Thermal management integrated assembly
Patent Information
- Application Number
- CN202511410235.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Priority Date
- 2025-03-25
- Filing Date
- 2025-09-29
- Publication Date
- 2026-10-09
AI Technical Summary
流道集成件上的两个节流阀容易对另外两个流道接口上安装的其他部件或装置造成干涉
[0008]在本申请中,板式换热器的第一流道口部和第二流道口部与流道集成块连接,第三流道口部和第四流道口部能够用于安装其他部件或装置,用于安装第一节流阀的第一安装腔沿第一直线延伸,用于安装第二节流阀的第二安装腔沿第二直线延伸,第一直线与第二直线相交,第三流道口部和第四流道口部中的至少一者位于第一直线和第二直线之间,从而能够减少第一节流阀和第二节流阀对安装在板式换热器上的其他部件或装置造成的干涉。
Smart Images

Figure CN122881276A_ABST
Abstract
Description
Technical Field
[0001] This application relates to the field of thermal management technology, and more specifically, to a thermal management integrated component. Background Technology
[0002] The integrated thermal management assembly includes thermal management components, flow channel integration components, and plate heat exchangers. Thermal management components may include, for example, heat exchangers or expansion valves. The flow channel integration components integrate two or more flow channels, enabling communication between the thermal management components. The thermal management components are mounted on the flow channel integration components, which are then mounted on the plate heat exchangers.
[0003] To improve the integration of thermal management integrated components, related technologies install two throttling valves on the flow channel assembly. Plate heat exchangers have four flow channel interfaces, two of which are used to connect to the flow channel assembly, while the other two need to connect to other components or devices. The two throttling valves on the flow channel assembly can easily interfere with other components or devices installed on the other two flow channel interfaces. Therefore, related technologies require improvements to the structure of the flow channel assembly. Summary of the Invention
[0004] Therefore, this application provides a method to reduce the interference caused by two throttling valves installed on the flow channel assembly to other components or devices installed on the plate heat exchanger.
[0005] The thermal management integrated component provided in this application includes a plate heat exchanger, a first throttling valve, a second throttling valve, and a flow channel integrated block. The flow channel integrated block is installed on the plate heat exchanger, and both the first throttling valve and the second throttling valve are installed on the flow channel integrated block.
[0006] The plate heat exchanger has a first heat exchange channel and a second heat exchange channel. The channel integration block has a connecting channel, a first mounting cavity, and a second mounting cavity. The connecting channel connects the first mounting cavity, the second mounting cavity, the first heat exchange channel, and the second heat exchange channel. The first throttling valve portion is located in the first mounting cavity, and the second throttling valve portion is located in the second mounting cavity. The first mounting cavity extends along a first straight line, and the second mounting cavity extends along a second straight line. The first straight line intersects the second straight line.
[0007] The plate heat exchanger includes a first flow channel opening, a second flow channel opening, a third flow channel opening, and a fourth flow channel opening. The first heat exchange flow channel passes through the first flow channel opening and the third flow channel opening, and the second heat exchange flow channel passes through the second flow channel opening and the fourth flow channel opening. The first flow channel opening and the second flow channel opening are connected to the flow channel integrated block, and at least one of the third flow channel opening and the fourth flow channel opening is located between the first straight line and the second straight line.
[0008] In this application, the first and second flow channel openings of the plate heat exchanger are connected to the flow channel integrated block, and the third and fourth flow channel openings can be used to install other components or devices. The first mounting cavity for installing the first throttle valve extends along a first straight line, and the second mounting cavity for installing the second throttle valve extends along a second straight line. The first straight line intersects the second straight line, and at least one of the third and fourth flow channel openings is located between the first and second straight lines, thereby reducing the interference of the first and second throttle valves on other components or devices installed on the plate heat exchanger. Attached Figure Description
[0009] Figure 1 A perspective view of a thermal management integrated component provided in one embodiment of this application;
[0010] Figure 2 for Figure 1 An exploded view of the provided thermal management integrated components;
[0011] Figure 3 for Figure 1 A partial cross-sectional view of the provided thermal management integrated component from a first angle;
[0012] Figure 4 for Figure 1 A partial cross-sectional view of the provided thermal management integrated component from a second angle;
[0013] Figure 5 for Figure 1 A partial cross-sectional view of the provided thermal management integrated component from a third angle;
[0014] Figure 6 for Figure 1 A schematic diagram of the provided thermal management integrated components;
[0015] Figure 7 for Figure 1 A partial cross-sectional view of the provided thermal management integrated component from a fourth angle;
[0016] Figure 8 for Figure 1 A partial cross-sectional view of the provided thermal management integrated component from the fifth angle;
[0017] Figure 9 for Figure 1 A three-dimensional schematic diagram of the flow channel integration block of the provided thermal management integrated component;
[0018] Figure 10 for Figure 1 A three-dimensional schematic diagram from another angle of the flow channel integration block included in the provided thermal management integrated component;
[0019] Figure 11 A perspective view of a thermal management integrated component provided for another embodiment of this application;
[0020] Figure 12 for Figure 11 A partial cross-sectional view of the provided thermal management integrated component;
[0021] Figure 13 for Figure 11 A three-dimensional schematic diagram of the flow channel integration block included in the provided thermal management integrated component;
[0022] Figure 14 for Figure 11 A three-dimensional schematic diagram from another angle of the flow channel integration block included in the provided thermal management integrated component;
[0023] Figure 15 This is a schematic diagram of a thermal management system provided in one embodiment of this application. Detailed Implementation
[0024] To better understand the technical solution of this application, the embodiments of this application will be described in detail below with reference to the accompanying drawings.
[0025] It should be clearly stated that the described technical solutions are only a part of the technical solutions in this application, not all of them. Based on the technical solutions in this application, all other technical solutions obtained by a person skilled in the art without inventive effort are within the scope of protection of this application.
[0026] The thermal management integration assembly 100 includes thermal management components and flow channel integration components. The thermal management components may be, for example, heat exchangers, throttling valves, etc., and the flow channel integration components integrate two or more flow channels to enable communication between the thermal management components. The thermal management integration assembly 100 can improve the integration level of the thermal management system 1000. However, related technologies require further improvements to the thermal management integration assembly 100 to reduce the cost of the corresponding thermal management system 1000.
[0027] The inventors discovered that, in order to reduce clogging of the throttle valve, related technologies include installing a filter device 5 before the throttle valve, allowing the fluid to pass through the filter before flowing into the throttle valve. Some thermal management systems 1000 include at least two throttle valves, thus requiring at least two filter devices 5.
[0028] This application provides a thermal management integrated component 100, for example... Figures 1-10 or Figures 11-14 As shown, this can help reduce the number of filter devices 5 in the corresponding thermal management system 1000, thereby reducing costs.
[0029] The thermal management integrated component 100 provided in this application, for example Figure 1 or Figure 11 As shown, the system includes a plate heat exchanger 1, a first throttling valve 2, a second throttling valve 3, and a flow channel assembly 4. The flow channel assembly 4 is mounted on the plate heat exchanger 1, and both the first throttling valve 2 and the second throttling valve 3 are mounted on the flow channel assembly 4. The plate heat exchanger 1 has a first heat exchange flow channel 11 and a second heat exchange flow channel 12. The first throttling valve 2 has a first valve port 21 and a second valve port 22, one of which is the inlet of the first throttling valve 2, and the other is the outlet of the first throttling valve 2. The second throttling valve 3 has a third valve port 31 and a fourth valve port 32, one of which is the inlet of the second throttling valve 3, and the other is the outlet of the second throttling valve 3. The flow channel integrated block 4 has a first channel 41, a second channel 42, and a third channel 43. The first valve port 21 can communicate with the inner cavity of the filter device 5. The second valve port 22 and the first heat exchange flow channel 11 are both connected to the first channel 41. The second valve port 22 and the third valve port 31 are both connected to the second channel 42. The fourth valve port 32 and the second heat exchange flow channel 12 are both connected to the third channel 43. Alternatively, the first channel 41 connects the second valve port 22 and the first heat exchange flow channel 11, the second channel 42 connects the second valve port 22 and the third valve port 31, and the third channel 43 connects the fourth valve port 32 and the second heat exchange flow channel 12.
[0030] The thermal management integrated component 100 provided in this application includes a flow channel integrated block 4, which has a first channel 41, a second channel 42, and a third channel 43. The second valve port 22 of the first throttling valve 2 and the first heat exchange flow channel 11 are both connected to the first channel 41. The second valve port 22 of the first throttling valve 2 and the third valve port 31 of the second throttling valve 3 are both connected to the second channel 42. The fourth valve port 32 and the second heat exchange flow channel 12 are both connected to the third channel 43. Furthermore, the first valve port 21 can communicate with the inner cavity of the filter device 5. In this way, the first throttling valve 2 and the second throttling valve 3 can share the filter device 5, which is beneficial to reducing the number of filter devices 5 in the thermal management system 1000 corresponding to the thermal management integrated component 100, thereby reducing the cost of the thermal management system 1000 corresponding to the thermal management integrated component 100.
[0031] It is understood that the plate heat exchanger 1 included in the thermal management integrated component 100 of this application is a subcooled heat exchanger. Within the plate heat exchanger 1, the first heat exchange channel 11 and the second heat exchange channel 12 are fluidly isolated, and both the first heat exchange channel 11 and the second heat exchange channel 12 are used for the flow of refrigerant. The first throttling valve 2 and the second throttling valve 3 can be, for example, expansion valves, such as electronic expansion valves (EXV).
[0032] In some embodiments, the flow channel integrated block 4 is a single piece. Related technologies use a connecting pipe 7 to connect the first throttle valve 2 and the second throttle valve 3. Because the connecting pipe 7 has multiple weld points, such as welding to the outer pipe 7 of the throttle valve and filter device 5, and welding between the main pipe and branch pipe at branch or confluence points, oxide scale easily forms on the pipe during welding. This oxide scale is easily detached and mixes with the fluid (e.g., refrigerant) flowing through the pipe during the operation of the thermal management system 1000. Therefore, a filter device 5 needs to be installed before both the first throttle valve 2 and the second throttle valve 3 connected by a pipe. This application uses a flow channel integrated block 4, which is a single piece, reducing the number of weld points compared to pipe connections, thereby reducing impurities introduced during the welding process. In other words, the single-piece design of the flow channel integrated block 4 reduces weld points, thus reducing impurities mixed with the refrigerant during the operation of the thermal management system 1000. Therefore, the first throttle valve 2 and the second throttle valve 3 can share the filter device 5 to meet filtration requirements. In some embodiments, the first channel 41, the second channel 42, and the third channel 43 of the flow channel block 4 are all machined or formed using a sand core process. In some embodiments, the flow channel block 4 is made of steel, such as carbon steel or stainless steel; or the flow channel block 4 is made of aluminum alloy. The flow channel block 4 made of steel or aluminum alloy further reduces the generation of impurities during the welding process.
[0033] In some embodiments, the plate heat exchanger 1 includes a plurality of plates stacked together; the thermal management integrated assembly 100 has a first opening 51 and a second opening 52, the first opening 51 connecting a first channel 41 and a first heat exchange flow channel 11, and the second opening 52 connecting a third channel 43 and a second heat exchange flow channel 12. Along the stacking direction of the plurality of plates, the first opening 51 and the second opening 52 are located on the same side of the flow channel integrated block 4, and the first opening 51 and the second opening 52 are located on the same side of the plate heat exchanger 1. This facilitates the connection between the flow channel integrated block 4 and the plate heat exchanger 1.
[0034] In some embodiments, both the first opening 51 and the second opening 52 are disposed on the flow channel integration block 4. For example Figure 10 or Figure 14As shown, the flow channel integrated block 4 includes a first connecting portion 610, a second connecting portion 620, and a body portion 630. Both the first connecting portion 610 and the second connecting portion 620 protrude from the body portion 630. A portion of a first channel 41 is disposed in the body portion 630, and another portion of the first channel 41 is disposed in the first connecting portion 610. A first opening 51 is disposed in the first connecting portion 610. A portion of a third channel 43 is disposed in the body portion 630, and another portion of the third channel 43 is disposed in the second connecting portion 620. There is a gap between the first connecting portion 610 and the second connecting portion 620. The first connecting portion 610 and the second connecting portion 620 are respectively fixedly connected to the plate heat exchanger 1. A second opening 52 is disposed in the second connecting portion 620. The first connecting portion 610 is at least partially located in the first heat exchange flow channel 11, and the second connecting portion 620 is at least partially located in the second heat exchange flow channel 12. That is, the first connecting portion 610 and the second connecting portion 620 are respectively inserted into the plate heat exchanger 1. Further, for example... Figure 8 As shown, the plate heat exchanger 1 includes a side plate 15, which includes a main body 151 and a flange 152. The flange 152 protrudes from the main body 151. The flange 152 includes a first flange 153 and a second flange 154. A first connecting part 610 is at least partially inserted into the first flange 153 and is welded to the first flange 153. A second connecting part 620 is at least partially inserted into the second flange 154 and is welded to the second flange 154.
[0035] In other embodiments, both the first opening 51 and the second opening 52 are disposed in the plate heat exchanger 1, for example, in the flanged portion 152 described above. The first opening 51 is disposed in the first flanged portion 153, and the second opening 52 is disposed in the second flanged portion 154. The first flanged portion 153 is at least partially inserted into the first connecting portion 610, and the second flanged portion 154 is at least partially inserted into the second connecting portion 620. Alternatively, one of the first opening 51 and the second opening 52 is disposed in the flow channel integration block 4, and the other of the first opening 51 and the second opening 52 is disposed in the plate heat exchanger 1. This application does not limit the connection method between the flow channel integration block 4 and the plate heat exchanger 1, as long as the two can be connected to achieve the communication between the first channel 41 and the first heat exchange flow channel 11, and the communication between the third channel 43 and the second heat exchange flow channel 12.
[0036] In some embodiments, the body portion 630 includes a first mounting portion 631 and a second mounting portion 632, a first mounting cavity 45 is disposed in the first mounting portion 631, and a second mounting cavity 46 is disposed in the second mounting portion 632. At least a portion of the first mounting portion 631 and the second mounting portion 632 are spaced apart. This helps to reduce mutual interference when the first throttle valve 2 and the second throttle valve 3 are installed into the flow channel integrated block 4, and also helps to reduce the weight of the flow channel integrated block.
[0037] In some embodiments, the plate heat exchanger 1 has inter-plate flow channels 14 and distribution flow channels 13. The inter-plate flow channels 14 are located between two adjacent plates and include at least two first inter-plate flow channels 141 and at least two second inter-plate flow channels 142. The distribution flow channels 13 include first distribution flow channels 131 and second distribution flow channels 132. At least two first inter-plate flow channels 141 are connected to the first distribution flow channel 131, and at least two second inter-plate flow channels 142 are connected to the second distribution flow channel 132. The first heat exchange flow channel 11 includes at least two first inter-plate flow channels 141 and the first distribution flow channel 131, and the second heat exchange flow channel 12 includes at least two second inter-plate flow channels 142 and the second distribution flow channel 132. The first opening 51 connects the first channel 41 and the first distribution channel 131, and the extending direction of the first channel 41 is parallel to the extending direction of the first distribution channel 131; the second opening 52 connects the third channel 43 and the second distribution channel 132, and the extending direction of the third channel 43 is parallel to the extending direction of the second distribution channel 132, for example... Figure 8 As shown. This reduces the flow resistance between the flow channel assembly and the plate heat exchanger 1. Furthermore, the first channel 41 is coaxial with the first distribution channel 131. Furthermore, the third channel 43 is coaxial with the second distribution channel 132.
[0038] In some embodiments, the second channel 42 has a first connecting port 421 and a second connecting port 422, the first connecting port 421 communicating with the second valve port 22 and the second connecting port 422 communicating with the third valve port 31. The thermal management integrated assembly 100 has a thickness direction T1, and along the thickness direction T1 of the thermal management integrated assembly 100, the flow channel integrated block 4 is at least partially located on one side of the plate heat exchanger 1; along the thickness direction T1, the distance between the second channel 42 and the plate heat exchanger 1 is a constant, the distance between the second valve port 22 and the plate heat exchanger 1 is equal to the distance between the second channel 42 and the plate heat exchanger 1, and the distance between the third valve port 31 and the plate heat exchanger 1 is equal to the distance between the second channel 42 and the plate heat exchanger 1. This helps to reduce the flow resistance of the second channel 42. In some embodiments, the thickness direction T1 of the thermal management integrated assembly 100 is in the same direction as the direction of the stacking of the plurality of plates of the plate heat exchanger 1 described above. In some embodiments, the thickness direction T1 of the thermal management integrated component 100 is perpendicular to the extension direction of the second channel 42.
[0039] In some embodiments, the flow channel integrated block 4 has a first mounting cavity 45, and the first throttle valve 2 includes a first valve port portion 210 and a second valve port portion 220. The first valve port 21 is disposed in the first valve port portion 210, and the second valve port 22 is disposed in the second valve port portion 220. Both the first valve port portion 210 and the second valve port portion 220 are located in the first mounting cavity 45, and both the first valve port 21 and the second valve port 22 are in communication with the first mounting cavity 45. The first channel 41 has a first channel opening 411, and the second channel 42 has a first connecting port 421. Both the first channel opening 411 and the first connecting port 421 are disposed through the wall of the first mounting cavity 45. The first channel opening 411 is farther away from the second valve port portion 220 relative to the first connecting port 421. For example... Figure 5 As shown, the first mounting cavity 45 includes a first sub-mounting cavity 451 and a second sub-mounting cavity 452. A first valve port 210 is located in the first sub-mounting cavity 451, and the first valve port 21 communicates with the first sub-mounting cavity 451. A second valve port 220 is located in the second sub-mounting cavity 452, and the second valve port 22 communicates with the second sub-mounting cavity 452. Both the first channel 41 and the second channel 42 communicate with the second sub-mounting cavity 452.
[0040] In some embodiments, the flow channel integrated block 4 has a second mounting cavity 46, and the second throttle valve 3 includes a third valve port portion 310 and a fourth valve port portion 320. The third valve port 31 is disposed in the third valve port portion 310, and the fourth valve port 32 is disposed in the fourth valve port portion 320. Both the third valve port portion 310 and the fourth valve port portion 320 are located in the second mounting cavity 46, and both the third valve port 31 and the fourth valve port 32 are in communication with the second mounting cavity 46. The second channel 42 and the third channel 43 are both in communication with the second mounting cavity 46. The third channel 43 has a second channel opening 431, and the second channel 42 has a second connecting port 422. Both the second channel opening 431 and the second connecting port 422 are disposed through the wall surface of the second mounting cavity 46. Specifically, the second mounting cavity 46 includes a third sub-mounting cavity 461 and a fourth sub-mounting cavity 462. The third valve port 310 is located in the third sub-mounting cavity 461 and communicates with the third sub-mounting cavity 461. The fourth valve port 320 is located in the fourth sub-mounting cavity 462 and communicates with the fourth sub-mounting cavity 462. The second channel 42 communicates with the third sub-mounting cavity 461 and the third channel 43 communicates with the fourth sub-mounting cavity 462.
[0041] The installation of the first throttle valve 2 and the second throttle valve 3 will be described below.
[0042] In some embodiments, the flow channel integrated block 4 has a connecting channel 40, a first mounting cavity 45, and a second mounting cavity 46. The connecting channel 40 connects the first mounting cavity 45, the second mounting cavity 46, the first heat exchange flow channel 11, and the second heat exchange flow channel 12. A first throttling valve 2 is partially located in the first mounting cavity 45, and a second throttling valve 3 is partially located in the second mounting cavity 46. The first mounting cavity 45 extends along a first straight line L1, and the second mounting cavity 46 extends along a second straight line L2. The plate heat exchanger 1 includes a first flow channel opening 161, a second flow channel opening 162, a third flow channel opening 163, and a fourth flow channel opening 164. The first heat exchange channel 11 passes through the first channel opening 161 and the third channel opening 163, and the second heat exchange channel 12 passes through the second channel opening 162 and the fourth channel opening 164. The first channel opening 161 and the second channel opening 162 are connected to the channel assembly block 4, and at least one of the third channel opening 162 and the fourth channel opening 164 is located between the first straight line L1 and the second straight line L2. In this way, interference of the first throttle valve 2 and the second throttle valve 3 on the devices or components installed in the third channel opening 162 and the fourth channel opening 164 can be reduced.
[0043] In some embodiments, the thermal management integrated assembly 100 has a thickness direction T1, and along the thickness direction T1 of the thermal management integrated assembly 100, the flow channel integrated block 4 is at least partially located on one side of the plate heat exchanger 1. A plane perpendicular to the thickness direction T1 of the thermal management integrated assembly 100 is defined as a projection plane. The orthographic projection of a first straight line L1 onto the projection plane is a first projection line P1, the orthographic projection of a second straight line L2 onto the projection plane is a second projection line P2, and the orthographic projection of the plate heat exchanger 1 onto the projection plane is a third projection P3. The outer contour of the third projection P3 includes a first straight side C. The third projection P3 has a first central axis O1, which is parallel to the first straight side C. The first projection line P1 forms a first angle with the first central axis O1, and the second projection line P2 forms a second angle with the first central axis O1. The angles α1 of the first angle and α2 of the second angle satisfy the following relationship: 0° < α1 ≤ 90°, 0° < α2 ≤ 90°.
[0044] The plate heat exchanger 1 has a thickness direction T, a length direction L, and a width direction D. Multiple plates are stacked along the thickness direction T of the plate heat exchanger 1, and the thickness direction T, length direction L, and width direction D of the plate heat exchanger 1 are perpendicular to each other. In the application of the thermal management integrated component 100, the length direction L of the plate heat exchanger 1 is perpendicular to the direction of gravity.
[0045] In some embodiments, the angles α1 of the first included angle and α2 of the second included angle satisfy the following relationship: 15° < α1 ≤ 20°, 15° < α2 ≤ 20°. This reduces the influence of gravity on the first throttle valve 2 and the second throttle valve 3, and simultaneously reduces the interference of the installation of the first throttle valve 2 and the second throttle valve 3 on the devices or components installed in the third flow channel opening 162 and the fourth flow channel opening 164.
[0046] For example Figure 2 As shown, along the length L of the plate heat exchanger 1, the first flow channel opening 161 and the second flow channel opening 162 are located on the same side of the plate heat exchanger 1, and the third flow channel opening 163 and the fourth flow channel opening 164 are located on the same side of the plate heat exchanger 1. The first flow channel opening 161 and the third flow channel opening 163 are located on opposite sides of the plate heat exchanger 1. Both the first flow channel opening 161 and the second flow channel opening 162 are connected to the flow channel assembly block 4. Specifically, the first flow channel opening 161 is connected to the first connecting part 610 mentioned above, and the second flow channel opening 162 is connected to the second connecting part 620 mentioned above. The third flow channel opening 163 and the fourth flow channel opening 164 are respectively connected to straight pipes or other components. The setting that the angle between the first projection line P1 and the first straight side C is less than or equal to 20°, and the angle between the second projection line P2 and the first straight side C is less than or equal to 20°, can reduce the interference between the first throttle valve 2 and the second throttle valve 3 and the third flow channel opening 163 and the fourth flow channel opening 164, while ensuring that the height direction of the first throttle valve 2 and the second throttle valve 3 is as parallel as possible to the direction of gravity. The height direction of the first throttle valve 2 is parallel to the extension direction of the first mounting cavity 45. The height direction of the second throttle valve 3 is parallel to the extension direction of the second mounting cavity 46. Specifically, for example... Figure 6 As shown, the angle between the first projection line P1 and the first straight side C is 18°, and the angle between the second projection line P2 and the first straight side C is also 18°. During the design process, while ensuring that the first throttle valve 2 and the second throttle valve 3 do not interfere with the third flow channel inlet 163 connector 7 and the fourth flow channel inlet 164 connector 7, the smaller the angle between the height direction and the gravity direction of the first throttle valve 2, the better. Correspondingly, the smaller the angle between the first projection line P1 and the first straight side C, the better. Similarly, the smaller the angle between the height direction and the gravity direction of the second throttle valve 3, the smaller the angle between the second projection line P2 and the first straight side C, the better.
[0047] In some embodiments, the height direction of the first straight line L1, or the first throttle valve 2, is perpendicular to the thickness direction T1 of the thermal management integrated assembly 100, and the height direction of the second straight line L2, or the second throttle valve 3, is perpendicular to the thickness direction T1 of the thermal management integrated assembly 100.
[0048] In some embodiments, the outer contour of the third projection P3 includes a second straight edge K, and the length of the first straight edge C is greater than the length of the second straight edge K. Along the length direction of the plate heat exchanger, the first flow channel opening 161 and the second flow channel opening 162 are located at the same end of the plate heat exchanger. Along the length direction of the plate heat exchanger, the third flow channel opening 163 and the fourth flow channel opening 164 are located at opposite ends of the plate heat exchanger 1, respectively. A flow channel integrated block is installed at one end of the plate heat exchanger along its length. The first mounting cavity 45 has a first mounting port 453, and the second mounting cavity 46 has a second mounting port 463. Along the length direction of the plate heat exchanger 1, the first mounting port 453 and the second mounting port 463 face the same side of the plate heat exchanger 1.
[0049] In other embodiments, the outer contour of the third projection P3 includes a second straight edge K, and the length of the first straight edge C is less than the length of the second straight edge K. Along the width direction of the plate heat exchanger, the first flow channel opening 161 and the second flow channel opening 162 are located at the same end of the plate heat exchanger, and the flow channel integrated block is installed at one end of the length direction of the plate heat exchanger; the first mounting cavity 45 has a first mounting port 453, and the second mounting cavity 46 has a second mounting port 463. Along the width direction of the plate heat exchanger 1, the first mounting port 453 and the second mounting port 463 face the same side of the plate heat exchanger 1.
[0050] In some embodiments, the thermal management integrated assembly 100 includes a filter connected to a third flow channel opening 163, the filter having a filter chamber 6 communicating with a first heat exchange flow channel 11.
[0051] In some embodiments, the thermal management integrated assembly 100 includes the filter device 5 described above, with a first valve port 21 communicating with the inner cavity of the filter device 5.
[0052] In a first embodiment, the thermal management integrated assembly 100 includes a connecting pipe 7, one end of which is connected to the flow channel integrated block 4, and the other end of which is connected to the filter device 5. Both the first mounting cavity 45 and the inner cavity of the filter device 5 are connected to the pipe of the connecting pipe 7. That is, the filter device 5 is externally connected to the flow channel integrated block 4. The connecting pipe 7 and the flow channel integrated block 4 can be fixedly connected or limitedly connected, or they can be detachably connected, for example, for the purpose of facilitating filter replacement. Specifically, for example... Figure 3 As shown, the flow channel integrated block 4 has a first mounting cavity 45 and a fourth channel 44. The first throttle valve 2 is at least partially located in the first mounting cavity 45, and the first channel 41, the second channel 42, and the fourth channel 44 are all connected to the first mounting cavity 45. For example Figure 3As shown, the first mounting cavity 45 includes a first sub-mounting cavity 451 and a second sub-mounting cavity 452. As described above, the first throttle valve 2 includes a first valve port portion 210 and a second valve port portion 220. The first valve port 21 is disposed in the first valve port portion 210, which is located in the first sub-mounting cavity 451 and communicates with it. The pipe of the connecting pipe 7 is also connected to the first sub-mounting cavity 451. The second valve port 22 is disposed in the second valve port portion 220, which is located in the second sub-mounting cavity 452 and communicates with it. Both the first channel 41 and the second channel 42 are connected to the second sub-mounting cavity 452. The fourth channel 44 communicates with the first mounting cavity 45, specifically, it communicates with the first sub-mounting cavity 451. A portion of the connecting pipe 7 is located in the fourth channel 44 and is sealed and fixedly connected to the wall of the fourth channel 44.
[0053] In the second embodiment, the thermal management integrated assembly 100 has a filter chamber 6, which is at least partially disposed in the flow channel integrated block 4. The thermal management integrated assembly 100 includes a filter section 63 located in the filter chamber 6. That is, the flow channel integrated block 4 integrates a filter device 5. Specifically, for example... Figure 4 or Figure 12 As shown, the flow channel integrated block 4 has a first mounting cavity 45 and a fourth channel 44. The first throttle valve 2 is at least partially located in the first mounting cavity 45. The first channel 41, the second channel 42, and the fourth channel 44 are all connected to the first mounting cavity 45. The specific installation method of the first throttle valve 2 in the first mounting cavity 45 can be referred to the description of the first embodiment. In the second embodiment, both the first mounting cavity 45 and the filter cavity 6 are connected to the fourth channel 44. The fourth channel 44 has a third channel opening 441 and a fourth channel opening 442. The third channel opening 441 penetrates through the wall of the first mounting cavity 45, and the fourth channel opening 442 penetrates through the wall of the filter cavity 6. Specifically, for example... Figure 3 As shown, the filter section 63 is a filter screen with filter holes; the filter chamber 6 includes a first filter chamber 61 and a second filter chamber 62, which are located on both sides of the filter screen, and both the first filter chamber 61 and the second filter chamber 62 are connected to the filter holes. The fourth channel 44 connects the first filter chamber 61 and the first sub-mounting cavity 451. Thus, the fluid first enters the first filter chamber 61, is filtered by the filter screen, enters the second filter chamber 62, and then enters the first sub-mounting cavity 451 through the fourth channel 44 and enters the first valve port 21. In some embodiments, at least a portion of the flow cross-sectional area of the filter chamber 6 is larger than the flow cross-sectional area of the fourth channel 44.
[0054] In some implementations, for example Figure 1As shown, along the thickness direction T1 of the thermal management integrated assembly 100, the plate heat exchanger 1 and the filter device 5 are located on both sides of the flow channel integrated block 4; along the thickness direction T1 of the thermal management integrated assembly 100, the first channel 41 and the fourth channel 44 are located on both sides of the first mounting cavity 45. For example, combined with Figure 1 and Figure 3 As shown, the first channel 41 extends along the thickness direction T1 of the thermal management integrated assembly 100, and the fourth channel 44 extends at least partially along the thickness direction T1 of the thermal management integrated assembly 100. The extension direction of the filter cavity 6 is perpendicular to the extension direction of the first channel 41. Along the extension direction of the filter cavity 6, the first filter cavity 61 and the second filter cavity 62 are located on both sides of the filter section 63, respectively.
[0055] In some embodiments, the distribution channel 13 includes a third distribution channel 133 and a fourth distribution channel 134, with at least two first inter-plate channels 141 communicating with the third distribution channel 133 and at least two second inter-plate channels 142 communicating with the fourth distribution channel 134. The first heat exchange channel 11 includes the third distribution channel 133, and the second heat exchange channel 12 includes the fourth distribution channel 134, for example... Figure 7 As shown. The first distribution channel 131 penetrates the first channel opening 161 described above, the second distribution channel 132 penetrates the second channel opening 162 described above, the third distribution channel 133 penetrates the third channel opening 163 described above, and the fourth distribution channel 134 penetrates the fourth channel opening 164 described above. In some embodiments, the first channel opening 161 includes the first flange 153 described above, and the second channel opening 162 includes the second flange 154 described above. In some embodiments, to increase the connection strength with the outer pipe, the third channel opening 163 and the fourth channel opening 164 may also be provided with flanges 152.
[0056] In some embodiments, the thermal management integrated assembly 100 has a first mode. In the first mode, the refrigerant enters the filter device 5, for example, the second filter chamber 62 of the filter device 5, is filtered by the filter section 63, and then enters the first filter chamber 61; it then passes through the fourth channel 44 to the first valve port 21, and enters the first throttling valve 2 through the first valve port 21, and then flows out of the first throttling valve 2 from the second valve port 22. Part of the refrigerant flowing out of the second valve port 22 enters the first distribution channel 131 of the plate heat exchanger 1 through the first channel 41, and is distributed from the first distribution channel 131 to at least two first inter-plate channels 141, and then flows out from the third distribution channel 133; another part enters the third valve port 31 of the second throttling valve 3 through the second channel 42, and then flows out of the second throttling valve 3 from the fourth valve port 32 and enters the second distribution channel 132 of the plate heat exchanger 1, and is distributed from the second distribution channel 132 to at least two second inter-plate channels 142, and then flows out from the fourth distribution channel 134. In the first mode, the first throttle valve 2 does not throttle the refrigerant flowing through it, while the second throttle valve 3 does throttle the refrigerant flowing through it.
[0057] In some embodiments, the thermal management integrated assembly 100 has a second mode in which refrigerant enters a third distribution channel 133 and is distributed from the third distribution channel 133 to at least two first inter-plate channels 141, then enters the first distribution channel 131, and subsequently flows out from the first distribution channel 131 to a first channel 41. A portion of the refrigerant flowing out of the first channel 41 reaches the second valve port 22, flows through the first throttling valve 2, and then flows out from the first valve port 21; another portion of the refrigerant enters the second channel 42 and flows from the second channel 42 to the third valve port 31, passes through the second throttling valve 3, and then flows out from the fourth valve port 32. The refrigerant flowing out from the fourth valve port 32 enters the second distribution channel 132 and is distributed from the second distribution channel 132 to at least two second inter-plate channels 142, and then flows out from the fourth distribution channel 134. In the second mode, both the first throttling valve 2 and the second throttling valve 3 throttle the flow of refrigerant.
[0058] In some embodiments, the third flow channel opening 163 described above is connected to a filter 8, thereby enabling the filtration of refrigerant entering the third distribution flow channel 133. In some embodiments, the filter 8 includes a housing portion 81, an inner filter portion 82, and a connecting pipe portion 83. The housing portion 81 has a cavity 810, the inner filter portion 82 is located in the cavity 810, and the inner filter portion 82 is connected to the housing portion 81. The connecting pipe portion 83 is connected to the third flow channel opening 163 of the plate heat exchanger 1, and the connecting pipe portion 83 has a lumen 830 that communicates with the cavity 810 and the first heat exchange flow channel 11. The housing portion 81 is at least partially integrally formed with the connecting pipe portion 83. For example... Figure 7As shown, the outer casing 81 includes a first outer casing 811 and a second outer casing 812, which are sealed together. Both the first outer casing 811 and the second outer casing 812 are located on the periphery of the cavity 810. Along the extending direction of the connecting pipe 83, the first outer casing 811 is closer to the connecting pipe 83 than the second outer casing 812. The first outer casing 811 is integrally formed with the connecting pipe 83, for example... Figure 7 As shown. Of course, in some embodiments, the outer casing 81 and the connecting pipe 83 can be separately provided, for example... Figure 12 As shown.
[0059] In some embodiments, the thermal management integrated assembly 100 includes a temperature sensing tube 9, such as a copper tube, which is at least partially located within the flow channel integrated block 1.
[0060] A second aspect of this application provides a thermal management system 1000, including a thermal management integrated component 100 and a filter device 5. The thermal management integrated component 100 includes a plate heat exchanger 1, a first throttling valve 2, a second throttling valve 3, and a flow channel integrated block 4. The flow channel integrated block 4 is installed on the plate heat exchanger 1, and both the first throttling valve 2 and the second throttling valve 3 are installed on the flow channel integrated block 4. The plate heat exchanger 1 has a first heat exchange flow channel 11 and a second heat exchange flow channel 12. The first throttling valve 2 has a first valve port 21 and a second valve port 22, one of which is the inlet of the first throttling valve 2, and the other is the outlet of the first throttling valve 2. The second throttling valve 3 has a third valve port 31 and a fourth valve port 32, one of which is the inlet of the second throttling valve 3, and the other is the outlet of the second throttling valve 3. The flow channel integrated block 4 has a first channel 41, a second channel 42, and a third channel 43. The first valve port 21 can communicate with the inner cavity of the filter device 5. The second valve port 22 and the first heat exchange flow channel 11 are both connected to the first channel 41. The second valve port 22 and the third valve port 31 are both connected to the second channel 42. The fourth valve port 32 and the second heat exchange flow channel 12 are both connected to the third channel 43. Alternatively, the first channel 41 connects the second valve port 22 and the first heat exchange flow channel 11, the second channel 42 connects the second valve port 22 and the third valve port 31, and the third channel 43 connects the fourth valve port 32 and the second heat exchange flow channel 12.
[0061] The thermal management system 1000 provided in the second aspect of this application, for example... Figure 15As shown, the system includes a thermal management integrated component 100, which includes a flow channel integrated block 4. The flow channel integrated block 4 has a first channel 41, a second channel 42, and a third channel 43. The second valve port 22 of the first throttling valve 2 and the first heat exchange flow channel 11 are both connected to the first channel 41. The second valve port 22 of the first throttling valve 2 and the third valve port 31 of the second throttling valve 3 are both connected to the second channel 42. The fourth valve port 32 and the second heat exchange flow channel 12 are both connected to the third channel 43. Furthermore, the first valve port 21 is connected to the inner cavity of the filter device 5. In this way, the first throttling valve 2 and the second throttling valve 3 can share the filter device 5, which helps to reduce the number of filter devices 5 in the thermal management system 1000 and thus reduce the cost of the thermal management system 1000.
[0062] In some embodiments, the thermal management system 1000 has a cooling mode and a heating mode. In the cooling mode, the thermal management integration component 100 is in the first mode described above; in the heating mode, the thermal management integration component 100 is in the second mode described above.
[0063] In some embodiments, the thermal management system has a cooling mode, in which the first valve port 21 is the inlet of the first throttle valve 2, the second valve port 22 is the outlet of the first throttle valve 2, the third valve port 31 is the inlet of the second throttle valve 3, and the fourth valve port 32 is the outlet of the second throttle valve 3.
[0064] In some embodiments, the thermal management system has a heating mode, in which the second valve port 22 is the inlet of the first throttle valve 2, the first valve port 21 is the outlet of the first throttle valve 2, the third valve port 31 is the inlet of the second throttle valve 3, and the fourth valve port 32 is the outlet of the second throttle valve 3.
Claims
1. A thermal management integrated component, characterized in that, It includes a plate heat exchanger (1), a first throttle valve (2), a second throttle valve (3), and a flow channel integrated block (4). The flow channel integrated block (4) is installed on the plate heat exchanger (1), and the first throttle valve (2) and the second throttle valve (3) are both installed on the flow channel integrated block (4). The plate heat exchanger (1) has a first heat exchange channel (11) and a second heat exchange channel (12). The channel integration block (4) has a connecting channel (40), a first mounting cavity (45), and a second mounting cavity (46). The connecting channel (40) connects the first mounting cavity (45), the second mounting cavity (46), the first heat exchange channel (11), and the second heat exchange channel (12). The first throttle valve (2) is partially located in the first mounting cavity (45), and the second throttle valve (3) is partially located in the second mounting cavity (46). The first mounting cavity (45) extends along a first straight line (L1), and the second mounting cavity (46) extends along a second straight line (L2). The first straight line (L1) and the second straight line (L2) intersect. The plate heat exchanger (1) includes a first flow channel opening (161), a second flow channel opening (162), a third flow channel opening (163), and a fourth flow channel opening (164). The first heat exchange flow channel (11) passes through the first flow channel opening (161) and the third flow channel opening (163), and the second heat exchange flow channel (12) passes through the second flow channel opening (162) and the fourth flow channel opening (164). The first flow channel opening (161) and the second flow channel opening (162) are connected to the flow channel integrated block (4), and at least one of the third flow channel opening (162) and the fourth flow channel opening (164) is located between the first straight line (L1) and the second straight line (L2).
2. The thermal management integrated component as described in claim 1, characterized in that, The thermal management integrated assembly (100) has a thickness direction (T1), and along the thickness direction (T1) of the thermal management integrated assembly (100), the flow channel integrated block (4) is at least partially located on one side of the plate heat exchanger (1). A plane perpendicular to the thickness direction (T1) of the thermal management integrated component (100) is defined as the projection plane. The orthographic projection of the first straight line (L1) onto the projection plane is the first projection line (P1). The orthographic projection of the second straight line (L2) onto the projection plane is the second projection line (P2). The orthographic projection of the plate heat exchanger (1) onto the projection plane is the third projection (P3). The outer contour of the third projection (P3) includes a first straight side (C). The third projection (P3) has a first central axis (O1). The first central axis (O1) is parallel to the first straight side (C). The first projection line (P1) forms a first angle with the first central axis (O1). The second projection line (P2) forms a second angle with the first central axis (O1). The angles α1 of the first angle and α2 of the second angle satisfy the following relationship: 0° < α1 ≤ 90°, 0° < α2 ≤ 90°.
3. The thermal management integrated component as described in claim 2, characterized in that, The angles α1 of the first included angle and α2 of the second included angle satisfy the following relationship: 15°<α1≤20°, 15°<α2≤20°.
4. The thermal management integrated component as described in claim 2 or 3, characterized in that, The outer contour of the third projection (P3) includes a second straight edge (K), and the length of the first straight edge (C) is greater than the length of the second straight edge (K); Along the length of the plate heat exchanger, the first flow channel opening (161) and the second flow channel opening (162) are located at the same end of the plate heat exchanger, and the flow channel integrated block is installed at one end of the plate heat exchanger along its length; the first mounting cavity (45) has a first mounting port (453), and the second mounting cavity (46) has a second mounting port (463). Along the length of the plate heat exchanger (1), the first mounting port (453) and the second mounting port (463) face the same side of the plate heat exchanger (1).
5. The thermal management integrated component as described in claim 2 or 3, characterized in that, The outer contour of the third projection (P3) includes a second straight edge (K), and the length of the first straight edge (C) is less than the length of the second straight edge (K); Along the width direction of the plate heat exchanger, the first flow channel opening (161) and the second flow channel opening (162) are located at the same end of the plate heat exchanger, and the flow channel integrated block is installed at one end of the length direction of the plate heat exchanger; the first mounting cavity (45) has a first mounting port (453), and the second mounting cavity (46) has a second mounting port (463). Along the width direction of the plate heat exchanger (1), the first mounting port (453) and the second mounting port (463) face the same side of the plate heat exchanger (1).
6. The thermal management integrated component as described in any one of claims 1 to 3, characterized in that, The channel (40) includes a first channel (41), a second channel (42) and a third channel (43). The first channel (41) connects the first mounting cavity (45) and the first heat exchange channel (11). The second channel (42) connects the first mounting cavity (45) and the second mounting cavity (46). The third channel (43) connects the second mounting cavity (46) and the second heat exchange channel (12). The extension direction of the first channel (41) and the extension direction of the third channel (43) are both parallel to the thickness direction (T1) of the thermal management integrated component (100), and the extension direction of the second channel (42) is perpendicular to the thickness direction (T1) of the thermal management integrated component (100).
7. The thermal management integrated component as described in claim 6, characterized in that, The flow channel integrated block (4) includes a first connecting part (610), a second connecting part (620) and a body part (630), wherein the first connecting part (610) and the second connecting part (620) both protrude from the body part (630); A portion of the first channel (41) is disposed in the first connecting portion (610), and another portion of the first channel (41) is disposed in the body portion (630); the second channel (42), the first mounting cavity (45), and the second mounting cavity (46) are all disposed in the body portion (630); a portion of the third channel (43) is disposed in the second connecting portion (620), and another portion of the third channel (43) is disposed in the body portion (630); There is a gap between the first connecting part (610) and the second connecting part (620), and the first connecting part (610) and the second connecting part (620) are respectively fixedly connected to the plate heat exchanger (1).
8. The thermal management integrated component as described in claim 7, characterized in that, The main body (630) includes a first mounting part (631) and a second mounting part (632), the first mounting cavity (45) is disposed in the first mounting part (631), the second mounting cavity (46) is disposed in the second mounting part (632), and the first mounting part (631) has at least a gap with the second mounting part (632).
9. The thermal management integrated component as described in any one of claims 1 to 3, 7 and 8, characterized in that, The flow channel assembly is a single piece.
10. The thermal management integrated component as described in any one of claims 1 to 3, 7 and 8, characterized in that, The first throttle valve (2) includes a first valve port portion (210) and a second valve port portion (220). The first throttle valve (2) has a first valve port (21) and a second valve port (22). The first valve port (21) is disposed in the first valve port portion (210), and the second valve port (22) is disposed in the second valve port portion (220). The first valve port portion (210) and the second valve port portion (220) are both located in the first mounting cavity (45). The first valve port (21) and the second valve port (22) are both connected to the first mounting cavity (45). One of the first valve port (21) and the second valve port (22) is the inlet of the first throttle valve (2), and the other of the first valve port (21) and the second valve port (22) is the outlet of the first throttle valve (2). The second throttle valve (3) includes a third valve port (310) and a fourth valve port (320). The second throttle valve (3) has a third valve port (31) and a fourth valve port (32). The third valve port (31) is disposed in the third valve port (310), and the fourth valve port (32) is disposed in the fourth valve port (320). The third valve port (310) and the fourth valve port (320) are both located in the second mounting cavity (46). The third valve port (31) and the fourth valve port (32) are both connected to the second mounting cavity (46). One of the third valve port (31) and the fourth valve port (32) is the inlet of the second throttle valve (3), and the other of the third valve port (31) and the fourth valve port (32) is the outlet of the second throttle valve (3).