A tunnel construction method

By combining vertical freezing pipes and curved freezing pipes, the construction of the connecting passage and the left and right main tunnels was carried out simultaneously, solving the problem of long tunnel construction cycle and improving construction efficiency and safety.

CN122407201APending Publication Date: 2026-07-17CHANGJIANG SURVEY PLANNING DESIGN & RES CO LTD

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
CHANGJIANG SURVEY PLANNING DESIGN & RES CO LTD
Filing Date
2026-04-09
Publication Date
2026-07-17

AI Technical Summary

Technical Problem

In the current tunnel construction, the connecting passage and the left and right main tunnels cannot be constructed simultaneously, resulting in a long overall tunnel construction period.

Method used

A freezing scheme combining vertical freezing pipes and curved freezing pipes was adopted to pre-freeze the strata around the connecting passage. The connecting passage area was then frozen using both vertical and curved freezing pipes, ensuring that the freezing construction was separated from the shield tunneling construction of the left and right main tunnels in both time and space.

Benefits of technology

It significantly shortened the overall construction period of the tunnel section, avoided the delays and safety risks caused by cross-construction, and solved the problem of site occupation for arranging freezing equipment in the tunnel during horizontal freezing construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN122407201A_ABST
    Figure CN122407201A_ABST
Patent Text Reader

Abstract

本发明提供一种隧道施工方法,包括:布置垂直冻结管和曲线冻结管;通过垂直冻结管和曲线冻结管对联络通道周边地层进行冻结;对左右主线隧道进行盾构施工;当左右主线隧道穿过拟建联络通道区域后,且拟建联络通道区域冻结完成后,开挖联络通道;完成左右主线隧道和联络通道的后续施工。本发明可以解决现有的隧道的联络通道不能与左右主线隧道同步施工导致隧道整体施工周期长的问题。