudinal length of the freezing reinforcement is approximately 3m. In this embodiment, the backfilling height of the cement-modified soil is calculated to be 3m above the pipe jacking machine according to the following formula, and then clean water is injected to 2m below the ground surface.

[0052]

[0053]

[0054] Simultaneously, the remaining frozen pipes outside the two rows of frozen pipes on the left and right sides of the pipe jacking machine are thawed and removed using circulating hot brine. The specific method for removing the frozen pipes is as follows: the frozen holes are forcibly thawed using preheated hot brine. After thawing with hot brine for 5-8 minutes, the thawed frozen pipes are tested using a truck crane. When the frozen pipe is heated to the point where it can be twisted appropriately, it can be pulled out. When it is pulled out about 0.5m, the circulation of hot brine can be stopped, and the brine in the pipe can be discharged with compressed air to quickly pull out the frozen pipe.

[0055] S5. Pipe jacking machine reaches the design position: After the backfilling is completed, the pipe jacking machine exits the tunnel for the second time and jacks to the design position.

[0056] When the tip of the pipe jacking machine is 6m away from the receiving tunnel entrance, the grouting of the first pipe section is stopped. During the subsequent jacking process, the grouting position is gradually moved back to ensure that a soil plug of about 6m is formed before the pipe enters the tunnel, so as to avoid a large loss of friction-reducing mud during the tunneling process, which would cause a sudden increase in the friction resistance around the pipe section.

[0057] The pipe jacking machine advances within the backfill soil of the receiving well, with the advancing speed controlled at 5-10 mm / min. Advancement stops when the first pipe section protrudes 50 cm from the receiving tunnel entrance. Supports are set at predetermined positions on the receiving frame track to prevent the pipe jacking machine from sliding forward. The rectangular pipe section body uses a first longitudinal tensioning member to prevent the pipe section from loosening. The first longitudinal tensioning member is formed by pre-embedding temporary steel plates on the top and bottom plates of the first 5 rectangular pipe sections. The tie rods are welded to the pre-embedded steel plates to prevent adjacent rectangular pipe sections from loosening after the jacking force is removed. The first longitudinal tensioning member is removed after construction is completed.

[0058] For pipe sections 1-10, a 1:1 dual-liquid grout is injected through 1-inch holes to solidify the grout and seal any possible water seepage channels between the pipe sections and the receiving tunnel. At this time, two rows of freezing pipes on the left and right sides of the pipe jacking machine are removed. If serious leakage occurs at the tunnel entrance after the pipe jacking machine enters the receiving tunnel, underwater concrete is poured into the receiving well in time to apply back pressure, and the amount of friction-reducing grout injected into the friction-reducing injection holes is replenished in time.

[0059] S6. Pumping out water and clearing soil in the receiving well and sealing the tunnel entrance: Pumping out water in the receiving well and clearing backfill soil in layers, and sealing the receiving tunnel entrance as the clearing progresses.

[0060] Check the solidification effect of the grout injected in S5. If the effect is good, start pumping water into the receiving well and clean the backfill soil in layers. When cleaning the backfill soil, closely observe whether there is water overflow in the soil. If water overflow occurs, stop cleaning and continue grouting the wall thickness of pipe sections 1-10. If there is no water overflow, continue cleaning in layers and seal the receiving tunnel door at the same time as the cleaning progress.

[0061] S7. Separation of the pipe jacking machine from the pipe section: The pipe jacking machine is separated from the first pipe section, moved horizontally to the hoisting hole position, disassembled and hoisted out of the well;

[0062] Remove soil from the earth pressure chamber and screw conveyor of the jacking machine head; dismantle the hydraulic oil pipes and electrical cables related to the cutterhead and pipe jacking machine system; dismantle the two screw conveyors; use telescopic correction jacks and additional pads to detach the jacking machine head from the pipe section, push the jacking machine head forward as a whole, and place it smoothly on the receiving platform; use small jacks and steel jacks to push the pipe jacking machine to the receiving hoisting hole position; disassemble the front and rear shells and upper and lower shells of the pipe jacking machine; use a truck crane to lift the jacking machine head out of the well in sections;

[0063] S8. Closure of intermediate station: After the pipe jacking is completed, the intermediate station is closed and filled with concrete.

[0064] When the pipe jacking machine begins to enter the receiving well, the top of the intermediate cylinder retracts to its minimum position, so that the front and rear shell pipe openings of the intermediate chamber are connected and tightly fitted.

[0065] After the jacking construction is completed and before the jacking cylinder is removed, double-liquid cement grout is injected from high to low outwards through the P2 grouting hole of the intermediate station to replace the thixotropic mud that plays a drag-reducing role during the jacking of the pipe and fill the gap between the front and rear shells. If there is any leakage, secondary grouting is performed. After the grouting is completed, the grouting hole is sealed. The grouting should be uniform and dense. The outside of the intermediate station should be evenly wrapped to ensure that groundwater outside the pipe cannot seep in, creating a relatively dry environment for the subsequent welding work of the intermediate station closure.

[0066] The jacking equipment in the relay room is dismantled sequentially from front to back, including the relay room circuit, control system, oil pump station, oil lines, jacks, etc. The dismantling order for each relay room is: top first, then both sides, and finally bottom. The connecting plates of the front and rear shells of the relay room are welded, and the annular inner lining plate of the rear section is welded to the front shell section to completely seal the moving parts of the relay room. The oil stains on the surface of the relay room are wiped off with detergent, the steel mesh is installed, the formwork is installed, and the micro-expansion concrete is poured in three stages in the order of bottom first, then both sides, and finally bottom.

[0067] The second longitudinal tensioner is used to insert the prestressing tendons through the prestressing ducts pre-embedded inside all rectangular pipe sections, and the prestressing is carried out after the pipe sections are topped.

[0068] S9. Grout curing around pipe sections: Cement grout curing is carried out using a system and pipeline for injecting thixotropic mud.

[0069] Grout solidification method: After receiving the grout, the grout is injected from both ends to the middle.

[0070] Grouting sequence: In this embodiment, the entire line consists of 183 pipe sections. Grouting is carried out in sections of 5 sections each, for a total of 37 sections. During grouting, the bottom two grouting holes of sections 1-5 and 183-179 are grouted first, then the two grouting holes on both sides of sections 1-5 and 183-179 are grouted, and finally the top two grouting holes of sections 1-5 and 183-179 are grouted. This sequence is repeated until the entire line is completed. After the grout has solidified, the main channel grout pipe, the arc-shaped grout pipe inside the pipe, and the ball valve are removed and cleaned on-site to prevent the grout from solidifying and clogging.

[0071] Grout curing parameters: water-cement ratio of the cured cement grout is 0.7-0.8, slurry specific gravity is 1.26-1.28, grouting pressure is 0.3-0.5 MPa, and grouting volume is ≥1.02 m³. 3 / Festival;

[0072] During the grouting process, strengthen the monitoring of the road surface and pipelines, strictly control the grouting pressure and grouting volume, and avoid adverse disturbances caused by excessive or insufficient pressure. At the same time, strengthen the monitoring of the tunnel.

[0073] The above are merely embodiments of the present invention and do not limit the patent scope of the present invention. Any equivalent solutions made using the contents of the present invention specification, whether directly or indirectly applied to other related technical fields, are similarly within the patent protection scope of the present invention.

Claims

1. A method for receiving large-section rectangular pipe jacking in water-rich sand layers, characterized in that, Includes the following steps: S1. Receiving preparation: The distance between the pipe jacking machine and the receiving well is designated as the pipe jacking receiving section, and preparation is made to start pipe jacking receiving; S2. Receiving Tunnel Removal: After the receiving tunnel reinforcement meets the design requirements and passes the acceptance test, the retaining structure within the receiving tunnel area shall be removed. During the removal process, ensure that the retaining structure is removed while the reinforcement is in good condition. S3. Installation of receiving frame and water-stopping device: After the receiving tunnel is excavated, the position of the receiving tunnel is measured and confirmed. The receiving frame of the pipe jacking machine is installed according to the actual elevation of the pipe jacking machine, and the water-stopping device is installed at the receiving tunnel. S4. Backfilling of soil and water in the receiving well: After the receiving frame and water-stopping device are installed, immediately backfill the receiving well with soil and water to balance the soil and water pressure inside and outside the receiving well. S5. Pipe jacking machine reaches the design position: After the backfilling is completed, the pipe jacking machine exits the tunnel for the second time and jacks to the design position. S6. Pumping out water and clearing soil in the receiving well and sealing the tunnel entrance: Pumping out water in the receiving well and clearing backfill soil in layers, and sealing the receiving tunnel entrance as the clearing progresses. S7. Separation of the pipe jacking machine from the pipe section: The pipe jacking machine is separated from the first pipe section, moved horizontally to the hoisting hole position, disassembled and hoisted out of the well; S8. Closure of intermediate station: After the pipe jacking is completed, the intermediate station is closed and filled with concrete. S9. Grout curing around pipe sections: Cement grout curing is carried out using a system and pipeline for injecting thixotropic mud. In step S4, the remaining frozen pipes outside the two rows of frozen pipes on the left and right sides of the pipe jacking machine are simultaneously thawed and removed by circulating hot brine. The specific method for removing the frozen pipes is as follows: the frozen holes are forcibly thawed by preheated hot brine. After thawing with hot brine for 5-8 minutes, the thawed frozen pipes are tested by using a truck crane. When the frozen pipe is heated to the point where it can be twisted appropriately, it can be pulled out. When it is pulled out 0.5m, the circulation of hot brine can be stopped, and the brine in the pipe can be discharged by compressed air to quickly pull out the frozen pipe. In S5, the pipe jacking machine advances within the backfill soil of the receiving well, with the advancing speed controlled at 5-10 mm / min. The advancement stops when the first pipe section protrudes 50 cm from the receiving tunnel entrance. Supports are set at predetermined positions on the receiving frame track to prevent the pipe jacking machine from sliding forward. The rectangular pipe section body uses a first longitudinal tensioning member to prevent the pipe section from loosening. The first longitudinal tensioning member is formed by pre-embedding temporary steel plates on the top and bottom plates of the first 5 rectangular pipe sections. The tie rods are welded to the pre-embedded steel plates to prevent adjacent rectangular pipe sections from loosening after the jacking force is removed. The first longitudinal tensioning member is removed after construction is completed. In S8, when the pipe jacking machine begins to enter the receiving well, the top of the intermediate cylinder is fully retracted to the minimum position, so that the front and rear shell pipe openings of the intermediate chamber are connected and tightly fitted. After the jacking construction is completed and before the jacking cylinder is removed, double-liquid cement grout is injected from high to low outward through the grouting hole of the intermediate station to replace the thixotropic mud that plays a drag-reducing role during the jacking pipe construction and fill the gap between the front and rear shells. If there is leakage, secondary grouting is performed. After the grouting is completed, the grouting hole is sealed. The jacking equipment in the relay room is dismantled sequentially from front to back, followed by the relay room circuit, control system, oil pump station, oil lines, and jacks. The dismantling order for each relay room is: top first, then both sides, and finally bottom. The connecting plates between the front and rear shells of the relay room are welded, and the annular inner lining plate of the rear section is welded to the front shell section to completely seal the moving parts of the relay room. The oil stains on the surface of the relay room are wiped off with detergent, the steel mesh is installed, the formwork is installed, and the micro-expansion concrete is poured in three stages in the order of top first, then both sides, and finally bottom. The second longitudinal tensioning member is used to insert the prestressing tendons through the prestressing ducts pre-embedded inside all rectangular pipe sections, and the prestressing is carried out after the pipe sections are topped.

2. The method for receiving and constructing a large-section rectangular pipe jacking in a water-rich sand layer as described in claim 1, characterized in that, In S1, the reinforcement of the receiving tunnel portal adopts a combination of triaxial mixing piles and vertical freezing. The freezing reinforcement method is to reinforce the soil of the plate freezing wall. The frozen wall is closely attached to the underground continuous wall of the receiving well. The actual number of active freezing days is determined according to the temperature field monitoring at the project site. After freezing, nine cross-shaped probe holes are drilled at the receiving tunnel portal using a water drill. The depth of the probe holes exceeds the underground continuous wall by 100mm and the diameter of the probe holes is 50mm. Temperature measuring wires are installed in the probe holes to measure the temperature of the probe holes and evaluate the freezing effect of the receiving tunnel portal.

3. The method for receiving large-section rectangular pipe jacking in water-rich sand layers as described in claim 1 or 2, characterized in that, In S2, before the diaphragm wall is demolished, nine observation holes with a diameter of 80 mm are drilled at the receiving tunnel entrance. The drilling depth is ensured to reach the reinforced soil. Ball valves are installed at the drilling locations, and the outside of the ball valves is sealed with quick-drying cement. Before the diaphragm wall is demolished, the ball valves are opened periodically to observe whether water flows out. The condition of the reinforced soil outside the receiving tunnel entrance is continuously monitored. Once it is determined that there is basically no open water, the diaphragm wall is demolished immediately.

4. The method for receiving large-section rectangular pipe jacking in water-rich sand layers as described in claim 1 or 2, characterized in that, In S3, the receiving frame includes a receiving base and a guiding device. The receiving base includes a concrete guide platform, 32#a channel steel and P43 guide rail. The guide platform is made of C30 concrete and is reinforced with Φ16 main bars and Φ8@300 stirrups. The channel steel is anchored with Φ20@400 anchor bars. The central axis of the receiving base is consistent with the tunnel design axis. Two guiding devices are set at the bottom of the receiving portal. The guiding devices are 5mm lower than the bottom of the pipe jacking machine head, and the receiving base is 5mm lower than the guiding devices.

5. The method for receiving large-section rectangular pipe jacking in water-rich sand layers as described in claim 1 or 2, characterized in that, In S3, the water-stopping device includes two annular steel plates and a webbing wire. The height of the annular steel plates is 10-30mm higher than the outer wall of the jacking pipe section, and the thickness is 3mm. Triangular supports are set between the two annular steel plates. A 10mm high cut is made at the position corresponding to each triangular support, and webbing wire is inserted between the two annular steel plates. The height of the webbing wire is 25cm. Two grouting holes are reserved on the top, bottom, left and right of the portal steel ring as subsequent emergency grouting holes.

6. The method for receiving large-section rectangular pipe jacking in water-rich sand layers as described in claim 1 or 2, characterized in that, In S5, when the tip of the pipe jacking machine is 6m away from the receiving tunnel entrance, the grouting of the first pipe section is stopped, and the grouting position is gradually moved back during the subsequent jacking process to ensure that a complete 6m soil plug is formed before the pipe enters the tunnel.

7. The method for receiving large-section rectangular pipe jacking in water-rich sand layers as described in claim 1 or 2, characterized in that, In S9, after receiving the grout, grouting is performed from both ends towards the middle; the water-cement ratio of the cured cement grout is 0.7-0.8, the grout specific gravity is 1.26-1.28, the grouting pressure is 0.3-0.5 MPa, and the grouting volume is ≥1.02 m³. 3 / Festival.