Cement-soil mixing pile sectional grouting control method

By establishing mechanical and grouting benchmarks during cement-soil mixing pile construction, determining the stability window and grouting response value using drill bit load and flow detection, freezing candidate boundaries, and establishing boundary acceptance zones, the problem of inaccurate grout volume attribution near the soil interface was solved, improving the accuracy and continuity of construction control.

CN122837560BActive Publication Date: 2026-11-24CCCC FIRST HARBOR ENGINEERING CO LTD +1
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202611327203.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2026-08-31
Publication Date
2026-11-24
Estimated Expiration
2046-08-31

AI Technical Summary

Technical Problem

Under construction conditions where different soil layers such as soft soil, silt, clay and sand are distributed alternately, existing technologies make it difficult to stably confirm the segment boundaries near the soil layer interfaces, resulting in inaccurate grout volume attribution and affecting subsequent construction control.

Method used

By establishing mechanical and grouting benchmarks before the design soil interface search zone, and using low-high-low flow rate detection of drill string load and grouting flow rate, the stable window and grouting response value are determined, candidate boundaries are frozen and boundary acceptance sections are established, and effective segment boundaries are determined based on the drill string load stability state and grouting state sequence. During the boundary confirmation process, the flow rate sequence and pressure stability are maintained to continuously assign and control the grout volume.

Benefits of technology

This method enables the confirmation of stable segment boundaries near the soil interface, reduces the premature inclusion of grout volume in incorrect grouting sections, improves the accuracy and continuity of construction control, and reduces the impact of transient disturbances on segment boundary judgment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN122837560B_ABST
    Figure CN122837560B_ABST
Patent Text Reader

Abstract

The application discloses a cement-soil mixing pile segmented grouting control method, and particularly relates to the technical field of cement-soil mixing pile grouting control, and is used for solving the problem that in the existing cement-soil mixing pile construction process, the soil layer interface change is out of sync with the drill tool load response and the grouting pressure response, the grouting segmented boundary is difficult to accurately determine, the slurry amount in the transition zone is prone to error attribution, and the subsequent segmented grouting control is affected. By forming a mechanical reference and a grouted reference before designing a soil layer interface search area, a candidate boundary is formed according to continuous disengagement of the drill tool load, the slurry amount to be attributed is accumulated in the boundary receiving area, the same sequence flow detection is performed to form a grouted state sequence, and then the effective segmented boundary is determined in combination with the mechanical stable state and the grouted stable state, so that the judgment deviation caused by single mechanical response or direct segmentation of the preset interface is reduced, and the condition that the slurry amount in the interface transition stage is misattributed in advance is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of grouting control technology for cement-soil mixing piles, specifically a method for segmented grouting control of cement-soil mixing piles. Background Technology

[0002] Cement-soil mixing piles typically involve sinking, lifting, and rotating the drill bit to mix cement slurry and other solidifying materials with the in-situ soil to form a solidified pile. During construction, drilling speed, lifting speed, and grouting volume are usually controlled based on the designed geological data, drill bit operating parameters, and grouting parameters. Existing technologies have begun to utilize construction response to identify geological formations and implement dynamic control. For example, the paper "Construction Device and Method for Mixing Piles with Dynamic Adjustment of Grouting, Lifting, and Sinking Speeds" (CN113309087A) uses a penetration tester installed at the drill bit to obtain the specific penetration resistance and adjusts the grouting volume and drilling speed according to the identified geological type. The paper "Construction Method for Large-Diameter Onshore Four-Axis Mixing Piles" (CN114000501A) establishes the relationship between the designed top elevation of the embedded layer and the drilling current and its variation characteristics through trial insertion. Based on this, the actual top elevation of the embedded layer is determined, and the grouting process is adjusted in conjunction with the grouting pipeline length and grout condition.

[0003] However, under construction conditions where different soil layers such as soft soil, silt, clay, and sandy soil are interspersed, the changes in soil resistance reflected by changes in drill string load, the changes in pressure and flow rate in the grouting pipeline, and the actual grouting state after the grout enters the new soil layer do not necessarily occur synchronously at the same construction depth. Existing schemes mostly adjust the grouting volume and drilling parameters directly based on geological identification results, drill string load, or preset stratum location. Although some schemes consider the length of the grouting pipeline and the grouting switching process, for construction sections near the soil interface that are in a transitional state, there may still be situations where the mechanical response has changed but the grouting state has not yet stabilized, or there is a time difference between the grout metering position and the actual construction position.

[0004] In the aforementioned scenario, if the grouting segment boundary is determined upon the first load change or when the design interface is reached, and the grout volume generated in between is directly included in the preceding or subsequent grouting segment, the attribution of grout volume during the boundary transition period may be affected by differences in the timing of interface judgment. This further leads to the grout volume already injected, the remaining target grout volume, and subsequent pumping and advance control of the subsequent grouting segment being established on a boundary foundation that has not yet been fully confirmed. Furthermore, when subsequent construction responses differ from the original boundary judgment, there is a lack of a mechanism for continuous transfer and correction of existing grout volume attribution and control status. Therefore, how to combine the mechanical response and grouting response near the soil interface to stably confirm the segment boundary, and maintain the adjustability of the transition grout volume and subsequent control status during the boundary confirmation process, is a technical problem that needs to be solved in the segmented grouting control of cement-soil mixing piles. Summary of the Invention

[0005] To address the shortcomings of existing technologies, this invention provides a segmented grouting control method for cement-soil mixing piles, thereby solving the problems mentioned in the background section.

[0006] To achieve the above objectives, the present invention provides the following technical solution:

[0007] A method for controlling segmented grouting in cement-soil mixing piles includes:

[0008] 1. Before entering the designed soil interface search zone, collect drill bit load, grouting pressure, and grouting flow rate, and perform low-flow-high-flow-low-flow detection to establish the mechanical and grouting reference for the current grouting section. A stable window is formed when the actual grouting flow rate is continuously within the target flow rate allowable zone and the duration reaches the lockout period, and the grouting pressure range within this period does not exceed the allowable pressure fluctuation and the difference between the average pressure values ​​of the first and second halves does not exceed the allowable pressure drift. A stable window is formed when all three flow stages have stable windows, the actual high-low flow rate difference is greater than the minimum distinguishable flow rate difference, and the difference between two low-flow stable grouting pressures does not exceed the allowable recovery. When the difference is small, it is determined to be a complete detection cycle; the drill string load records of the two low flow rate stable windows of the consecutive complete detection cycles are sorted and screened according to the locked retention ratio, and the minimum and maximum values ​​of the retained records are used to form the lower boundary and upper boundary of the mechanical reference; the complete detection cycle in which the average value of the drill string load of the two low flow rate stable windows is located between the two boundaries is determined to be a qualified detection cycle, and the slurry response value is formed according to the ratio of pressure change to flow rate change, and the slurry response values ​​of the consecutive qualified detection cycles are sorted and screened to form the lower boundary and upper boundary of the slurry reference, and the maximum value of the low flow rate recovery difference is used to form the recovery boundary;

[0009] 2. After entering the search area, candidate boundaries are formed based on the continuous separation of the drill string load from the mechanical reference. The candidate boundaries are frozen, boundary acceptance sections are established, and the amount of slurry to be assigned is accumulated.

[0010] Third, in the boundary receiving section, keep the drill speed and footage speed under control, perform sequential flow detection, and form a slurry state sequence based on the pressure response;

[0011] IV. When the drill string load remains on the same side of the mechanical reference within the mechanical stability observation window and the range does not exceed the mechanical stability fluctuation limit, a stable state is formed after the drill string load leaves the mechanical reference; when the continuous effective slurry-receiving state sequence items remain in the same departure direction, the low flow recovery difference does not exceed the recovery boundary, and the span of the slurry response value does not exceed the slurry stability fluctuation limit, a stable state is formed after the slurry-receiving state sequence leaves the slurry-receiving reference; the starting point of the construction section where the two stable states overlap along the locked construction direction is taken as the effective segment boundary;

[0012] 5. Divide the grout volume to be assigned according to the effective segment boundary and include it in the corresponding grouting segment. Subtract the confirmed grout volume from the target grout volume of the next grouting segment to generate the remaining target grout volume, and control the pumping and advance.

[0013] 6. Perform sequential flow detection in the next grouting section. If the grouting response maintains the stable state of the section, submit a valid segment boundary; otherwise, cancel the boundary, rebuild the boundary receiving section, and write back the control status.

[0014] Furthermore, when the drill string load continuously deviates from the mechanical reference on the same side while simultaneously satisfying the minimum number of effective sampling points and the continuous deviance footage threshold, the depth corresponding to the first effective sampling point of the continuous deviance sequence is frozen as a candidate boundary.

[0015] The candidate boundary is used as the fixed starting point for the boundary section, and starting from the sampling time corresponding to the candidate boundary, the amount of grout to be assigned is accumulated according to the average value of adjacent effective grouting flow rate and the corresponding actual time interval.

[0016] Furthermore, the sequential flow detection within the boundary receiving section inherits the low flow setpoint, high flow setpoint, and stable window that were locked when forming the slurry receiving reference, and maintains the rules.

[0017] When the drill bit speed and drilling speed are kept within the locked allowable range, the actual high and low flow rate changes are greater than the minimum distinguishable flow rate difference, the low flow rate recovery difference does not exceed the allowable recovery difference, and the detection occupied range does not exceed the maximum detection drilling length of a single round, it is determined as a valid detection round, and a slurry-receiving state sequence is formed according to the actual completion order.

[0018] Furthermore, the amount of slurry to be assigned is determined based on the time corresponding to the effective segment boundary;

[0019] When the effective segment boundary corresponds to a time point between two adjacent effective mixing head depth sampling points, the time point is determined according to the depth change ratio, and the cross-boundary cumulative interval is split. The slurry volume of the sub-intervals before and after the boundary is calculated and included in the corresponding grouting section. The division result satisfies the allowable difference of slurry volume conservation.

[0020] Furthermore, the remaining target grout volume is divided by the remaining construction length from the current position of the mixing head to the end position of the next grouting section to form the subsequent unit advance grout volume requirement;

[0021] The target pumping flow rate is determined by this requirement and the current effective advance rate. When the target pumping flow rate exceeds the upper limit of allowable flow rate, the upper limit of allowable flow rate is used and the advance rate is calculated in reverse. When it is lower than the continuous stable lower limit, the continuous stable lower limit of flow rate is used and the advance rate is calculated in reverse. The advance rate calculated in reverse is kept within the allowable range of the next grouting section.

[0022] Furthermore, the continuous effective sequence items that participated in the formation of the stable state of the slurry when forming the effective segment boundary are used as reference records;

[0023] When the number of consecutive valid confirmation rounds obtained in the next grouting section reaches the locked number, and each round maintains the original separation direction, the low flow recovery difference does not exceed the recovery boundary, and the span of the grouting response value formed together with the reference record does not exceed the grouting stability fluctuation limit, the effective segment boundary will be converted to the submitted state.

[0024] If any valid confirmation round fails to maintain the original separation direction, the low flow recovery difference exceeds the recovery boundary, or the span of the slurry response value after addition exceeds the slurry stability fluctuation limit, the valid segment boundary will be changed to the cancelled state, the slurry volume dependent on the boundary will be restored to the slurry volume to be assigned, and the boundary acceptance section will be reconstructed with the original frozen candidate boundary.

[0025] Compared with the prior art, the present invention has the following beneficial effects:

[0026] 1. This invention establishes a mechanical reference and a grouting reference for the current grouting section before entering the search zone of the designed soil interface. After entering the search zone, the drill load continuously deviates from the mechanical reference to form and freeze candidate boundaries. Within the boundary acceptance section, the amount of grout to be assigned is continuously accumulated, and a grouting state sequence is formed by performing sequential flow detection. Then, the effective segment boundary is determined based on the overlap between the stable state of the drill load and the stable state of the grouting state sequence. This avoids directly completing the segmentation based solely on a single change in drill load or a preset soil interface position. The segment boundary can be constrained by both the construction machinery response and the actual grouting response. Furthermore, the grout volume generated during the boundary confirmation period can be temporarily deferred, reducing the situation where the grout volume during the interface transition stage is prematurely included in the previous or subsequent grouting section.

[0027] 2. This invention maintains a consistent flow sequence, stability window, pressure fluctuation, pressure drift, flow difference, and recovery difference in the low-flow-high-flow-low flow detection process during benchmark formation, boundary acceptance section judgment, and subsequent confirmation of the next grouting section. It also combines the mechanical stability observation window, allowable deviation of grouting response, grouting stability fluctuation limit, and continuous effective detection rounds for joint judgment. This provides a unified comparison scale for the formation process from candidate boundary to effective segment boundary, and can distinguish between short-term measurement fluctuations, failed detection rounds, and changes in the actual grouting state, reducing the impact of local instantaneous disturbances on the segment boundary judgment results.

[0028] 3. This invention links candidate boundaries, boundary acceptance sections, grout volumes to be assigned, effective segment boundaries, confirmed grout volumes, remaining target grout volumes, and subsequent confirmation status with versions and retains original records. After the effective segment boundary is formed, the grout volumes to be assigned are re-divided according to the corresponding time, and the remaining target grout volumes and pumping and advance control are updated accordingly. At the same time, if the subsequent grout response does not remain stable, the effective segment boundary is revoked, the boundary acceptance section is rebuilt, and the grout volume assignment and control status based on the boundary are written back. This ensures a continuous correspondence between segment judgment, grout volume settlement, and construction control, and allows the boundary submission, revocation, and re-judgment process to be recalculated and traced based on existing records. Attached Figure Description

[0029] Figure 1 A schematic diagram of the overall process for the segmented grouting control method for cement-soil mixing piles;

[0030] Figure 2 A schematic diagram illustrating the data processing logic between the mechanical reference and the slurry-receiving reference.

[0031] Figure 3 A schematic diagram showing the freezing of candidate boundaries, the establishment of boundary acceptance sections, and the cumulative amount of slurry to be assigned.

[0032] Figure 4 A schematic diagram of the detection of the same flow rate and the formation of the slurry state sequence within the boundary receiving section;

[0033] Figure 5 A schematic diagram showing the effective segmentation boundary determined jointly by the mechanically stable state and the slurry-induced stable state;

[0034] Figure 6 A schematic diagram of effective segmented boundary-driven slurry volume division and remaining target slurry volume control;

[0035] Figure 7 This is a schematic diagram illustrating the closed loop of subsequent confirmation, submission, and revocation of effective segment boundaries;

[0036] Figure 8 This is a diagram illustrating the relationship between key versions and construction records. Detailed Implementation

[0037] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0038] Example: Combined with Appendix Figures 1-8 This embodiment provides a method for controlling segmented grouting of cement-soil mixing piles, including:

[0039] 1. Before entering the designed soil interface search zone, collect drill string load, grouting pressure, and grouting flow rate, and perform low-flow-high-flow-low-flow detection to establish the mechanical and grouting reference for the current grouting section. A stable window is formed when the actual grouting flow rate is continuously within the target flow rate allowable zone for a duration that reaches the lockout period, and the grouting pressure range within this period does not exceed the allowable pressure fluctuation, and the difference between the average pressure values ​​of the first and second halves does not exceed the allowable pressure drift. A stable window is formed when all three flow stages have stable windows, the actual high-low flow rate difference is greater than the minimum distinguishable flow rate difference, and the difference between two stable low-flow grouting pressures does not exceed the allowable recovery difference. A complete detection cycle is identified. The drill string load records from two consecutive complete detection cycles during low-flow stability windows are sorted and filtered according to the retention ratio. The minimum and maximum values ​​of the retained records form the lower and upper boundaries of the mechanical reference. Complete detection cycles where the average drill string load values ​​from both low-flow stability windows are between these two boundaries are identified as qualified detection cycles. The slurry response value is calculated based on the ratio of pressure change to flow rate change. The slurry response values ​​from consecutive qualified detection cycles are sorted and filtered to form the lower and upper boundaries of the slurry reference. The maximum low-flow recovery difference forms the recovery boundary. The specific implementation is as follows:

[0040] Before designing the soil interface search area, the continuous construction section where the current mixing head has not yet entered the design soil interface search area is determined by the pile driver depth measurement signal. The location of the design soil interface search area is taken from the exploration layer record used for this pile and the corresponding soil interface location in the construction design. When the construction design gives the upper and lower search boundaries of the interface, the boundary is directly used. When only the design interface depth is given, the exploration boreholes that are clearly associated with the current pile position, the current pile group, or the current construction pile area in the construction design or the exploration layer record of this pile are used as the center. When there are multiple clearly associated exploration boreholes, all of them are included. When the data gives a priority for associated borehole groups, only the highest priority borehole group is used. When no priority is given, all clearly associated boreholes are used. The exploration boreholes are not temporarily added or deleted by the on-site construction personnel according to the distance. The maximum absolute deviation of the interface depth corresponding to the selected exploration borehole from the design interface depth and the allowable error of the pile driver depth measurement are taken as the search distance, and the search area is formed accordingly. When there is no record of the above clearly associated boreholes, the search distance given by the construction design is used. When the construction design does not give a search distance, this interface is not used to re-establish the benchmark in this step.

[0041] The search area and the version of the data used are locked before the pile is started, and will not be changed during the construction of the same pile.

[0042] The current grouting section is the pile depth section located before the design soil layer interface search area along the construction direction, and is constructed continuously using the same set of design cement dosage and construction parameters. This step does not re-divide this section based on the data collection results. The normal advance is defined as the mixing head maintaining the current construction direction, the advance speed being within the allowable speed range locked before pile opening, and there being no drilling stoppage or reverse movement. If the remaining construction length before the search area is not less than the cumulative advance length required to complete the specified number of low-flow-high-flow-low-flow detections according to the current allowable advance speed, it is considered to have sufficient construction length. Otherwise, a new mechanical benchmark and grouting benchmark for the current grouting section will not be formed.

[0043] This step only uses records of the period when the slurry pump is continuously supplying slurry and the mixing head is advancing normally, and does not use records of the periods when the slurry pump is started and stopped, the pipeline is flushed, or the drilling is stopped and restarted.

[0044] The drilling load uses the same measuring diameter that can continuously characterize the change in soil resistance of the mixing head. The torque of the power head can be used, and the unit is kilonewton-meter. When the equipment only provides the drive motor current, the current is used, and the unit is ampere. The measuring diameter must not be changed during the period when the same pile forms the mechanical reference for the current grouting section.

[0045] The grouting pressure is the pressure value measured at a fixed pressure measuring position between the grout pump outlet and the drill pipe rotary joint, in megapascals (MPa); the grouting flow rate is the actual volumetric flow rate measured at a fixed flow measuring position on the same grouting main pipe, in liters per minute (L / min).

[0046] The drill string load, grouting pressure, and grouting flow rate are continuously recorded by the on-site construction controller at a unified clock. At the same time, the pile number, sampling time, mixing head depth, detection stage, measurement diameter, sensor calibration mark, and construction parameter version are also recorded.

[0047] After all sensor records are converted to a unified clock, the sampling time of the drill string load is used as the merging time. Grouting pressure and grouting flow rate are merged using valid records with the smallest time difference that do not exceed the pre-locked allowable deviation. If there are two records with equal time difference, the earlier record is used. If the time difference exceeds the allowable deviation, the corresponding field is recorded as missing.

[0048] Continuous recordings are sequentially time-aligned, denoised, and supplemented with missing measurements within the allowable range. If only one sampling point is continuously recorded, and the rate of change of that point relative to the valid points before and after it exceeds the maximum achievable rate of change locked according to the equipment nameplate or debugging records, and the valid points before and after it are still within the allowable fluctuation range of the measurement, it is considered an isolated jump and is removed. If two or more consecutive sampling points change in the same direction, they should not be deleted as isolated jumps.

[0049] Missing measurements are only filled when a single measurement field is missing, the duration does not exceed the preset filling limit, and there are valid records before and after the gap. The filling value is determined according to the linear change of the valid values ​​before and after the gap over time. It must not cross the flow switching time, grout pump start and stop time, and detection cycle boundary. It must not fill the section where drill load, grouting pressure, and grouting flow are missing at the same time.

[0050] If the boundary is exceeded, the measurement is continuously out of range, or the sensor calibration status fails, the corresponding detection cycle will fail. If there is still sufficient construction length in front of the search area, the process will be restarted from the low flow stage. If the maximum number of repetitions locked before pile opening still cannot obtain the specified cycle, no callable benchmark will be formed and the record will be retained for on-site verification.

[0051] After the above data collection is completed, the construction controller performs low-flow-high-flow-low-flow detection. Both low and high flow rates are determined from the approved continuous construction flow rate range of the current grouting section. The low flow rate should ensure that the grout volume per unit depth under the current advance conditions is not lower than the lower limit of construction allowable. The high flow rate should not exceed the upper limit of continuous stable operation of the grout pump, the allowable flow rate of the pipeline, and the grouting pressure upper limit of the current grouting section corresponding to the grouting supply range. For the design soil layer interface that needs to be submitted for boundary confirmation by performing sequential flow detection in the next grouting section, the selected low and high flow rates should also be within the common allowable range of safe continuous construction of adjacent grouting sections before and after the interface. If there is no common allowable range, the subsequent submission confirmation mode will not be enabled for this interface. The minimum distinguishable flow rate difference is the sum of the maximum allowable error of the flow meter and the dead zone of the grout pump control. The actual flow rate difference between the two must be greater than the minimum distinguishable flow rate difference. The same set diameter is maintained during the benchmark formation period.

[0052] The construction controller initially maintains a low flow rate. After the actual grouting flow rate continuously remains within the target flow rate allowable band for a preset holding period, a stable window is formed. The single-sided width of the target flow rate allowable band is the sum of the maximum allowable error of the flow meter and the steady-state repeatability error of the grout pump.

[0053] The difference between the maximum and minimum grouting pressure within the stable window must not exceed the allowable pressure fluctuation, and the difference between the average pressure in the first half and the average pressure in the second half of the window must not exceed the allowable pressure drift. The allowable pressure fluctuation is the sum of the difference between the positive and negative measurement error limits of the pressure sensor and the maximum pressure range obtained from repeated steady-state tests at the same flow rate before construction. The allowable pressure drift is the sum of the difference between the positive and negative measurement error limits of the pressure sensor and the difference between the maximum average pressure values ​​in the first and second halves of the window obtained from repeated steady-state tests. The number of repeated steady-state tests, the time period for each value acquisition after entering the stable state, and the version of the commissioning record used are used to form a detection parameter version and lock it before pile commencement. When the above specifications are changed subsequently, only a new version is formed, without overwriting the version already used for the current pile reference.

[0054] Once the conditions are met, the arithmetic mean of all effective grouting pressures in the stable window is taken as the first low-flow stable grouting pressure, and the arithmetic mean of all effective grouting flows is taken as the first low-flow stable grouting flow. Then, the flow is switched to high flow and the high-flow stable grouting pressure and high-flow stable grouting flow are obtained according to the same rules. Then, the low flow is restored and the second low-flow stable grouting pressure and the second low-flow stable grouting flow are obtained.

[0055] During the exploration, maintain the original construction direction and do not actively switch the drill speed and footage status unrelated to the exploration; terminate the exploration round when the grouting pressure reaches the upper limit of the allowable limit, the grout pump cannot enter the target flow allowable zone, the measurement record fails, or the drill load exceeds the equipment safety boundary.

[0056] A complete detection cycle is defined as follows: The cycle is completed when the grouting pressure and flow rate are stable in all three stages (low flow, high flow, low flow), the actual flow rate difference exceeds the minimum distinguishable flow rate difference, the absolute difference between the second low flow rate stable grouting pressure and the first low flow rate stable grouting pressure does not exceed the allowable recovery difference, and no termination occurs as described above. The allowable recovery difference is the sum of the difference between the positive and negative measurement error limits of the pressure sensor and the maximum pressure repetition deviation obtained by the grout pump under the same low flow rate and repeated steady-state grouting. The prescribed number of detection cycles, retention ratio, maximum number of repetitions, and upper limit for missing measurements used to form the mechanical and grouting references are directly given by the detection parameter version formed during pre-pile commissioning. This parameter version is formed and locked based on the equipment sampling capacity, the design allowable construction length, and the pre-construction trial operation records.

[0057] After obtaining the required number of consecutive complete detection cycles, the mechanical reference for the current grouting section is formed only by using the effective records of the drill string load within the first and second low-flow stability windows of each complete detection cycle. All effective records are sorted by value, and the number of records to be retained is determined according to the retention ratio locked before pile opening. If the total number of records multiplied by the retention ratio has a decimal, it is rounded up. The total number of records minus the number of retained records is the number to be eliminated. The records are eliminated equally from the low-value end and the high-value end. If the number of records to be eliminated is odd, the extra record is eliminated from the high-value end. The minimum value of the retained records is used as the lower boundary of the mechanical reference, the maximum value is used as the upper boundary of the mechanical reference, and the arithmetic mean is used as the center value of the mechanical reference.

[0058] Once the mechanical reference is formed, it remains locked during the current reference formation process in the grouting section. Subsequent new complete detection cycles must not recalculate the mechanical reference in reverse. The arithmetic mean of the drill string load in the first low flow rate stable window and the second low flow rate stable window of each complete detection cycle is obtained. When both average values ​​are within the range of the lower boundary to the upper boundary of the mechanical reference, the complete detection cycle is determined to be a qualified detection cycle.

[0059] For each qualified detection cycle, the average value of two low-flow stable grouting pressures and the average value of two low-flow stable grouting flows are first obtained. The pressure change is obtained by subtracting the average value of the two low-flow stable grouting pressures from the high-flow stable grouting pressure, and the flow change is obtained by subtracting the average value of the two low-flow stable grouting flows from the high-flow stable grouting flow. The value obtained by dividing the pressure change by the flow change is taken as the grouting response value of that cycle, and the absolute difference between the second low-flow stable grouting pressure and the first low-flow stable grouting pressure is recorded as the low-flow recovery difference.

[0060] The grouting response values ​​from a specified number of consecutive qualified detection rounds are sorted numerically. Using the same retention ratio and rounding rules as the mechanical reference, the lower and upper boundaries of the grouting reference are formed. The maximum value among the low-flow recovery differences of qualified detection rounds is used as the recovery boundary. These three factors together constitute the grouting reference for the current grouting section. When an unqualified detection round occurs, the consecutive qualified round count is reset to zero, and the count restarts from the next complete detection round. New complete detection rounds are only determined based on the locked mechanical reference and do not form a new mechanical reference. The grouting reference is formed when a specified number of consecutive qualified detection rounds are obtained. If a specified number of consecutive qualified detection rounds are not obtained before entering the design soil layer interface search area, or if the maximum number of repetitions is reached, the grouting reference remains unretrievable, and the existing records are retained for on-site verification.

[0061] The mechanical benchmark, grouting benchmark, along with the original sampling record, complete detection rounds, qualified detection rounds, stable values ​​at each stage, grouting response values, parameter version, and sensor calibration identifier are written into the current pile construction record. The record is jointly determined by the pile number, the current grouting section identifier, the detection round, the sampling time, and the parameter version. When the same record arrives repeatedly, only the first one is validly written into the benchmark formation. Subsequent records are only left as traces and cannot be overwritten. After the benchmark is formed, the corresponding version is locked, and subsequent modifications only require adding a new version.

[0062] Only after obtaining a specified number of continuous and complete detection cycles to form a mechanical benchmark, and then obtaining a specified number of continuous and qualified detection cycles to form a grouting benchmark and completing the record locking, can both benchmarks be set to a callable state for the next step to read after entering the design soil layer interface search area.

[0063] Preferably, in a set of representative working conditions, a continuous construction length of 1.0m is reserved before the search area, the drill string load is based on the drive motor current, the sampling rhythm of drill string load, grouting pressure and grouting flow rate is 10Hz, the allowable deviation of time alignment is no more than 50ms, and the allowable duration of missing measurements is no more than 0.2s; the low flow rate is set to 55L / min, the high flow rate is set to 75L / min, each flow rate level is maintained for 5s, the upper limit of grouting pressure is set to 0.8MPa, and a mechanical reference is formed after obtaining 3 consecutive complete detection cycles. The mechanical reference adopts the effective record of the middle 80% of the drill string load after sorting.

[0064] Under this condition, the first low-flow stable grouting pressures for the three rounds were 0.39 MPa, 0.40 MPa, and 0.39 MPa, respectively; the high-flow stable grouting pressures were 0.53 MPa, 0.54 MPa, and 0.52 MPa, respectively; and the second low-flow stable grouting pressures were 0.40 MPa, 0.40 MPa, and 0.39 MPa, respectively. The effective drill string load records were concentrated between 78A and 84A. After the mechanical reference was established, the drill string loads in the three low-flow stable windows were all within the corresponding mechanical reference range, thus determining three consecutive qualified detection rounds. Based on this, the grout receiving reference was formed, and the mechanical reference, grout receiving reference, and corresponding original detection records were locked as the records that could be called up for the current grouting section.

[0065] II. After entering the search area, candidate boundaries are formed based on the continuous departure of the drill string load from the mechanical reference. The candidate boundaries are frozen, boundary acceptance sections are established, and the amount of slurry to be assigned is accumulated. The specific implementation is as follows:

[0066] The search begins when the mixing head first enters the design soil interface search area along the locked construction direction. The on-site construction controller continues to obtain the drill load according to the drill load measurement caliber locked in the previous stage, and locks the callable version of the mechanical reference for the current grouting section at the first effective sampling moment upon entering the search area. The mechanical reference version must not be switched during this search. If no candidate boundary has been formed, the search ends when the mixing head reaches the end of the search area along the locked construction direction. If the candidate boundary has been frozen, the search will not end because the mixing head has crossed the end of the search area, and the boundary acceptance section that has been established will continue to extend with the normal construction progress.

[0067] The measurement location, unit, sampling clock, time alignment, isolated jump rejection, and allowable missing measurement completion rules for drill string load all follow the locked caliber established when the mechanical reference was formed.

[0068] Within the search area, the drill string load at each valid sampling point is compared with the lower boundary and upper boundary of the mechanical reference. If the drill string load is greater than the upper boundary of the mechanical reference, it is recorded as upward separation; if it is less than the lower boundary of the mechanical reference, it is recorded as downward separation; if it is equal to either boundary or between the two boundaries, it is recorded as not separated. Continuous separation is only recognized when the consecutive valid sampling points are always located on the same side of the mechanical reference. If any valid sampling point returns to the mechanical reference range, moves from one side of the mechanical reference to the other side, or has a drill string load that cannot be replenished, the current consecutive separation sampling point count and cumulative footage length are simultaneously reset to zero, and the count is restarted from the next valid sampling point that meets the same-side separation condition.

[0069] Continuous disengagement is established when both the minimum number of valid sampling points and the continuous disengagement footage threshold are met. The minimum number of valid sampling points is directly given by the continuous disengagement parameter version formed and locked during pre-pile commissioning. This parameter version is formed based on the drill string load sampling cycle and the minimum continuous confirmation period used to exclude single-point and short-term fluctuations in the commissioning record. The number of sampling intervals between the first and last valid sampling points in the continuous sequence is used as the basis for calculating the duration. The footage length corresponding to the maximum allowable footage speed, the number of sampling intervals, the locked sampling cycle, and the maximum allowable footage speed are compared with the upper limit of the allowable error range for pile driver depth measurement, and the larger one is taken as the continuous disengagement footage threshold.

[0070] The actual continuous divergence length is determined by the depth difference between the depth of the mixing head and the depth of the mixing head at the first valid sampling point in the continuous sequence along the locked construction direction when the confirmation conditions are met. When the number of valid sampling points on the same side reaches the specified number and the depth difference reaches the continuous divergence threshold, the drill string load is considered to have continuously diverged from the mechanical reference.

[0071] The candidate boundary is taken as the stirring head depth corresponding to the first valid sampling point of the continuous deviance sequence. At the same time, the time of sampling point, drill string load, deviance direction and stirring head depth when the confirmation condition is met are recorded. The depth when the confirmation condition is met is not used to replace the candidate boundary.

[0072] In this step, candidate boundaries are only set to an unformed state and a frozen state. The unformed state is maintained until the continuous detachment condition is met. When the condition is met for the first time, the unformed state is changed to the frozen state in one go. The on-site construction controller writes the candidate boundary depth, corresponding sampling time, detachment direction, confirmed depth, mechanical reference version and construction direction in the same recording cycle. After freezing, the candidate boundary depth and corresponding sampling time shall not be moved due to subsequent changes in drill string load, shall not be revoked in this step, and shall not form a second candidate boundary. Repeated freezing requests under the same pile number, current grouting section identifier and current search identifier are only accepted for the first valid record.

[0073] If the continuous separation condition is not met before the search zone reaches its endpoint, no candidate boundary, boundary receiving section, or slurry volume to be assigned will be formed.

[0074] After the candidate boundary is frozen, the candidate boundary depth is used as the fixed starting point of the boundary acceptance section, and the current depth actually reached by the mixing head along the locked construction direction is used as the active end point to establish the boundary acceptance section. The fixed starting point shall not be changed, and the active end point shall only be updated along the construction direction with the normal construction advance. After the candidate boundary is frozen, the extension of the boundary acceptance section is not limited by the endpoint of the design soil layer interface search area. The final termination boundary of this step is uncertain.

[0075] When the mixing head stops advancing, the active end of the boundary bearing section remains unchanged; when the construction direction changes unplanned or the equipment safety protection action is triggered, the extension of the active end also stops and the existing records are retained.

[0076] The boundary acceptance section is associated with at least the candidate boundary depth, active end depth, construction direction, the sampling time corresponding to the candidate boundary, the current recording time, and the frozen version of the candidate boundary. Only one active boundary acceptance section is retained for the same pile and the same candidate boundary.

[0077] The amount of grout to be assigned is accumulated from the sampling time corresponding to the candidate boundary. Its physical diameter is the accumulated value of the grout liquid that has been actually measured at the fixed grouting flow measurement position in the previous step and has not yet been determined to be assigned to the final grouting section in this step. The measurement time at the fixed flow measurement position is not the same as the actual time when the grout reaches the nozzle. The soil layer action position corresponding to the grout is not determined in this step.

[0078] Since the candidate boundary is only frozen after continuous deviance confirmation, the on-site construction controller first calls the valid grouting flow records that have been retained between the sampling time and the freezing time corresponding to the candidate boundary to trace the accumulation, and then continues to accumulate according to the real-time grouting flow.

[0079] For two adjacent valid grouting flow sampling times, the arithmetic mean of the two actual grouting flow rates is taken. The actual time interval between the two sampling times is converted into minutes. The actual grout volume measured in that sampling interval is obtained by using the average grouting flow rate and the time interval. Then, the grout volumes are added segment by segment in ascending order of sampling time to form the grout volume to be assigned. Each cumulative interval simultaneously records the start sampling time, end sampling time, start mixing head depth, end mixing head depth, and grout volume in that interval, so that the cumulative results can be recalculated along the construction depth and time.

[0080] When the mixing head stops advancing and the grouting flow rate is 0, neither the boundary receiving section nor the grout volume to be assigned increases; when the mixing head stops advancing but there is still an effective grouting flow rate at the fixed flow measurement position, the active end of the boundary receiving section remains unchanged, and the corresponding actual metered grout is still included in the grout volume to be assigned.

[0081] When there are short-term missing measurements of grouting flow rate that can be supplemented according to the rules of the previous step, the valid records after supplementation will continue to be accumulated. When there are missing flow rates that cannot be automatically supplemented, the flow meter calibration status is invalid, or the flow record cannot meet the lock time correspondence requirements, the automatic continuous accumulation of the grout volume to be assigned will be stopped, the candidate boundary, boundary acceptance section and the cumulative value confirmed before the missing measurement will be retained, and the grout volume record to be assigned will be set to an incomplete state. It cannot be submitted as a complete grout volume to be assigned to the subsequent steps that need to assign grout volume. Subsequent supplementation will only accept the restored original historical records of the equipment or independent field metering records with the same time correspondence. Manual average flow estimation will not be used to cross the missing measurement interval. The complete state can only be restored after the supplementation is completed and the time correspondence rules are met again.

[0082] Candidate boundaries, boundary acceptance sections, and grout volumes to be assigned are uniquely associated with each other based on the pile number, current grouting section identifier, current search identifier, and parameter version. The original drill string load, continuous detachment sequence, candidate boundary freeze record, boundary acceptance section extension record, and cumulative grout volume record at each sampling interval are retained according to the original time sequence. When the same uniquely associated record arrives repeatedly, only the first one is validly written to participate in the formation of the current result. Subsequent records are retained and must not cover the frozen state.

[0083] When verifying candidate boundaries, the continuous separation judgment is re-executed according to the established sequence using the locked mechanical reference and the original drill string load record. The depth of the first valid sampling point in the newly obtained continuous sequence should be consistent with the frozen candidate boundary. When verifying the slurry volume to be assigned, the flow rate is re-accumulated according to the saved sampling interval flow rate record. Based on the flow rate measurement error calibrated by the fixed flow rate measurement position, the flow rate measurement error of each accumulation interval is converted into the allowable error of the accumulated slurry volume according to the corresponding actual duration and then accumulated interval by interval. This error is then combined with the rounding error of the recorded value to form the allowable difference value for verifying the slurry volume to be assigned. If the difference between the re-accumulated result and the current slurry volume to be assigned exceeds this allowable difference value, the corresponding slurry volume to be assigned should not be set to the complete state.

[0084] This implementation method is applicable to cement-soil mixing pile construction equipment where the drill load, mixing head depth, and grouting flow rate can correspond continuously. It can be implemented when the drill load is based on the power head torque or drive motor current, but it must be consistent with the mechanical reference when it is formed.

[0085] Preferably, in a set of representative working conditions, the mechanical reference uses the drive motor current, with a lower boundary of 78A and an upper boundary of 84A. The drill string load sampling rhythm is 10Hz, the minimum number of consecutive effective sampling points is set to 10, and the continuous deviation footage threshold is set to 0.10m. After the stirring head enters the search area, the drive motor current continuously exceeds 84A from a depth of 9.82m. If the specified number of effective sampling points is met at a depth of 9.93m and the continuous footage reaches 0.11m, then 9.82m is frozen as the candidate boundary, and the current is set from 9.82m... The grouting flow rate is traced back to the corresponding sampling time. When the mixing head reaches 9.93m at the time of freezing, the boundary receiving section first forms a continuous range from 9.82m to 9.93m, and then continues to extend with the normal advance. When it crosses the end of the search area, it still maintains the fixed starting point. When the mixing head reaches 10.05m, the grout volume to be assigned is 18.6L accumulated at each sampling interval. Then, 18.6L and its corresponding time-depth interval cumulative record, together with the candidate boundary, the current end of the boundary receiving section and the mechanical reference version, are locked for the next step to continue to call.

[0086] III. In the boundary receiving section, maintain controlled drill bit rotation speed and drilling speed, perform sequential flow detection, and form a grouting state sequence based on pressure response. Specific implementation is as follows:

[0087] After the candidate boundary is frozen and the boundary acceptance section is established, the on-site construction controller uses the construction direction locked when the candidate boundary is frozen to continuously obtain the drill bit speed, mixing head depth, grouting pressure and grouting flow rate within the boundary acceptance section. The drill bit speed is taken as the actual speed measurement value of the power head or drill rod, in revolutions per minute. The advance speed is obtained by dividing the depth change of two adjacent effective mixing head depth sampling values ​​along the locked construction direction by the corresponding actual time interval. Positive values ​​are taken along the locked construction direction, and reverse movement does not meet the controlled conditions.

[0088] The allowable range of drill bit rotation speed is the intersection of the allowable range of the current grouting section locked construction parameters and the allowable range of the piling machine continuous operation. The allowable range of the drilling speed is determined according to the same diameter. After the candidate boundary is frozen, the current grouting section range is still used, and the construction parameters of the next grouting section are not switched in advance. If there is no intersection, this step of detection is not performed.

[0089] Each round of sequential flow detection begins from the first low flow stage and ends at the second low flow stabilization window. After completing the predetermined time alignment and noise reduction, all valid sampled values ​​of drill bit rotation speed and drilling speed should be within the corresponding allowable range. Values ​​equal to the range boundary are still considered controlled. If any valid sampled value exceeds the allowable range, then the slurry-receiving state sequence item will not be formed in that round.

[0090] When a single field of drill bit speed or agitator depth is missing for a short period of time, it shall be continuously supplemented according to adjacent valid values ​​only if the duration of the missing measurement does not exceed the upper limit of the lock-up supplementation and there are valid original records before and after the gap. It shall not cross the boundary of flow rate switching, drill bit stoppage, construction direction change and detection cycle. If both drill bit speed and agitator depth are missing or there are records that cannot be supplemented, the current cycle shall be terminated. The established slurry state sequence shall remain unchanged. After the controlled conditions are met again and the lock-up period is reached, the cycle shall restart from the first low flow rate. Local records of the failed cycle shall not be spliced.

[0091] After the drill bit speed and drilling speed meet the controlled conditions, sequential flow detection is performed. Sequential flow detection directly inherits the low flow rate setting value, high flow rate setting value, low flow rate-high flow rate-low flow rate execution sequence, target flow rate allowable zone, stable window maintenance rule, allowable pressure fluctuation, allowable pressure drift, minimum distinguishable flow rate difference, and allowable recovery difference locked when the grouting benchmark of the current grouting section is formed in step 1. The above parameters are not re-formed in this step. The maximum allowable maintenance period, maximum single-round detection drilling length, minimum interval between adjacent detection rounds, maximum detection rounds, and allowable detection length of the boundary acceptance section for each flow rate stage are directly given by the version of sequential flow detection parameters formed before construction. This version is formed and locked under the premise of simultaneously meeting the constraints of stable grouting time of the grout pump, pile driver depth measurement error, predetermined pile depth resolution scale, and workable length of the boundary acceptance section. It cannot be temporarily recalculated or replaced during operation.

[0092] The construction controller first obtains the first low-flow stable grouting pressure and stable grouting flow, then obtains the high-flow stable grouting pressure and stable grouting flow, and then obtains the second low-flow stable grouting pressure and stable grouting flow. If a stable window cannot be formed even after each flow stage reaches the maximum allowable holding period, the detection round is terminated.

[0093] Records that do not enter the stable window during flow switching are retained only as their original values ​​and do not participate in the formation of pressure response; the current cycle is also terminated when the grouting pressure reaches the upper limit of the allowable range, the grout pump cannot enter the target flow allowable range, or the pressure or flow measurement fails.

[0094] The depth of the mixing head from the start of the first low flow stage to the end of the second low flow stabilization window constitutes the detection range of this round. The length of this range along the locked construction direction shall not exceed the maximum detection advance length of a single round locked by the same flow detection parameter version; if it exceeds this, even if all three flow stages form a stabilization window, this round will not enter the slurry-receiving state sequence.

[0095] Adjacent sequential flow detection rounds are executed sequentially. After the previous round ends, the mixing head continues to advance normally along the locked construction direction until the minimum interval position locked by the sequential flow detection parameter version is reached after the previous round ends at the previous round's termination depth. Only when the drill bit rotation speed and advance speed meet the controlled conditions again can the next round begin. The starting depth of the next round must not fall into the detection range occupied by the previous round.

[0096] A round is considered a valid detection round if the three flow stages in the same round all reach stable values, the drill bit speed and advance speed are controlled throughout the process, the actual high and low flow rate changes are greater than the minimum distinguishable flow rate difference, the absolute difference between the second low flow rate stable grouting pressure and the first low flow rate stable grouting pressure does not exceed the allowable recovery difference, and the single-round detection occupancy range does not exceed the maximum detection advance length.

[0097] For each effective detection cycle, the arithmetic mean of the first low-flow stable grouting pressure and the second low-flow stable grouting pressure is taken, and the pressure change is obtained by subtracting this average value from the high-flow stable grouting pressure. The arithmetic mean of the first low-flow stable grouting flow rate and the second low-flow stable grouting flow rate is taken, and the flow rate change is obtained by subtracting this average value from the high-flow stable grouting flow rate. The pressure change is then divided by the flow rate change as the grouting response value for that cycle. At the same time, the absolute difference between the second low-flow stable grouting pressure and the first low-flow stable grouting pressure is recorded as the low-flow recovery difference. The pressure and flow rate units of the grouting response value are kept consistent with those in step 1 throughout the entire pile.

[0098] Each valid detection round corresponds to one item in the grouting state sequence. This item is associated with the detection round, starting depth, ending depth, stable grouting pressure in three stages, stable grouting flow rate, grouting response value, low flow recovery difference, minimum and maximum actual drill bit rotation speed in this round, minimum and maximum actual drilling speed, version of allowable drill bit rotation speed, version of allowable drilling speed, and version of candidate boundary freezing. The items are arranged according to the actual completion order of the detection rounds along the locked construction direction, and are not forcibly sorted according to the depth value. Therefore, the same sequence caliber is used for both drilling and hoisting operations.

[0099] If any round fails due to excessive speed, excessive pressure, unstable flow, inability to recover from low flow, inability to make up for missing measurements, or excessive single-round advance, only the original record of that round is saved and not written into the grouting state sequence. Subsequent rounds may not use the local stage of that round for splicing. Only one valid sequence record can be formed for the same station number, candidate boundary freezing version, and detection round. Duplicate records are only fully written into the sequence formation the first time.

[0100] The slurry-receiving state sequence only allows new valid detection rounds to be added at the end, without modifying locked sequence items; once the minimum number of valid sequence items locked before commencement is reached, it is set to a callable state for the next stage to read; if the minimum number is not reached, it remains incomplete; if the maximum number of detection rounds is reached or the allowable detection length of the boundary acceptance section is still insufficient, no subsequent judgment result is formed.

[0101] The grout volume to be assigned established in step 2 continues to be accumulated according to its locked sampling interval accumulation rule during the execution of this step. During the low flow and high flow switching period of this step, the grout that actually passes through the fixed grouting flow measurement position will continue to be included in the grout volume to be assigned. This step does not change the final assignment of the grout volume.

[0102] When on-site communication is interrupted, the original records of each round, the round order, and the cumulative record of the slurry volume to be assigned are maintained locally. After the communication is restored, the records are submitted according to the original sampling time. Rounds whose sequence cannot be confirmed must not be written into the slurry receiving status sequence.

[0103] During the review, the stable values ​​of each stage are re-obtained according to the locked rounds, and the slurry response value and low flow recovery difference are re-formed. The difference between the result and the corresponding item in the sequence should be within the allowable range formed by sensor measurement error and recording rounding error; otherwise, the sequence item shall not be called as a valid item.

[0104] Preferably, in a set of representative working conditions, the allowable range of drill bit rotation speed is 36 r / min to 40 r / min, the allowable range of drilling speed is 0.45 m / min to 0.55 m / min, the low flow rate is set to 55 L / min, the high flow rate is set to 75 L / min, each flow rate stage is maintained for 5 seconds, the maximum detection footage length per round is set to 0.15 m, the minimum interval between adjacent rounds is set to 0.05 m, and the minimum number of effective sequence items is set to 3; three rounds of effective detection are continuously completed within the boundary acceptance section, with the first round consisting of three stages. The stable grouting pressures were 0.40 MPa, 0.52 MPa, and 0.40 MPa for the first round, 0.41 MPa, 0.57 MPa, and 0.42 MPa for the second round, and 0.43 MPa, 0.62 MPa, and 0.43 MPa for the third round. The drill bit speed and drilling speed in each round were within the locked allowable range. The high and low flow rate changes all exceeded the minimum distinguishable flow rate difference, and the low flow rate recovery met the requirements. Based on this, the construction controller generated three grouting status records, which were then arranged into a callable grouting status sequence according to the actual construction sequence.

[0105] IV. When the drill string load remains on the same side of the mechanical reference within the mechanical stability observation window and the range does not exceed the mechanical stability fluctuation limit, a stable state is formed after the drill string load deviates from the mechanical reference; when the continuous effective slurry-receiving state sequence items remain in the same deviating direction, the low flow recovery difference does not exceed the recovery boundary, and the span of the slurry-receiving response value does not exceed the slurry-receiving stability fluctuation limit, a stable state is formed after the slurry-receiving state sequence deviates from the slurry-receiving reference; the starting point of the construction section where the two stable states overlap along the locked construction direction is taken as the effective segment boundary, specifically implemented as follows:

[0106] Once the grouting state sequence reaches the callable state, the on-site construction controller reads the mechanical reference, grouting reference, continuous record of drill string load after the candidate boundary, record of all sequential flow detection cycles, and grouting state sequence associated with the same pile number, the same current grouting section, and the same candidate boundary freezing version. The mechanical reference and grouting reference continue to use the aforementioned locked version and are not re-formed in this step.

[0107] First, the stable state is determined based on the record after the drill string load leaves the mechanical reference. The recognized departure direction must inherit the departure direction in the candidate boundary freeze record. When the candidate boundary is formed by upward departure, only the drill string load record above the upper boundary of the mechanical reference is used. When the candidate boundary is formed by downward departure, only the drill string load record below the lower boundary of the mechanical reference is used. For departure in the opposite direction, only the original record is retained and it does not participate in the formation of the stable state of this candidate boundary.

[0108] When detaching upwards, the upper boundary of the mechanical reference is used as the corresponding mechanical reference boundary; when detaching downwards, the lower boundary of the mechanical reference is used as the corresponding mechanical reference boundary. The difference between each effective drill string load participating in the stability judgment and the corresponding mechanical reference boundary must be greater than the maximum absolute measurement error in the effective calibration record of the current drill string load measurement channel.

[0109] The mechanical stability observation window uses the number of valid sampling points locked before pile driving. The first window is established starting from the valid sampling point corresponding to the candidate boundary according to the sampling time. If the condition is not met, the window is re-established by moving one valid sampling point along the locked construction direction each time. If there is a window that cannot be filled in the missing measurements, the window becomes invalid and restarts from the first valid sampling point after the missing measurements are completed.

[0110] The number of valid sampling points and their corresponding minimum advance lengths included in the mechanical stability observation window shall not be less than the number and advance threshold used in the continuous departure judgment in step 2. All drill string loads within the window shall always be located on the same side of the mechanical reference corresponding to the candidate boundary, satisfying the aforementioned measurement error margin. Furthermore, the range obtained by subtracting the minimum value from the maximum value of the drill string load within the window shall not exceed the mechanical stability fluctuation limit.

[0111] The mechanical stability fluctuation limit is formed based on the drill string load records of the low flow stability window used to determine the lower boundary, upper boundary, and center value of the mechanical reference after the retention ratio was selected when the mechanical reference was formed in step 1. The retained records are restored in chronological order according to the original sampling time. Reference windows are established only within the same original low flow stability window using the same number of effective sampling points as the mechanical stability observation window. Each reference window is shifted one retained continuous effective sampling point, without crossing the breakpoints, flow stage boundaries, or detection round boundaries formed by the rejected records. The difference between the maximum and minimum drill string loads in each reference window is obtained. The maximum range obtained from all effective reference windows is added to the maximum absolute measurement error of the current drill string load as the mechanical stability fluctuation limit. If the available reference records after the retention ratio selection are insufficient to form a complete reference window, this version of the mechanical reference shall not be used in this step.

[0112] The observation window that first meets the above conditions forms the stable state after the drill string load is removed from the mechanical reference. The depth corresponding to the first valid sampling point of this window is taken as the starting depth of the mechanically stable state. Subsequently, windows of the same size are used for inspection, each shifted by one valid sampling point. When a window fails to maintain the candidate boundary departure direction, fails to meet the measurement error margin, or the range exceeds the mechanical stability fluctuation limit for the first time, the mechanically stable state terminates at the depth corresponding to the last valid sampling point before the first valid sampling point of the unqualified window. The depth range of the mechanically stable state is formed from the starting depth to the ending depth.

[0113] Subsequently, the stable state is determined based on the records after the grouting state sequence deviates from the grouting reference. The grouting reference continues to use the lower boundary, upper boundary, and recovery boundary of the grouting reference. For each grouting state sequence item, the allowable deviation of the grouting response is first formed according to the pressure and flow measurement diameter locked in step 3. Specifically, based on the original measured values ​​of the three stable grouting pressures and three stable grouting flows of the sequence item, the error limit is determined according to the maximum absolute measurement error of the corresponding sensor. When the highest possible grouting response value is obtained, the high-flow stable grouting pressure is adjusted towards the limit of increasing pressure change, the two low-flow stable grouting pressures are adjusted towards the limit of decreasing pressure change, and the high-flow stable grouting flow and the two low-flow stable grouting flow are adjusted towards the limit of decreasing flow change while still maintaining a positive value. When the lowest possible grouting response value is obtained, the adjustment is carried out in the opposite direction, and the calculations are performed separately according to the exact same formation sequence as the grouting response value in step 3. If any combination of error limits results in a flow rate change of no more than 0, the sequence item shall not form an allowable deviation in slurry response and shall be transferred to on-site verification; otherwise, the maximum absolute difference between the highest and lowest slurry response values ​​and the original slurry response value of the sequence item shall be taken as the allowable deviation in slurry response of the item.

[0114] When the slurry response value is higher than the upper boundary of the slurry reference and the excess exceeds the allowable deviation of the slurry response, it is recorded as upward detachment; when it is lower than the lower boundary of the slurry reference and the excess exceeds the allowable deviation of the slurry response, it is recorded as downward detachment. When it is equal to the boundary, within the reference range, or the excess does not exceed the allowable deviation, the detachment condition is not met. The low flow recovery difference of this sequence item should also not exceed the recovery boundary of the slurry reference.

[0115] The slurry stability fluctuation limit is formed by the slurry response values ​​actually used to determine the lower and upper boundaries of the slurry reference after being screened by the retention ratio when forming the slurry reference in step 1. The reference response span is obtained by subtracting the minimum value from the maximum value among the retained slurry response values. Then, the allowable deviation of the slurry response formed by the qualified detection rounds corresponding to these retained slurry response values ​​according to the same error caliber is obtained. The maximum allowable deviation of the slurry response is taken and the reference response span together to form the slurry stability fluctuation limit. The slurry response values ​​that did not participate in the formation of the slurry reference boundary after being sorted and eliminated in step 1 are not included in the formation of the slurry stability fluctuation limit in this step.

[0116] When the number of consecutive valid grouting state sequence items that are pre-locked are kept in the same detachment direction, the low flow recovery difference of each item does not exceed the recovery boundary, and the difference between the maximum and minimum values ​​of the grouting response values ​​of the consecutive sequence items does not exceed the grouting stability fluctuation limit, a stable state is formed after the grouting state sequence is detached from the grouting reference. The continuity is judged according to the original execution order of all detection rounds in step 3. When there is a failed detection round between two valid sequence items, the record cannot be completed, or the construction is interrupted, the continuous count is immediately cleared to zero and does not continue to accumulate across that round.

[0117] In the earliest consecutive sequence of items that meet the conditions, the starting depth of the first probe's occupied interval is taken as the starting depth of the grouting stable state, and the ending depth of the last probe's occupied interval is taken as the end of the current grouting stable state. When subsequent valid sequence items continue to meet the same-direction separation, recovery boundary, and grouting stability fluctuation limit, the end of the state extends to the ending depth of the newly added sequence item. When a probe round that does not meet the conditions appears for the first time, the grouting stable state terminates at the ending depth of the last sequence item that meets the conditions before that round. After the grouting stable state terminates, the next grouting stable state is searched again from the first valid complete probe round after the failed probe round, so that one or more mutually separated grouting stable state depth intervals can be formed along the construction direction.

[0118] After the mechanically stable state depth range and the grout-stable state depth range are formed, they are uniformly mapped to the same pile depth construction range according to the locked construction direction. The overlapping construction range that is simultaneously covered by the two in the actual construction direction is taken. When there is an overlapping construction range, the depth that appears after the locked construction direction from the mechanically stable state starting depth and the grout-stable state starting depth is taken as the starting point of the overlapping construction range, and this starting point is determined as the effective segment boundary.

[0119] The drilling sequence is determined based on the actual drilling sequence, and the lifting sequence is determined based on the actual lifting sequence. The larger or smaller value is not directly taken from the depth value.

[0120] A valid segment boundary must simultaneously meet the following requirements: it must be located after or coincide with the frozen candidate boundary along the construction direction, within the already formed boundary acceptance section, and the separation direction of the mechanically stable state must be consistent with the separation direction when the candidate boundary is frozen. If any condition is not met, the boundary position will not be manually corrected, and a valid segment boundary will not be formed in this round.

[0121] When two stable state depth intervals do not overlap, the candidate boundary remains frozen, and existing records retain their original versions. After any mechanically stable state or grout-stable state terminates, the next stable state is searched again from the first valid record after the corresponding failure position. As the boundary acceptance section extends and new callable records are added, the same rules continue to be applied. When there are multiple mechanically stable state depth intervals and multiple grout-stable state depth intervals, the set of states that first form overlapping construction intervals is selected according to the locked construction direction, and the valid segment boundary is determined according to the rules in line 80.

[0122] The maximum advance range is calculated along the construction direction starting from the frozen candidate boundary. Its termination position is the position corresponding to the construction length confirmed by the maximum boundary locked before construction and the position reached first along the construction direction from the starting point of the next design soil layer interface search area. If no overlapping construction section is formed when the position is reached, the effective segment boundary is not forcibly determined, and the existing records are retained and transferred to the site for verification.

[0123] The current step's judgment parameter version consists of the number of valid sampling points in the mechanical stability observation window, the corresponding minimum advance length, the mechanical stability fluctuation limit, the allowable deviation of the slurry response forming diameter, the slurry stability fluctuation limit, the number of continuous slurry state sequence items, and the maximum judgment advance range. This parameter is locked before the first execution of this step's judgment and cannot be modified or overwritten during the judgment period.

[0124] After the effective segment boundary is formed for the first time, the effective segment boundary depth, construction direction, candidate boundary depth, candidate boundary separation direction, mechanical stability state start depth and end depth, grouting stability state start depth and end depth, overlapping construction interval, mechanical reference version, grouting reference version, candidate boundary freezing version, and current judgment parameter version are written into the current pile construction record. Only the first fully formed effective segment boundary record is accepted for the same pile number and candidate boundary freezing version. Subsequent results should only leave traces and should not be overwritten.

[0125] This step only determines the effective segment boundaries and does not change the amount of slurry to be assigned that is continuously accumulated in step 2.

[0126] Before the effective segment boundary is called by the next step, the above formation process is re-executed using the locked mechanical reference, grouting reference, original drill string load record after the candidate boundary, all exploration round records in step 3, and the current judgment parameter version. The newly obtained mechanical stability state starting depth, grouting stability state starting depth, and effective segment boundary should all be consistent with the locked record. If they are inconsistent, the boundary should not be set to the callable state. The callable state is only a data validity indicator of the effective segment boundary, indicating that the boundary can be temporarily used for grout volume division and control calculation in step 5. Its business status remains pending confirmation until it is converted to the submitted or withdrawn status in step 6.

[0127] Preferably, in a set of representative working conditions, the mechanical reference is 78A to 84A, the candidate boundary is 9.82m with the departure direction upward, the maximum absolute measurement error of the drill string load is 1A, the mechanical stability observation window corresponds to a continuous advance of 0.10m, the mechanical stability fluctuation limit is 5A, and the drill string load continuously meets the stability conditions from 9.94m in the range of 89A to 93A, thus forming a mechanically stable depth range starting from 9.94m; the slurry receiving reference is 0.0065MPa / (L / min) to 0.0072MPa / (L / min), the recovery boundary is 0.02MPa, and the slurry receiving response values ​​of three consecutive slurry receiving state sequences are 0.0083MPa / (L / min), 0... The allowable deviations of the grouting response for 0.0085 MPa / (L / min) and 0.0084 MPa / (L / min) are all less than the difference between the grouting reference upper boundary and the low flow recovery difference. The span of the three grouting response values ​​does not exceed the grouting stability fluctuation limit. The first detection interval starts at 10.02 m, thus forming a grouting stability depth interval starting at 10.02 m. This grouting stability interval overlaps with the mechanical stability interval after 9.94 m. Therefore, the 10.02 m that appears after drilling is taken as the starting point of the overlapping construction interval and determined as the effective segment boundary. This interval, along with the two stability intervals and each locked version, is written into the current pile construction record.

[0128] V. Divide the grout volume to be assigned according to the effective segment boundary and include it in the corresponding grouting segment. Subtract the confirmed grout volume from the target grout volume of the next grouting segment to generate the remaining target grout volume. Control the pumping and advance. The specific implementation is as follows:

[0129] After the effective segment boundary is set to the callable state, the on-site construction controller reads the effective segment boundary associated with the same station number and the same candidate boundary frozen version, the grout volume to be assigned in the complete state and the cumulative record of each sampling interval, and reads the grout volume and construction parameter record corresponding to the next grouting section in the current construction design version; first, the grout volume to be assigned is divided according to the effective segment boundary.

[0130] When the effective segment boundary corresponds to the original drill bit load sampling point or the starting record of the slurry state sequence detection formed in step 4, the unified clock sampling time of the original record is directly used as the corresponding time of the effective segment boundary. When the effective segment boundary is located between two adjacent effective mixing head depth sampling points and there are no original sampling points with completely identical depths, after confirming that the mixing head maintains the same construction direction between the two sampling points and there is no drilling stop or reverse movement, the corresponding time of the effective segment boundary is continuously determined within the corresponding actual time interval according to the proportion of the depth change of the two sampling points to the total depth change. When there is drilling stop, reverse movement, or the depth record cannot be completed, the corresponding time of the boundary shall not be automatically determined.

[0131] The amount of grout to be assigned that is actually measured at the fixed grouting flow measurement position before the effective segment boundary time is included in the current grouting segment, and the amount of grout to be assigned that is actually measured from that time onwards is included in the next grouting segment; when the mixing head stops at the effective segment boundary and continues to supply grout, the amount of grout measured after the boundary time is still included in the next grouting segment.

[0132] For each sampling cumulative interval that is completely located on one side of the effective segment boundary corresponding to the time, the grout volume of the interval is directly included in the corresponding grouting segment. When the effective segment boundary corresponding to the time is located inside a certain cumulative interval, the original cumulative interval is split into two time intervals before and after the time. The sampling values ​​of two adjacent effective grouting flow rates change linearly with time. The grouting flow rate at the boundary time is obtained by linear interpolation of the flow rate values ​​at both ends and the corresponding time of the boundary. Then, the grout volume of the two sub-intervals before and after the boundary is calculated by multiplying the arithmetic mean of the adjacent flow rates, which is consistent with step 2, by the cumulative caliber of the corresponding actual time interval, and included in the corresponding grouting segment. The same cumulative interval is not allowed to be repeatedly assigned.

[0133] After all divisions are completed, the grout volume included in the current grouting section is added to the grout volume included in the next grouting section, and compared with the grout volume to be assigned in this division. Based on the flow measurement error calibrator given in the fixed flow measurement position calibration record, the flow measurement error of each participating division interval is converted into the cumulative grout volume allowable error according to the corresponding actual duration and accumulated interval by interval. Then, it is combined with the record rounding error to form the allowable difference value for grout volume conservation in this division. If the difference between the two exceeds the allowable difference value, the grout volume assignment result for this division is not submitted.

[0134] Since construction may continue after the effective segment boundary is determined, when the grout volume is divided, the end time of the latest effective grout volume cumulative interval that has been fully written into the on-site construction controller is taken as the end time of the grout volume settlement. The grout volume that is still in the pending assignment state before this time is frozen for the above division. The newly formed complete effective grout volume record after the grout volume settlement end time is directly included in the next grouting segment according to the determined effective segment boundary, and is no longer included in the grout volume to be assigned in this time.

[0135] When the volume of slurry to be assigned is incomplete, the effective segment boundary cannot be called, the boundary corresponding time cannot be uniquely obtained, or the participating interval lacks a complete time-depth correspondence, the original record is maintained, and the assignment is not completed by using average flow rate or manual estimation.

[0136] After the division is completed, the unique record of the cumulative interval, the grouting section to which it belongs, the grout volume included, the effective segment boundary version, and the grout volume settlement deadline will be associated and saved. The original grout volume to be assigned and the original cumulative record shall not be overwritten. The same cumulative interval can only be included once under the same effective segment boundary version.

[0137] The next grouting segment starts from the effective segment boundary along the locked construction direction and terminates at the termination position of the grouting segment in the current construction design version; if there is no subsequent design boundary position, it terminates at the design construction end point of this pile, and this termination position remains locked during the control of the remaining target grout volume.

[0138] When the construction design specifies the target grout volume per unit advance, the target grout volume for the next grouting segment is formed by the construction length from the effective segment boundary to the termination position of the next grouting segment corresponding to that target grout volume per unit advance. When the construction design only specifies the total target grout volume for the original grouting segment, the target grout volume per unit advance is formed only when the construction design, locked construction parameters, or grout volume control record corresponding to that grouting segment clearly indicate that the total target grout volume is evenly distributed according to the original grouting segment length. Then, the target grout volume for the next grouting segment is formed by combining the total target grout volume and the original grouting segment length. Standard grout volume; if uniform distribution by length is not explicitly permitted, it shall not be automatically converted to uniform volume. If the construction design has given the grout volume distribution rules after the segment boundary adjustment, the target grout volume for the next grouting segment shall be formed according to the rules. If neither uniform distribution nor grout volume distribution rules after boundary adjustment are explicitly given, this step shall not automatically form the target grout volume for the next grouting segment, nor generate new remaining target grout volume and pumping advance control records. The valid segment boundaries and the formed grout volume records shall be retained and transferred to the construction design for review. Only when the construction design explicitly stipulates that the total target grout volume remains unchanged after the segment boundary adjustment shall the original locked total target grout volume be directly adopted.

[0139] When the construction design uses the grout quality caliber, the grout density corresponding to the grout mix ratio locked before the start of the next grouting section is converted into a volume caliber consistent with the fixed flow measurement position. Once the target grout volume is formed, it cannot be modified in reverse by subsequent fluctuations in grout density.

[0140] The confirmed grout volume is limited to the total volume of grout that has been actually measured by the fixed grouting flow measurement location, has a complete and valid source record, and uniquely belongs to the next grouting segment from the time corresponding to the effective segment boundary to the current calculation time. This includes the grout volume to be assigned to the next grouting segment in this instance, as well as the actual grout volume directly included in the next grouting segment after the grout volume settlement deadline. Pumping setpoints, theoretical grout supply, estimated quantities for non-recoverable missing measurement intervals, and grout volumes already assigned to other grouting segments are not included.

[0141] The remaining target grout volume is generated by subtracting the confirmed grout volume from the target grout volume for the next grouting section. When the difference is greater than 0, the actual difference is used. When the difference is equal to or less than 0, the remaining target grout volume is set to 0, and the actual grout volume exceeding the target grout volume is retained separately. The allowable difference for grout volume control is formed by the minimum verifiable grout volume at the fixed flow measurement position and the rounding accuracy of the record. The minimum verifiable grout volume is the minimum cumulative grout volume that can be distinguished at the fixed flow measurement position within one minimum effective cumulative interval. When the equipment provides cumulative volume resolution, this resolution is used directly. When the equipment only provides flow measurement resolution, it is converted according to this resolution and the minimum effective cumulative time period. When the remaining target grout volume is not greater than the allowable difference for grout volume control, the continued adjustment for the purpose of supplementing the target grout volume can be stopped, but the original calculated difference is still retained.

[0142] Subsequently, the remaining construction length from the current position of the mixing head to the end position of the next grouting section along the locked construction direction is obtained; when the remaining construction length is greater than 0 and the remaining target grout volume exceeds the allowable difference in grout volume control, the remaining target grout volume is used to form the subsequent unit advance grout volume requirement according to the remaining construction length, and the pumping and advance are controlled accordingly.

[0143] The permissible pumping flow rate range is the common range of the permissible flow rate range of the next grouting section's construction parameters, the continuous stable operating range of the grout pump, the permissible flow rate range of the grout delivery pipeline, and the permissible grout supply range corresponding to the upper limit of the grouting pressure. Boundary values ​​can be used. The controller first uses the current effective advance speed as the candidate advance speed, multiplies the subsequent unit advance grout volume requirement by this candidate advance speed, and performs unit conversion to obtain the target pumping flow rate. If the obtained target pumping flow rate is within the permissible range, the current advance speed is maintained and this pumping flow rate is used. If the target pumping flow rate exceeds the permissible upper limit, the permissible upper limit flow rate is used, and then this limited flow rate is divided by the subsequent unit advance grout volume requirement and the unit is converted to obtain the corresponding advance speed. If the target pumping flow rate is lower than the continuous stable lower limit, the continuous stable lower limit flow rate is used, and the corresponding advance speed is obtained according to the same reverse conversion caliber. The adjusted advance speed must still be within the locked permissible range of the next grouting section. If there is no combination that can simultaneously meet the unit advance grout volume requirement, the permissible pumping flow rate range, and the permissible advance speed range, normal advance with excessive parameters will not continue, and the current remaining target grout volume will be retained.

[0144] When the remaining construction length is equal to 0 and the remaining target grout volume still exceeds the allowable difference in grout volume control, no unit advance grout volume and corresponding pumping-advance control relationship shall be formed, and grout shall not be continuously supplied to make up the remaining target grout volume while the position of the mixing head remains unchanged. The actual difference shall be retained and transferred to the on-site construction for handling.

[0145] If the remaining target grout volume is 0 and there is still construction length remaining in the next grouting section, and the construction design allows grouting to be stopped after the target grout volume is completed, no new pumping volume will be generated based on the remaining target grout volume; if the construction design requires maintaining a minimum continuous grout supply, construction will continue according to the locked minimum allowable grout supply volume, and the actual grout volume thereafter will be registered as the actual grout volume exceeding the target grout volume, while the remaining target grout volume will remain 0.

[0146] During construction, for each new complete and effective grout volume accumulation interval formed, the confirmed grout volume of the next grouting section is updated first, then the remaining target grout volume and remaining construction length are re-formed, and finally the pumping and advance control records are updated. The effective segment boundary version, the grout volume settlement deadline, and the construction design version jointly determine the current grout volume settlement record. The confirmed grout volume shall not be updated before the assigned grout volume division and total quantity verification are completed. The new remaining target grout volume shall not be formed before the confirmed grout volume is updated. The pumping and advance control shall not be updated before the new remaining target grout volume is formed. When the same settlement record is executed repeatedly, only recalculation and verification are performed, and no repeated accumulation is performed.

[0147] If a new complete slurry volume record is generated before the control record is officially adopted, the slurry volume should be included in the confirmed slurry volume and the remaining target slurry volume should be recalculated before updating the control record.

[0148] When using equipment that can simultaneously provide calibrated cumulative pump volume and mixing head depth, the difference between adjacent cumulative pump volumes can be used to form the actual slurry volume for each interval, instead of the interval slurry volume formed by the cumulative grouting flow rate. However, the fixed metering position, unified time reference, effective segment boundary corresponding time, and grouting segment attribution rules remain unchanged.

[0149] Preferably, in a set of representative working conditions, the effective segment boundary is 10.02m. Before the deadline for this grout volume settlement, the total grout volume to be assigned is 36.0L. After segmenting, 21.5L is included in the current grouting segment, and 14.5L is included in the next grouting segment. The sum of the two is consistent with 36.0L. The adjusted construction length of the next grouting segment is 6.0m, and the target grout volume per unit advance is 70L / m. Therefore, the target grout volume for the next grouting segment is 420L. After the deadline for grout volume settlement, an additional 35L is actually measured and directly included in the next grouting segment. Therefore, the grout volume has been confirmed. The current grout volume is 49.5L, and the remaining target grout volume is 370.5L. When the current remaining construction length is 5.7m, the subsequent unit advance grout volume requirement is 65L / m. When the current effective advance speed is 0.50m / min, the corresponding pumping flow rate is 32.5L / min. This flow rate is within the locked allowable pumping flow rate range, so the advance speed of 0.50m / min is maintained and pumping continues at 32.5L / min. Subsequently, the confirmed grout volume, remaining target grout volume, and subsequent pumping and advance control records are updated sequentially according to each newly formed complete grout volume accumulation interval.

[0150] VI. Perform sequential flow detection in the next grouting section. If the grouting response maintains a stable state in that section, submit a valid segment boundary; otherwise, cancel the boundary, rebuild the boundary receiving section, and write back the control status. The specific implementation is as follows:

[0151] After the effective segment boundary is formed and pumping and advance control for the next grouting section are initiated in step 5, the operational status of this effective segment boundary remains pending confirmation. New sequential flow rate detection records are obtained in the next grouting section. The effective position of the first effective pumping and advance control record in step 5 is determined by the depth corresponding to the first effective sampling point after the new pumping flow rate and new advance speed have actually entered the target allowable range of step 5, as confirmed by the on-site construction controller. The subsequent confirmation starting point is the position that appears after locking the construction direction, between the termination position of the last effective detection round involved in the formation of the grouting stability state during step 4 when the effective segment boundary is formed and the effective position of the first effective pumping and advance control record in step 5. The starting position of each detection round used for subsequent confirmation must be after this subsequent confirmation starting point; detection rounds already involved in the formation of the effective segment boundary must not be reused.

[0152] The sequential flow detection performed in the next grouting section will continue to use the low-flow-high-flow-low-flow sequence locked in step 3, the low-flow setpoint, the high-flow setpoint, the target flow allowable band, the stability window, the allowable pressure fluctuation, the allowable pressure drift, the minimum distinguishable flow difference, the allowable recovery difference, the maximum detection advance length per round, the minimum interval between adjacent detection rounds, and the maximum allowable holding time for each flow stage, without reselecting the detection flow rate; if the originally locked low or high flow rate does not fall within the allowable range of the construction parameters for the next grouting section, the continuous and stable operating range of the grout pump, the allowable range of the grout delivery pipeline, and the common range of the grout supply range corresponding to the upper limit of the grouting pressure, a valid confirmation round will not be formed under the current conditions, and alternative detection will not be formed by changing the flow setpoint.

[0153] During the sequential flow detection, the detection flow command temporarily replaces the conventional pumping flow command formed in step 5 based on the remaining target slurry volume. The drill bit speed and advance speed remain within the allowable range locked in the next grouting section. In each round, stable grouting pressure and stable grouting flow are obtained sequentially for the first low flow, high flow, and second low flow. The slurry response value and low flow recovery difference are formed according to the same diameter as in step 3. A round is considered a valid confirmation round when all three stages are stable, the actual high and low flow changes exceed the minimum distinguishable flow difference, the low flow recovery difference does not exceed the allowable recovery difference, the drill bit speed and advance speed do not exceed the limits, and the detection occupied interval does not exceed the maximum detection advance length of a single round.

[0154] If any stage becomes unstable, measurement gaps cannot be filled, speed exceeds limits, or detection space exceeds limits, that round is recorded as a failed round. Only the record is retained, and the continuous confirmation count is reset to zero. The count restarts from the next valid complete round. It is not considered evidence of a change in the grouting state, nor can it be spliced ​​with the previous and subsequent rounds. When the detection ends and the effective segment boundary is still in a state of pending confirmation, only the detection grout volume interval with complete and valid flow accumulation records is included in the confirmed grout volume of the next grouting segment according to the caliber of step 5, and the remaining target grout volume is updated. The interval with unfillable grouting flow gaps remains in an incomplete state and cannot be included in the confirmed grout volume. After the above grout volume update is completed, regular pumping and advance control are resumed.

[0155] The stable state of this segment is fixed by using the continuous effective sequence items that actually participated in the formation of the slurry-receiving stable state when the effective segment boundary was first formed in step 4 as the reference record. The slurry-receiving reference separation direction, each slurry-receiving response value, slurry-receiving stability fluctuation limit, slurry-receiving reference recovery boundary and slurry-receiving response allowable deviation of this set of records are locked. New records added after step 4 shall not change this reference record.

[0156] The number of consecutive valid confirmation rounds required in step 6 is directly taken from the minimum number of consecutive valid sequence items locked when forming the slurry-receiving stable state in step 4. Each valid confirmation round is compared with the slurry-receiving reference according to the allowable deviation of the slurry-receiving response in step 4. When the original stable state is upward detachment, the new slurry-receiving response value should continue to be higher than the upper boundary of the slurry-receiving reference and the excess should be greater than the corresponding allowable deviation of the slurry-receiving response. When the original stable state is downward detachment, it should continue to be lower than the lower boundary of the slurry-receiving reference and the excess should be greater than the corresponding allowable deviation of the slurry-receiving response. At the same time, the low flow recovery difference should not exceed the recovery boundary of the slurry-receiving reference.

[0157] The original stable state reference record is arranged together with the current consecutive valid confirmation rounds. The difference between the maximum and minimum values ​​of all slurry response values ​​is taken. If the difference does not exceed the slurry stability fluctuation limit and all consecutive valid confirmation rounds maintain the original deflection direction and recovery conditions, the slurry response is considered to have maintained the stable state of that segment. If the continuous confirmation is interrupted due to a failed round, the counting starts again from the next valid complete round. The new set is only compared with the original stable state reference record and the consecutive confirmation rounds after the restart, and the confirmation rounds before the interruption are not continued to be included.

[0158] If the slurry response value of any valid confirmation round re-enters the slurry reference range, moves to the other side of the slurry reference, is located on the original detachment side but exceeds the allowable deviation of the slurry response, the low flow recovery difference exceeds the recovery boundary, or the span of the aforementioned slurry response value exceeds the slurry stability fluctuation limit after the addition of this round, this valid round constitutes a confirmation record of failure to maintain the stable state of this segment, and the accumulation of subsequent confirmation rounds is immediately stopped and the process is cancelled.

[0159] The maximum subsequent confirmation range starts from the subsequent confirmation starting point and ends at the position that is reached first along the construction direction between the pre-locked maximum confirmed construction length corresponding to the position and the termination position of the next grouting section; if the required number of consecutive valid confirmation rounds cannot be obtained after reaching the termination position, it is also considered that the maintenance confirmation has not been completed and the process is cancelled.

[0160] When the grouting response maintains a stable state in this segment, the effective segment boundary is submitted from the pending confirmation state to the submitted state. In step 5, the grouting segment ownership, confirmed grout volume, remaining target grout volume, and current pumping advance control based on this boundary remain effective, and the subsequent confirmation rounds, submission times, and associated versions are written into the boundary record.

[0161] If the grout response fails to maintain a stable state for that segment or fails to complete the confirmation within the maximum subsequent confirmation range, the effective segment boundary will be changed from a pending confirmation state to a revoked state, and the end time of the latest grout volume cumulative interval that has been fully written when the revocation condition is met will be used as the revocation write-back deadline. From the time corresponding to the original frozen candidate boundary in step 2 to the revocation write-back deadline, all actual measured grout volumes associated with the candidate boundary and whose attribution depends on the revoked effective segment boundary will be reset to a pending attribution state, including the grout volume between the candidate boundary that was previously assigned to the current grouting segment and the revoked effective segment boundary, the grout volume that was previously assigned to the next grouting segment, the grout volume directly included in the next grouting segment after the grout volume settlement deadline in step 5, and the grout volume included in the next grouting segment during the confirmation and detection period in step 6. The grout volume that was previously confirmed to belong to the previous grouting segment along the construction direction of the original frozen candidate boundary will not be reverted, and all original cumulative records and historical attribution records will continue to be retained and will not be accumulated repeatedly.

[0162] Subsequently, the original frozen candidate boundary in step 2 is used as the fixed starting point, and the depth of the stirring head corresponding to the cancellation and rewrite deadline is used as the end reconstruction boundary receiving section. The cancelled effective segment boundary cannot be used as a new candidate boundary or a new section starting point. The actual slurry volume newly formed after the cancellation and rewrite deadline is directly added to the slurry volume to be assigned in the reconstruction boundary receiving section.

[0163] When writing back the control status, the effective segment boundary record is set to "cancelled," the original candidate boundary remains frozen, the reconstructed boundary receiving segment is set to the current active segment, the aforementioned grout volume is restored to the pending assignment state, and the target grout volume, confirmed grout volume, remaining target grout volume, and pumping advance control records of the next grouting segment formed based on the cancelled boundary are marked as no longer used as the current control basis; at the same time, the actual pumping flow rate and advance speed of the last group before the cancellation trigger are recorded as still within the allowable range of equipment and construction. During the cancellation and write-back period, the control combination is only temporarily maintained if the last control combination is simultaneously within the common allowable range of construction parameters of the two adjacent grouting segments, the continuous and stable working range of the grout pump, the allowable range of the grout delivery pipeline, and the safe range of grouting pressure; if any condition is not met, normal advance is suspended, and the grout pump is taken over by the equipment safety protection state, and no normal pumping and advance control commands based on the cancelled effective segment boundary or the old remaining target grout volume are sent until the write-back is completed. All newly added slurry volumes with complete and valid metering records during the period prior to the completion of the write-back are included in the slurry volumes to be assigned, and equipment safety protection commands always take priority.

[0164] The pending confirmation state is only allowed to transition to the submitted or withdrawn state once. Both submitted and withdrawn states are final states. The same valid segment boundary version cannot return to the pending confirmation state again, nor can it be submitted and withdrawn at the same time. Duplicate state requests only verify the original record and do not repeatedly change the slurry volume and control status. After the withdrawal and write-back are completed, the original frozen candidate boundary and the reconstructed boundary acceptance section are used as the current acceptance state. The process then re-enters the sequential flow detection in step 3 and the subsequent valid segment boundary determination chain in step 4. Candidate boundaries are not regenerated.

[0165] Preferably, in a set of representative working conditions, the original steady-state reference grouting response values ​​locked in step 4 are 0.0083 MPa / (L / min), 0.0085 MPa / (L / min), and 0.0084 MPa / (L / min), the upper boundary of the grouting reference is 0.0072 MPa / (L / min), and the recovery boundary is 0.02 MPa, requiring 3 consecutive valid confirmation rounds; subsequently, after confirming the starting point, 3 new grouting response values ​​of 0.0084 MPa / (L / min), 0.0086 MPa / (L / min), and 0.0085 MPa / (L / min) are obtained. If the slurry response span formed by the original stable state reference record and the slurry response value of the second valid confirmed round falls back to the slurry reference range, then the valid segment boundary is submitted as submitted. If the slurry response value of the second valid confirmed round falls back to the slurry reference range, then the round forms valid counter-evidence, the valid segment boundary is immediately revoked, the boundary receiving section is reconstructed with the original frozen candidate boundary, and the slurry volume to be assigned and the current control state are restored according to the revocation and write-back deadline.

[0166] In the operational scenario shown in this embodiment: taking a cement-soil mixing pile with continuous drilling and synchronous grouting as an example, the construction design sets up a soil interface search zone between adjacent grouting sections near a pile depth of approximately 10m. Before construction, the construction design version, exploration layer records, detection parameter versions, sensor calibration records, and the allowable detection flow range for adjacent grouting sections before and after the pile have been locked. A continuous normal construction length of no less than 1.0m is maintained before the mixing head enters the search zone. The drill string load is characterized by the drive motor current. The drill string load, grouting pressure, and grouting flow rate are all uniformly recorded by the on-site construction controller according to a 10Hz rhythm. The low flow rate is set to 55L / min, and the high flow rate is set to 75L / min. The system was kept level for 5 seconds. Under the conditions of continuous slurry supply from the pump, normal drilling progress of the mixing head, and no drilling stoppage or reverse movement, three rounds of low-flow-high-flow-low-flow detection were completed. After time alignment, elimination of isolated jumps, and supplementation of short-term missing measurements within the allowable range, all three rounds of detection met the requirements of stable flow rate, pressure fluctuation, low flow recovery, and equipment safety. The construction controller formed a mechanical reference from 78A to 84A based on the drill string load record within the low flow stability window, and formed a slurry receiving reference based on the number of consecutive qualified detection rounds. The slurry receiving reference range was locked from 0.0065MPa / (L / min) to 0.0072MPa / (L / min), and the recovery boundary was locked at 0.02MPa. Thus, the reference before the search area was established.

[0167] The mixing head then entered the search area along the original construction direction. The drive motor current continuously exceeded the upper boundary of the mechanical reference by 84A starting from 9.82m. When the mixing head reached 9.93m, the same-side separation record had simultaneously met the minimum number of effective sampling points and the 0.10m continuous separation advance threshold. Therefore, the on-site construction controller did not use 9.93m as the boundary, but instead traced back to the first effective sampling point of the continuous separation sequence, freezing 9.82m as the candidate boundary and using 9.82m as the fixed starting point of the boundary acceptance section. Since the candidate boundary was frozen only after subsequent confirmation, the controller simultaneously traced the actual grouting flow rate since the time corresponding to 9.82m and continued to accumulate the grout volume to be assigned in real time with the construction. When the mixing head reached 10.05m, the grout volume to be assigned had accumulated to 18.6L. Thereafter, this grout volume continued to remain in the assignment state as the construction of the boundary acceptance section increased.

[0168] After the candidate boundary was frozen, the drill bit speed was maintained at 36 r / min to 40 r / min and the drilling speed was maintained at 0.45 m / min to 0.55 m / min. The sequential flow rate detection of 55 L / min–75 L / min–55 L / min was continued. Three effective detection cycles were obtained sequentially within the boundary acceptance section. Three grouting status records were formed based on the pressure and actual flow rate during the first low flow rate, high flow rate, and second low flow rate stabilization phase of each cycle. These records were then arranged into a grouting status sequence according to the actual construction sequence. The corresponding grouting response values ​​were 0.0083 MPa / (L / min), 0.0085 MPa / (L / min), and 0.0084 MPa / (L / min). The low flow rate recovery difference for each cycle did not exceed [a certain value]. The drill bit load stabilizes at 89A to 93A after 9.94m, which is significantly higher than the upper boundary of the mechanical reference and exceeds the measurement error margin. Therefore, a mechanically stable depth range starting from 9.94m is formed. The slurry-receiving state sequence starts from the first detection zone at 10.02m and remains on the same side of the upper boundary of the slurry-receiving reference. Its response span does not exceed the slurry-receiving stability fluctuation limit, thus forming a slurry-receiving stable depth range starting from 10.02m. The two stable depth ranges overlap after 10.02m. The controller takes the 10.02m that appears after drilling down as the starting point of the overlapping construction range, determines 10.02m as the effective segment boundary and sets it to the callable state, while its business status remains pending confirmation.

[0169] At this point, the total accumulated grout volume to be assigned during the boundary confirmation process has reached 36.0L. The controller divides the accumulated grout volume interval according to the unified clock time corresponding to 10.02m. 21.5L corresponds to the construction period before the effective segment boundary and is included in the current grouting segment; 14.5L corresponds to the construction period after the effective segment boundary and is included in the next grouting segment. The sum of these two parts remains 36.0L. The current construction design specifies a grout volume of 70L / m per unit advance for the next grouting segment. After the effective segment boundary adjustment, the construction length of this grouting segment is 6.0m, thus forming a target grout volume of 420L for the next grouting segment. After the grout volume settlement deadline, another 35L of complete actual measured grout volume is directly included in the next grouting segment, plus the aforementioned 14.5L. Subsequently, the confirmed grout volume for the next grouting section is 49.5L. After deducting the confirmed grout volume from the target grout volume, the remaining target grout volume is 370.5L. At this time, there is still a remaining construction length of 5.7m from the mixing head to the end position of this grouting section. Therefore, the subsequent unit advance grout volume requirement is 65L / m. When the current effective advance speed is maintained at 0.50m / min, the corresponding pump flow rate is 32.5L / min. This flow rate is within the allowable range of the construction parameters, grout pump, grout delivery pipeline, and grouting pressure for the next grouting section. Based on this, the controller maintains an advance speed of 0.50m / min and continues normal construction at 32.5L / min. Subsequently, each time a complete grout volume accumulation interval is formed, the confirmed grout volume, remaining target grout volume, and pumping and advance control records are updated sequentially.

[0170] After the control state actually takes effect, the controller starts acquiring new follow-up confirmation records from the position that appears after the last grouting stability detection round in step 4 and the control activation position in step 5, along the construction direction. Then, it continuously completes three rounds of sequential flow rate detection from 55 L / min to 75 L / min to 55 L / min, generating grouting response values ​​of 0.0084 MPa / (L / min), 0.0086 MPa / (L / min), and 0.0085 MPa / (L / min), respectively. All three rounds continue to exceed the upper boundary of the grouting reference, with the excess exceeding the allowable deviation of each grouting response. The low flow recovery difference does not exceed 0.02 MPa, and the grouting response span formed together with the original stable state reference record remains unchanged. The grouting stability fluctuation limit was exceeded, therefore it was determined that the grouting response of the next grouting section would continue to maintain the stable state of that section. The on-site construction controller submitted the 10.02m effective segment boundary from the pending confirmation state to the submitted state. The grout volume attribution, confirmed grout volume, remaining target grout volume, and pumping advance control already formed in step 5 remained effective. The mechanical reference version, grouting reference version, candidate boundary frozen version, effective segment boundary version, grout volume settlement record, and 3 rounds of subsequent confirmation records were associated and saved. This completed the entire operation process of the pile from the establishment of the pre-search zone reference, freezing of candidate boundaries, temporary storage of transitional grout volume, confirmation of mechanical and grouting dual stability, formation of effective segment boundary, reassignment of grout volume, control of the remaining grout volume of the next grouting section, to the final submission of the boundary.

[0171] It should be noted that the methods, systems, devices, or equipment described in the above embodiments can be implemented in software, hardware, or a combination of both, depending on the actual application scenario. When implemented in software, the corresponding program instructions can be stored in a computer-readable storage medium and executed by a processor to achieve the processing steps or functions described in the above embodiments. For the specific processing procedures of each functional module in the system, device, or equipment, refer to the corresponding processing procedures in the foregoing method embodiments.

[0172] The above description is merely a specific embodiment of the present invention, used to illustrate the technical solution of the present invention, and is not intended to limit the scope of protection of the present invention. Without departing from the technical concept of the present invention, any equivalent substitutions, reasonable modifications, or combinations made by those skilled in the art based on the disclosure of this specification should be determined according to the claims to determine whether they fall within the scope of protection of the present invention.

Claims

1. A method for controlling segmented grouting in cement-soil mixing piles, characterized in that, include:

1. Before entering the designed soil interface search area, collect drill string load, grouting pressure, and grouting flow rate, and perform low-flow-high-flow-low-flow detection to form the mechanical reference and grouting reference for the current grouting section. When the actual grouting flow rate is continuously within the target flow rate allowable zone and the duration reaches the lock-in period, and the grouting pressure range does not exceed the allowable pressure fluctuation and the difference between the average pressure values ​​of the first and second halves does not exceed the allowable pressure drift, a stable window is formed. When stable windows are formed in all three flow stages, the actual high-low flow rate difference is greater than the minimum distinguishable flow rate difference, and the difference between the two low-flow stable grouting pressures does not exceed the allowable recovery difference, it is determined as a complete detection cycle. Sort the drill string load records of the two low-flow stable windows of the continuous complete detection cycles and filter them according to the lock-in retention ratio, using the minimum and maximum values ​​of the retained records to form the lower boundary and upper boundary of the mechanical reference. A complete detection cycle in which the average value of the drill string load in two low-flow stable windows is located between the two boundaries is determined as a qualified detection cycle. The grout response value is formed according to the ratio of pressure change to flow rate change. The grout response values ​​of consecutive qualified detection cycles are sorted and screened to form the lower boundary and upper boundary of the grout reference. The recovery boundary is formed by the maximum value of the low-flow recovery difference.

2. After entering the search area, candidate boundaries are formed based on the continuous separation of the drill string load from the mechanical reference. The candidate boundaries are frozen, boundary acceptance sections are established, and the amount of slurry to be assigned is accumulated. Third, in the boundary receiving section, keep the drill speed and footage speed under control, perform sequential flow detection, and form a slurry state sequence based on the pressure response; IV. When the drill string load remains on the same side of the mechanical reference within the mechanical stability observation window and the range does not exceed the mechanical stability fluctuation limit, a stable state is formed after the drill string load leaves the mechanical reference; when the continuous effective slurry-receiving state sequence items remain in the same departure direction, the low flow recovery difference does not exceed the recovery boundary, and the span of the slurry response value does not exceed the slurry stability fluctuation limit, a stable state is formed after the slurry-receiving state sequence leaves the slurry-receiving reference; the starting point of the construction section where the two stable states overlap along the locked construction direction is taken as the effective segment boundary; 5. Divide the grout volume to be assigned according to the effective segment boundary and include it in the corresponding grouting segment. Subtract the confirmed grout volume from the target grout volume of the next grouting segment to generate the remaining target grout volume, and control the pumping and advance.

6. Perform sequential flow detection in the next grouting section. If the grouting response maintains the stable state of the section, submit a valid segment boundary; otherwise, cancel the boundary, rebuild the boundary receiving section, and write back the control status.

2. The method for controlling segmented grouting of cement-soil mixing piles according to claim 1, characterized in that, When the drill string load continuously deviates from the mechanical reference on the same side while simultaneously satisfying the minimum number of effective sampling points and the continuous deviance footage threshold, the depth corresponding to the first effective sampling point of the continuous deviance sequence is frozen as a candidate boundary. The candidate boundary is used as the fixed starting point for the boundary section, and starting from the sampling time corresponding to the candidate boundary, the amount of grout to be assigned is accumulated according to the average value of adjacent effective grouting flow rate and the corresponding actual time interval.

3. The method for controlling segmented grouting of cement-soil mixing piles according to claim 1, characterized in that, The low flow rate setpoint, high flow rate setpoint, and stable window locked when the slurry receiving reference are inherited and maintained according to the rules of the sequential flow rate detection within the boundary section; When the drill bit speed and drilling speed are kept within the locked allowable range, the actual high and low flow rate changes are greater than the minimum distinguishable flow rate difference, the low flow rate recovery difference does not exceed the allowable recovery difference, and the detection occupied range does not exceed the maximum detection drilling length of a single round, it is determined as a valid detection round, and a slurry-receiving state sequence is formed according to the actual completion order.

4. The method for controlling segmented grouting of cement-soil mixing piles according to claim 1, characterized in that, The amount of slurry to be assigned is determined based on the time corresponding to the effective segment boundary. When the effective segment boundary corresponds to a time point between two adjacent effective mixing head depth sampling points, the time point is determined according to the depth change ratio, and the cross-boundary cumulative interval is split. The slurry volume of the sub-intervals before and after the boundary is calculated and included in the corresponding grouting section. The division result satisfies the allowable difference of slurry volume conservation.

5. The method for controlling segmented grouting of cement-soil mixing piles according to claim 1, characterized in that, Divide the remaining target grout volume by the remaining construction length from the current position of the mixing head to the end position of the next grouting section to form the subsequent unit advance grout volume requirement; The target pumping flow rate is determined by this requirement and the current effective advance rate. When the target pumping flow rate exceeds the upper limit of allowable flow rate, the upper limit of allowable flow rate is used and the advance rate is calculated in reverse. When it is lower than the continuous stable lower limit, the continuous stable lower limit of flow rate is used and the advance rate is calculated in reverse. The advance rate calculated in reverse is kept within the allowable range of the next grouting section.

6. The method for controlling segmented grouting of cement-soil mixing piles according to claim 1, characterized in that, The continuous effective sequence items that participated in the formation of the slurry-receiving stable state when forming effective segment boundaries are used as reference records; When the number of consecutive valid confirmation rounds obtained in the next grouting section reaches the locked number, and each round maintains the original separation direction, the low flow recovery difference does not exceed the recovery boundary, and the span of the grouting response value formed together with the reference record does not exceed the grouting stability fluctuation limit, the effective segment boundary will be converted to the submitted state. If any valid confirmation round fails to maintain the original separation direction, the low flow recovery difference exceeds the recovery boundary, or the span of the slurry response value after addition exceeds the slurry stability fluctuation limit, the valid segment boundary will be changed to the cancelled state, the slurry volume dependent on the boundary will be restored to the slurry volume to be assigned, and the boundary acceptance section will be reconstructed with the original frozen candidate boundary.

Citation Information

Patent Citations

  • Mixing pile construction device and method capable of dynamically adjusting guniting, lifting and sinking speeds

    CN113309087A

  • Large-diameter onshore four-shaft mixing pile construction method

    CN114000501A

  • Segmented variable-frequency grouting control method for cement-soil mixing pile

    CN121738166A

  • Cement mixing pile construction parameter self-adaptive regulation and control system based on edge calculation

    CN122362837A