A tool for wind turbine tower assembly elements and method of use thereof
Patent Information
- Application Number
- CN202610985743.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-07-03
- Publication Date
- 2026-10-20
AI Technical Summary
[0003]但是现有技术中,现有风电机组塔架进行柱状塔筒部分搭建过程中,由于塔筒之间连接螺栓的孔洞数量较多,同时由于塔筒悬吊高度较高,进而导致进行塔筒对接过程中容易受环境因素影响,且仅通过施工人员人为观测,使塔筒不易对齐连接,导致实际施工效率欠佳
(1)本发明中,使用时,将调节机构通过底座放置于底层塔筒本体内部,根据塔筒本体内部空间规格,进而增减延伸杆使用数量,使顶条一端能够贴近底层塔筒本体内壁,此时在限位弹簧的支撑下,使抵片能够挤压对应贴块,使贴块能够带动贴杆挤压贴合底层塔筒本体内壁,在贴杆的支撑下,使限位弹簧能够反向支撑推片,使推片配合抵杆和限位框能够同步带动顶条、延伸杆、转杆和转块挤压底座位于塔筒本体的中心处,此时通过旋转限位螺帽,进而使限位螺帽能够推送卡架挤压贴合对应抵片,继而配合贴杆和贴块能够固定限制抵片的使用位置,进而能够固定限制底座的使用位置,再通过顶管穿过底层塔筒本体对应的连接螺栓的孔洞,进而根据顶管贯穿的连接螺栓的孔洞位置,将两个夹块配合限位圈将激光警示笔本体插设于待拼接的塔筒本体对应位置的连接螺栓的孔洞内部,使激光警示笔本体在塔筒本体悬吊过程中能够清晰指引悬吊的位置,方便在天气状况不佳时依旧能够高效进行塔筒本体的悬吊迎接处理,使设备能够高效进行应有功能的实现。
Smart Images

Figure FT_1 
Figure FT_2 
Figure FT_3
Abstract
Description
Technical Field
[0001] This invention belongs to the field of assembly equipment technology, specifically a tool for assembling components for wind turbine towers and its usage method. Background Technology
[0002] Wind power generation refers to the conversion of wind kinetic energy into mechanical kinetic energy, and then into electrical kinetic energy. It involves a wind turbine rotating under the influence of wind, converting the kinetic energy of the wind into the mechanical energy of the turbine shaft, and a generator rotating under the drive of the turbine shaft to generate electricity. It is an important form of wind energy utilization.
[0003] However, in the existing technology, during the construction of the columnar tower section of the existing wind turbine tower, the large number of holes for connecting bolts between the tower sections, coupled with the high suspension height of the tower sections, makes the tower section docking process susceptible to environmental factors. Furthermore, relying solely on manual observation by construction personnel makes it difficult to align and connect the tower sections, resulting in poor actual construction efficiency. Summary of the Invention
[0004] The purpose of this invention is to provide a tool for assembling wind turbine tower components and a method for using it, which enables efficient splicing of tower sections.
[0005] The technical solution adopted in this invention is as follows: A tool for assembling components of a wind turbine tower, comprising: an adjustment mechanism for providing the power required for splicing; A limiting mechanism is used to provide stable position support.
[0006] The adjusting mechanism includes a base, three rotating blocks, three take-up rollers, three rotating rods, three extension rods, three top bars, three bottom tubes, three limiting tubes, three connecting tubes, three top tubes, and a linkage component. The three rotating blocks are rotatably connected to the outer surface of the base. Each rotating rod is rotatably connected to one end of a corresponding rotating block. Each extension rod is threaded to one end of a corresponding rotating rod. Each top bar is threaded to one end of a corresponding extension rod. Each bottom tube is fixedly connected to the top of a corresponding top bar. Each limiting tube is threaded to the top of a corresponding bottom tube. Each connecting tube is threaded to the top of a corresponding limiting tube. Each top tube is threaded to the top of a corresponding connecting tube. Each take-up roller is rotatably connected to the outer surface of the base. The linkage component is disposed on the base.
[0007] Each of the bottom tubes has an extension hole on one side of its outer surface. The interior of each extension hole is connected to the interior of the corresponding connecting tube. Each limiting tube has a first guide block and a second guide block fixedly connected inside.
[0008] The base has a rotating gear rotatably connected to its top, a worm gear fixedly connected to its top, a connecting gear fixedly connected to the top of each take-up roller, and each connecting gear meshes with the rotating gear. A worm is rotatably connected to the outer surface of the base, and the worm meshes with the worm wheel.
[0009] Each of the rotating blocks has a bolt threaded to its top, and each of the top bars has a limit groove on one side of its outer surface.
[0010] Each of the winding rollers has a traction rope body wound on its outer surface. One end of each traction rope body slides through the corresponding extension hole and also slides through the corresponding first guide block and second guide block. One end of each traction rope body extends to the outside of the top pipe, and a locking block is fixedly connected to one end of each traction rope body.
[0011] The linkage components are provided in three sets. Each set of linkage components includes a guide wheel, two clamping blocks and a laser warning pen body. The guide wheel is sleeved on the corresponding bottom tube. Each laser warning pen body is inserted between the two clamping blocks. Each laser warning pen body has a limiting ring on its outer surface.
[0012] The limiting mechanism comprises three sets, each set including a limiting frame, a stop piece, a limiting spring, a stop rod, a bracket, a slider, and two adhesive rods. The limiting frame is fixedly connected to the top of the corresponding top bar. The stop piece is slidably inserted into the limiting frame. The limiting spring is slidably inserted into the limiting frame. The stop rod is threadedly connected to one end of the limiting frame. The bracket is slidably sleeved on the outer surface of the stop rod. One end of the bracket is in contact with the outer surface of one side of the stop piece. The slider is slidably inserted into the corresponding limiting groove. Adhesive blocks are fixedly connected to both outer surfaces of the slider by bolts. Each adhesive rod is threadedly connected to the interior of the corresponding adhesive block.
[0013] Each of the abutments has a limit nut threaded onto its outer surface, and a pusher plate is rotatably connected to one end of each abutment.
[0014] A method of using a tool for assembling components on a wind turbine tower includes the following steps: S1. Position Adjustment: Place the adjustment mechanism inside the bottom tower body via the base. Adjust the number of extension rods according to the internal space of the tower body, so that one end of the top bar can be close to the inner wall of the bottom tower body. At this time, under the support of the limit spring, the abutment can press the corresponding block, and the block can drive the stick to press against the inner wall of the bottom tower body. Under the support of the stick, the limit spring can support the push plate in the opposite direction, so that the push plate, together with the abutment and the limit frame, can synchronously drive the top bar, extension rod, rotating rod and rotating block to press the base to the center of the tower body. At this time, by rotating the limit nut, the limit screw can be adjusted. The cap can push the card holder to press and fit the corresponding abutment, and then, together with the abutment rod and abutment block, it can fix and restrict the use position of the abutment, and then fix and restrict the use position of the base. Then, the top tube passes through the hole of the corresponding connecting bolt of the bottom tower body, and then, according to the position of the hole of the connecting bolt through which the top tube passes, the two clamps and the limiting ring are used to insert the laser warning pen body into the hole of the corresponding connecting bolt of the tower body to be spliced. This allows the laser warning pen body to clearly guide the suspension position during the suspension of the tower body, so that the tower body can still be suspended and received efficiently even in bad weather conditions. S2. Rapid Assembly: When the tower body to be assembled approaches the bottom tower body, the laser warning pen illuminates the area, allowing construction workers to easily locate the corresponding bolt holes. The laser warning pen is then removed from between the two clamping blocks. One end of the traction rope at the top of the jacking pipe is secured between the two clamping blocks using a locking block. At this point, the construction workers use an existing electric drill to rotate the worm gear. The rotating worm gear, in conjunction with the worm wheel, drives the rotating gear, which in turn drives three connecting gears. These connecting gears then synchronously drive the corresponding winding roller, enabling the winding roller to pull and rewind the tower. The traction rope body allows it to move and retract along the extension holes and guide wheels of the jacking pipe, connecting pipe, limiting pipe, and bottom pipe. This allows the traction rope body to work with the locking blocks and corresponding clamping blocks to align the holes of the corresponding connecting bolts with the corresponding jacking pipe. At this point, the worm gear rotation stops, and the tower body to be spliced is lowered. This allows the jacking pipe to push out the clamping blocks inside the holes of the corresponding connecting bolts, enabling the holes of the connecting bolts of the tower body to be spliced and the bottom tower body to be quickly aligned through the jacking pipe and connecting pipe. This facilitates the rapid setting of the connecting bolts of the tower body to be spliced and the bottom tower body, allowing for efficient tower splicing.
[0015] In summary, due to the adoption of the above technical solution, the beneficial effects of the present invention are: (1) In this invention, when in use, the adjustment mechanism is placed inside the bottom tower body through the base. According to the internal space specifications of the tower body, the number of extension rods used is increased or decreased so that one end of the top bar can be close to the inner wall of the bottom tower body. At this time, under the support of the limiting spring, the abutment can press the corresponding patch, and the patch can drive the patch rod to press and adhere to the inner wall of the bottom tower body. Under the support of the patch rod, the limiting spring can support the push plate in the opposite direction, so that the push plate, together with the abutment rod and the limiting frame, can synchronously drive the top bar, extension rod, rotating rod and rotating block to press the base to the center of the tower body. At this time, by rotating the limiting nut, the limiting nut can push the card holder. The corresponding support plate is pressed and bonded together. Then, with the help of the support rod and support block, the position of the support plate can be fixed and restricted. This, in turn, can fix and restrict the position of the base. Then, the jacking pipe passes through the hole of the corresponding connecting bolt on the bottom tower body. Based on the position of the hole of the connecting bolt through which the jacking pipe passes, the two clamps and the limiting ring are used to insert the laser warning pen body into the hole of the corresponding connecting bolt on the tower body to be spliced. This allows the laser warning pen body to clearly guide the suspension position during the suspension of the tower body. This facilitates efficient suspension and reception of the tower body even in bad weather conditions, enabling the equipment to perform its intended functions efficiently.
[0016] (2) In this invention, when the tower body to be spliced is close to the bottom tower body, under the illumination of the laser warning pen body, the construction personnel can easily determine the holes of the corresponding connecting bolts, and then remove the laser warning pen body between the two corresponding clamps. One end of the traction rope body at the top of the corresponding jacking pipe is clamped between the two corresponding clamps by a clamp. At this time, the construction personnel use existing electric drilling equipment to drive the worm to rotate, so that the rotating worm and the worm wheel can drive the rotating gear to rotate, and then the rotating gear can drive the three linkage gears to rotate, and then the rotating linkage gears can synchronously drive the corresponding winding roller to rotate, so that the winding roller can pull and wind the traction rope body, and thus the traction... The rope body can move and retract along the extension holes and guide wheels of the jacking pipe, connecting pipe, limiting pipe, and bottom pipe, allowing the traction rope body to move in conjunction with the locking blocks and corresponding clamping blocks to align the holes of the corresponding connecting bolts with the corresponding jacking pipe. At this point, the worm gear stops rotating, and the tower body to be spliced is lowered, allowing the jacking pipe to push out the clamping blocks inside the holes of the corresponding connecting bolts. This allows the holes of the connecting bolts of the tower body to be spliced and the holes of the connecting bolts of the bottom tower body to be spliced to be quickly aligned through the jacking pipe and connecting pipe, thereby facilitating the rapid setting of the connecting bolts of the tower body to be spliced and the bottom tower body, enabling the tower to be spliced efficiently and the equipment to perform its intended functions efficiently.
[0017] (3) In this invention, by rotating the bolt, one end of the bolt can be pressed against the outer surface of the base, thereby preventing the rotating block from rotating upward and ensuring that the adjustment mechanism can be stably set inside the bottom tower body, so that the equipment can efficiently perform its intended functions. Attached Figure Description
[0018] Figure 1 This is a perspective view of the invention in use; Figure 2 This is a first-view perspective perspective view of the present invention; Figure 3 This is a second-view perspective perspective view of the present invention; Figure 4 This is a first-view sectional perspective view of the present invention; Figure 5 This is a partially sectional perspective view of the adjustment mechanism of the present invention. Figure 6 For the present invention Figure 5 Enlarged view of point A in the middle; Figure 7 For the present invention Figure 5 Enlarged view at point B in the middle; Figure 8 This is a cross-sectional perspective view of the limiting mechanism of the present invention.
[0019] In the diagram, the markings are: 1. Adjustment mechanism; 101. Base; 102. Rotating block; 103. Clamp; 104. Rotating rod; 105. Take-up roller; 106. Connecting gear; 107. Rotating gear; 108. Worm gear; 109. Worm; 110. Traction rope body; 111. Extension rod; 112. Top bar; 113. Bottom tube; 114. Guide wheel; 115. Limiting tube; 116. First guide block; 17. Second guide block; 118. Connecting pipe; 119. Jacking pipe; 120. Locking block; 121. Clamping block; 122. Laser warning pen body; 2. Limiting mechanism; 201. Limiting frame; 202. Abutment plate; 203. Limiting spring; 204. Push plate; 205. Abutment rod; 206. Locking bracket; 207. Limiting nut; 208. Slider; 209. Adhesive block; 210. Adhesive rod; 3. Tower body. Detailed Implementation
[0020] To make the objectives, technical solutions, and advantages of this invention clearer, the invention will be further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative and not intended to limit the invention.
[0021] For examples, please refer to [link / reference]. Figures 1-4A tool for assembling components for wind turbine towers, comprising an adjustment mechanism 1 and a limiting mechanism 2, wherein the adjustment mechanism 1 provides the power required for splicing and the limiting mechanism 2 provides stable position support.
[0022] The details are as follows: Please see Figures 5-7The adjusting mechanism 1 includes a base 101, three rotating blocks 102, three take-up rollers 105, three rotating rods 104, three extension rods 111, three top bars 112, three bottom tubes 113, three limiting tubes 115, three connecting tubes 118, three top tubes 119, and linkage components. The three rotating blocks 102 are rotatably connected to the outer surface of the base 101. Each rotating rod 104 is rotatably connected to one end of the corresponding rotating block 102. Each extension rod 111 is threaded to one end of the corresponding rotating rod 104. Each top bar 112 is threaded to one end of the corresponding extension rod 111. Each bottom tube 113 is fixedly connected to the top of the corresponding top bar 112. Each limiting tube 115 is threaded to the top of the corresponding bottom tube 113. Each connecting pipe 118 is threaded to the top of the corresponding limiting pipe 115, and each top pipe 119 is threaded to the top of the corresponding connecting pipe 118. Each take-up roller 105 is rotatably connected to the outer surface of the base 101. A linkage component is mounted on the base 101. Each bottom pipe 113 has an extension hole on one side of its outer surface, and the interior of each extension hole communicates with the interior of the corresponding connecting pipe 118. A first guide block 116 and a second guide block 117 are fixedly connected inside each limiting pipe 115. A rotating gear 107 is rotatably connected to the top of the base 101, and a worm gear 108 is fixedly connected to the top of the rotating gear 107. A linkage gear 106 is fixedly connected to the top of each take-up roller 105. Each linkage gear 106 and the rotating... All gears 107 are meshed. A worm gear 109 is rotatably connected to the outer surface of the base 101. The worm gear 109 meshes with the worm wheel 108. A bolt 103 is threadedly connected to the top of each rotating block 102. A limit groove is formed on one side of the outer surface of each top bar 112. A traction rope body 110 is wound on the outer surface of each take-up roller 105. One end of each traction rope body 110 slides through the corresponding extension hole, and one end of each traction rope body 110 slides through the corresponding first guide block 116 and second guide block 117. One end of each traction rope body 110 extends to the outside of the top tube 119. A locking block 120 is fixedly connected to one end of each traction rope body 110. There are three sets of linkage components. Each set of linkage components includes... The system includes a guide wheel 114, two clamping blocks 121, and a laser warning pen body 122. The guide wheel 114 is sleeved on the corresponding bottom tube 113. Each laser warning pen body 122 is inserted between the two clamping blocks 121. Each laser warning pen body 122 has a limiting ring on its outer surface. By rotating the limiting nut 207, the limiting nut 207 can push the bracket 206 to press and adhere to the corresponding abutment 202. Then, in conjunction with the abutment rod 210 and the abutment block 209, the position of the abutment 202 can be fixed and restricted, thereby fixing and restricting the position of the base 101. The top tube 119 passes through the hole of the corresponding connecting bolt of the bottom tower body 3, and the position of the connecting bolt through which the top tube 119 passes is determined according to the position of the hole.The two clamps 121, in conjunction with the limiting rings, insert the laser warning pen body 122 into the holes of the connecting bolts at the corresponding positions on the tower body 3 to be assembled. This allows the laser warning pen body 122 to clearly guide the suspension position of the tower body 3 during its suspension process, facilitating efficient suspension and preparation of the tower body 3 even in adverse weather conditions. When the tower body 3 to be assembled approaches the bottom tower body 3, the laser warning pen body 122 illuminates the holes of the corresponding connecting bolts, enabling construction workers to easily locate them and remove the corresponding clamps. The laser warning pen body 122 between blocks 121 has one end of the traction rope body 110 at the top of the corresponding jacking pipe 119 secured between the two corresponding clamping blocks 121 via a locking block 120. At this time, the construction worker uses an existing electric drill to drive the worm gear 109 to rotate, so that the rotating worm gear 109, in conjunction with the worm wheel 108, can drive the rotating gear 107 to rotate. In turn, the rotating gear 107 can drive the three connecting gears 106 to rotate, and then the rotating connecting gears 106 can synchronously drive the corresponding winding roller 105 to rotate, so that the winding roller 105... The traction rope body 110 can be pulled and wound, allowing it to retract along the extension holes of the jacking pipe 119, connecting pipe 118, limiting pipe 115, bottom pipe 113, and guide wheel 114. This allows the traction rope body 110 to move in conjunction with the locking block 120 and corresponding clamping block 121 to align the hole of the corresponding connecting bolt with the corresponding jacking pipe 119. At this point, the rotation of the worm gear 109 stops, and the tower body 3 to be spliced is lowered, allowing the jacking pipe 119 to push out the clamping block 121 inside the hole of the corresponding connecting bolt, thus allowing the tower body to be spliced to be aligned. The holes for the connecting bolts 3 and the holes for the connecting bolts of the bottom tower body 3 can be quickly aligned through the jacking pipe 119 and the connecting pipe 118, thus facilitating the rapid setting of the connecting bolts between the tower body 3 to be assembled and the bottom tower body 3. This allows for efficient splicing of the tower. By rotating the clamp 103, one end of the clamp 103 can be pressed against the outer surface of the base 101, thereby preventing the rotating block 102 from rotating upwards. This ensures that the adjusting mechanism 1 can be stably set inside the bottom tower body 3, enabling the equipment to efficiently perform its intended functions. Please see Figure 8The limiting mechanism 2 consists of three sets. Each set includes a limiting frame 201, a stop piece 202, a limiting spring 203, a stop rod 205, a retainer 206, a slider 208, and two abutment rods 210. The limiting frame 201 is fixedly connected to the top of the corresponding top bar 112. The stop piece 202 is slidably inserted into the limiting frame 201. The limiting spring 203 is slidably inserted into the limiting frame 201. The stop rod 205 is threadedly connected to one end of the limiting frame 201. The retainer 206 is slidably sleeved on the outer surface of the stop rod 205. One end of the retainer 206 is in contact with one side of the outer surface of the stop piece 202. The slider 208 is slidably inserted into the corresponding limiting groove. Abutment blocks 209 are fixedly connected to both sides of the outer surface of the slider 208 by bolts. Each abutment rod 210 is threadedly connected to the corresponding abutment block 209. The outer surface of each stop rod 205 is threaded... With the limit nut 207 connected, each abutment 205 has a pusher 204 rotatably connected to one end. The adjustment mechanism 1 is placed inside the bottom tower body 3 via the base 101. The number of extension rods 111 is increased or decreased according to the internal space specifications of the tower body 3, so that one end of the top bar 112 can be close to the inner wall of the bottom tower body 3. At this time, under the support of the limit spring 203, the abutment 202 can press the corresponding patch 209, so that the patch 209 can drive the patch rod 210 to press and adhere to the inner wall of the bottom tower body 3. Under the support of the patch rod 210, the limit spring 203 can support the pusher 204 in the opposite direction, so that the pusher 204, together with the abutment 205 and the limit frame 201, can synchronously drive the top bar 112, extension rod 111, rotating rod 104 and rotating block 102 to press the base 101 to the center of the tower body 3.
[0023] The following is a detailed description of a method for using a tool for assembling components of a wind turbine tower, provided by an embodiment of the present invention. The method includes the following steps: Step 1, Position Adjustment: Place the adjustment mechanism 1 inside the bottom tower body 3 via the base 101. Adjust the number of extension rods 111 according to the internal space specifications of the tower body 3, so that one end of the top bar 112 can be close to the inner wall of the bottom tower body 3. At this time, under the support of the limiting spring 203, the abutment 202 can press the corresponding patch 209, so that the patch 209 can drive the patch rod 210 to press and adhere to the inner wall of the bottom tower body 3. Under the support of the patch rod 210, the limiting spring 203 can support the pusher 204 in the opposite direction, so that the pusher 204, together with the abutment 205 and the limiting frame 201, can synchronously drive the top bar 112, extension rod 111, rotating rod 104 and rotating block 102 to press the base 101 to the center of the tower body 3. At this time, by rotating the limiting nut 207, the position is adjusted. The limiting nut 207 can push the bracket 206 to press and adhere to the corresponding abutment 202. Then, in conjunction with the abutment rod 210 and the abutment block 209, the position of the abutment 202 can be fixed and restricted. This, in turn, can fix and restrict the position of the base 101. Then, the top tube 119 passes through the hole of the corresponding connecting bolt of the bottom tower body 3. Based on the position of the hole of the connecting bolt through which the top tube 119 passes, the two clamps 121, in conjunction with the limiting ring, insert the laser warning pen body 122 into the hole of the corresponding connecting bolt of the tower body 3 to be spliced. This allows the laser warning pen body 122 to clearly guide the suspension position during the suspension of the tower body 3, making it convenient to carry out the suspension and reception of the tower body 3 efficiently even in bad weather conditions, so that the equipment can efficiently perform its intended functions. Step Two, Rapid Assembly: When the tower body 3 to be assembled approaches the bottom tower body 3, under the illumination of the laser warning pen body 122, the construction personnel can easily determine the holes of the corresponding connecting bolts. Then, the laser warning pen body 122 between the two corresponding clamping blocks 121 is removed. One end of the traction rope body 110 at the top of the corresponding jacking pipe 119 is secured between the two corresponding clamping blocks 121 via the clamping block 120. At this time, the construction personnel use existing electric drilling equipment to drive the worm gear 109 to rotate. The rotating worm gear 109, in conjunction with the worm wheel 108, drives the rotating gear 107 to rotate. The rotating gear 107 then drives the three connecting gears 106 to rotate, which in turn synchronously drives the corresponding winding roller 105 to rotate. The winding roller 105 then pulls and winds the traction rope body 110, thus... The traction rope body 110 can retract and move along the extension holes of the jacking pipe 119, connecting pipe 118, limiting pipe 115, bottom pipe 113, and guide wheel 114, so that the traction rope body 110 can cooperate with the locking block 120 and the corresponding clamping block 121 to move the corresponding connecting bolt hole to align with the corresponding jacking pipe 119. At this time, the worm gear 109 stops rotating, and the tower body 3 to be spliced is lowered, so that the jacking pipe 119 can push out the clamping block 121 inside the corresponding connecting bolt hole, so that the connecting bolt holes of the tower body 3 to be spliced and the connecting bolt holes of the bottom tower body 3 can be quickly aligned through the jacking pipe 119 and connecting pipe 118, thereby facilitating the rapid setting of the connecting bolts of the tower body 3 to be spliced and the bottom tower body 3, enabling the tower to be spliced efficiently and the equipment to perform its intended functions efficiently.
[0024] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, and improvements made within the spirit and principles of the present invention should be included within the protection scope of the present invention.
Claims
1. A tool for assembling components on a wind turbine tower, characterized in that, include: Adjustment mechanism (1), which is used to provide the power required for splicing; Limiting mechanism (2) is used to provide stable position support.
2. The tool for assembling components of a wind turbine tower as described in claim 1, characterized in that: The adjusting mechanism (1) includes a base (101), three rotating blocks (102), three take-up rollers (105), three rotating rods (104), three extension rods (111), three top bars (112), three bottom tubes (113), three limiting tubes (115), three connecting tubes (118), three top tubes (119), and a linkage component. The three rotating blocks (102) are rotatably connected to the outer surface of the base (101), each rotating rod (104) is rotatably connected to one end of the corresponding rotating block (102), and each extension rod (111) is threaded to one end of the corresponding rotating rod (104). Each of the top bars (112) is threaded to one end of the corresponding extension rod (111), each of the bottom tubes (113) is fixedly connected to the top of the corresponding top bar (112), each of the limiting tubes (115) is threaded to the top of the corresponding bottom tube (113), each of the connecting tubes (118) is threaded to the top of the corresponding limiting tube (115), each of the top tubes (119) is threaded to the top of the corresponding connecting tube (118), and each of the winding rollers (105) is rotatably connected to the outer surface of the base (101). The linkage component is set on the base (101).
3. A tool for assembling components for wind turbine towers as described in claim 2, characterized in that: Each of the bottom tubes (113) has an extension hole on one side of its outer surface. The interior of each extension hole is connected to the interior of the corresponding connecting tube (118). Each of the limiting tubes (115) has a first guide block (116) and a second guide block (117) fixedly connected inside.
4. A tool for assembling components for wind turbine towers as described in claim 3, characterized in that: A rotating gear (107) is rotatably connected to the top of the base (101), and a worm gear (108) is fixedly connected to the top of the rotating gear (107). A connecting gear (106) is fixedly connected to the top of each take-up roller (105), and each connecting gear (106) meshes with the rotating gear (107). A worm (109) is rotatably connected to the outer surface of the base (101), and the worm (109) meshes with the worm gear (108).
5. A tool for assembling components for wind turbine towers as described in claim 4, characterized in that: Each of the rotating blocks (102) has a bolt (103) threaded to its top, and each of the top bars (112) has a limit groove on one side of its outer surface.
6. A tool for assembling components for wind turbine towers as described in claim 5, characterized in that: Each of the winding rollers (105) has a traction rope body (110) wrapped around its outer surface. One end of each traction rope body (110) slides through the interior of the corresponding extension hole, and one end of each traction rope body (110) slides through the corresponding first guide block (116) and second guide block (117). One end of each traction rope body (110) extends to the outside of the top tube (119), and one end of each traction rope body (110) is fixedly connected to a locking block (120).
7. A tool for assembling components for wind turbine towers as described in claim 6, characterized in that: The linkage components are provided in three sets. Each set of linkage components includes a guide wheel (114), two clamping blocks (121) and a laser warning pen body (122). The guide wheel (114) is sleeved on the corresponding bottom tube (113). Each laser warning pen body (122) is inserted between the two clamping blocks (121). Each laser warning pen body (122) has a limiting ring on its outer surface.
8. A tool for assembling components for wind turbine towers as described in claim 7, characterized in that: The limiting mechanism (2) consists of three sets. Each set of the limiting mechanism (2) includes a limiting frame (201), a stop plate (202), a limiting spring (203), a stop rod (205), a bracket (206), a slider (208), and two sticking rods (210). The limiting frame (201) is fixedly connected to the top of the corresponding top bar (112). The stop plate (202) is slidably inserted into the limiting frame (201). The limiting spring (203) is slidably inserted into the limiting frame (205). 1) Inside, the abutment (205) is threaded to one end of the limiting frame (201), the bracket (206) is slidably sleeved on the outer surface of the abutment (205), one end of the bracket (206) is in contact with the outer surface of one side of the abutment (202), the slider (208) is slidably inserted into the corresponding limiting groove, and the outer surfaces of both sides of the slider (208) are fixedly connected with the patch (209) by bolts, and each of the patch rods (210) is threaded to the inside of the corresponding patch (209).
9. A tool for assembling components for wind turbine towers as described in claim 8, characterized in that: Each of the abutments (205) has a limit nut (207) threaded on its outer surface, and a pusher plate (204) is rotatably connected to one end of each abutment (205).
10. A method of using a tool for assembling components on a wind turbine tower, characterized in that, The tool used in the assembly of wind turbine tower components as described in claim 9 includes the following steps: S1. Position Adjustment: Place the adjustment mechanism (1) inside the bottom tower body (3) via the base (101). Adjust the number of extension rods (111) according to the internal space specifications of the tower body (3) so that one end of the top bar (112) can be close to the inner wall of the bottom tower body (3). At this time, under the support of the limiting spring (203), the abutment (202) can press the corresponding patch (209), so that the patch (209) can drive the patch rod (210) to press and fit against the inner wall of the bottom tower body (3). Under the support of the patch rod (210), the limiting spring (203) can support the pusher (204) in the opposite direction, so that the pusher (204) can work with the abutment (205) and the limiting frame (201) to simultaneously drive the top bar (112), extension rod (111), rotating rod (104) and rotating block (102) to press the base (101) at the center of the tower body (3). At this time, by rotating the limiting nut (207), the limiting nut (207) can push the card holder (206) to press and adhere to the corresponding abutment (202). Then, with the help of the sticking rod (210) and the sticking block (209), the position of the abutment (202) can be fixed, and the position of the base (101) can be fixed. Then, the top tube (119) passes through the hole of the corresponding connecting bolt of the bottom tower body (3). Then, according to the position of the hole of the connecting bolt through which the top tube (119) passes, the two clamps (121) are used in conjunction with the limiting ring to insert the laser warning pen body (122) into the hole of the connecting bolt of the tower body (3) to be spliced. This allows the laser warning pen body (122) to clearly guide the position of the tower body (3) during the suspension process, so that the tower body (3) can still be suspended efficiently even in bad weather conditions. S2. Quick splicing: When the tower body (3) to be spliced is close to the bottom tower body (3), under the illumination of the laser warning pen body (122), the construction personnel can easily determine the holes of the corresponding connecting bolts, and then remove the laser warning pen body (122) between the two corresponding clamps (121). The traction rope body (110) at the top of the corresponding jacking pipe (119) is clamped between the two corresponding clamps (121) through the clamp (120). At this time, the construction personnel use the existing electric drill to drive the worm (109) to rotate, so that the rotating worm (109) and the worm wheel (108) can drive the rotating gear (107) to rotate, so that the rotating gear (107) can drive the three connecting gears (106) to rotate, and then the rotating connecting gears (106) can synchronously drive the corresponding winding roller (105) to rotate, so that the winding roller (105) can pull the winding traction rope body. (110) allows the traction rope body (110) to migrate and retract along the extension holes of the top pipe (119), connecting pipe (118), limiting pipe (115), bottom pipe (113) and guide wheel (114), so that the traction rope body (110) can cooperate with the clamping block (120) and the corresponding clamping block (121) to migrate the hole of the corresponding connecting bolt and align it with the corresponding top pipe (119). At this time, stop rotating the worm (109) and lower the tower body (3) to be spliced, so that the top pipe (119) can push out the clamping block (121) inside the hole of the corresponding connecting bolt, so that the hole of the connecting bolt of the tower body (3) to be spliced and the hole of the connecting bolt of the bottom tower body (3) can be quickly aligned through the top pipe (119) and connecting pipe (118), thereby facilitating the quick setting of the connecting bolts of the tower body (3) to be spliced and the bottom tower body (3), so that the tower can be spliced efficiently.