一种曲面幕墙施工方法
By dividing the curved curtain wall construction into blocks and using BIM models, combined with stiffness reinforcement and auxiliary passage structures, the problems of low construction efficiency and difficulty in ensuring quality were solved, and efficient and stable curtain wall installation was achieved.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- SHANGHAI MECHANIZED CONSTR GRP
- Filing Date
- 2025-11-06
- Publication Date
- 2026-07-17
AI Technical Summary
Existing methods for constructing curved curtain walls suffer from problems such as cumbersome procedures, large on-site workload, low installation efficiency, and difficulty in ensuring installation quality.
The construction blocks are divided using a BIM model. First, panels are assembled on the support plane to form blocks. Then, stiffness reinforcement and auxiliary passage structures are installed. Finally, external hoisting equipment is used to hoist the blocks to the main building and fix them in place. The temporary structures are then dismantled.
This improved the efficiency and quality of curtain wall installation, prevented deformation of the construction blocks during hoisting and installation, and ensured the stability and safety of the construction.
Smart Images

Figure CN121183891B_ABST