Permanent foundation pit support anti-seepage structure under high visibility rate and construction method
By employing a combined structure of anti-seepage wall, SMW method piles, solidified soil and waterproof layer in the foundation pit support, and using a mixture of natural sodium bentonite and cement and mineral-based binder, the problems of cement grout leakage and sidewall waterproofing failure are solved, achieving efficient water stopping and structural stability, and is suitable for complex strata and narrow spaces.
Patent Information
- Application Number
- CN202511274399.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2025-09-08
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2045-09-08
AI Technical Summary
When constructing foundation pits in karst landform areas, conventional foundation pit support techniques are prone to problems such as cement grout leakage and hole collapse under conditions of high cavern exposure and water-rich strata. Furthermore, the sidewall waterproofing material is easily penetrated by plant roots, leading to the failure of its waterproofing performance.
The structure adopts a combination of seepage-proof wall, SMW method piles, solidified soil and waterproof layer. Natural sodium bentonite and cement mixture is used as water-stopping material, combined with mineral-based cementitious curing agent to form solidified soil. The support components improve the structural stability through components such as mounting plates, support shells and tie rods.
It effectively seals karst caves, improves water-stopping effect, reduces environmental disturbance, enhances structural stability, adapts to complex strata, reduces costs, and prevents cement slurry overflow and sidewall loosening. It is suitable for old urban areas and narrow spaces.
Smart Images

Figure CN121295744B_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of karst engineering, specifically the permanent foundation pit support and seepage prevention structure and construction method under high cavern rate. Background Technology
[0002] In urban areas and karst landform areas (limestone areas), when carrying out foundation pit support engineering for building construction, geological conditions with a high rate of caverns are often encountered. The terrain is narrow and close to surrounding buildings. During the construction process, cement grout leakage is prone to occur in karst engineering, water-rich strata, especially water-rich high-permeability sandy strata, which can lead to serious hole collapse. Therefore, corresponding foundation pit support technology is required. Common foundation pit support construction techniques generally use cement as the spraying material. By mixing cement slurry with soil, a cement-soil wall is formed to achieve the function of water stoppage. However, groundwater is very abundant in limestone areas, which can easily lead to the dilution of cement slurry, thus making the actual water stoppage effect unable to meet the design standards. Furthermore, conventional sidewall waterproofing materials typically do not employ root-penetration resistant types. However, in practical applications, homeowners often plant greenery in the area to pursue overall aesthetics. Due to the inherent limitations of sidewall rolls, plant roots may penetrate the material, thereby compromising its waterproofing performance.
[0003] Therefore, the present invention provides a permanent foundation pit support and seepage prevention structure and construction method with a high hole exposure rate. Summary of the Invention
[0004] In order to overcome the shortcomings of the prior art, at least one technical problem raised in the background art is solved.
[0005] The technical solution adopted by the present invention to solve its technical problem is: a permanent foundation pit support and seepage prevention structure with high hole visibility rate, including a foundation pit body, an anti-seepage wall is set inside the foundation pit body, an SMW method pile is set inside the anti-seepage wall, a solidified soil is set inside the SMW method pile, a waterproof layer is set inside the solidified soil, and a structural wall is set inside the waterproof layer. The inner side of the structural wall is provided with a support component to support the structural wall and improve its stability.
[0006] Preferably, the waterproof layer includes a waterproof membrane and a waterproof protective layer.
[0007] Preferably, the support assembly includes multiple mounting plates fixed to the inner side of the structural wall, a support housing rotatably connected to one side of the mounting plates, a tie rod slidably inserted into the inner cavity of the support housing, and an anchor plate rotatably connected to the bottom of the tie rod.
[0008] Preferably, the cross-section of the inner cavity of the support housing is T-shaped, and the cross-section of the tie rod is T-shaped.
[0009] Preferably, the support assembly further includes a plurality of positioning holes communicating with the top of the inner cavity of the support housing, an opening on the surface of the pull rod, an inner compartment located at the bottom of the opening inside the pull rod, a plug inserted into the inner cavity of the opening, a first spring fixed to the bottom of the plug, a connecting rod slidably inserted between the opening and the first spring, a connecting block fixed to the bottom of the connecting rod, and a limiting component acting on the connecting block, wherein the bottom of the first spring is fixed to the bottom of the inner wall of the opening, and the top of the first spring is fixed to the surface of the connecting rod.
[0010] Preferably, the limiting component includes a first threaded rod slidably inserted into the inner cavity of the inner compartment, the outer end of the first threaded rod being threadedly connected to the inner wall of the support housing, the inner end of the first threaded rod being rotatably connected to the surface of the abutment block, one side of the top of the abutment block being inclined, and the bottom of the connecting block being inclined.
[0011] Preferably, the support assembly further includes a central shaft disposed between the four sets of anchor plates, limiting grooves opened on both sides of the central shaft, a sliding disk slidably inserted into the inner cavity of the limiting groove, a second threaded rod rotatably connected to one side of the sliding disk, threaded holes opened on one side of the four anchor plates, and a second spring fixed to the side of the sliding disk away from the adjacent position of the second threaded rod. One side of the second spring is fixed to the inner wall of the limiting groove, and one side of the second threaded rod extends into the interior of the adjacent position of the threaded hole. The support assembly further includes a guide rod inserted through the sliding disk at the upper and lower ends of the second threaded rod, and both sides of the guide rod are fixed to the inner wall of the limiting groove.
[0012] A construction method for a permanent foundation pit support and seepage prevention structure, which employs the aforementioned permanent foundation pit support and seepage prevention structure, includes the following steps: S1: Using the double-pipe jet grouting pile machine technology, a seepage-proof wall is constructed; S2: After forming the pile body using a three-axis mixing pile machine, an I-beam is inserted to construct the SMW method pile. S3: The structural walls are made of C30 grade concrete to ensure the compactness of the concrete during pouring and vibration. S4: After the surface of the structural wall is treated, waterproof membrane is laid to ensure there are no hollow areas, and then a waterproof protective layer is laid. S5: Clean the side wall base, carry out the pouring of solidified soil, and after the pouring is completed, carry out appropriate curing measures; S6: Install support components to support the structural wall.
[0013] The beneficial effects of this invention are as follows: 1. By improving the material of the water-stop curtain, the cement grout is replaced with a mixture of natural sodium bentonite and cement. The property of bentonite to expand when it comes into contact with water and form a colloid can effectively seal the karst (soil) cavities. It has better water-stopping effect and cost-effectiveness than the traditional cement grouting method for karst cavities. It also has less disturbance to the surrounding environment and better adaptability to old urban areas and complex geological scenarios. 2. Because the colloid formed by bentonite has poor fluidity and easily combines with the surrounding soil once formed, it ensures that the liquid will not overflow the project site in the subsequent process, avoiding potential safety risks and further reducing the impact on the surrounding environment. 3. Mineral-based cementitious solidifying agents are used to form solidified soil from waste engineering mud. The resulting material is similar to foamed concrete, which effectively solves the problem of insufficient backfill compaction caused by narrow side wall space. 4. The sidewall waterproofing material uses solidified soil, which, after hardening, not only effectively protects the waterproofing material but also has its own seepage prevention function. Attached Figure Description
[0014] The invention will now be further described with reference to the accompanying drawings.
[0015] Figure 1 This is a schematic diagram of the overall structure of the present invention; Figure 2 In this invention Figure 1 Enlarged structural diagram at point A; Figure 3 In this invention Figure 1 Enlarged structural diagram at point B; Figure 4 This is a three-dimensional structural diagram of the support component in this invention; Figure 5 This is a partial three-dimensional structural cross-sectional view of the support component in this invention; Figure 6 In this invention Figure 5 Enlarged structural diagram at point C; Figure 7 This is a three-dimensional cross-sectional view of the central axis in this invention; Figure 8 This is a schematic diagram of the construction method of the present invention.
[0016] In the diagram: 1. Foundation pit body; 2. Anti-seepage wall; 3. SMW method pile; 4. Stabilized soil; 5. Waterproof layer; 51. Waterproof membrane; 52. Waterproof protective layer; 6. Structural wall; 7. Support shell; 8. Mounting plate; 9. Tie rod; 10. Anchor plate; 11. Positioning hole; 12. Opening; 13. Insert block; 14. Connecting rod; 15. First spring; 16. Connecting block; 17. Inner chamber; 18. Abutment block; 19. First threaded rod; 20. Central shaft; 21. Second threaded rod; 22. Threaded hole; 23. Limiting groove; 24. Sliding disc; 25. Guide rod; 26. Second spring. Detailed Implementation
[0017] To make the technical means, creative features, objectives and effects of this invention easier to understand, the invention will be further described below in conjunction with specific embodiments.
[0018] Example 1: like Figures 1 to 7 As shown, the permanent foundation pit support seepage prevention structure with high hole exposure rate according to the embodiment of the present invention includes a foundation pit body 1, a seepage prevention wall 2 is provided inside the foundation pit body 1, an SMW method pile 3 is provided inside the seepage prevention wall 2, a solidified soil 4 is provided inside the SMW method pile 3, a waterproof layer 5 is provided inside the solidified soil 4, a structural wall 6 is provided inside the waterproof layer 5, and a support component is provided inside the structural wall 6 to support the structural wall 6 and improve its stability. The waterproof layer 5 includes a waterproof membrane 51 and a waterproof protective layer 52.
[0019] The seepage-proof wall 2 replaces the traditional cement mixing piles as a water-stop curtain. At the same time, the improved material is changed from cement grout to natural sodium-based bentonite + 10% cement. The grouting pressure is 18-22 MPa. A double-pipe jet grouting machine is used. The SMW method pile 3 adopts a three-axis mixing pile + I-beam to improve the overall rigidity of the foundation pit. The solidified soil 4 is formed by mixing engineering waste soil and grout, and adding mineral-based cementitious curing agents. The waterproof layer 5 adopts a double-layer structure. The waterproof membrane 51 is a fiber-reinforced root-penetration resistant modified bitumen waterproof membrane. The waterproof protective layer 52 is an ALC precast panel. The structural wall 6 is poured with impermeable C30 concrete.
[0020] By improving the materials of the waterproofing curtain, cement grout is replaced with a mixture of natural sodium-based bentonite and cement. Utilizing the property of bentonite to swell and form a colloid upon contact with water, it effectively seals cavities in the soluble soil. Because the bentonite colloid has poor fluidity and easily combines with the surrounding soil once formed, it ensures that liquid will not overflow the project site during subsequent processes, avoiding potential safety risks. A mineral-based gelling agent is used, and waste engineering slurry is used to form solidified soil. The resulting material is similar to foamed concrete, effectively solving the problem of insufficient backfill compaction caused by narrow sidewall spaces. The solidified soil used for the sidewall waterproofing not only effectively protects the waterproofing material after hardening but also possesses its own seepage-proof function. This can solve the problem of cement grout leakage that is prone to occur in karst engineering and water-rich strata, especially water-rich and highly permeable sandy strata, which can lead to serious hole collapse. Compared with the traditional cement grouting method for karst caves, it has better water-stopping effect and cost-effectiveness, and causes less disturbance to the surrounding environment. It is also more adaptable to old urban areas and complex geological scenarios.
[0021] like Figures 1 to 7 As shown, the support assembly includes multiple mounting plates 8 fixed to the inner side of the structural wall 6, a support housing 7 rotatably connected to one side of the mounting plates 8, a tie rod 9 slidably inserted into the inner cavity of the support housing 7, and an anchor plate 10 rotatably connected to the bottom of the tie rod 9. The cross-section of the inner cavity of the support housing 7 is T-shaped, and the cross-section of the tie rod 9 is T-shaped. After the structural wall 6 is poured, a set of screw holes are pre-set on the inner side of the structural wall 6, and the mounting plate 8 is fixed to the inner side of the structural wall 6 with bolts. Then, the length of the tie rod 9 inside the support shell 7 is adjusted, and the angle of the anchor plate 10 is adjusted by rotating the anchor plate 10 so that it is parallel to the bottom surface of the foundation pit. Since the total length of the tie rod 9 and the support shell 7 can be adjusted, it can meet the needs of foundation pits of various depths. Then, the anchor rods pre-set on the surface of the anchor plate 10 are hammered into the soil deep in the foundation pit, which can support the structural wall 6, improve the stability of the structural wall 6, and prevent the structural wall 6 from deforming or cracking under stress. Furthermore, due to the shape setting of the inner cavity of the support shell 7 and the tie rod 9, the tie rod 9 can be prevented from detaching from the inner cavity of the support shell 7 by the contact between the top surface of the tie rod 9 and the bottom of the inner cavity of the support shell 7.
[0022] like Figures 1 to 7As shown, the support assembly also includes a plurality of positioning holes 11 communicating with the top of the inner cavity of the support housing 7, an opening 12 opened on the surface of the pull rod 9, an inner compartment 17 opened inside the pull rod 9 at the bottom of the opening 12, an insert block 13 inserted into the inner cavity of the opening 12, a first spring 15 fixed to the bottom of the insert block 13, a connecting rod 14 slidably inserted between the opening 12 and the first spring 15, a connecting block 16 fixed to the bottom of the connecting rod 14, and a limiting component acting on the connecting block 16. The bottom of the first spring 15 is fixed to the bottom of the inner wall of the opening 12, and the top of the first spring 15 is fixed to the surface of the connecting rod 14. When the sliding rod 9 slides within the cavity of the support housing 7, the insertion block 13 slides into the opening 12 due to the contact between the inner wall of the positioning hole 11 and the inner wall of the support housing 7. This compresses the adjacent first spring 15, causing it to deform. Furthermore, the contact between the connecting rod 14 and the hole wall between the opening 12 and the connecting block 16 limits the insertion block 13 until the total length of the mounting plate 8 and the rod 9 is adjusted. Under the rebound force of the first spring 15, the insertion block 13 is inserted into the cavity of the adjacent positioning hole 11, thereby positioning the mounting plate 8. The limiting component also contacts the connecting block 16, thus fixing the mounting plate 8 in the positioned position and ensuring that the total length of the mounting plate 8 and the rod 9 remains constant.
[0023] like Figures 1 to 7 As shown, the limiting component includes a first threaded rod 19 that is slidably inserted into the inner cavity of the inner compartment 17. The outer end of the first threaded rod 19 is threadedly connected to the inner wall of the support housing 7. The inner end of the first threaded rod 19 is rotatably connected to the surface of the abutment block 18. One side of the top of the abutment block 18 is inclined, and the bottom of the connecting block 16 is inclined. After the insert 13 is inserted into the adjacent positioning hole 11 to limit the pull rod 9, the first threaded rod 19 is rotated to extend into the depth of the inner cavity of the support housing 7 through the cooperation of the threaded structure with the inner wall of the pull rod 9. Since the abutment block 18 is limited by the inner cavity of the inner chamber 17, the abutment block 18 moves towards the connecting block 16 until the top surface of the abutment block 18 abuts against the bottom surface of the connecting block 16. This limits the height of the insert 13 and the connecting rod 14. Since the abutment block 18 and the connecting block 16 are set at an angle, the contact area between the abutment block 18 and the surface of the connecting block 16 is increased, which improves the stability of the abutment block 18 supporting the connecting block 16. Furthermore, since the threaded structure of the first threaded rod 19 and the pull rod 9 can limit the position of the abutment block 18, the total length of the mounting plate 8 and the pull rod 9 remains constant.
[0024] like Figures 1 to 7As shown, the support assembly also includes a central shaft 20 disposed between four sets of anchor plates 10, a limiting groove 23 opened on both sides of the central shaft 20, a sliding disk 24 slidably inserted into the cavity of the limiting groove 23, a second threaded rod 21 rotatably connected to one side of the sliding disk 24, a threaded hole 22 opened on one side of one of the four anchor plates 10, and a second spring 26 fixed to the side of the sliding disk 24 away from the adjacent position of the second threaded rod 21. One side of the second spring 26 is fixed to the inner wall of the limiting groove 23, and one side of the second threaded rod 21 extends into the interior of the adjacent position of the threaded hole 22. After the multiple supporting shells 7 are installed, a central shaft 20 is placed between two anchor plates 10 located at the four corners of the inner side of the structural wall 6. The second threaded rod 21 and the sliding plate 24 are slid so that the second threaded rod 21 can approach the adjacent threaded hole 22. The second threaded rod 21 is rotated so that it can extend into the inside of the threaded hole 22 through the cooperation of the threaded structure between the second threaded rod 21 and the threaded hole 22. This allows the central shaft 20 to be fixed between the two adjacent anchor plates 10. Furthermore, the second spring 26 is provided and its rebound force ensures the vibration force at the four corners of the structural wall 6, thereby improving the stability of the four corners of the inner side of the structural wall 6.
[0025] like Figures 1 to 7 As shown, the support assembly also includes a guide rod 25 that is inserted through the sliding disk 24 at the upper and lower ends of the second threaded rod 21, and the two sides of the guide rod 25 are fixed to the inner wall of the limiting groove 23; The guide rod 25 supports the sliding disk 24 and limits its movement, thus making the movement of the second threaded rod 21 and the sliding disk 24 more stable.
[0026] Example 2: like Figure 8 As shown in Example 1, another embodiment of the present invention is as follows: A construction method for a permanent foundation pit support and seepage prevention structure under high void ratio conditions, the method using the aforementioned permanent foundation pit support and seepage prevention structure includes the following steps: S1: Using the double-pipe jet grouting pile machine technology, a seepage-proof wall 2 was constructed; S2: After the pile body is formed by the three-axis mixing pile machine, I-beams are inserted to construct the SMW method pile 3; S3: Structural wall 6 uses C30 grade concrete to ensure the compactness of the concrete during pouring and vibration. S4: After the surface treatment of the structural wall is completed, the waterproof membrane 51 is laid to ensure that there are no hollow areas, and then the waterproof protective layer 52 is laid. S5: Clean the side wall base, carry out the pouring of solidified soil 4, and after the pouring is completed, carry out appropriate curing measures; S6: Install support components to support structural wall 6.
[0027] The terms "front," "back," "left," "right," "top," and "bottom" all refer to the figures in the accompanying drawings. Figure 1 Based on the perspective of the observer, the side of the device facing the observer is defined as the front, the left side of the observer is defined as the left, and so on.
[0028] The foregoing has shown and described the basic principles, main features, and advantages of the present invention. Those skilled in the art should understand that the present invention is not limited to the above embodiments. The embodiments and descriptions in the specification are merely illustrative of the principles of the invention. Various changes and modifications can be made to the invention without departing from its spirit and scope, and all such changes and modifications fall within the scope of the present invention as claimed. The scope of protection of the present invention is defined by the appended claims and their equivalents.
Claims
1. A permanent foundation pit support and seepage prevention structure with high void ratio, characterized in that: The foundation pit body (1) includes an anti-seepage wall (2) inside the foundation pit body (1), an SMW method pile (3) inside the anti-seepage wall (2), a solidified soil (4) inside the SMW method pile (3), a waterproof layer (5) inside the solidified soil (4), and a structural wall (6) inside the waterproof layer (5). The inner side of the structural wall (6) is provided with a support component to support the structural wall (6) and improve its stability; The support assembly includes multiple mounting plates (8) fixed to the inner side of the structural wall (6), a support housing (7) rotatably connected to one side of the mounting plate (8), a tie rod (9) slidably inserted into the inner cavity of the support housing (7), and an anchor plate (10) rotatably connected to the bottom of the tie rod (9). The cross-section of the inner cavity of the supporting shell (7) is T-shaped, and the cross-section of the tie rod (9) is T-shaped; The support assembly further includes a plurality of positioning holes (11) communicating with the top of the inner cavity of the support housing (7), an opening (12) opened on the surface of the pull rod (9), an inner compartment (17) opened inside the pull rod (9) at the bottom of the opening (12), a plug (13) inserted into the inner cavity of the opening (12), a first spring (15) fixed to the bottom of the plug (13), a connecting rod (14) slidably inserted between the opening (12) and the first spring (15), a connecting block (16) fixed to the bottom of the connecting rod (14), and a limiting component acting on the connecting block (16). The bottom of the first spring (15) is fixed to the bottom of the inner wall of the opening (12), and the top of the first spring (15) is fixed to the surface of the connecting rod (14). The limiting component includes a first threaded rod (19) that is slidably inserted into the inner cavity of the inner compartment (17). The outer end of the first threaded rod (19) is threaded to the inner wall of the supporting housing (7). The inner end of the first threaded rod (19) is rotatably connected to the surface of the abutment block (18). One side of the top of the abutment block (18) is inclined. The bottom of the connecting block (16) is inclined. The support assembly also includes a central shaft (20) disposed between four sets of anchor plates (10), a limiting groove (23) opened on both sides of the central shaft (20), a sliding disk (24) slidably inserted into the cavity of the limiting groove (23), a second threaded rod (21) rotatably connected to one side of the sliding disk (24), a threaded hole (22) opened on one side of the four anchor plates (10), and a second spring (26) fixed to the side of the sliding disk (24) away from the adjacent position of the second threaded rod (21). One side of the second spring (26) is fixed to the inner wall of the limiting groove (23), and one side of the second threaded rod (21) extends into the interior of the adjacent position of the threaded hole (22). The support assembly also includes a guide rod (25) inserted through the sliding disk (24) at the upper and lower ends of the second threaded rod (21). Both sides of the guide rod (25) are fixed to the inner wall of the limiting groove (23).
2. The permanent foundation pit support and seepage prevention structure with high void ratio according to claim 1, characterized in that: The waterproof layer (5) includes a waterproof membrane (51) and a waterproof protective layer (52).
3. A construction method for a permanent foundation pit support and seepage prevention structure with a high penetration rate, wherein the method uses the permanent foundation pit support and seepage prevention structure described in claim 2, and includes the following steps: S1: Using the double-pipe jet grouting machine technology, a seepage-proof wall was constructed (2). S2: After forming the pile body using a three-axis mixing pile machine, an I-beam is inserted to construct the SMW method pile (3). S3: The structural wall (6) uses C30 impermeable concrete to ensure the compactness of the concrete during pouring and vibration. S4: After the surface treatment of the structural wall is completed, waterproof membrane (51) is laid to ensure that there are no hollow areas, and then waterproof protective layer (52) is laid. S5: Clean the side wall base, carry out the pouring of solidified soil (4), and after the pouring is completed, carry out appropriate curing measures; S6: Install support components to support the structural wall (6).