A construction process for a shaft
Patent Information
- Application Number
- CN202611152439.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Priority Date
- 2026-05-26
- Filing Date
- 2026-07-31
- Publication Date
- 2026-09-01
AI Technical Summary
[0002]现有的沉井施工时,一般是在地面上拼装水泥墙然后挖空下部做整体下沉,水泥墙重量较大,施工难度大,施工时间长,而且施工过程中风险较大,不利于避开地下管路设施,施工成本高
本发明实施例提供一种竖井施工工艺,包括如下步骤:
Smart Images

Figure CN122669984A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of shaft construction technology, and more specifically, to a shaft construction process. Background Technology
[0002] In existing caisson construction, cement walls are typically assembled on the ground, and then the lower part is excavated for overall sinking. Cement walls are heavy, making construction difficult, time-consuming, and risky. It is also not conducive to avoiding underground pipeline facilities, resulting in high construction costs. Summary of the Invention
[0003] The purpose of this invention is to provide a vertical shaft construction process, which mainly involves fixing the top and excavating the bottom, assembling it with steel formwork. The construction process is safer than that of caisson construction; it also saves time, uses lightweight materials, has strong load-bearing capacity, is suitable for various strata, avoids underground pipeline facilities, is inexpensive, and can be installed section by section, allowing the shaft to be set into various shapes.
[0004] The technical solution adopted in this invention is as follows: This application provides a vertical shaft construction process, including the following steps: A vertical shaft of a certain depth is excavated in the ground. Then, multiple shaft support frames are placed on the inner wall of the excavated shaft and fixed. An upper fixing plate is fixed to the top of the shaft. Multiple shaft support frames are stacked in the vertical direction and fixed together between each pair of adjacent shaft support frames. After securing the upper shaft support frame, continue excavating the shaft downwards. After excavating to a certain depth, continue installing shaft support frames on the inner wall of the excavated shaft. The newly installed shaft support frames are then secured to the upper shaft support frame. The above steps are repeated cyclically to excavate the shaft section by section and install the shaft support frame; After the shaft is excavated, the starting hole for the pipe jacking machine and the installation hole for the integrated pusher are excavated on both sides of the shaft near the bottom. The integrated pusher is then installed in the installation hole.
[0005] Furthermore, in some embodiments of the present invention, each shaft support frame includes multiple steel templates connected end to end, and adjacent steel templates are fixedly connected by bolts and nuts.
[0006] Furthermore, in some embodiments of the present invention, along the vertical direction, every two adjacent shaft support frames are fixedly connected by bolts and nuts.
[0007] Furthermore, in some embodiments of the present invention, low-pressure grouting surface treatment is performed in the shaft excavation area.
[0008] Furthermore, in some embodiments of the present invention, a frame, guide rails, and ventilation system are provided at the bottom of the shaft in a horizontal direction with respect to the ground.
[0009] Compared with the prior art, the embodiments of the present invention have at least the following advantages or beneficial effects: This invention provides a vertical shaft construction process, including the following steps: A vertical shaft of a certain depth is excavated in the ground. Then, multiple shaft support frames are placed on the inner wall of the excavated shaft and fixed. An upper fixing plate is fixed to the top of the shaft. Multiple shaft support frames are stacked in the vertical direction and fixed together between each pair of adjacent shaft support frames. After securing the upper shaft support frame, continue excavating the shaft downwards. After excavating to a certain depth, continue installing shaft support frames on the inner wall of the excavated shaft. The newly installed shaft support frames are then secured to the upper shaft support frame. The above steps are repeated cyclically to excavate the shaft section by section and install the shaft support frame; After the shaft is excavated, the starting hole for the pipe jacking machine and the installation hole for the integrated pusher are excavated on both sides of the shaft near the bottom. The integrated pusher is then installed in the installation hole.
[0010] It mainly involves fixing the top and hollowing out the bottom, then assembling it with steel formwork. The construction process is safer than that of caisson construction. It also saves time, uses lightweight materials, has strong load-bearing capacity, is suitable for various geological formations, avoids underground pipeline facilities, is inexpensive, and can be installed section by section, allowing the well to be set into various shapes. Attached Figure Description
[0011] To more clearly illustrate the technical solutions of the embodiments of the present invention, the accompanying drawings used in the embodiments will be briefly introduced below. It should be understood that the following drawings only show some embodiments of the present invention and should not be regarded as a limitation on the scope. For those skilled in the art, other related drawings can be obtained based on these drawings without creative effort.
[0012] Figure 1 Construction provided for embodiments of the present invention Figure 1 ; Figure 2 Construction provided for embodiments of the present invention Figure 2 .
[0013] Icons: 1-Vertical shaft; 2-Vertical shaft support frame; 3-Pipe jacking machine starting hole; 4-Integrated pusher mounting hole; 5-Upper fixing plate. Detailed Implementation
[0014] To make the objectives, technical solutions, and advantages of the embodiments of the present invention clearer, the technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. The components of the embodiments of the present invention described and shown in the accompanying drawings can generally be arranged and designed in various different configurations.
[0015] Therefore, the following detailed description of the embodiments of the invention provided in the accompanying drawings is not intended to limit the scope of the claimed invention, but merely to illustrate selected embodiments of the invention. All other embodiments obtained by those skilled in the art based on the embodiments of the invention without inventive effort are within the scope of protection of the invention.
[0016] It should be noted that similar labels and letters in the following figures indicate similar items. Therefore, once an item is defined in one figure, it does not need to be further defined and explained in subsequent figures.
[0017] In the description of the embodiments of the present invention, it should be noted that if terms such as "center," "upper," "lower," "left," "right," "vertical," "horizontal," "inner," or "outer" indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings, or the orientation or positional relationship commonly used when the product of the invention is in use, they are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation, and therefore should not be construed as a limitation of the present invention. Furthermore, if terms such as "first" or "second" appear, they are only used to distinguish descriptions and should not be construed as indicating or implying relative importance.
[0018] Furthermore, the use of terms such as "horizontal" or "vertical" does not imply that the component must be absolutely horizontal or vertical, but rather that it can be slightly tilted. For example, "horizontal" simply means that its direction is more horizontal relative to "vertical," not that the structure must be completely horizontal, but can be slightly tilted.
[0019] In the description of the embodiments of the present invention, it should also be noted that, unless otherwise explicitly specified and limited, the terms "set" and "connection" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; and they can refer to the internal connection of two components. Those skilled in the art can understand the specific meaning of the above terms in the present invention according to the specific circumstances.
[0020] Example like Figure 1and Figure 2 As shown, this embodiment provides a vertical shaft construction process, including the following steps: A vertical shaft 1 of a certain depth is excavated on the ground. After excavation, as follows: Figure 1 As shown in Figure a, multiple shaft support frames 2 are then placed on the inner wall of the excavated shaft 1 and fixed. The top of the shaft 1 is fixed with an upper fixing plate 5. Multiple shaft support frames 2 are stacked in the vertical direction and each pair of adjacent shaft support frames 2 are fixed together. After securing the upper shaft support frame 2, continue excavating the shaft 1 downwards. After excavating to a certain depth, install the shaft support frame 2 on the inner wall of the excavated shaft 1. Secure the newly installed shaft support frame 2 to the upper shaft support frame 2. Once secured, as shown... Figure 2 As shown; Following the above steps, excavate the vertical shaft 1 section by section and install the vertical shaft support frame 2; After the excavation of shaft 1 is completed, as follows Figure 2 As shown, the starting hole 3 of the pipe jacking machine and the installation hole 4 of the integrated pusher are excavated on both sides of the shaft 1 near the bottom. The integrated pusher is installed in the installation hole 4.
[0021] Each shaft support frame 2 includes multiple steel templates connected end-to-end, with adjacent templates secured by bolts and nuts. Vertically, every two adjacent shaft support frames 2 are also secured by bolts and nuts. Low-pressure grouting is applied to the excavation area of the shaft 1. A frame, guide rails, and ventilation system are installed at the bottom of the shaft, horizontally aligned with the ground.
[0022] This application uses a fixed top and hollowed-out bottom method, and assembles the structure using steel formwork. The construction process is safer than that of caisson construction. It also saves time, uses lightweight materials, has strong load-bearing capacity, is suitable for various geological formations, avoids underground pipeline facilities, is inexpensive, and can be installed section by section. The well can be set into various shapes, such as elliptical, circular and other structures.
[0023] The above are merely preferred embodiments of the present invention and are not intended to limit the present invention. It is obvious to those skilled in the art that the present application is not limited to the details of the above exemplary embodiments, and that the present application can be implemented in other specific forms without departing from the spirit or basic characteristics of the present application.
[0024] Therefore, the embodiments should be considered exemplary and non-limiting in all respects. The scope of this application is defined by the appended claims rather than the foregoing description, and thus all variations falling within the meaning and scope of equivalents of the claims are intended to be included within this application. No reference numerals in the claims should be construed as limiting the scope of the claims. Various modifications and variations of this invention will be apparent to those skilled in the art. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of this invention should be included within the scope of protection of this invention.
Claims
1. A vertical shaft construction process, characterized in that: Includes the following steps: A vertical shaft of a certain depth is excavated in the ground. Then, multiple shaft support frames are placed on the inner wall of the excavated shaft and fixed. An upper fixing plate is fixed to the top of the shaft. Multiple shaft support frames are stacked in the vertical direction and fixed together between each pair of adjacent shaft support frames. After securing the upper shaft support frame, continue excavating the shaft downwards. After excavating to a certain depth, continue installing shaft support frames on the inner wall of the excavated shaft. The newly installed shaft support frames are then secured to the upper shaft support frame. The above steps are repeated cyclically to excavate the shaft section by section and install the shaft support frame; After the shaft is excavated, the starting hole for the pipe jacking machine and the installation hole for the integrated pusher are excavated on both sides of the shaft near the bottom. The integrated pusher is then installed in the installation hole.
2. The shaft construction process according to claim 1, characterized in that: Each shaft support frame consists of multiple steel templates connected end to end, with adjacent steel templates fixed together by bolts and nuts.
3. The vertical shaft construction process according to claim 1, characterized in that: Along the vertical direction, every two adjacent shaft support frames are fixedly connected by bolts and nuts.
4. The shaft construction process according to claim 1, characterized in that: Low-pressure grouting was carried out on the ground in the shaft excavation area.
5. The shaft construction process according to claim 1, characterized in that: A frame, guide rails, and ventilation system are installed at the bottom of the shaft in a horizontal direction with the ground.