新型钻孔灌注桩桩端复合式后压浆施工方法

By combining open and capsule grouting methods with a composite grouting device, the problem of unstable grouting in traditional grouting processes is solved, significantly improving the bearing capacity and frictional resistance of pile foundations, shortening the construction period, and reducing costs.

CN122406758APending Publication Date: 2026-07-17SHENZHEN ZHONGTIEERJU ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
SHENZHEN ZHONGTIEERJU ENG CO LTD
Filing Date
2026-04-17
Publication Date
2026-07-17

AI Technical Summary

Technical Problem

Traditional post-grouting technology at the pile end cannot accurately control the grouting area, grouting pressure, and grouting volume, resulting in unstable grouting effects and large fluctuations in the degree of increase in single pile bearing capacity.

Method used

A composite grouting device is adopted, combining open grouting and capsule grouting. Through an open-closed-open composite grouting method, grouting is injected into the soil layer around the pile tip to form a cement extrusion enlargement head, thereby improving the bearing capacity of the pile foundation.

Benefits of technology

Significantly improve the ultimate bearing capacity and side friction of pile foundations, shorten pile length or increase pile spacing, increase construction speed, reduce costs, and achieve fixed-area, fixed-quantity, and fixed-pressure control of cement grout.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN122406758A_ABST
    Figure CN122406758A_ABST
Patent Text Reader

Abstract

本发明公开了新型钻孔灌注桩桩端复合式后压浆施工方法及配套复合式注浆装置,属于桩基工程施工技术领域。针对传统桩端后注浆工艺注浆参数控制精度低、效果不稳定、单桩承载力提升波动大的缺陷,本发明采用开放式—闭合式—开放式的三段复合注浆方式,配套装置集成开放式注浆体系与带柔性注浆胶囊的闭合式注浆体系,随钢筋笼同步下放预埋,成桩后完成开塞与分级复合注浆。本发明可对桩端土层实现渗透、劈裂、压密加固,精准控制注浆参数,单桩极限承载力达常规灌注桩2.5倍以上,可缩短桩长、节约成本、缩短工期,显著提升桩基承载稳定性。