Visual test model for whole shield tunneling process

By designing a visualized test model for the entire shield tunneling process, the problems of incomplete observation and insufficient data collection in shield model tests were solved, enabling precise monitoring and control of the shield construction process, and making it suitable for various test scenarios.

CN121558390APending Publication Date: 2026-02-24CHINA UNIV OF MINING & TECH
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202511814243.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-12-04
Publication Date
2026-02-24

AI Technical Summary

Technical Problem

Existing shield tunneling model testing technology is difficult to achieve full-process visual observation, synchronous acquisition of multi-physics field data, and adaptation to various test scenarios, making it difficult to effectively control engineering risks during shield tunneling construction.

Method used

Design a visualization test model for the entire shield tunneling process, including a transparent model box, a shield simulation system, a propulsion control system, a data acquisition system, and an intelligent electrical control system, to achieve synchronous monitoring and control of soil displacement changes and soil pressure in the sealed chamber.

Benefits of technology

It enables precise visualization and data acquisition of the tunnel boring machine (TBM) process, improves the convenience of test operation and data reliability, is applicable to various TBM tunneling test scenarios, and provides a precise and efficient test platform.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN121558390A_ABST
    Figure CN121558390A_ABST
Patent Text Reader

Abstract

The invention discloses a shield tunneling whole process visualization test model, which belongs to the technical field of shield simulation tests and comprises a model box body, a shield simulation system, a propulsion control system, an acquisition system and an intelligent electric control system. The model box body is used for loading transparent soil, three surfaces are provided with transparent toughened glass, and the top is provided with a sliding cover plate; the shield simulation system comprises a pipe joint, a shield shell, a cutterhead and a sealing bin, and has the functions of reduction cutting, deslagging and grouting; the propelling system provides fine propelling speed and stable driving force; the acquisition system synchronously acquires the internal displacement of the soil body and the soil pressure data of the sealing bin; and the intelligent electric control system realizes parameter setting, real-time monitoring and cooperative control. The model solves the problems that an existing model is incomplete in observation, low in control precision and poor in scene adaptability, multiple scenes such as tunneling excavation and excavation face instability can be simulated, and a precise test carrier is provided for shield construction mechanism research and risk prevention and control.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of shield tunneling simulation test technology, and in particular relates to a visualization test model of the entire shield tunneling process. Background Technology

[0002] As a core construction technology in tunnel engineering, shield tunneling has been widely applied in major projects such as urban rail transit, cross-river and cross-sea tunnels, and underground utility tunnels due to its advantages such as strong adaptability to complex geological conditions, high construction efficiency, and minimal disturbance to the surrounding environment. However, shield tunneling is a complex dynamic process involving the coupling of multiple systems, including the shield machine, soil, and surrounding environment. It is susceptible to engineering risks such as face instability and collapse, mud-water splitting, segment floating, and settlement of surrounding buildings due to uncertainties in geological conditions (e.g., soft soil rheology, piping in water-rich sand layers, karst development) and dynamic changes in construction parameters (e.g., cutterhead rotation speed, advance speed, grouting pressure). Since actual shield tunneling is carried out in a closed underground space, it is difficult to directly observe the evolution of the displacement and stress fields inside the soil and the working status of key shield components (cutterhead, sealing chamber, and muck removal system). Therefore, shield model testing has become a core means to study the construction mechanism, optimize construction parameters, and control engineering risks.

[0003] Existing shield tunneling model testing technology has mainly gone through three development stages: full-section model, half-section visualization model, and early full-section visualization model. However, each stage of technology has significant limitations and cannot meet the current requirements of complex engineering projects for testing accuracy, observation dimensions, and scenario adaptability.

[0004] Full-section solid model: Early shield tunneling model tests mostly used full-section solid models that were geometrically similar to actual engineering projects. By simulating core processes such as cutterhead cutting and segment assembly during shield tunneling, the test results obtained had a high degree of consistency with actual working conditions and were highly reliable. However, the soil in these models is filled with natural soil or standard sand, and the overall structure is opaque. It is impossible to directly observe the dynamic processes such as displacement evolution, muck flow, and grout diffusion inside the soil. The internal mechanisms can only be inferred through indirect means such as surface settlement observation and segment stress monitoring outside the model. This makes it difficult to capture the incubation process of sudden risks such as excavation face instability and mud-water splitting, and the completeness and guidance of the test data are limited.

[0005] Half-section visualization model: To solve the observation challenges of full-section models, researchers proposed setting the longitudinal section of the tunnel axis as a transparent plexiglass or acrylic plate to form a half-section model. This type of model allows direct observation of soil deformation at a fixed section through a transparent panel, significantly reducing model manufacturing costs and operational complexity. It has been applied in fundamental research on shield tunneling face stability and soil-segment interaction. However, the half-section model suffers from inherent boundary effects: the friction coefficient between the transparent panel and the soil, as well as the interaction between the constraints and the soil interior, differ significantly, easily leading to "interface distortion" in soil stress distribution and displacement trajectory. This deviation is particularly pronounced when simulating soft soil rheology and high-water-pressure strata, making it difficult to support the optimization of precise construction parameters.

[0006] In summary, as tunnel boring machine (TBM) projects advance into deeper and more complex geological conditions (such as ultra-deep water-rich tunnels and soft soil-hard rock composite strata), there is an urgent need for a TBM model testing technology that can accurately simulate actual working conditions, achieve full-process visual observation, synchronously collect multi-physics field data, and adapt to various test scenarios. This technology is needed to overcome the shortcomings of existing technologies in terms of observation completeness, control accuracy, data coordination, and scenario adaptability, and to provide more reliable test support for the study of TBM construction mechanisms and engineering risk prevention and control.

[0007] To address this, a visual experimental model for the entire shield tunneling process is proposed. Summary of the Invention

[0008] To address the aforementioned technical problems, this invention proposes a visual experimental model for the entire shield tunneling process.

[0009] To achieve the above objectives, this invention provides a visual experimental model for the entire shield tunneling process, comprising:

[0010] The model box is used to load transparent soil material. The bottom is fixed to the base, the three sides are transparent, one side is a metal panel with holes, and the top is a sliding cover.

[0011] The shield tunneling simulation system is mounted on the holes in the metal panel and located inside the model box. The shield tunneling simulation system includes a pipe section, which is fixed to the metal panel. A shield shell is integrally formed at the end of the pipe section away from the metal panel. A cutterhead is installed at the end of the shield shell near the outer side. A sealing chamber is sealed and fixed inside the shield shell. The sealing chamber is spaced apart from the cutterhead.

[0012] The propulsion control system is located outside the model box and is connected to the shield tunneling simulation system to provide driving force for the shield tunneling simulation system;

[0013] The acquisition system includes a displacement image acquisition system and a stress data acquisition system; the displacement image acquisition system is mounted on the outside of the model box and is used to observe and record the displacement changes inside the soil; the stress data acquisition system is installed on the panel of the sealed chamber and is used to measure the transparent soil pressure inside the sealed chamber.

[0014] The intelligent electronic control system is used for human-machine interaction with personnel setting test parameters, collecting system information, and controlling the propulsion control system to drive the shield tunneling simulation system.

[0015] Optionally, a drive shaft is fixedly connected to the center of the cutter head, and a cutter head servo motor is driven by the drive shaft. Both the drive shaft and the cutter head servo motor are disposed inside the shield shell and the tube section.

[0016] Optionally, the cutter disc includes a double-layered ring with smooth edges. Three spokes are arranged inside the ring, and multiple scrapers are evenly embedded on each spoke. The scraper blades on the same ring face the same direction, while the scraper blades on different rings face opposite directions. The two rings are connected by a loose bolt at their center, and the two rings have a scissor-type structure.

[0017] Optionally, the back plate of the sealed chamber is provided with a grouting port and a slag discharge port; the grouting port is connected to an external grouting device, the slag discharge port is equipped with a slag discharge pipe, the slag discharge end of the slag discharge pipe is provided with a slag collection platform, and a gravity sensor is fixedly connected below the slag collection platform.

[0018] Optionally, the propulsion control system includes a front reaction wall and a rear reaction wall. Two helical screws are vertically arranged between the front and rear reaction walls, and the two helical screws are rotatably connected to the front and rear reaction walls. A movable push plate is rotatably connected to both helical screws. An opening is provided in the front reaction wall, and the pipe section passes through the opening and is fixedly connected to the movable push plate. Four transmission wheels are symmetrically mounted on the rear reaction wall, and the four transmission wheels are connected by a transmission belt. Two transmission wheels are fixedly connected to the two helical screws, and one of the remaining two transmission wheels is connected to a propulsion servo motor, while the other is movably connected to the rear reaction wall through a slide groove for adjusting the tension of the transmission belt.

[0019] Optionally, the propulsion control system further includes four guide slide rods, with both ends of the four guide slide rods vertically fixed to the front reaction wall and the rear reaction wall, respectively. The four guide slide rods pass through the movable push plate and are slidably connected to the movable push plate.

[0020] Optionally, safety blocks and limit switches are added to both sides of the four guide slides; the safety blocks are made of a material with relatively lower strength and stiffness than the moving push plate, the front reaction wall and the rear reaction wall; when the limit switch is touched, the limit switch controls the propulsion servo motor to immediately cut off the power.

[0021] Optionally, a reaction force push plate is provided parallel to the movable push plate. The reaction force push plate is fixedly connected to the movable push plate via a connecting rod, and the slag collection platform is fixedly connected to the connecting rod at the bottom. The reaction force push plate is rotatably connected to the two helical screws and slidably connected to the four guide slides.

[0022] Optionally, the displacement image acquisition system includes a laser emitter, of which two are provided, each mounted on the top or side of the model box via its own laser moving platform, and the laser emitter moves along the track of the laser moving platform on the top or side of the model box; it also includes a single-lens reflex digital camera for continuously taking pictures to record the changes in the spots within the cross-section formed by the laser emitter irradiating the transparent soil.

[0023] Optionally, the stress data acquisition system includes an earth pressure cell and a high-frequency data acquisition instrument. The earth pressure cell's measuring end is located inside the sealed chamber for measuring the earth pressure inside the sealed chamber. The earth pressure cell is electrically connected to the high-frequency data acquisition instrument so that the measurement data can be uploaded to the high-frequency data acquisition instrument.

[0024] Compared with the prior art, the present invention has the following advantages and technical effects:

[0025] This visualized test model of the entire shield tunneling process, through its integrated design of the model housing, shield simulation system, propulsion control system, data acquisition system, and intelligent electrical control system, possesses significant technical advantages and practical effects: The model housing adopts a three-sided transparent design with a top sliding cover, providing a clear view of the soil interior and facilitating the loading and unloading of transparent soil, component installation, and housing cleaning; the reserved holes in the metal panel ensure the stable assembly of the shield simulation system; The shield simulation system, with its built-in shield shell, cutterhead, and sealing chamber, accurately replicates the core structure of shield tunneling and can realistically simulate various key processes in shield tunneling; The propulsion control system provides stable driving force for the shield simulation system, ensuring precise and controllable tunneling; The data acquisition system, through dual configuration of displacement image acquisition and stress data acquisition, can simultaneously acquire data on internal soil displacement changes and soil pressure data in the sealing chamber, achieving comprehensive monitoring of the test process; The intelligent electrical control system establishes an efficient human-machine interaction platform, which can coordinate and control the collaborative work of various systems and record monitoring parameters in real time, greatly improving the convenience of test operation and data reliability. The overall structural design takes into account the needs of visualization and observation, the accuracy of test condition reproduction and the practicality of operation. It effectively solves the problems of traditional shield tunneling model tests, such as difficulty in directly observing internal processes, incomplete data collection and insufficient control precision. It can be adapted to various shield tunneling-related test scenarios and provides a precise and efficient test platform for shield tunneling technology research. Attached Figure Description

[0026] The accompanying drawings, which form part of this invention, are used to provide a further understanding of the invention. The embodiments of the invention and their descriptions are used to explain the invention and do not constitute an undue limitation of the invention. In the drawings:

[0027] Figure 1 This is a schematic diagram of the structure of the visual test model for the entire shield tunneling process of the present invention;

[0028] Figure 2 This is a schematic diagram of the shield tunneling simulation system and propulsion control system in this invention;

[0029] Figure 3 For the present invention Figure 2 Enlarged view of A in the middle;

[0030] Figure 4 This is a schematic diagram of the model box structure in this invention.

[0031] In the diagram: 1. Model box; 11. Metal panel; 12. Cover plate; 2. Shield tunneling simulation system; 22. Pipe section; 23. Shield shell; 24. Cutterhead; 25. Sealed chamber; 2401. Ring; 2402. Spoke; 2403. Scraper; 3. Propulsion control system; 31. Front reaction wall; 32. Rear reaction wall; 33. Helical screw; 34. Moving push plate; 35. Transmission wheel; 36. Guide slide bar; 37. Reaction push plate; 4. Data acquisition system; 5. Intelligent electrical control system. Detailed Implementation

[0032] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0033] To make the above-mentioned objects, features and advantages of the present invention more apparent and understandable, the present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments.

[0034] Reference Figures 1 to 4 As shown, this embodiment provides a visualization test model for the entire shield tunneling process, including:

[0035] Model box 1 is used to load transparent soil material. The bottom is fixed to the base, and the three sides are transparent. One side is a metal panel 11 with holes. A cover plate 12 is slidably installed on the top.

[0036] The shield tunneling simulation system 2 is mounted on the holes of the metal panel 11 and located inside the model box 1. The shield tunneling simulation system 2 includes a pipe section 22, which is fixed to the metal panel 11. The end of the pipe section 22 away from the metal panel 11 is integrally formed with a shield shell 23. A cutterhead 24 is installed inside the shield shell 23 near the outer side. A sealing chamber 25 is sealed and fixed inside the shield shell 23. The sealing chamber 25 and the cutterhead 24 are spaced apart.

[0037] The propulsion control system 3 is located outside the model box 1 and is connected to the shield simulation system 2 for transmission, providing driving force for the shield simulation system 2;

[0038] The acquisition system 4 includes a displacement image acquisition system 4 and a stress data acquisition system 4; the displacement image acquisition system 4 is mounted on the outside of the model box 1 and is used to observe and record the displacement changes inside the soil; the stress data acquisition system 4 is installed on the panel of the sealed chamber 25 and is used to measure the transparent soil pressure inside the sealed chamber 25.

[0039] The intelligent electronic control system 5 is used for human-machine interaction with personnel who set test parameters, to collect information from the acquisition system 4, and to control the propulsion control system 3 to drive the shield simulation system 2.

[0040] This visualized test model of the entire shield tunneling process, through the integrated design of model box 1, shield simulation system 2, propulsion control system 3, data acquisition system 4, and intelligent electrical control system 5, possesses significant technical advantages and practical effects: Model box 1 adopts a three-sided transparent design with a top sliding cover 12, which not only provides a clear view for observation inside the soil but also facilitates the loading and unloading of transparent soil, component installation, and box cleaning. The reserved holes in the metal panel 11 ensure the stable assembly of the shield simulation system 2; The shield simulation system 2 houses the shield shell 23, cutterhead 24, and sealed chamber 25. The system accurately replicates the core structure of a tunnel boring machine (TBM), realistically simulating various key processes during TBM tunneling. The propulsion control system 3 provides stable driving force to the TBM simulation system 2, ensuring precise and controllable tunneling. The data acquisition system 4, through dual configuration of displacement image acquisition and stress data acquisition, can simultaneously acquire data on internal soil displacement changes and soil pressure within the sealed chamber 25, achieving comprehensive monitoring of the test process. The intelligent electrical control system 5 establishes an efficient human-machine interaction platform, coordinating the collaborative work of various systems and recording monitoring parameters in real time, significantly improving the convenience of test operation and data reliability. The overall structural design balances the needs for visual observation, the accuracy of test condition replication, and operational practicality, effectively solving problems such as the difficulty in directly observing internal processes, incomplete data acquisition, and insufficient control precision in traditional TBM model tests. It is adaptable to various TBM tunneling-related test scenarios, providing a precise and efficient test platform for TBM construction technology research.

[0041] Model box 1 is a container for holding transparent soil material, providing the experimental equipment with functions for soil observation and constant pressure grouting. The interior of model box 1 is a 1m³ cube, composed of a base, boundary frame, tempered glass, and cover plate 12. All metal used in model box 1 is alloy steel, with a sheet metal and paint finish for rust prevention. The base, the main load-bearing component of model box 1, measures 1240mm × 1480mm × 15mm. Its four corners are chamfered, its top surface is smooth, and reinforcing ribs are welded to the bottom. Horizontal adjustment wheels are installed at the four corners for easy movement and transport of model box 1.

[0042] The boundary frame consists of two L-shaped columns, three bottom edges, a top ring beam, and a metal panel 11, connected together. Its main function is to fix the tempered glass and assist in load-bearing. The top ring beam is integrally cut and formed, with pre-drilled air holes and sealing grooves on its surface. Sealing gaskets can be added into the sealing grooves to achieve air pressurization and vacuuming operations. Ball bearing tracks and dust covers are installed on both sides of the top panel to facilitate the directional sliding of the cover plate 12. A limit stop is embedded at the front end of the top ring beam surface to prevent the cover plate 12 from sliding forward due to improper operation or tilting of the top panel. In addition, it is worth noting that many valuable and meaningful modifications were made to the metal panel 11. Window openings were added to increase the visibility area and viewing angle of the frame; holes were reserved for the installation, fixing, and waterproof sealing of the shield tunnel section 22 and sliding bearings; reinforcing ribs were added to the back to improve the load-bearing capacity of the frame; and a movable box was installed on the side to store the grout used for grouting. The bottom of the box is connected to the grouting port of the shield sealing chamber 25 through a grouting pipe. By changing the height of the box, constant pressure grouting with an error of less than 0.001 MPa can be achieved.

[0043] The cover plate 12 is a heavy-duty top cover welded from alloy steel, with numerous reinforcing ribs welded to the top. Due to its heavy weight, two jack ball bearings are installed on each side of the cover plate 12. Hydraulic lines are distributed between the ribs to provide oil pressure to the jacks. When the cover plate 12 needs to be moved, the entire cover plate 12 is first lifted using jacks, detaching it from the top frame of the model box 1. The weight of the entire cover plate 12 is then transferred to the ball bearings, allowing it to be easily moved along the ball bearing track. To accommodate the cover plate 12, a cover plate 12 storage platform is added to the rear of the model, allowing the top of the model to be fully opened for easy loading and unloading of transparent soil, top image acquisition, laser irradiation, and cleaning of the inside of the box.

[0044] The other three transparent facades of model box 1 are sealed with tempered glass. To meet the experimental requirements of bearing transparent soil and positive and negative air pressure, three pieces of 10mm thick tempered glass are bonded together with polyvinyl butyral film to form a three-layer tempered glass with a size of 1000mm×1000mm×30mm. Each contact surface between the tempered glass and the boundary frame is sealed and waterproofed. A transparent reinforcing film is pasted on the surface of the tempered glass to prevent high-hardness fused silica sand from scratching the glass surface, so that each tempered glass facade has a high-definition observation area of ​​850mm×850mm.

[0045] The shield shell 23 and the tube section 22 are formed by machining and electroplating from a single hollow steel tube with a wall thickness of 1cm. The outer diameter of the shield shell 23 is 16cm, and the outer diameter of the tube section 22 is 15.0cm. The outer diameter of the tube section 22 is slightly smaller to simulate the inherent gap between the shield and the segment ring in actual engineering. The center height of the shield shell 23 is 300mm from the bottom surface. The outer diameter of the shield shell 23 can be changed by modification, with a variation range of 100-200mm. The length of the shield shell 23 is 200mm. The front section of the shield shell 23 is connected to the sealing chamber 25, and the middle section of the tube section 22 is supported on the reserved holes in the model box 1 by sliding bearings.

[0046] The acquisition system 4 is an important module for recording the model test process and extracting the model test results. It is divided into the displacement image acquisition system 4 and the stress data acquisition system 4. The installation positions of the different acquisition systems 4 are different. The displacement image acquisition system 4 is set on the outside of the model box 1, providing the test model with the function of observing and recording the displacement changes inside the soil. The stress data acquisition system 4 is installed on the panel of the sealed chamber 25 and is used to measure the transparent soil pressure inside the sealed chamber 25.

[0047] The intelligent electrical control system 5 serves as the human-machine interface for driving servo motors and setting test parameters. This system consists of a motor control box and a computer. The motor control box houses a 100A circuit breaker, control transformer, power converter, programmable logic controller (PLC), intermediate relays, signal amplifiers, miniature air switches, servo drivers, and integrated terminal blocks. The 100A circuit breaker connects 220V to the entire motor control box, providing circuit protection and isolation maintenance functions. The circuit breaker is connected to the control transformer, which converts 220V AC to 24V DC, ensuring a stable 24V DC supply to the power converter under varying load conditions. The power converter, as the integrated power supply for subsequent electrical components, provides loss reduction, efficiency improvement, circuit protection, and current regulation. The programmable logic controller (PLC) is crucial for human-machine interaction. This controller can communicate and network, be programmed and configured according to actual needs, and achieve equipment start-up, stop, and parameter setting through logic control, process control, and motion control. To meet the model's numerous functionalities, intermediate relays were added to increase the number of contacts in the control loop, enabling more control functions. A signal amplifier then converts the input signal into a larger output signal to issue commands to the servo drive. As the core component of the servo system, the servo drive enables precise control of the servo motor, meeting the requirements of high-precision, high-speed, and high-reliability motion control. A small air switch is used to control the servo drive, providing a certain level of protection. Integrated terminal blocks are used to connect the distribution box to the equipment components, distributing the input power or signal lines to multiple output lines, achieving power or signal branching and distribution. This not only meets standardization and normalization requirements but also makes the wiring within the distribution box neater and more aesthetically pleasing.

[0048] An interactive program is installed on the computer, allowing for precise control of the servo motor and test parameters through a human-machine interface. Controllable test actions include: cutterhead 24 rotation, tunnel boring machine (TBM) excavation, auger rotation, light source displacement, and head adjustment. Cutterhead 24 control is divided into speed control and torque control. The cutterhead 24 can be controlled to rotate and cut the soil by setting either its speed or torque. The interactive interface is user-friendly. Before use, if the current torque fluctuates, click the "Torque Zero" button, enter the value in the corresponding box, and click "Cutterhead 24 Clockwise" or "Cutterhead 24 Reverse." The cutterhead 24 will then rotate according to the set speed or torque. If the cutterhead 24 torque is overloaded or exceeds the set limit, an alarm will be triggered and an emergency stop will occur. After the alarm is cleared, clicking "Alarm Reset" will restore the original state. The control methods and operation of other dialog boxes are similar to those of the cutterhead 24 control interface. The differences are that the tunneling control, light source control, and head control interfaces have added a "return to origin" function, and the head control interface also adds a cover plate 12 lifting button to control the movement of the cover plate 12. Through this interactive system, controllable parameters include: cutterhead 24 rotation speed, auger rotation speed, cutterhead 24 torque, light source position, light source movement speed, tunneling speed, tunneling position, head position, head lifting / lowering speed, and cover plate 12 lifting / lowering. Monitorable parameters include: cutterhead 24 rotation speed, cutterhead 24 torque, tunneling thrust, tunneling distance, muck weight, pressure inside the muck discharge pipe, light source position, and head position. The interactive interface records and plots the changes of these monitored parameters over time in real time. To assist in setting the auger rotation speed and ensure a dynamic balance between tunneling speed and muck discharge speed, a real-time curve showing the relationship between the advance distance and muck weight is displayed on the far right.

[0049] In some alternative implementations, a drive shaft is fixedly connected to the center of the cutter head 24, and a servo motor of the cutter head 24 is driven by the drive shaft. Both the drive shaft and the servo motor of the cutter head 24 are located inside the shield shell 23 and the tube section 22.

[0050] The shield tunneling simulation system 2 is the key core for recreating shield tunneling construction. It is placed inside the model box 1, with pipe sections 22 erected on pre-reserved holes in the model box 1, and connected to the propulsion control system 3 at the rear. It provides the test model with functions such as cutterhead 24 rotation cutting, shield tunneling excavation, muck auger discharge, and soil chamber grouting. The drive shaft is a solid long shaft, with one end fixed to the cutterhead 24 and the other end connected to the cutterhead 24 servo motor. The rotation of the drive shaft directly drives the cutterhead 24 to rotate, realizing the function of cutting the soil.

[0051] The cutterhead 24 servo motor is a 400W three-phase high-inertia servo motor. The motor shaft is connected to the drive shaft. This servo motor is the sole power source for the rotation of the shield cutterhead 24. Its rated speed is 3000 r / min, maximum speed is 6000 r / min, rated output torque is 1.27 N·m, and maximum output torque is 3.80 N·m. Both output power and speed meet the experimental requirements. A precision planetary reducer with a speed ratio of 200 is configured. This reducer has a rated output torque of 260 N·m and a maximum output torque of 520 N·m. It converts the high-speed, low-torque output of the cutterhead 24 servo motor into a low-speed, high-torque output, forming a servo motor-reducer power unit. This provides the model cutterhead 24 with a stable and precise rotational torque of 50-200 N·m and a cutterhead 24 speed of 1-10 r / min.

[0052] In some alternative embodiments, the cutter head 24 includes a double-layered ring 2401 with smooth edges. Three spokes 2402 are provided inside the ring 2401, and multiple scrapers 2403 are evenly embedded on each spoke 2402. The scrapers 2403 on the same ring 2401 have the same blade direction, while the scrapers 2403 on different rings 2401 have opposite blade directions. The two rings 2401 are connected by a loose bolt at their center, and the two rings 2401 have a scissor-type structure.

[0053] The cutter head 24 is a double-layered ring 2401 made of alloy steel electroplated. The cutter head 24 has an outer diameter of 16cm and smooth edges without cutters. The cutter head 24 has three spokes 2402 inside, and each spoke 2402 is inlaid with eight scrapers 2403. The upper and lower rings 2401 adopt a scissor-type structure. The opening ratio of the cutter head 24 can be changed by tightening and loosening the bolt in the central groove of the cutter head 24. The maximum opening ratio of the cutter head 24 can reach 60%, and the minimum opening ratio can reach 40%.

[0054] In some alternative implementations, the back plate of the sealed chamber 25 is provided with a grouting port and a slag discharge port; the grouting port is connected to an external grouting device, the slag discharge port is equipped with a slag discharge pipe, and a slag collection platform is provided at the slag discharge end of the slag discharge pipe, with a gravity sensor fixedly connected below the slag collection platform.

[0055] The sealing chamber 25 is installed between the cutterhead 24 and the shield shell 23, simulating the soil chamber of a shield tunnel. The sealing chamber 25 and the cutterhead 24 are not in direct contact; a 3mm gap exists between them, which will not affect the rotation of the cutterhead 24 in 0.2-0.5mm fused silica sand. The sealing chamber 25 and the shield shell 23 are bolted together, and a reinforced seal is applied to prevent pore liquid from flowing into the shield shell 23. The back plate of the sealing chamber 25 has a pre-drilled grouting port and a slag discharge port. The grouting port is located at the upper center of the back plate and can be connected to external grouting equipment to perform grouting and slag amendment injection functions. The slag discharge port is located at the lower center of the back plate and has an opening size of 25cm for installing a slag discharge pipe. Three earth pressure boxes were installed on the base of the sealed chamber 25, located at the top, middle and bottom of the earth chamber respectively. Due to the presence of the grouting hole at the top and the slag discharge port at the bottom, the positions of the upper and lower earth pressure boxes were slightly offset, but this did not affect the measurement of earth pressure inside the earth chamber or the comparison of earth pressure changes at different heights.

[0056] The slag discharge pipe is a hollow steel cylindrical tube, with the front end connected to the slag discharge port. The slag discharge port at the end of the steel pipe is aligned with the slag collection platform. A stainless steel auger is installed inside the steel pipe. The front end of the auger slightly extends into the sealed chamber 25, and the end is connected to a 100W three-phase high-inertia servo motor. This servo motor has a rated speed of 3000 r / min, a maximum speed of 6000 r / min, a rated output torque of 0.32 N·m, and a maximum output torque of 1.12 N·m. It is equipped with a precision planetary reducer with a speed ratio of 50. This reducer has a rated output torque of 22 N·m and a maximum output torque of 66 N·m, ensuring that the output power and speed meet the test requirements. This forms a servo motor-reducer power unit, providing rotational power to the auger. The auger and the slag discharge pipe work together to enable the shield tunneling simulation system 2 to have a spiral slag discharge function.

[0057] In some optional implementations, the propulsion control system 3 includes a front reaction wall 31 and a rear reaction wall 32. Two helical screws 33 are vertically arranged between the front reaction wall 31 and the rear reaction wall 32. The two helical screws 33 are rotatably connected to the front reaction wall 31 and the rear reaction wall 32. The two helical screws 33 are rotatably connected to a movable push plate 34. An opening is provided on the front reaction wall 31, and a pipe section 22 passes through the opening and is fixedly connected to the movable push plate 34. Four drive wheels 35 are symmetrically mounted on the rear reaction wall 32. The four drive wheels 35 are connected by a drive belt. Two drive wheels 35 are fixedly connected to the two helical screws 33 respectively. One of the remaining two drive wheels 35 is connected to a propulsion servo motor, and the other is movably connected to the rear reaction wall 32 through a slide groove for adjusting the tension of the drive belt.

[0058] The propulsion control system 3 is the power source for the forward propulsion of the shield model and the rear-mounted segments. Located at the rear of the test equipment and connected to the shield simulation system 2, it enables the test equipment to have precise propulsion capabilities, providing a propulsion speed within the range of 10-100 mm / min and a propulsion stroke of 500 mm. This system includes front and rear reaction walls 32, guide rods 36, screw rods 33, moving push plates 34, and servo motors. The front and rear reaction walls 32 are the supporting components of the propulsion control system 3, welded from alloy steel and painted for rust prevention. The reaction walls have support bases at their bottom, connected to the reaction walls by sixteen nuts. Adjusting the screwing distance of these nuts allows for leveling of the reaction walls and the overall system, enabling them to adapt to uneven ground conditions and overcome minor deformations that may occur during transportation, assembly, and use. The front reaction wall 31 has an opening for connecting and fixing the shield simulation system 2. The front and rear reaction walls 32 are connected to each other by two helical screws 33, which not only provide propulsion reaction force for the shield model, but also specify the rough direction for the installation and propulsion of the shield simulation system 2.

[0059] The propulsion servo motor is the only power unit in propulsion control system 3. This propulsion servo motor is a three-phase 200W high-inertia servo motor with a rated speed of 3000 r / min, a maximum speed of 6000 r / min, a rated output torque of 0.64 N·m, and a maximum output torque of 1.91 N·m. Both the output power and speed meet the experimental requirements. This propulsion servo motor features high precision, low hysteresis, and high response. Control methods include position control, speed control, torque control, and full closed-loop control, achieving precise control through continuous feedback loops. To improve the output torque of the propulsion servo motor and ensure sufficient thrust to support the smooth advancement of the tunnel boring machine, a precision planetary reducer with a speed ratio of 80 was added. This reducer has a rated output torque of 55 N·m and a maximum output torque of 165 N·m. Utilizing its internal gear transmission mechanism, it converts the high-speed, low-torque output of the servo motor into a low-speed, high-torque output, forming a servo motor-reducer power unit that provides stable and precise propulsion power of 100N-5000N to the tunnel boring machine model.

[0060] Four drive wheels 35 are installed on the rear reaction wall 32, and the drive wheels 35 are interconnected by drive belts. The symmetrical design of the four wheels makes the force on the rear reaction wall 32 and the drive belt more even. Among them, the bottom drive wheel 35 is equipped with the aforementioned servo motor-reducer power unit as the drive wheel, which drives the other three drive wheels 35 to rotate via the drive belt. The installation position of the top drive wheel 35 is pre-embedded with a sliding groove. By controlling the installation position of the top drive wheel 35, the tension and relaxation of the drive belt can be adjusted to achieve effective transmission. The left and right drive wheels 35 are fixedly connected to the screw rod 33. The other end of the screw rod 33 is connected to the front reaction wall 31 through a bearing flange, so that the screw rod 33 can rotate synchronously with the drive wheels 35. The screw rotation is used to precisely control the advancement distance of the moving push plate 34 and the reaction push plate 37.

[0061] The movable push plate 34 is an X-shaped panel made of alloy steel, cut in one piece and then electroplated. Its four corners are supported on the guide slide rod 36 via linear bearings, reducing frictional resistance and facilitating the forward and backward directional movement of the panel. A cavity is pre-drilled in the center of the movable push plate 34 for installing the shield tunneling simulation system 2.

[0062] In some alternative implementations, the propulsion control system 3 further includes four guide slide rods 36, with both ends of the four guide slide rods 36 vertically fixed to the front reaction wall 31 and the rear reaction wall 32, respectively, and the four guide slide rods 36 passing through the movable push plate 34 and slidably connected to the movable push plate 34.

[0063] The guide slide rod 36 is integrally cut from alloy steel and electroplated, resulting in a smooth surface and low coefficient of friction. This reduces power loss on the guide slide rod 36 and assists in the smooth advancement of the tunnel boring machine (TBM). The guide slide rod 36 is precisely connected to the front reaction wall 31 and the rear reaction wall 32 via flanges at both ends, with a drilling error not exceeding 2mm. This ensures the guide slide rod 36 is absolutely horizontal. The four guide slide rods 36 guarantee that the TBM model advances horizontally along the design axis during advancement. Compared to two guide slide rods 36, this effectively prevents the risk of the model tilting to one side, greatly improving sealing and accuracy.

[0064] In some optional implementations, safety blocks and limit switches are added to both sides of the four guide slides 36; the safety blocks are made of a material with relatively lower strength and stiffness than the moving push plate 34, the front reaction wall 31 and the rear reaction wall 32; when the limit switch is touched, the limit switch controls the propulsion servo motor to immediately cut off the power.

[0065] Safety blocks and limit switches are added to both sides of the guide slide bar 36. The safety blocks are made of carbon structural steel, which has relatively low material strength and rigidity. The deformation of the blocks absorbs the impact load when the moving push plate 34 and the reaction push plate 37 collide with the front and rear reaction walls 32. The limit switches are electrically connected to the propulsion servo motor. The propulsion system will be immediately de-energized the moment the limit switch is touched to prevent the shield model from exceeding the displacement limit when advancing and retreating.

[0066] In some alternative implementations, a reaction force push plate 37 is provided parallel to the movable push plate 34. The reaction force push plate 37 is fixedly connected to the movable push plate 34 by a connecting rod, and the slag collection platform is fixedly connected to the connecting rod at the bottom. The reaction force push plate 37 is threadedly rotatably connected to two helical screws 33 and slidably connected to four guide slides 36.

[0067] The reaction push plate 37 and the movable push plate 34 are made of the same material and are connected to the guide slide rod 36 in the same way. The reaction push plate 37 has a slightly different shape, with no cutting on the left and right sides, and is connected to the helical screw 33 by ball bearings. The rotation of the helical screw 33 will cause the reaction push plate 37 to move forward or backward. The movable push plate 34 and the reaction push plate 37 are fixedly connected by alloy steel pipes to ensure overall translation. A slag collection platform is built between the lower steel pipes to collect the slag discharged by the tunnel boring machine. A gravity sensor is installed under the platform panel to measure the mass of the discharged slag in real time.

[0068] In some optional implementations, the displacement image acquisition system 4 includes a laser emitter, of which two are provided, each mounted on the top or side of the model box 1 via its own laser moving platform. The laser emitter moves along the track of the laser moving platform on the top or side of the model box 1. It also includes a single-lens reflex digital camera for continuously taking pictures to record the changes in the spots within the cross-section formed by the laser emitter irradiating the transparent soil.

[0069] The displacement image acquisition system 4 consists of a DSLR camera, a laser emitter, a laser moving platform, and PIVlab software. Its working principle relies on the laser emitter irradiating transparent soil to form a cross-section. The DSLR camera continuously takes pictures to record changes in the spots within the cross-section. The PIVlab software analyzes and calculates the velocity and displacement of the spots to represent the velocity and displacement of the soil mass inside the transparent soil. The brightness of the spots within the cross-section significantly affects the accuracy of the displacement image acquisition. Therefore, two 5W linear laser emitters are selected. Each emitter is a cylinder 210mm high and 100mm in diameter at the base, with a fully enclosed waterproof and dustproof design. The emitted laser is 520nm green light, and the internal glass cylindrical mirror scatters the point light source into a linear line, achieving a 1:1 ratio between distance and laser line length. The laser thickness is adjustable to a minimum of 1mm. The base is a universal bracket for easy installation and direction adjustment. Laser safety glasses are provided to prevent personal injury during operation.

[0070] In addition, two laser moving platforms were designed, each with a servo motor-driven sliding rail mount for mounting the laser emitters. The low platform was placed in front of or to the side of model box 1, while the high platform was placed above model box 1. During the experiment, the origin positions of the two laser moving platforms were manually adjusted to ensure that the planes irradiated by the two laser emitters were the same. Subsequently, intelligent electronic control was used to strictly control the emission position of the laser emitters. By irradiating the same cross-section with the two laser emitters, the brightness of the spots in the transparent soil and the optical transmission distance of the transparent soil were further improved.

[0071] The DSLR camera is a single-lens reflex digital camera with autofocus and auto exposure. It has approximately 20.2 million effective pixels, a shutter speed of up to 1 / 4000 second (using a high shutter speed to control light intake and capture the instantaneous form of fast-moving objects), a maximum ISO of 25600 (the sensor is sensitive enough to capture green light transmitted through transparent soil), and an external large-aperture lens to increase light intake and adapt to shooting in dark environments. It has a continuous shooting speed of 4.5 frames per second, clearly capturing dynamic changes within the soil. A 128GB memory card is included for image storage, and a shutter release cable and tripod are provided to ensure consistent shooting angles and ranges during testing, facilitating post-processing (PIV) image processing.

[0072] PIVlab software, short for ParticleImageVelocimetry, is a GUI-based Matlab toolbox that offers advantages such as fast processing speed, high analysis accuracy, and strong noise reduction capabilities. Its working principle involves analyzing the displacement and velocity of the speckle field between different images of laser speckle fields captured by a DSLR camera within transparent soil using image digitization, image segmentation, and image correlation matching.

[0073] In some alternative implementations, the stress data acquisition system 4 includes an earth pressure cell and a high-frequency data acquisition instrument. The earth pressure cell measuring end is located inside the sealed chamber 25 to measure the earth pressure inside the sealed chamber 25, and the earth pressure cell is electrically connected to the high-frequency data acquisition instrument so that the measurement data can be uploaded to the high-frequency data acquisition instrument.

[0074] The stress data acquisition system 4 consists of an earth pressure cell and a high-frequency acquisition instrument. The earth pressure cell is a JTM-Y2000 foil-type miniature pressure cell with a diameter of 16mm. The exterior is sealed with an alloy material, and the interior contains a circular film-type adhesive-based full-bridge foil strain gauge. This pressure cell features small size, light weight, ease of use, accurate measurement, high output sensitivity, and stable performance, meeting the experimental requirements for measuring earth pressure within a sealed chamber of 25. The high-frequency acquisition instrument uses a YBY-6010 strain test and analysis instrument with a static acquisition frequency of 10Hz. It can simultaneously acquire and display all data from 20 channels and, through connection to a computer, can completely acquire and record the measured data.

[0075] In addition, the shield shell 23 and the pipe section 22 serve as supporting components of the shield simulation system 2. Not only are the cutterhead 24, the sealing chamber 25, the servo motor and other mechanisms installed in the front and rear sections, but the slag discharge pipe, drive shaft, grouting pipe and earth pressure box wiring are also laid out inside the shield shell 23 and the pipe section 22. Their ample internal space ensures that the components do not affect or entangle each other.

[0076] Using this visualized test model of the entire shield tunneling process, various shield tunneling simulation tests can be conducted, including but not limited to the following:

[0077] Visualized active instability test of shield tunnel excavation face: Transparent soil was used as the backfill material to simulate the shield tunneling machine being stopped. Over-excavation was carried out by continuously discharging soil through a screw conveyor to reproduce the active instability and collapse of the excavation face.

[0078] Visualized Shield Tunnel Excavation Face Slurry Splitting Test: Transparent soil was used as the backfill material and colored mud was used as the grouting material. The test simulated the shield tunneling machine being stopped. The grouting pressure was continuously increased through the grouting holes on the shield tunneling model machine to recreate the occurrence, extension and penetration of slurry splitting phenomenon at the excavation face.

[0079] Visualized shield tunneling excavation test: Using transparent soil as the soil material, the tunneling excavation of the shield machine is simulated through functions such as cutterhead rotation, spiral slag removal and constant speed propulsion. The displacement field distribution inside and on the surface of the soil can be observed and recorded.

[0080] Visualized shield tunneling process excavation face instability test: Transparent soil is used as the soil material to simulate the tunneling and excavation of the shield machine. In this process, active instability of the excavation face can also be combined to achieve instability while excavating, which better restores the instability phenomenon in actual engineering because most instability and collapse phenomena in engineering occur in the normal tunneling stage, rather than the shutdown stage.

[0081] Visualized shield tunneling through existing buildings and structures test: Using transparent soil as the soil material, piles, columns, station models, and surface buildings are pre-embedded in model box 1 to simulate the scenario of shield tunneling through existing buildings and structures. The deformation response of the soil and existing buildings and structures is observed and recorded. At the same time, tests such as excavation face instability and slurry splitting under existing buildings and structures can also be carried out.

[0082] This visualized test model of the entire shield tunneling process can be adapted to various shield tunneling-related test scenarios, providing a precise and efficient test platform for shield construction technology research.

[0083] All aspects not detailed in this invention are conventional technical means known to those skilled in the art.

[0084] In the description of this invention, it should be understood that the terms "longitudinal", "lateral", "up", "down", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings, and are only for the convenience of describing this invention, and are not intended to indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation, and therefore should not be construed as a limitation of this invention.

[0085] The embodiments described above are merely preferred embodiments of the present invention and are not intended to limit the scope of the present invention. Various modifications and improvements made by those skilled in the art to the technical solutions of the present invention without departing from the spirit of the present invention should fall within the protection scope defined by the claims of the present invention.

Claims

1. A visual experimental model for the entire process of tunnel boring machine (TBM) excavation, characterized in that, include: Model box (1) is used to load transparent soil material. The bottom is fixed to the base. The sides are transparent on three sides, and one side is a metal panel (11). Holes are opened on the metal panel (11), and a cover plate (12) is slidably installed on the top. The shield tunneling simulation system (2) is mounted on the holes of the metal panel (11) and located inside the model box (1). The shield tunneling simulation system (2) includes a pipe section (22), which is fixed to the metal panel (11). The end of the pipe section (22) away from the metal panel (11) is integrally formed with a shield shell (23). A cutterhead (24) is installed inside the shield shell (23) near the outer side. A sealing chamber (25) is sealed and fixed inside the shield shell (23). The sealing chamber (25) and the cutterhead (24) are spaced apart. The propulsion control system (3) is located outside the model box (1) and is connected to the shield simulation system (2) for transmission, providing driving force to the shield simulation system (2); The acquisition system (4) includes a displacement image acquisition system (4) and a stress data acquisition system (4); the displacement image acquisition system (4) is installed on the outside of the model box (1) and is used to observe and record the displacement changes inside the soil; the stress data acquisition system (4) is installed on the panel of the sealed chamber (25) and is used to measure the transparent soil pressure inside the sealed chamber (25); The intelligent electronic control system (5) is used to interact with the personnel who set the test parameters, collect information from the acquisition system (4), and control the propulsion control system (3) to drive the shield simulation system (2) to work.

2. The visualized test model for the entire shield tunneling process according to claim 1, characterized in that, The cutter head (24) is fixedly connected to a drive shaft at its center. The drive shaft is connected to a servo motor for the cutter head (24). Both the drive shaft and the servo motor for the cutter head (24) are located inside the shield shell (23) and the pipe section (22).

3. The visualized test model for the entire shield tunneling process according to claim 2, characterized in that, The cutter disc (24) includes a double-layered ring (2401), the edges of the two rings (2401) are smooth, and three spokes (2402) are provided inside the ring (2401). Multiple scrapers (2403) are evenly embedded on each spoke (2402). The blades of the scrapers (2403) on the same ring (2401) face the same direction, and the blades of the scrapers (2403) on different rings (2401) face opposite directions. The two rings (2401) are connected by a loose bolt at their center. The two rings (2401) have a scissor-like structure.

4. The visualized test model for the entire shield tunneling process according to claim 2, characterized in that, The sealing chamber (25) has a grouting port and a slag discharge port on its back plate; the grouting port is connected to an external grouting device, the slag discharge port is equipped with a slag discharge pipe, the slag discharge end of the slag discharge pipe is provided with a slag collection platform, and a gravity sensor is fixedly connected below the slag collection platform.

5. The visualized test model for the entire shield tunneling process according to claim 4, characterized in that, The propulsion control system (3) includes a front reaction wall (31) and a rear reaction wall (32). Two helical screws (33) are vertically arranged between the front reaction wall (31) and the rear reaction wall (32). The two helical screws (33) are rotatably connected to the front reaction wall (31) and the rear reaction wall (32). The two helical screws (33) are rotatably connected to a movable push plate (34). An opening is provided on the front reaction wall (31). The pipe section (22) passes through the opening and is fixedly connected to the movable push plate (34). Four transmission wheels (35) are symmetrically mounted on the rear reaction wall (32). The four transmission wheels (35) are connected by a transmission belt. Two transmission wheels (35) are fixedly connected to the two helical screws (33). One of the remaining two transmission wheels (35) is connected to a propulsion servo motor, and the other is movably connected to the rear reaction wall (32) through a slide groove for adjusting the tension of the transmission belt.

6. The visualized test model for the entire shield tunneling process according to claim 5, characterized in that, The propulsion control system (3) also includes four guide slide rods (36), the two ends of the four guide slide rods (36) are respectively vertically fixed to the front reaction wall (31) and the rear reaction wall (32), and the four guide slide rods (36) pass through the movable push plate (34) and are slidably connected to the movable push plate (34).

7. The visualized test model for the entire shield tunneling process according to claim 6, characterized in that, Safety blocks and limit switches are added to both sides of the four guide slides (36); the safety blocks are made of materials with relatively lower strength and stiffness than the moving push plate (34), the front reaction wall (31) and the rear reaction wall (32); when the limit switch is touched, the limit switch controls the propulsion servo motor to immediately cut off the power.

8. The visualized test model for the entire shield tunneling process according to claim 6, characterized in that, A reaction force push plate (37) is provided parallel to the movable push plate (34). The reaction force push plate (37) is fixedly connected to the movable push plate (34) through a connecting rod. The slag collection platform is fixedly connected to the connecting rod at the bottom. The reaction force push plate (37) is rotatably connected to the two spiral screws (33) and slidably connected to the four guide slides (36).

9. The visualized test model for the entire shield tunneling process according to claim 1, characterized in that, The displacement image acquisition system (4) includes a laser emitter. There are two laser emitters, which are respectively set on the top or side of the model box (1) via their respective laser moving platforms. The laser emitters move along the track of the laser moving platform on the top or side of the model box (1). It also includes a single-lens reflex digital camera for continuously taking pictures to record the changes in the spots in the cross-section formed by the laser emitter irradiating the transparent soil.

10. The visualized test model for the entire shield tunneling process according to claim 1, characterized in that, The stress data acquisition system (4) includes an earth pressure cell and a high-frequency acquisition instrument. The earth pressure cell measuring end is set inside the sealed chamber (25) to measure the earth pressure inside the sealed chamber (25). The earth pressure cell is electrically connected to the high-frequency acquisition instrument so that the measurement data can be uploaded to the high-frequency acquisition instrument.