A hot rolling production control method of dynamic violation check and slab recommendation

CN122905244APending Publication Date: 2026-10-13SHANGHAI MEISHAN IRON & STEEL CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202510388993.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-03-31
Publication Date
2026-10-13

AI Technical Summary

Technical Problem

[0008]然而以上方法大部分是以提升热装率和板坯间过渡平滑度等为目标进行设计的,这一定程度上满足热装率和生产量的需求,但是对于实际生产作业来说,却没有满足计划人员对特殊钢种的考虑,且未给计划人员提供违规情况检查以便他们人为干预,因此本文所提出的一种动态违规检查与板坯推荐的热轧排产方法不仅满足提升热装率、板坯平滑度的需要,而且增加了对特殊钢种(比如短尺坯、厚板坯)的考虑,并提升了和人工的交互性,让实际的排产结果更加贴合生产实际需求

Benefits of technology

[0109]本发明方法工艺操作稳定,通过本发明提供的生产控制方法,可以在保证生产安全、设备稳定运行的前提下,在1-2s的时间范围内生成一个轧制计划,有效提升人员操作效率,同时计划可以满足现场的需求,板坯之间过渡平滑,有效提升热装板坯在轧制计划中的占比,降低企业能源消耗,同时提出的动态违规检查和板坯推荐功能,可以让现场人员第一时间内判断出需要下发的指令,以便在最快的时间内生产出符合计划需求的板坯,且对于特殊钢种的考虑可以尽量使得库存中的板坯利用率最大化,合理化库存结构。总的来说,通过本发明不仅可以提供现场人员编制计划效率,还可以实现热装率升和计划平滑度的提升,同时增加对特殊品种的编排考虑以及增设动态违规检查和板坯推荐的功能,能在得到最优排产、提升人工计划编排的工作效率的同时给予更好的人工交互体验,灵活应对现场变化。

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN122905244A_ABST
    Figure CN122905244A_ABST
Patent Text Reader

Abstract

The present application relates to a kind of dynamic violation checks and slab recommendation hot rolling production control method, including quantitative description hot rolling production scheduling problem and slab grouping, and using heuristic algorithm to compile rolling plan, output is in the form of log, while the whole plan is checked again for violation, for the slab with violation is marked, and the rolling length, rolling width, rolling thickness, tapping temperature information of the slab meeting the requirements are calculated, and are displayed. By establishing hot rolling intelligent production scheduling model to realize the improvement of hot charging rate, the improvement of plan smoothness, while increasing the consideration of special varieties and adding the functions of dynamic violation checking and slab recommendation, the purpose is to get the optimal production scheduling, improve the work efficiency of manual planning arrangement, and give better human interaction experience, flexible response to on-site changes.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to a dynamic violation inspection and slab recommendation hot rolling production control method, belonging to the field of intelligent control technology for hot rolling processes in steel. Background Technology

[0002] In steel production, hot rolling is one of the key stages. Currently, with the diversification of market demand, steel companies' order structures are characterized by multiple varieties, small batches, and various specifications. This demand structure requires steel companies to not only meet diverse market demands but also strive for large-scale batch production to reduce production costs and improve efficiency. This places high demands on the planning, management, and organization of steel production.

[0003] In actual production, different types of slabs exhibit significant differences in steel grade, thickness, width, hardness, and other properties, posing challenges to the preparation of hot rolling schedules. The hot rolling schedule preparation process requires comprehensive consideration of production conditions, user needs, and the dimensional differences between slabs to rationally arrange the rolling sequence and rolling unit sequence on the rolling line. This not only affects the stability of product quality but also directly impacts production rhythm and efficiency. Furthermore, utilizing hot-charging and hot-delivery technology for continuously cast slabs allows hot slabs from continuous casting to be directly sent to the rolling line for rolling after being processed in a heating furnace. This method effectively reduces energy consumption and production costs while improving production efficiency. Therefore, rationally preparing the rolling sequence to ensure smooth transitions while maximizing the rolling of hot-charged slabs to increase the hot-charging rate (i.e., the proportion of hot-charged slabs in the rolling unit) is a crucial measure to enhance a company's market competitiveness. However, the preparation of hot rolling schedules requires consideration of numerous complex process constraints and the timeliness of schedule preparation; traditional manual preparation methods can no longer meet the needs of modern production planning and scheduling. Therefore, optimizing hot rolling plans to improve planning efficiency, optimize rolling sequence, ensure the timeliness and standardization of plans, and maximize hot charging rate have become important issues that hot rolling planners urgently need to address.

[0004] In conclusion, achieving efficient, low-cost, and high-quality production by optimizing hot rolling schedules while meeting diverse market demands has become a major challenge for steel companies. Therefore, there is an urgent need for a method and system that can effectively address these issues to improve the production management level and market competitiveness of steel enterprises.

[0005] Currently, researchers at home and abroad have conducted extensive research on hot rolling plans. The literature "A Hot Rolling Batch Planning Method that is conducive to improving the DHCR ratio" establishes a hot rolling batch planning optimization model that is conducive to improving DHCR (Direct Hot Charging Rate) and solves it using a two-exchange heuristic crossover algorithm.

[0006] The paper "A decomposition-based hierarchical optimization algorithm for hotrolling batch scheduling problem" incorporates the surface grade of the slab and hot loading and hot delivery as constraints into the mathematical model, establishes a vehicle path model with dual time windows, and uses a decomposition-based hierarchical optimization algorithm to solve it.

[0007] The paper "Solving the Hot Rolling Batch Planning Problem Based on PCVRP Using the PESAⅡ Algorithm" uses the PESAⅡ algorithm to solve the hot rolling batch planning problem based on PCVRP (Bonus Collection Vehicle Routing Problem) and obtains good experimental results.

[0008] However, most of the above methods are designed with the goal of improving the hot charging rate and the smoothness of the transition between slabs. This meets the requirements of hot charging rate and production volume to a certain extent, but for actual production operations, it does not meet the planners' consideration of special steel grades, nor does it provide planners with a violation check so that they can intervene manually. Therefore, the hot rolling production scheduling method with dynamic violation check and slab recommendation proposed in this paper not only meets the needs of improving hot charging rate and slab smoothness, but also adds consideration for special steel grades (such as short-length slabs and thick slabs), and improves the interactivity with humans, so that the actual scheduling results are more in line with the actual production needs. Summary of the Invention

[0009] The technical problem to be solved by this invention is to overcome the shortcomings of the above-mentioned technologies and provide a hot rolling production control method with dynamic violation inspection and slab recommendation. By establishing an intelligent hot rolling production scheduling model, the hot charging rate and the smoothness of the plan are improved. At the same time, the scheduling of special varieties is considered and the functions of dynamic violation inspection and slab recommendation are added. The purpose is to obtain the optimal production scheduling, improve the work efficiency of manual planning and scheduling, and provide a better manual interaction experience, so as to flexibly respond to changes on site.

[0010] To solve the above-mentioned technical problems, the technical solution proposed by this invention is: a hot-rolling production control method for dynamic violation inspection and slab recommendation, comprising the following steps:

[0011] Step 1: Quantitatively describe the hot rolling production scheduling problem.

[0012] Each rolling unit consists of two parts: the hot strip and the main strip. In the initial stage of the rolling unit, the hot strip is rolled to achieve thermal equilibrium and stability of the rolls. The hot strip accounts for a small proportion of the rolling unit, generally consisting of strips with lower hardness, before the main strip is rolled.

[0013] Step 1.1: Select decision variables for hot rolling production scheduling.

[0014] (1) Decision variable x ijk When slab j is within the rolling schedule k and is rolled immediately following slab i, then x ijk The value is 1 if it is not 1, otherwise it is 0.

[0015] (2) Decision variable y ik When slab i is within the rolling plan k, then y ik The value is 1 if it is not 1, otherwise it is 0.

[0016] (3) Decision variable s ik When slab i is the main material within the rolling plan k, then s ik The value is 1 if it is not 1, otherwise it is 0.

[0017] (4) Decision variable s′ ik When slab i is a hot roll material within the rolling plan k, then s′ ik The value is 1 if it is not 1, otherwise it is 0.

[0018] (5) Decision variable f ij When slab i is the hot rolling material and slab j is the main material, then f ij The value is 1 if it is not 1, otherwise it is 0.

[0019] (6) Decision variable z ijk When both slab i and slab j are within the rolling plan k, and slab i and slab j have the same width, then z ijk The value is 1 if it is not 1, otherwise it is 0.

[0020] Step 1.2: Quantitatively describe the hot rolling production scheduling target.

[0021] The hot rolling production scheduling objectives include: minimizing the jump penalty value between adjacent slabs and maximizing the hot charging rate of the rolling unit.

[0022] in:

[0023] (1) Minimize the jump penalty value between adjacent slabs

[0024] The jump penalty value between adjacent slabs includes: the sum of the jump penalty values ​​between adjacent slabs of the main body material, the sum of the jump penalty values ​​between adjacent slabs of the hot rolling material, and the jump penalty value between the main body material and the hot rolling material.

[0025] (2) Maximize the heat charging rate of the rolling unit

[0026] The hot charging rate of a rolling unit refers to the proportion of hot-charged slabs in a rolling unit to all slabs in that rolling unit.

[0027] Step 1.3: Quantitatively describe the process constraints of the specified hot rolling production schedule.

[0028] (1) Uniqueness constraint: A slab can only appear in one rolling unit, and there cannot be two identical slabs in the same rolling unit. A slab can only be adjacent to the previous and the next slab once.

[0029] (2) Rolling process constraints: In a rolling unit, the main material and the hot roll material can only be adjacent to each other at most once, and the hot roll material is in front and the main material is behind. They cannot be interspersed.

[0030] (3) Quantity constraint of hot rolling material: The number of hot rolling material blanks in a rolling unit should be between the maximum and minimum required values.

[0031] (4) Total rolling weight limit: Consider the working life and wear of the rolls, make reasonable production plans, avoid long-term high-load operation, reduce roll wear, improve utilization rate, and ensure the rational use of rolls.

[0032] (5) Width constraints: Width constraints include the width constraints of the main body material, the width constraints of the ironing roller material, and the width constraints between the ironing roller material and the main body material.

[0033] (6) Thickness constraint: The rolling thickness jump between adjacent slabs of the main material cannot exceed the given upper limit.

[0034] (7) Hardness constraint: The rolling hardness jump between adjacent slabs of the main material cannot exceed the given upper limit.

[0035] (8) Exit temperature constraint: The exit temperature jump between adjacent slabs of the main material cannot exceed the given upper limit.

[0036] (9) Constraint on the length of the same width: The total length of continuously rolled slabs of the same width should not exceed the given maximum length, otherwise it will affect the surface quality of the rolls and slabs.

[0037] Step 2: Group the slabs.

[0038] According to the production rules, special slabs, i.e. slabs with a thickness exceeding 6.5, are stored in set S1, while slabs with a length of less than 4.0 are stored in set S2. Finally, based on the steel tapping mark, grade, and attributes such as rolling length, rolling width, rolling thickness, and furnace exit temperature in the slab information, the data information is divided into two parts: hot roll material and main material, represented by sets S3 and S4 respectively.

[0039] Step 3: Based on the hot rolling scheduling problem quantitatively described in Step 1 and the slab grouping in Step 2, start compiling the rolling plan using a heuristic algorithm.

[0040] Step 3.1: Bind the slabs in set S2. Only two slabs with similar specifications can participate in production scheduling, and they must appear bound together. Therefore, use a function to find slabs with similar specifications in the set, bind them, and store them in set S4 for later use. Also, mark them as heat-rolling material and main body material.

[0041] Step 3.2: If the total number of slabs in set S1 exceeds 8, sort the slabs in set S1 according to the requirements in order of thickness from thickest to thinnest and width from widest to narrowest, and use this as the final output of the algorithm.

[0042] Step 3.3: Arrange the widest hot-charged slab as the first slab, denoted as slab i. Relax the constraints, select the hot-charged slab with the smallest penalty value and insert it at the end of the current rolling schedule. Continue to select the 1st, 2nd, ..., nth hot-charged slabs according to this rule until the constraints are not met or the number of available slabs is 0. If there are two hot-charged short-length slabs in the S4 set that meet the requirements, they are also treated as one slab and participate in the sorting in this step.

[0043] Step 3.4: Perform a violation check on the hot-charged slab plan. If there is a violation between two slabs, select the slab with the smallest total penalty value between the two from the cold slab set S1 and insert it between them. If no violation can be found, skip this step.

[0044] Step 3.5: According to the process specifications, select a heat-pressing roller material that has a reasonable transition with the first slab in the result set. If such a heat-pressing roller material exists, insert it at the beginning of the result set and skip this step. If not found, find the slab with the smallest transition penalty value with the first slab in the main material set S1 and insert it at the beginning of the result set. Repeat this step until a heat-pressing roller material that meets the standard is found and inserted at the beginning of the result set.

[0045] Step 3.6: Continue to select the heat-pressing roller material from the heat-pressing roller material set S2 according to the target with the smallest penalty value, and insert it at the beginning of the plan until the number of heat-pressing roller materials is 4. If there are two short-length blanks bound in the S4 set that meet the requirements, they are also treated as a blank and participate in the sorting of this step. If the number of heat-pressing roller materials is less than 4, mark them for the on-site planners to make a decision.

[0046] Step 3.7: Check whether the total weight of the slabs in the compiled plan is greater than the specified tonnage of 1500. If it is, retain this plan as plan1 and continue to compile the next plan. If it is not, continue to select the slab with the smallest penalty value between it and the last slab from sets S1 and S4 and insert it into the end of the result set.

[0047] Step 3.8: Insert the processed set from step 3.2 at the end of the result set.

[0048] Step 3.9: Output plan.

[0049] Step 4: Output in log format, and at the same time, perform another violation check on the entire plan, mark the non-compliant slabs, and calculate and display the rolling length, rolling width, rolling thickness, and furnace exit temperature information of the compliant slabs.

[0050] Specifically, step 1.2 is as follows:

[0051] (1) Minimize the jump penalty value between adjacent slabs

[0052] The jump penalty value between adjacent slabs includes: the sum of the jump penalty values ​​between adjacent slabs of the main body material, the sum of the jump penalty values ​​between adjacent slabs of the hot rolling material, and the jump penalty value between the main body material and the hot rolling material.

[0053] The jump penalty value between adjacent slabs is quantitatively described mathematically, resulting in the value that minimizes the jump penalty value between adjacent slabs:

[0054]

[0055] Where K is the set of rolling units, I is the set of slabs, and c ij s is the sum of the jump penalty values ​​between adjacent slabs of the main material. ik This indicates that the value is 1 when slab i is the main material in rolling plan k, and 0 otherwise. ijk This indicates that when slab j is within the rolling plan k and is rolled immediately after slab i, the value is 1; otherwise, it is 0. k∈K ∑ i∈I ∑ j∈I,j≠i c ij s ik s jk x ijk c′ represents the jump penalty value between adjacent slabs of the main material. ij s′ is the sum of the jump penalty values ​​between adjacent slabs of the hot rolling material. ik This indicates that the value is 1 when slab i is a hot roll material within the rolling plan k, and 0 otherwise. ∑ k∈K ∑ i∈I ∑ j∈I,j≠i c′ij s′ ik s′ jk x ijk f represents the jump penalty value between adjacent slabs of the hot rolling material. ij This indicates that the value is 1 when slab i is the hot rolling material and slab j is the main material, and 0 otherwise. ij The sum of the jump penalty values ​​for the main material and the ironing roller material, ∑ k∈K ∑ i∈I ∑ j∈I,j≠ i f ij mz ij x ijk This indicates the jump penalty value between the main material and the hot rolling material.

[0056] (2) Maximize the heat charging rate of the rolling unit

[0057] In order to effectively reduce energy consumption and production costs and improve production efficiency, the hot charging rate of the rolling unit will be maximized.

[0058] The maximum hot charging rate of the rolling unit is quantitatively described using mathematical expressions:

[0059]

[0060] Among them, w ak n represents the number of hot-charged slabs contained in the k-th rolling unit. k This represents the number of slabs in the k-th rolling unit.

[0061] Step 1.3: Quantitatively describe the process constraints of the specified hot rolling production schedule, as follows:

[0062] (1) Uniqueness constraint: A slab can only appear in one rolling unit, two identical slabs cannot exist in the same rolling unit, and a slab can only be adjacent to the preceding and following slabs once. The mathematical expression for this constraint is:

[0063] ∑ k∈K y ik ≤1, i∈I 1-1

[0064] y 0k =1,k=1,2,...,N 1-2

[0065] ∑ i∈I∪{0} x ijk =∑ j∈I∪{0} x jik =y ik , i∈I, k∈{0, 1, 2,..., n} 1-3

[0066]

[0067] Where K is the set of rolling units, I is the set of slabs, N is the total number of rolling units, and y ik This indicates that the value of slab i is 1 when it is within the rolling plan k, and 0 otherwise. ijk This indicates that when slab j is within the rolling plan k and is rolled immediately after slab i, the value is 1; otherwise, it is 0.

[0068] (2) Rolling process constraints: In a rolling unit, the main material and the hot roll material can only be adjacent to each other at most once, and the hot roll material must be in front of the main material and the main material must be behind it. They cannot be interleaved. The mathematical expression for this constraint is:

[0069] ∑ i∈I ∑ j∈I,i≠j s′ ik s jk x ijk ≤1, k=1,2,...,N1-6

[0070] Where I is the set of slabs, N is the total number of rolling units, and s′ ik This indicates that the value is 1 when slab i is a hot roll material within the rolling plan k, and 0 otherwise. ik This indicates that the value is 1 when slab i is the main material in rolling plan k, and 0 otherwise. ijk This indicates that when slab j is within the rolling plan k and is rolled immediately after slab i, the value is 1; otherwise, it is 0.

[0071] (3) Number of hot rolling slabs: The number of hot rolling slabs in a rolling unit should be between the maximum and minimum required values. The mathematical expression for this constraint is:

[0072] nw min ≤∑ i∈I s′ ik ≤nw max k = 1, 2, ..., N 1-7

[0073] Among them, nw min s′ represents the minimum number of hot roll slabs contained in a rolling unit. ik This indicates that the value is 1 when slab i is a hot roll material within the rolling plan k, and 0 otherwise. max This represents the maximum value of hot roll slabs contained in a rolling unit.

[0074] (4) Total Rolling Weight Limit: Considering the working life and wear of the rolls, production plans should be arranged reasonably to avoid long-term high-load operation, reduce roll wear, improve utilization rate, and ensure the rational use of rolls. The mathematical expression for this constraint is:

[0075] G min ≤∑ i∈I wei (s ik +s′ ik )y ik ≤G max k = 1, 2, ..., N 1-8

[0076] Among them, G min We represent the minimum weight rolled in a rolling unit. i G represents the weight of the slab. max s′ represents the maximum weight rolled in a single rolling unit. ik This indicates that the value is 1 when slab i is a hot roll material within the rolling plan k, and 0 otherwise. ik This indicates that the value is 1 when slab i is the main material in rolling plan k, and 0 otherwise.

[0077] (5) Width constraints: Width constraints include the width constraints of the main body material, the width constraints of the ironing roller material, and the width constraints between the ironing roller material and the main body material.

[0078] Width constraints, including those for the main body material, are as follows:

[0079] (w i -w j )s ik s jk x ijk ≥0,i,j∈I,k=1,2,...,N 1-9

[0080] (w i -w j )s ik s jk x ijk ≤WJ max ,i,j∈I,k=1,2,...,N 1-10

[0081] Among them, w i Indicates the rolling width of the slab, s ik This indicates that the value is 1 when slab i is the main material in rolling plan k, and 0 otherwise. ijk This indicates that the value is 1 when slab j is within the rolling plan k and is rolled immediately after slab i; otherwise, it is 0. WJ max This indicates the maximum jump in the rolling width of the main material.

[0082] The width constraint of the ironing roller material is:

[0083] (w j -w i )s′ ik s′ jk x ijk ≥0,i,j∈I,k=1,2,...,N 1-11

[0084] (w j -w i )s′ ik s′ jk x ijk ≤W′J max ,i,j∈I,k=1,2,...,N 1-12

[0085] Among them, s′ ik This indicates that the value is 1 when slab i is a hot roll material within the rolling plan k, and 0 otherwise. W′J max This indicates the maximum jump in width of the hot ironing roller.

[0086] The width constraint between the ironing roller material and the main body material is:

[0087] (w i -w j )f ij x ijk ≥0,i,j∈I,k=1,2,...,N 1-13

[0088] (w i -w j )f ij x ijk ≤WM′J max ,i,j∈I,k=1,2,...,N 1-14

[0089] Among them, f ij This indicates that the value is 1 when slab i is the hot rolling material and slab j is the main material, and 0 otherwise. WM′J max This indicates the maximum width jump between the main body materials of the hot ironing roller.

[0090] (6) Thickness constraint: The rolling thickness jump between adjacent slabs of the main material cannot exceed a given upper limit. The mathematical expression for this constraint is:

[0091] (th i -th j )y ik y jk x ijk ≥-TJ max ,i,j∈I,k=1,2,...,N 1-15

[0092] (th i -th j )y ik y jk x ijk ≥-TJ max ,i,j∈I,k=1,2,...,N 1-16

[0093] Where I is the set of slabs, N is the total number of rolling units, and th i Indicates the rolling thickness of the slab, y ik This indicates that the value of slab i is 1 when it is within the rolling plan k, and 0 otherwise. ijk This indicates that the value is 1 when slab j is within the rolling plan k and is rolled immediately after slab i; otherwise, it is 0. (TJ) max This indicates the maximum value of the thickness jump in the rolling process of the main material.

[0094] (7) Hardness constraint: The rolling hardness jump between adjacent slabs of the main material cannot exceed a given upper limit. The mathematical expression for this constraint is:

[0095] (h i -h j )y ik y jk x ijk ≥-HJ max ,i,j∈I,k=1,2,...,N 1-17

[0096] (h i -h j )y ik y jk x ijk ≥-HJ max ,i,j∈I,k=1,2,...,N 1-18

[0097] in, hi The rolling hardness of the slab is represented by I, where I is the set of slabs and N is the total number of rolling units. i Indicates the rolling thickness of the slab, y ik This indicates that the value of slab i is 1 when it is within the rolling plan k, and 0 otherwise. ijk This indicates that the value is 1 when slab j is within the rolling plan k and is rolled immediately after slab i; otherwise, it is 0. (HJ) max This indicates the maximum jump in the rolling hardness of the main material.

[0098] (8) Exit Temperature Constraint: The exit temperature jump between adjacent slabs of the main material cannot exceed a given upper limit. The mathematical expression for this constraint is:

[0099] (f i -f j )y ik y jk x ijk ≥-FT max ,i,j∈I,k=1,2,...,N 1-19

[0100] (f i -f j)y ik y jk x ijk ≤FT max ,i,j∈I,k=1,2,...,N 1-20

[0101] Among them, f i This indicates the furnace exit temperature of the slab, I is the set of slabs, N is the total number of rolling units, and th i Indicates the rolling thickness of the slab, y ik This indicates that the value of slab i is 1 when it is within the rolling plan k, and 0 otherwise. ijk This indicates that the value is 1 when slab j is within the rolling plan k and is rolled immediately after slab i; otherwise, it is 0. FT max This indicates the maximum temperature jump of the main material when it exits the furnace.

[0102] (9) Constraint on the length of slabs of the same width: The total length of continuously rolled slabs of the same width should not exceed the given maximum length, otherwise it will affect the surface quality of the rolls and slabs. The mathematical expression for this constraint is:

[0103]

[0104] Among them, z ijk This indicates that the value is 1 when both slab i and slab j are within the rolling plan k and slab i and slab j have the same width; otherwise, it is 0. i L represents the rolling width of the slab. same This indicates the maximum number of kilometers of the same width for the main material.

[0105] Step 4: Calculate the target value mentioned in step 1.2 (excluding the data in the final S1 set), output it in log form, and at the same time, perform a violation check on the entire plan again. Mark the slabs that violate the constraint rules mentioned in step 1.3 between the front and rear slabs, and calculate and display the rolling length, rolling width, rolling thickness and furnace exit temperature information of the slabs that meet the requirements.

[0106] An electronic device includes a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor, when executing the program, implements the aforementioned dynamic violation detection and slab recommendation hot rolling production control method.

[0107] A computer-readable storage medium having computer instructions stored thereon, which, when executed by a processor, implement the aforementioned dynamic violation detection and slab recommendation hot rolling production control method.

[0108] Compared with the prior art, the advantages of the present invention are as follows:

[0109] The method and process of this invention are stable. Through the production control method provided by this invention, a rolling plan can be generated within 1-2 seconds while ensuring production safety and stable equipment operation. This effectively improves personnel operating efficiency, and the plan can meet on-site needs. The transition between slabs is smooth, effectively increasing the proportion of hot-charged slabs in the rolling plan and reducing enterprise energy consumption. The proposed dynamic violation inspection and slab recommendation functions allow on-site personnel to determine the instructions that need to be issued in a timely manner, so as to produce slabs that meet the plan requirements in the shortest possible time. Furthermore, consideration for special steel grades can maximize the utilization rate of slabs in inventory and rationalize the inventory structure. In summary, this invention not only improves the efficiency of on-site personnel in creating plans but also increases the hot-charged rate and improves the smoothness of the plan. It also adds consideration for the scheduling of special varieties and includes dynamic violation inspection and slab recommendation functions, achieving optimal production scheduling, improving the efficiency of manual planning, and providing a better user experience while flexibly responding to on-site changes. Attached Figure Description

[0110] Figure 1 Rolling unit structure diagram. Detailed Implementation

[0111] To enhance understanding of the present invention, the present invention will be described in detail below with reference to embodiments.

[0112] Example 1: This implementation requires the following hardware system: at least one PC; at least one fiber optic or cable interface; and at least one router. These devices form a small local area network (LAN) and connect to the enterprise ERP system (an ERP system is a management platform built on information technology, using a systematic management approach to provide decision-making and operational tools for enterprise decision-makers and employees). Install a Microsoft SQL Server 2000 database system on the PC and configure the server address, server port, database name, username, and password.

[0113] Data files are retrieved from the enterprise FTP server and written to the local SQL Server. This includes information on slabs produced in steelmaking (hot-charged slabs) and slabs in the slab library (cold-charged slabs). The hot-rolled planned slab information and the core slab information in the slab library both include: slab number, tapping mark, grade, contract number, storage area, material number, roll length, roll width, roll thickness, furnace tapping temperature, PONO number, slab length, slab width, and slab thickness.

[0114] A dynamic violation detection and slab recommendation method for hot rolling production scheduling includes the following steps:

[0115] Step 1: Quantitatively describe the hot rolling production scheduling problem

[0116] Each rolling unit consists of two parts: the hot strip and the main strip. In the initial stage of the rolling unit, the hot strip is rolled to achieve thermal equilibrium and stability of the rolls. The hot strip accounts for a small proportion of the rolling unit and is generally made of strip with lower hardness, followed by the rolling of the main strip. Figure 1 As shown.

[0117] Step 1.1: Select decision variables for hot rolling production scheduling.

[0118] (1) Decision variable x ijk When slab j is within the rolling schedule k and is rolled immediately following slab i, then x ijk The value is 1; otherwise, it is 0.

[0119] (2) Decision variable y ik When slab i is within the rolling plan k, then y ik The value is 1 if it is not 1, otherwise it is 0.

[0120] (3) Decision variable s ik When slab i is the main material within the rolling plan k, then s ik The value is 1 if it is not 1, otherwise it is 0.

[0121] (4) Decision variable s′ ik When slab i is a hot roll material within the rolling plan k, then s′ ik The value is 1 if it is not 1, otherwise it is 0.

[0122] (5) Decision variable f ij When slab i is the hot rolling material and slab j is the main material, then f ij The value is 1; otherwise, it is 0.

[0123] (6) Decision variable z ijk When both slab i and slab j are within the rolling plan k, and slab i and slab j have the same width, then z ijk The value is 1; otherwise, it is 0.

[0124] Step 1.2: Quantitatively describe the hot rolling production scheduling target.

[0125] The hot rolling production scheduling objectives include: minimizing the jump penalty value between adjacent slabs and maximizing the hot charging rate of the rolling unit.

[0126] in:

[0127] (1) Minimize the jump penalty value between adjacent slabs

[0128] The jump penalty value between adjacent slabs includes: the sum of the jump penalty values ​​between adjacent slabs of the main body material, the sum of the jump penalty values ​​between adjacent slabs of the hot rolling material, and the jump penalty value between the main body material and the hot rolling material.

[0129] The jump penalty value between adjacent slabs is quantitatively described mathematically, resulting in the value that minimizes the jump penalty value between adjacent slabs:

[0130]

[0131] Where K is the set of rolling units, I is the set of slabs, and c ij s is the sum of the jump penalty values ​​between adjacent slabs of the main material. ik This indicates that the value is 1 when slab i is the main material in rolling plan k, and 0 otherwise. ijk This indicates that when slab j is within the rolling plan k and is rolled immediately after slab i, the value is 1; otherwise, it is 0. k∈K ∑ i∈I ∑ j∈I,j≠i c ij s ik s jk x ijk c′ represents the jump penalty value between adjacent slabs of the main material. ij s′ is the sum of the jump penalty values ​​between adjacent slabs of the hot rolling material. ik This indicates that the value is 1 when slab i is a hot roll material within the rolling plan k, and 0 otherwise. ∑ k∈K ∑ i∈I ∑ j∈I,j≠i c′ ij s′ ik x ijk f represents the jump penalty value between adjacent slabs of the hot rolling material. ij This indicates that the value is 1 when slab i is the hot rolling material and slab j is the main material, and 0 otherwise. ij The sum of the jump penalty values ​​for the main material and the ironing roller material, ∑ k∈K ∑ i∈I ∑ j∈I,j≠i f ij mz ij x ijk This indicates the jump penalty value between the main material and the hot rolling material.

[0132] (2) Maximize the heat charging rate of the rolling unit

[0133] In order to effectively reduce energy consumption and production costs and improve production efficiency, the hot charging rate of the rolling unit will be maximized.

[0134] The maximum hot charging rate of the rolling unit is quantitatively described using mathematical expressions:

[0135]

[0136] Among them, w ak n represents the number of hot-charged slabs contained in the k-th rolling unit. k This represents the number of slabs in the k-th rolling unit.

[0137] Step 1.3: Quantitatively describe the process constraints of the specified hot rolling production schedule, as follows:

[0138] (1) Uniqueness constraint: A slab can only appear in one rolling unit, two identical slabs cannot exist in the same rolling unit, and a slab can only be adjacent to the preceding and following slabs once. The mathematical expression for this constraint is:

[0139] ∑ k∈K y ik ≤1, i∈I 1-1

[0140] y 0k =1,k=1,2,...,N 1-2

[0141] ∑ i∈I∪{0} x ijk =∑ j∈I∪{0} x jik =y ik , i∈I, k∈{0, 1, 2,..., n} 1-3

[0142]

[0143] Where K is the set of rolling units, I is the set of slabs, N is the total number of rolling units, and y ik This indicates that the value of slab i is 1 when it is within the rolling plan k, and 0 otherwise. ijk This indicates that when slab j is within the rolling plan k and is rolled immediately after slab i, the value is 1; otherwise, it is 0.

[0144] (2) Rolling process constraints: In a rolling unit, the main material and the hot roll material can only be adjacent to each other at most once, and the hot roll material must be in front of the main material and the main material must be behind it. They cannot be interleaved. The mathematical expression for this constraint is:

[0145] ∑ i∈I ∑ j∈I,i≠j s′ ik s jk x ijk ≤1,k=1,2,...,N 1-6

[0146] Where I is the set of slabs, N is the total number of rolling units, and s′ ik This indicates that the value is 1 when slab i is a hot roll material within the rolling plan k, and 0 otherwise.ik This indicates that the value is 1 when slab i is the main material in rolling plan k, and 0 otherwise. ijk This indicates that when slab j is within the rolling plan k and is rolled immediately after slab i, the value is 1; otherwise, it is 0.

[0147] (3) Number of hot rolling slabs: The number of hot rolling slabs in a rolling unit should be between the maximum and minimum required values. The mathematical expression for this constraint is:

[0148] nw min ≤Σ i∈I s′ ik ≤nw max k = 1, 2, ..., N 1-7

[0149] Among them, nw min s′ represents the minimum number of hot roll slabs contained in a rolling unit. ik This indicates that the value is 1 when slab i is a hot roll material within the rolling plan k, and 0 otherwise. max This represents the maximum value of hot roll slabs contained in a rolling unit.

[0150] (4) Total Rolling Weight Limit: Considering the working life and wear of the rolls, production plans should be arranged reasonably to avoid long-term high-load operation, reduce roll wear, improve utilization rate, and ensure the rational use of rolls. The mathematical expression for this constraint is:

[0151] G min ≤∑ i∈I we i (s ik +s′ ik )y ik ≤G max k = 1, 2, ..., N (1-8)

[0152] Among them, G min We represent the minimum weight rolled in a rolling unit. i G represents the weight of the slab. max s′ represents the maximum weight rolled in a single rolling unit. ik This indicates that the value is 1 when slab i is a hot roll material within the rolling plan k, and 0 otherwise. ik This indicates that the value is 1 when slab i is the main material in rolling plan k, and 0 otherwise.

[0153] (5) Width constraints: Width constraints include the width constraints of the main body material, the width constraints of the ironing roller material, and the width constraints between the ironing roller material and the main body material.

[0154] Width constraints, including those for the main body material, are as follows:

[0155] (w i -w j )s ik s jk x ijk ≥0,i,j∈I,k=1,2,...,N 1-9

[0156] (w i -w j )s ik s jk x ijk ≤WJ max ,i,j∈I,k=1,2,...,N 1-10

[0157] Among them, w i Indicates the rolling width of the slab, s ik This indicates that the value is 1 when slab i is the main material in rolling plan k, and 0 otherwise. ijk This indicates that the value is 1 when slab j is within the rolling plan k and is rolled immediately after slab i; otherwise, it is 0. WJ max This indicates the maximum jump in the rolling width of the main material.

[0158] The width constraint of the ironing roller material is:

[0159] (w j -w i )s′ ik s′ jk x ijk ≥0,i,j∈I,k=1,2,...,N 1-11

[0160] (w j -w i )s′ ik s′ jk x ijk ≤W′J max ,i,j∈I,k=1,2,...,N 1-12

[0161] Among them, s′ ik This indicates that the value is 1 when slab i is a hot roll material within the rolling plan k, and 0 otherwise. W′J max This indicates the maximum jump in width of the hot ironing roller.

[0162] The width constraint between the ironing roller material and the main body material is:

[0163] (w i -w j )f ij x ijk ≥0,i,j∈I,k=1,2,...,N 1-13

[0164] (wi -w j )f ij x ijk ≤WM′J max ,i,j∈I,k=1,2,...,N 1-14

[0165] Among them, f ij This indicates that the value is 1 when slab i is the hot rolling material and slab j is the main material, and 0 otherwise. WM′J max This indicates the maximum width jump between the main body materials of the hot ironing roller.

[0166] (6) Thickness constraint: The rolling thickness jump between adjacent slabs of the main material cannot exceed a given upper limit. The mathematical expression for this constraint is:

[0167] (th i -th j )y ik y jk x ijk ≥-TJ max ,i,j∈I,k=1,2,...,N 1-15

[0168] (th i -th j )y ik y jk x ijk ≤TJ max ,i,j∈I,k=1,2,...,N 1-16

[0169] Where I is the set of slabs, N is the total number of rolling units, and th i Indicates the rolling thickness of the slab, y ik This indicates that the value of slab i is 1 when it is within the rolling plan k, and 0 otherwise. ijk This indicates that the value is 1 when slab j is within the rolling plan k and is rolled immediately after slab i; otherwise, it is 0. (TJ) max This indicates the maximum value of the thickness jump in the rolling process of the main material.

[0170] (7) Hardness constraint: The rolling hardness jump between adjacent slabs of the main material cannot exceed a given upper limit. The mathematical expression for this constraint is:

[0171] (h i -h j )y ik y jk x ijk ≥-HJ max ,i,j∈I,k=1,2,...,N 1-17

[0172] (h i -hj )y ik y jk x ijk ≤HJ max ,i,j∈I,k=1,2,...,N 1-18

[0173] Among them, h i The rolling hardness of the slab is represented by I, where I is the set of slabs and N is the total number of rolling units. i Indicates the rolling thickness of the slab, y ik This indicates that the value of slab i is 1 when it is within the rolling plan k, and 0 otherwise. ijk This indicates that the value is 1 when slab j is within the rolling plan k and is rolled immediately after slab i; otherwise, it is 0. (HJ) max This indicates the maximum jump in the rolling hardness of the main material.

[0174] (8) Exit Temperature Constraint: The exit temperature jump between adjacent slabs of the main material cannot exceed a given upper limit. The mathematical expression for this constraint is:

[0175] (f i -f j )y ik y jk x ijk ≥-FT max ,i,j∈I,k=1,2,...,N 1-19

[0176] (f i -f j )y ik y jk x ijk ≥FT max ,i,j∈I,k=1,2,...,N 1-20

[0177] Among them, f i This indicates the furnace exit temperature of the slab, I is the set of slabs, N is the total number of rolling units, and th i Indicates the rolling thickness of the slab, y ik This indicates that the value of slab i is 1 when it is within the rolling plan k, and 0 otherwise. ijk This indicates that the value is 1 when slab j is within the rolling plan k and is rolled immediately after slab i; otherwise, it is 0. FT max This indicates the maximum temperature jump of the main material when it exits the furnace.

[0178] (9) Constraint on the length of slabs of the same width: The total length of continuously rolled slabs of the same width should not exceed the given maximum length, otherwise it will affect the surface quality of the rolls and slabs. The mathematical expression for this constraint is:

[0179]

[0180] Among them, z ijk This indicates that the value is 1 when both slab i and slab j are within the rolling plan k and slab i and slab j have the same width; otherwise, it is 0. i L represents the rolling width of the slab. same This indicates the maximum number of kilometers of the same width for the main material.

[0181] Step 2: Group the slabs.

[0182] According to the production rules, special slabs, i.e. slabs with a thickness exceeding 6.5, are stored in set S1, while slabs with a length of less than 4.0 are stored in set S2. Finally, based on the steel tapping mark, grade, and attributes such as rolling length, rolling width, rolling thickness, and furnace exit temperature in the slab information, the data information is divided into two parts: hot roll material and main material, represented by sets S3 and S4 respectively.

[0183] Step 3: Based on the hot rolling scheduling problem quantitatively described in Step 1 and the slab grouping in Step 2, start compiling the rolling plan using a heuristic algorithm.

[0184] Step 3.1: Bind the slabs in set S2. Only two slabs with similar specifications can participate in production scheduling, and they must appear bound together. Therefore, use a function to find slabs with similar specifications in the set, bind them, and store them in set S4 for later use. Also, mark them as heat-rolling material and main body material.

[0185] Step 3.2: If the total number of slabs in set S1 exceeds 8, sort the slabs in set S1 according to the requirements in order of thickness from thickest to thinnest and width from widest to narrowest, and use this as the final output of the algorithm.

[0186] Step 3.3: Arrange the widest hot-charged slab as the first slab, denoted as slab i. Relax the constraints, select the hot-charged slab with the smallest penalty value and insert it at the end of the current rolling schedule. Continue to select the 1st, 2nd, ..., nth hot-charged slabs according to this rule until the constraints are not met or the number of available slabs is 0. If there are two hot-charged short-length slabs in the S4 set that meet the requirements, they are also treated as one slab and participate in the sorting in this step.

[0187] Step 3.4: Perform a violation check on the hot-charged slab plan. If there is a violation between two slabs, select the slab with the smallest total penalty value between the two from the cold slab set S1 and insert it between them. If no violation can be found, skip this step.

[0188] Step 3.5: According to the process specifications, select a heat-pressing roller material that has a reasonable transition with the first slab in the result set. If such a heat-pressing roller material exists, insert it at the beginning of the result set and skip this step. If not found, find the slab with the smallest transition penalty value with the first slab in the main material set S1 and insert it at the beginning of the result set. Repeat this step until a heat-pressing roller material that meets the standard is found and inserted at the beginning of the result set.

[0189] Step 3.6: Continue to select the heat-pressing roller material from the heat-pressing roller material set S2 according to the target with the smallest penalty value, and insert it at the beginning of the plan until the number of heat-pressing roller materials is 4. If there are two short-length blanks bound in the S4 set that meet the requirements, they are also treated as a blank and participate in the sorting of this step. If the number of heat-pressing roller materials is less than 4, mark them for the on-site planners to make a decision.

[0190] Step 3.7: Check whether the total weight of the slabs in the compiled plan is greater than the specified tonnage of 1500. If it is, retain this plan as plan1 and continue to compile the next plan. If it is not, continue to select the slab with the smallest penalty value between it and the last slab from sets S1 and S4 and insert it into the end of the result set.

[0191] Step 3.8: Insert the processed set from step 3.2 at the end of the result set.

[0192] Step 3.9: Output plan.

[0193] Step 4: Output in log format, and at the same time, perform another violation check on the entire plan, mark the non-compliant slabs, and calculate and display the rolling length, rolling width, rolling thickness, and furnace exit temperature information of the compliant slabs.

[0194] It should be noted that the above embodiments are not intended to limit the scope of protection of the present invention. Equivalent transformations or substitutions made based on the above technical solutions all fall within the scope of protection of the claims of the present invention.

Claims

1. A method for controlling hot-rolled production with dynamic violation inspection and slab recommendation, characterized in that, Includes the following steps: Step 1: Quantitatively describe the hot rolling production scheduling problem. Each rolling unit consists of two parts: the hot strip and the main strip. In the initial stage of the rolling unit, in order to achieve thermal equilibrium and stability of the rolls, the hot strip needs to be rolled. The hot strip accounts for a small proportion of the rolling unit, and it is made of strip with lower hardness. Then the main strip is rolled. Step 1.1: Select decision variables for hot rolling production scheduling. (1) Decision variable x ijk When slab j is within the rolling schedule k and is rolled immediately following slab i, then x ijk The value is 1 if it is not 1, otherwise it is 0. (2) Decision variable y ik When slab i is within the rolling plan k, then y ik The value is 1 if it is not 1, otherwise it is 0. (3) Decision variable s ik When slab i is the main material within the rolling plan k, then s ik The value is 1 if it is not 1, otherwise it is 0. (4) Decision variable s′ ij When slab i is a hot roll material within the rolling plan k, then s′ ik The value is 1 if it is not 1, otherwise it is 0. (5) Decision variable f ij When slab i is the hot rolling material and slab j is the main material, then f ij The value is 1 if it is not 1, otherwise it is 0. (6) Decision variable z ijk When both slab i and slab j are within the rolling plan k, and slab i and slab j have the same width, then z ijk The value is 1 if it is not 1, otherwise it is 0. Step 1.2: Quantitatively describe the hot rolling production scheduling target. Hot rolling production scheduling objectives include: minimizing the jump penalty between adjacent slabs and maximizing the hot charge rate of rolling units. in: (1) Minimize the jump penalty value between adjacent slabs. The jump penalty value between adjacent slabs includes: the sum of the jump penalty values ​​between adjacent slabs of the main body material, the sum of the jump penalty values ​​between adjacent slabs of the hot rolling material, and the jump penalty value between the main body material and the hot rolling material. (2) Maximize the hot charging rate of the rolling unit. The hot charging rate of a rolling unit refers to the proportion of hot-charged slabs in a rolling unit out of all slabs in that rolling unit. Step 1.3: Quantitatively describe the process constraints of the specified hot rolling production schedule. (1) Uniqueness constraint: A slab can only appear in one rolling unit, two identical slabs cannot exist in the same rolling unit, and a slab can only be adjacent to the preceding and following slabs once. (2) Rolling process constraints: In a rolling unit, the main material and the hot roll material can only be adjacent to each other at most once, and the hot roll material must be in front of the main material and the main material must be behind it. They cannot be interleaved. (3) Quantity constraint of hot rolling material: The number of hot rolling material slabs in a rolling unit should be between the maximum and minimum required values. (4) Total rolling weight limit: Considering the working life and wear of the rolls, production plans should be arranged reasonably to avoid long-term high-load operation, reduce roll wear, improve utilization rate, and ensure the rational use of rolls. (5) Width constraints: Width constraints include the width constraints of the main body material, the width constraints of the ironing roller material, and the width constraints between the ironing roller material and the main body material. (6) Thickness constraint: The rolling thickness jump between adjacent slabs of the main material cannot exceed the given upper limit. (7) Hardness constraint: The rolling hardness jump between adjacent slabs of the main material cannot exceed the given upper limit. (8) Exit temperature constraint: The exit temperature jump between adjacent slabs of the main material cannot exceed the given upper limit. (9) Constraint on length of continuous width: The total length of continuously rolled slabs of the same width should not exceed the given maximum length, otherwise it will affect the surface quality of the rolls and slabs. Step 2: Group the slabs. According to production rules, special slabs, i.e., slabs with a thickness exceeding 6.5 mm, are stored in set S1, while slabs with a length of 4.0 mm or less are stored in set S2. Finally, based on the steel tapping mark, grade, and attributes such as rolling length, rolling width, rolling thickness, and furnace exit temperature in the slab information, the data is divided into two parts: hot roll material and main material, represented by sets S3 and S4 respectively. Step 3: Based on the quantitative description of the hot rolling scheduling problem in Step 1 and the slab grouping in Step 2, a heuristic algorithm is used to begin compiling the rolling plan. Step 3.1: Bind the slabs in set S2. Only two slabs with similar specifications can participate in production scheduling, and they must appear bound together. Therefore, use a function to find slabs with similar specifications in the set, bind them, and store them in set S4 for later use. Also, mark them as heat-pressing roller material and main body material. Step 3.2: If the total number of slabs in set S1 exceeds 8, sort the slabs in set S1 according to the requirements, from thickest to thinnest and from widest to narrowest, and use this as the final output of the algorithm. Step 3.3: Arrange the widest hot-charged slab as the first slab, denoted as slab i. Relax the constraints, select the hot-charged slab with the smallest penalty value and insert it at the end of the current rolling schedule. Continue selecting the 1st, 2nd, ..., nth hot-charged slabs according to this rule until the constraints are not met or the number of selectable slabs is 0. If there are two bound hot-charged short-length slabs in set S4 that meet the requirements, they are also treated as one slab and included in this sorting step. Step 3.4: Perform a violation check on the hot-charged slab plan. If a violation exists between two slabs, select the slab with the smallest sum of penalties between the two from the cold-charged slab set S1 and insert it between them. If no violation is found, skip this step. Step 3.5: According to the process specifications, select a heat-pressing roller material that has a reasonable transition with the first slab in the result set. If such a heat-pressing roller material exists, insert it at the beginning of the result set and skip this step. If not found, search for the slab in the main material set S1 that has the smallest transition penalty value with the first slab set and insert it at the beginning of the result set. Repeat this step until a heat-pressing roller material that meets the standard is found and inserted at the beginning of the result set. Step 3.6: Continue selecting heat-sealing rollers from set S2 based on the target with the smallest penalty value and insert them at the beginning of the plan until the number of heat-sealing rollers is 4. If there are two short-length blanks bound together in set S4 that meet the requirements, they are also treated as one blank and included in the sorting of this step. If the number of heat-sealing rollers is less than 4, mark them for the on-site planners to make a decision. Step 3.7: Check if the total weight of the slabs in the compiled plan exceeds the specified tonnage of 1500. If it does, retain this plan as plan1 and continue compiling the next plan. If it does not, continue selecting the slab with the smallest penalty value between it and the last slab from sets S1 and S4 and insert it into the end of the result set. Step 3.8: Insert the processed set from Step 3.2 at the end of the result set. Step 3.9: Output plan, Step 4: Output in log format, and at the same time, perform another violation check on the entire plan, mark the non-compliant slabs, and calculate and display the rolling length, rolling width, rolling thickness, and furnace exit temperature information of the compliant slabs.

2. The hot-rolled production control method for dynamic violation inspection and slab recommendation according to claim 1, characterized in that, In step 1.2, the specific details are as follows: (1) Minimize the jump penalty value between adjacent slabs. The jump penalty value between adjacent slabs includes: the sum of the jump penalty values ​​between adjacent slabs of the main body material, the sum of the jump penalty values ​​between adjacent slabs of the hot rolling material, and the jump penalty value between the main body material and the hot rolling material. The jump penalty value between adjacent slabs is quantitatively described mathematically, resulting in the value that minimizes the jump penalty value between adjacent slabs: Where K is the set of rolling units, I is the set of slabs, and c ij s is the sum of the jump penalty values ​​between adjacent slabs of the main material. ik This indicates that the value is 1 when slab i is the main material in rolling plan k, and 0 otherwise. ijk This indicates that when slab j is within the rolling plan k and is rolled immediately after slab i, the value is 1; otherwise, it is 0. ∑ k∈K ∑ i∈I ∑ j∈I,j≠i c ij s ik s jk x ijk c′ represents the jump penalty value between adjacent slabs of the main material. ij s′ is the sum of the jump penalty values ​​between adjacent slabs of the hot rolling material. ik This indicates that the value is 1 when slab i is a hot roll material within the rolling plan k, and 0 otherwise. ∑ h∈K ∑ i∈I ∑ j∈I,j≠i c′ ij s′ ik s′ jk x ijk f represents the jump penalty value between adjacent slabs of the hot rolling material. ij This indicates that the value is 1 when slab i is the hot rolling material and slab j is the main material, and 0 otherwise. ij The sum of the jump penalty values ​​for the main material and the ironing roller material, ∑ h∈K ∑ i∈I ∑ j∈I,j≠i f ij mz ij x ijk This indicates the jump penalty value between the main material and the hot rolling material. (2) Maximize the heat charging rate of the rolling unit To effectively reduce energy consumption and production costs, and improve production efficiency, the hot charging rate of the rolling unit will be maximized. The maximum hot charging rate of the rolling unit is quantitatively described using mathematical expressions: Among them, w ak n represents the number of hot-charged slabs contained in the k-th rolling unit. k This represents the number of slabs in the k-th rolling unit.

3. The hot-rolled production control method for dynamic violation inspection and slab recommendation according to claim 1, characterized in that: Step 1.3: Quantitatively describe the process constraints of the specified hot rolling production schedule, as follows: (1) Uniqueness constraint: A slab can only appear in one rolling unit, two identical slabs cannot exist in the same rolling unit, and a slab can only be adjacent to the preceding and following slabs once. The mathematical expression for this constraint is: ∑ k∈K and ik ≤1, i∈I 1-1 and 0k =1,k=1,2,...,N 1-2 ∑ i∈I∪{0} x ijk =∑ j∈I∪{0} x jik =y ik ,i∈I,k∈{0,1,2,...,n} 1-3 Where K is the set of rolling units, I is the set of slabs, N is the total number of rolling units, and y ik This indicates that the value of slab i is 1 when it is within the rolling plan k, and 0 otherwise. ijk This indicates that the value is 1 when slab j is within the rolling plan k and is rolled immediately after slab i; otherwise, it is 0. (2) Rolling process constraints: In a rolling unit, the main material and the hot roll material can only be adjacent to each other at most once, and the hot roll material must be in front of the main material and the main material must be behind it. They cannot be interleaved. The mathematical expression for this constraint is: ∑ i∈I ∑ j∈I,,i≠j s′ ik s jk x ijk ≤1,k=1,2,...,N 1-6 Where I is the set of slabs, N is the total number of rolling units, and s′ ik This indicates that the value is 1 when slab i is a hot roll material within the rolling plan k, and 0 otherwise. ik This indicates that the value is 1 when slab i is the main material in rolling plan k, and 0 otherwise. ijk This indicates that the value is 1 when the slab is within the rolling plan k and immediately follows the slab i during rolling; otherwise, it is 0. (3) Number of hot rolling slabs: The number of hot rolling slabs in a rolling unit should be between the maximum and minimum required values. The mathematical expression for this constraint is: nw min ≤∑ i∈I s′ ik ≤nw max ,k=1,2,...,N 1-7 Among them, nw min s′ represents the minimum number of hot roll slabs contained in a rolling unit. ik This indicates that the value is 1 when slab i is a hot roll material within the rolling plan k, and 0 otherwise. max This represents the maximum value of hot-rolled slabs contained in a rolling unit. (4) Total Rolling Weight Limit: Considering the working life and wear of the rolls, production plans should be arranged reasonably to avoid long-term high-load operation, reduce roll wear, improve utilization rate, and ensure the rational use of rolls. The mathematical expression for this constraint is: G min ≤∑ i∈I we i (s ik +s′ ik )y ik ≤G max ,k=1,2,...,N 1-8 Among them, G min We represent the minimum weight rolled in a rolling unit. i G represents the weight of the slab. max s′ represents the maximum weight rolled in a single rolling unit. ik This indicates that the value is 1 when slab i is a hot roll material within the rolling plan k, and 0 otherwise. ik This indicates that the value is 1 when slab i is the main material in rolling plan k, and 0 otherwise. (5) Width constraints: Width constraints include the width constraints of the main body material, the width constraints of the ironing roller material, and the width constraints between the ironing roller material and the main body material. Width constraints, including those for the main body material, are as follows: (w i -w j )s ik s jk x ijk ≥0,i,j∈I,k=1,2,...,N 1-9 (w i -w j )s ik s jk x ijk ≤WJ max ,i,j∈I,k=1,2,...,N 1-10 Among them, w i Indicates the rolling width of the slab, s ik This indicates that the value is 1 when slab i is the main material in rolling plan k, and 0 otherwise. ijk This indicates that the value is 1 when the slab is within the rolling plan k and immediately follows the slab i during rolling; otherwise, it is 0. WJ max This indicates the maximum jump in the rolling width of the main material. The width constraint of the ironing roller material is: (w j -w i )s′ ik s′ jk x ijk ≥0,i,j∈I,k=1,2,...,N 1-11 (w j -w i )s′ ik s′ jk x ijk ≤W′J max ,i,j∈I,k=1,2,...,N 1-12 Among them, s′ ik This indicates that the value is 1 when slab i is a hot roll material within the rolling plan k, and 0 otherwise. W′J max This indicates the maximum jump in width of the ironing roller. The width constraint between the ironing roller material and the main body material is: (w i -w j )f ij x ijk ≥0,i,j∈I,k=1,2,...,N 1-13 (w i -w j )f ij x ijk ≤WM′J max ,i,j∈I,k=1,2,...,N 1-14 Among them, f ij This indicates that the value is 1 when slab i is the hot rolling material and slab j is the main material, and 0 otherwise. WM′J max This indicates the maximum width jump between the main body materials of the hot ironing roller. (6) Thickness constraint: The rolling thickness jump between adjacent slabs of the main material cannot exceed a given upper limit. The mathematical expression for this constraint is: (th i -th j )y ik y jk x ijk ≥-TJ max ,i,j∈I,k=1,2,...,N 1-15 (th i -th j )y′ ik y jk x ijk ≤TJ max ,i,j∈I,k=1,2,...,N 1-16 Where I is the set of slabs, N is the total number of rolling units, and th i Indicates the rolling thickness of the slab, y ik This indicates that the value of slab i is 1 when it is within the rolling plan k, and 0 otherwise. ijk This indicates that when slab j is within the rolling plan k and is rolled immediately after slab i, the value is 1; otherwise, it is 0. (TJ) max This indicates the maximum jump in the rolling thickness of the main material. (7) Hardness constraint: The rolling hardness jump between adjacent slabs of the main material cannot exceed a given upper limit. The mathematical expression for this constraint is: (h i -h j )y ik y jk x ijk ≥-HJ max ,i,j∈I,k=1,2,...,N 1-17 (h i -h j )y ik y jk x ijk ≤HJ max ,i,j∈I,k=1,2,...,N 1-18 Among them, h i The rolling hardness of the slab is represented by I, where I is the set of slabs and N is the total number of rolling units. i Indicates the rolling thickness of the slab, y ik This indicates that the value of slab i is 1 when it is within the rolling plan k, and 0 otherwise. ijk This indicates that the value is 1 when slab j is within the rolling plan k and is rolled immediately after slab i; otherwise, it is 0. (HJ) max This indicates the maximum jump in the rolling hardness of the main material. (8) Exit Temperature Constraint: The exit temperature jump between adjacent slabs of the main material cannot exceed a given upper limit. The mathematical expression for this constraint is: (f i -f j )y ik y jk x ijk ≥-FT max ,i,j∈I,k=1,2,...,N 1-19 (f i -f j )y ik y jk x ijk ≤FT max ,i,j∈I,k=1,2,...,N 1-20 Among them, f i This indicates the furnace exit temperature of the slab, I is the set of slabs, N is the total number of rolling units, and th i Indicates the rolling thickness of the slab, y ik This indicates that the value of slab i is 1 when it is within the rolling plan k, and 0 otherwise. ijk This indicates that the value is 1 when slab j is within the rolling plan k and is rolled immediately after slab i; otherwise, it is 0. FT max This indicates the maximum jump in the furnace temperature of the main material. (9) Constraint on the length of slabs of the same width: The total length of continuously rolled slabs of the same width should not exceed the given maximum length, otherwise it will affect the surface quality of the rolls and slabs. The mathematical expression for this constraint is: Among them, z ijk The value is 1 when both slab i and slab k are within the rolling plan k and slab i and slab have the same width; otherwise, it is 0. i L represents the rolling width of the slab. same This indicates the maximum number of kilometers of the same width for the main material.

4. The hot-rolled production control method for dynamic violation inspection and slab recommendation according to claim 1, characterized in that, Step 4: Calculate the target value mentioned in Step 1.2 and output it in log form. At the same time, perform another violation check on the entire plan. Mark the slabs that violate the constraint rules mentioned in Step 1.3 between the front and rear slabs, and calculate and display the rolling length, rolling width, rolling thickness and furnace exit temperature information of the slabs that meet the requirements.

5. An electronic device, comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that: When the processor executes the program, it implements a dynamic violation detection and slab recommendation hot rolling production control method as described in any one of claims 1 to 4.

6. A computer-readable storage medium storing computer instructions thereon, characterized in that: When executed by the processor, the computer instructions implement a dynamic violation detection and slab recommendation hot rolling production control method as described in any one of claims 1-4.