A method and system for generating multi-stage construction schemes for power transmission tower pile foundations

By acquiring the engineering information set of transmission tower pile foundations, identifying the pile foundation layout and matching working conditions, and generating multi-stage construction plans, the problem of differences and sequential relationships in the construction stages of transmission tower pile foundation construction plans is solved, thereby improving the accuracy and safety of the construction plans.

CN123070531APending Publication Date: 2026-11-10STATE GRID ZHEJIANG ELECTRIC POWER CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611120308.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-07-27
Publication Date
2026-11-10

AI Technical Summary

Technical Problem

Existing technologies lack effective methods to simultaneously address the differences and construction sequence relationships of different construction stages of transmission tower pile foundations, resulting in insufficiently accurate construction scheme generation, increased computational workload, and difficulty in meeting specific response control requirements.

Method used

By acquiring the target tower site engineering information set, identifying the pile foundation layout, and calling the pre-established construction response database for working condition matching, the construction measures for each construction stage are determined, and a multi-stage construction plan is generated.

Benefits of technology

It improves the accuracy and safety of construction plans, reduces the workload of repetitive modeling and calculation, and increases the reuse efficiency of parametric calculation results.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123070531A_ABST
    Figure CN123070531A_ABST
Patent Text Reader

Abstract

This invention relates to the field of power transmission line engineering technology, and more particularly to a method and system for generating multi-stage construction schemes for power transmission tower pile foundations. The method includes: identifying the current pile foundation layout at the target tower location based on the number of piles and the plane coordinates of the center of each pile in the target tower location engineering information set; extracting the construction condition characteristics of each construction stage during the construction of the power transmission tower pile foundation from the target tower location engineering information set, and performing condition matching on the construction condition characteristics of each construction stage to determine the engineering response corresponding to different construction measures in each construction stage; and, under the current pile foundation layout at the tower location, judging the engineering response corresponding to different construction measures to determine the target tower location construction measures for each construction stage, thereby generating a multi-stage construction scheme for the target tower location. This invention reduces the workload of repetitive modeling and calculation by generating multi-stage combined construction schemes adapted to the engineering conditions of the target tower location, thus ensuring the safety of the construction scheme.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of power transmission line engineering technology, and in particular to a method and system for generating multi-stage construction schemes for power transmission tower pile foundations. Background Technology

[0002] Transmission line projects typically span large spatial areas, with significant differences in geological, hydrological, and surrounding load conditions between different tower locations. For transmission towers using bored pile foundations, drilling is a crucial step in foundation construction. During the drilling process, the stability of the borehole wall is influenced by various factors, including soil strength, distribution of weak layers, groundwater conditions, and mud wall protection. For tower foundations using a pile group arrangement, the construction process also involves the excavation of the foundation pit, which can cause horizontal displacement of the soil along the pit side, heave of the pit bottom, and surface settlement. Furthermore, when the tower location is near buildings or roads, the foundation pit may be affected by asymmetric additional loads, further altering the aforementioned engineering responses.

[0003] However, existing engineering practices and scheme generation methods still have shortcomings. Specifically, the control factors, engineering responses, and construction measures corresponding to different construction stages differ significantly, and there is a clear construction sequence relationship between adjacent stages. The drilling stage mainly focuses on borehole wall deformation and abnormal seepage state; the pile cap foundation pit excavation stage mainly focuses on horizontal displacement of the pit side and bottom heave; and the peripheral load check and support stage needs to further consider the impact of surface settlement and additional loads. Existing technologies lack a response state organization method that simultaneously addresses the differences between the above stages and the construction sequence relationship. The judgment results and measures formed in the first stage are difficult to continuously transmit to the next stage, which easily leads to the simple parallelism of multiple independent judgment processes. At the same time, there are essential differences in the construction evaluation content and subsequent processes between single pile foundations and pile group foundations with pile cap foundation pit construction requirements. For single pile foundations, the scheme generation mainly involves the judgment of the hole forming stage; for pile group foundations, after completing the hole forming judgment, it is necessary to further judge the foundation pit excavation and support measures. If the same generation process is used, it will not only increase unnecessary analysis steps, but also make it difficult to reflect the unique response and measure requirements of pile group foundation construction.

[0004] Furthermore, the distribution of transmission tower sites is scattered, and the geological, hydrological, foundation layout and surrounding load conditions vary greatly between different tower sites. If a complete numerical calculation model is re-established for each target tower site and the engineering response corresponding to various measures is calculated, a large amount of computational work is required. On the other hand, it is difficult to make full use of the existing parametric analysis results and it is also impossible to determine whether the candidate measures meet the specific response control requirements under the target working conditions. Summary of the Invention

[0005] To address the above technical problems, this invention provides a method and system for generating multi-stage construction schemes for power transmission tower pile foundations.

[0006] In a first aspect, the present invention provides a method for generating a multi-stage construction scheme for the pile foundation of a power transmission tower, the method comprising the following steps: Obtain the target tower location engineering information set for the target transmission tower pile foundation, and identify the current tower location pile foundation layout form based on the number of piles and the plane coordinates of the center of each pile in the target tower location engineering information set; Construction condition characteristics of each construction stage during the construction of the transmission tower pile foundation are extracted from the target tower site engineering information set, and the construction condition characteristics of each construction stage are matched by calling the pre-established construction response database to determine the engineering response corresponding to different construction measures in each construction stage; the construction stages include the drilling stage, the foundation pit excavation stage, and the support stage. Under the current layout of the pile foundation at the tower site, the engineering response corresponding to different construction measures is judged, and the target tower site construction measures for each construction stage are determined. The construction measures for the target tower sites at each construction stage are combined according to the construction sequence to generate a multi-stage construction plan for the target tower sites.

[0007] In a further implementation, the step of identifying the current pile foundation layout of the tower site based on the number of piles and the plane coordinates of the center of each pile in the target tower site engineering information set includes: The number of piles and the plane coordinates of the center of each pile are read from the target tower site engineering information set; When the number of piles is one, the current pile foundation layout of the tower site will be identified as a single pile foundation; When the number of piles is greater than one and multiple pile foundations share a pile cap and there is a need for pile cap pit excavation, the current pile foundation layout of the tower location will be identified as a pile group foundation. When the current pile foundation layout is a group pile foundation and adopts a matrix arrangement, the row and column layout of the group pile foundation is determined according to the number of different coordinate positions of the center plane coordinates of each pile in two mutually orthogonal arrangement directions. The number of different coordinate positions in the two mutually orthogonal arrangement directions are respectively taken as the number of rows and the number of columns, and the product of the number of rows and the number of columns is the row and column layout of the group pile foundation.

[0008] In a further implementation scheme, the target tower site engineering information set includes geological condition parameters, hydrological condition parameters, pile foundation parameters, pile cap pit parameters, and surrounding load parameters; the step of extracting the construction condition characteristics of each construction stage during the construction of the transmission tower pile foundation from the target tower site engineering information set includes: The design pile diameter, design pile length, stratum lithology parameters, and groundwater level parameters are extracted from the geological condition parameters, hydrological condition parameters, and pile foundation parameters of the target tower site engineering information set to form the construction condition characteristics of the drilling stage. Among them, the stratum lithology parameters include the thickness of the soft soil layer, the burial depth of the top boundary of the weak layer, the burial depth of the bottom boundary of the weak layer, the burial depth of the top boundary of the high permeability layer, the thickness of the high permeability layer, and the permeability coefficient of the high permeability layer; the groundwater level parameters include the groundwater level, the head difference, and the mud equivalent head. From the pile foundation parameters, pile cap pit parameters, and geological condition parameters of the target tower site project information set, the pile diameter, pile length, pile spacing, pit width, pit length, pit excavation depth, soft soil layer thickness, and soil strength and stiffness parameters are extracted to form the construction condition characteristics of the pit excavation stage. From the pile foundation parameters, foundation pit parameters, and surrounding load parameters of the target tower site project information set, the excavation depth of the foundation pit, the additional load of the building, the distance between the building and the foundation pit, the direction of the building's action relative to the foundation pit, the additional traffic load, the distance between the road and the foundation pit, and the direction of the traffic load are extracted to form the construction condition characteristics of the support stage.

[0009] In a further implementation scheme, the step of calling a pre-established construction response database to match the construction condition characteristics of each construction stage and determine the engineering response corresponding to different construction measures in each construction stage includes: The pre-established construction response database is invoked; the construction response database stores multiple standard construction condition characteristics and reference engineering responses corresponding to different construction measures under each standard construction condition characteristic. The construction conditions of the current construction stage are matched with the standard construction conditions to determine the target standard conditions that match the construction conditions of each construction stage. The reference engineering response under the construction measures corresponding to the target standard working condition characteristics is read from the construction response database and used as the engineering response corresponding to the construction measures under the current construction stage.

[0010] In a further implementation, the step of matching the construction condition characteristics of the current construction stage with the standard construction condition characteristics to determine the target standard condition characteristics that match the construction condition characteristics of each construction stage includes: If the construction condition characteristics of the current construction stage are continuous construction condition parameters, then the standard construction condition characteristics whose absolute value of the difference with the construction condition characteristics of the current construction stage does not exceed the preset allowable deviation will be used as candidate standard construction condition characteristics. If the construction condition characteristics of the current construction stage are discrete construction condition parameters, then the standard construction condition characteristics with the same category will be used as candidate standard construction condition characteristics. When multiple candidate standard working condition features exist, the working condition distance between the current construction stage working condition feature and the candidate standard working condition feature is calculated, and the candidate standard working condition feature with the smallest working condition distance is taken as the target standard working condition feature.

[0011] In a further implementation plan, when the current tower location pile foundation layout is a single pile foundation, only the drilling construction measures for the drilling stage are determined. When the current tower location pile foundation layout is a pile group foundation, the drilling construction measures, the excavation construction measures, and the support measures are determined sequentially.

[0012] In a further implementation plan, when the current construction stage is the drilling stage and the current tower site pile foundation layout is a single pile foundation or a group pile foundation, the step of judging the engineering response corresponding to different construction measures and determining the target tower site construction measures for each construction stage includes: The engineering response corresponding to the benchmark drilling measure in the drilling stage of the construction response database is compared with the preset drilling response control limit. If the engineering response is within the preset drilling response control limit, the benchmark drilling measure is determined as the drilling construction measure.

[0013] In a further implementation plan, when the current construction stage is the foundation pit excavation stage and the current tower location pile foundation layout is a group pile foundation, the step of judging the engineering response corresponding to different construction measures and determining the target tower location construction measures for each construction stage includes: The target construction measures of the drilling stage are transferred to the foundation pit excavation stage, and the surrounding load status of the current tower site in the foundation pit excavation stage is determined according to the surrounding load parameters. The surrounding load conditions and the construction conditions of the foundation pit excavation stage are combined into the target foundation pit evaluation conditions, and the engineering responses corresponding to unsupported vertical excavation and slope excavation measures are matched in the construction response database according to the target foundation pit evaluation conditions. The engineering response corresponding to the unsupported vertical excavation measure is compared with the preset response control limits, and the first unsupported vertical excavation measure that meets all response control limits is determined as the foundation pit construction measure.

[0014] In a further implementation plan, when the current construction stage is the support stage and the current tower site pile foundation layout is a pile group foundation, the step of judging the engineering response corresponding to different construction measures and determining the target tower site construction measures for each construction stage includes: When neither the unsupported vertical excavation measure nor the slope excavation measure meets all response control limits, the engineering response corresponding to different support measures is read sequentially according to the preset support measure level, and compared with the preset response control limits. The support measure that meets all response control limits for the first time is determined as the foundation pit support measure.

[0015] Secondly, the present invention provides a multi-stage construction scheme generation system for power transmission tower pile foundations, the system comprising: The data acquisition module is used to acquire the target tower site engineering information set of the target transmission tower pile foundation, and to identify the current tower site pile foundation layout form based on the number of piles and the plane coordinates of the center of each pile in the target tower site engineering information set. The working condition matching module is used to extract the construction working condition characteristics of each construction stage in the construction of the transmission tower pile foundation from the target tower site engineering information set, and call the pre-established construction response database to perform working condition matching on the construction working condition characteristics of each construction stage to determine the engineering response corresponding to different construction measures in each construction stage; the construction stages include the drilling stage, the foundation pit excavation stage, and the support stage. The scheme generation module is used to identify the engineering response corresponding to different construction measures under the current pile foundation layout of the tower site, and determine the target tower site construction measures for each construction stage. The scheme combination module is used to combine the construction measures of the target tower site in each construction stage according to the construction sequence to generate a multi-stage construction scheme for the target tower site.

[0016] This invention provides a method and system for generating multi-stage construction schemes for transmission tower pile foundations. The method involves acquiring a target tower location engineering information set for the target transmission tower pile foundation, and identifying the current tower location pile foundation layout based on the number of piles and the plane coordinates of each pile's center in the target tower location engineering information set. Construction condition characteristics of each construction stage during the transmission tower pile foundation construction process are extracted from the target tower location engineering information set, and a pre-established construction response database is used to match the construction condition characteristics of each construction stage, determining the engineering responses corresponding to different construction measures in each construction stage. The construction stages include drilling, excavation, and support. Under the current tower location pile foundation layout, the engineering responses corresponding to different construction measures are judged to determine the target tower location construction measures for each construction stage. The target tower location construction measures for each construction stage are combined according to the construction sequence to generate a multi-stage construction scheme for the target tower location. Compared with existing technologies, this method performs phased working condition matching and progressive judgment on the drilling, excavation and support stages of the transmission tower pile foundation construction process according to the construction sequence. It also realizes the diversion of construction process for different foundation layout forms according to the pile foundation layout form, thereby generating a multi-stage combined construction scheme adapted to the engineering conditions of the target tower site. This improves the reuse efficiency of existing parametric calculation results and reduces the workload of repeated modeling and calculation, while ensuring the safety of the construction scheme. Attached Figure Description

[0017] Figure 1 This is a schematic diagram of the process for generating a multi-stage construction scheme for power transmission tower pile foundations provided in an embodiment of the present invention; Figure 2 This is a flowchart illustrating the process of generating a multi-stage construction scheme for power transmission tower pile foundations provided in an embodiment of the present invention. Figure 3 This is a schematic diagram illustrating the state transmission relationship at different construction stages provided in an embodiment of the present invention; Figure 4 This is a schematic diagram of the target tower location construction measure determination process provided in the embodiments of the present invention; Figure 5 This is a block diagram of the multi-stage construction scheme generation system for power transmission tower pile foundations provided in this embodiment of the invention.

[0018] Explanation of reference numerals in the attached diagram: 101, Data acquisition module; 102, Working condition matching module; 103, Scheme generation module; 104, Scheme combination module. Detailed Implementation

[0019] The embodiments of the present invention are described in detail below with reference to the accompanying drawings. The embodiments are given for illustrative purposes only and should not be construed as limiting the present invention. The accompanying drawings are for reference and illustration only and do not constitute a limitation on the scope of patent protection of the present invention, because many changes can be made to the present invention without departing from the spirit and scope of the present invention.

[0020] Figure 1 This is a schematic flowchart of a method for generating a multi-stage construction scheme for transmission tower pile foundations provided in an embodiment of the present invention. The present invention provides a method for generating a multi-stage construction scheme for transmission tower pile foundations, such as... Figure 1 As shown, the method includes the following steps: S1. Obtain the target tower location engineering information set for the target transmission tower pile foundation, and identify the current tower location pile foundation layout form based on the number of piles and the plane coordinates of the center of each pile in the target tower location engineering information set.

[0021] In some implementations, the step of identifying the pile foundation layout of the current tower site based on the number of piles and the plane coordinates of the center of each pile in the target tower site engineering information set includes: The number of piles and the plane coordinates of the center of each pile are read from the target tower site engineering information set; When the number of piles is one, the current pile foundation layout of the tower site will be identified as a single pile foundation; When the number of piles is greater than one and multiple pile foundations share a pile cap and there is a need for pile cap pit excavation, the current pile foundation layout of the tower location will be identified as a pile group foundation. When the current pile foundation layout is a group pile foundation and adopts a matrix arrangement, the row and column layout of the group pile foundation is determined according to the number of different coordinate positions of the center plane coordinates of each pile in two mutually orthogonal arrangement directions. The number of different coordinate positions in the two mutually orthogonal arrangement directions are respectively taken as the number of rows and the number of columns, and the product of the number of rows and the number of columns is the row and column layout of the group pile foundation.

[0022] In a specific embodiment, this embodiment classifies and structures geological survey data, hydrological monitoring data, design drawing data, site survey data, and surrounding environmental survey data of the target transmission tower pile foundation location to obtain a target tower site engineering information set. This target tower site engineering information set includes at least geological condition parameters, hydrological condition parameters, pile foundation parameters, pile cap pit parameters, site construction space parameters, and surrounding load parameters. Specifically, the geological condition parameters include at least the stratum type, thickness of each soil layer, depth range of each soil layer, soil strength parameters, soil stiffness parameters, soil weight, and permeability coefficient. The hydrological condition parameters include at least the groundwater level, the difference in water head inside and outside the borehole, the equivalent water head pressure of the mud wall, and external hydraulic recharge conditions. The pile foundation parameters include at least the design pile diameter, design pile length, number of piles, and the number of piles per pile. The central plane coordinates, pile layout, and pile spacing are specified. The central plane coordinates of each pile refer to the coordinate position of the center point of each pile on its pile cap plane. The pile cap pit parameters include at least the pile cap dimensions, pit length, pit width, and pit excavation depth. The site construction space parameters include at least the available construction width around the pit, the distance from the pit edge to the site boundary or obstacle, the site slope, and the feasibility of slope protection. The surrounding load parameters include at least the additional load value generated by adjacent buildings on the pit sidewall, the distance between the building and the pit, the direction of the building's action relative to the pit, the additional load value generated by road traffic, the straight-line distance from the road edge to the pit edge, and the direction of the traffic load relative to the pit. In this embodiment, engineering parameters scattered from different sources are organized in a unified structure to construct the target tower site engineering information set.

[0023] Then, in this embodiment, the number of piles and the plane coordinates of the center of each pile are read from the pile foundation parameters of the target tower site engineering information set. When there is only one pile, the current tower site pile foundation layout is identified as a single pile foundation. A single pile foundation only involves the determination of the construction plan for the drilling stage and does not require subsequent excavation of the foundation pit. Therefore, this embodiment can terminate the activation of the state node of the subsequent stage after completing the identification of the drilling stage. When the number of piles is greater than one, this embodiment further determines whether these pile foundations share the same foundation and therefore require excavation of the foundation pit. If multiple pile foundations share the same foundation and require excavation of the foundation pit, the current tower site pile foundation layout is identified as a pile group foundation. Since pile group foundations share the same foundation, after completing the drilling construction, it is necessary to identify the excavation of the pile group foundation pit and the necessary support measures. Therefore, it is necessary to activate the state nodes of the subsequent pit excavation stage and support stage. When the current tower site pile foundation layout is a pile group foundation, this embodiment further determines whether the pile group foundation adopts a matrix rule layout. The specific determination method is as follows: This embodiment reads the plane coordinates of the center of each pile and counts the number of different coordinate values ​​of these coordinate points in two mutually orthogonal directions. If there are multiple different coordinate values ​​in both orthogonal directions and the piles are arranged in a row-column alignment in the two directions, then the pile group foundation is considered to adopt a matrix-style layout. In this case, the number of different coordinate positions in one orthogonal direction is determined as the number of columns of the pile group foundation, and the number of different coordinate positions in the other orthogonal direction is determined as the number of rows of the pile group foundation. Then, the product of the number of rows and the number of columns is calculated. The product of the number of rows and the number of columns is the row and column arrangement of the pile group foundation. The row and column arrangement of the pile group foundation includes, but is not limited to, a 2x2 arrangement and a 3x3 arrangement. For example, if multiple different coordinate values ​​are identified in two orthogonal directions... If the number of coordinate positions is two, the row and column arrangement of the pile group foundation is identified as 2x2; if the number of coordinate positions is three, it is identified as 3x3. For multiple pile foundations sharing a pile cap but the pile positions do not meet the above matrix arrangement rules, they are classified as other pile group foundation arrangements. This type of foundation also has the requirement of pile cap pit construction, but its pile position arrangement is not suitable for expression by multiplying the number of rows and columns. This embodiment realizes the separation of construction process between single pile foundation and pile group foundation by identifying the foundation arrangement form. The single pile foundation directly enters the scheme generation process after the hole drilling construction measures are determined, while the pile group foundation continues to enter the response judgment process of the pile cap pit excavation stage and the necessary surrounding load check and support stage, so as to adopt different construction scheme generation processes for different foundation forms.

[0024] S2. Extract the construction condition characteristics of each construction stage during the construction of the transmission tower pile foundation from the target tower site engineering information set, and call the pre-established construction response database to match the construction condition characteristics of each construction stage to determine the engineering response corresponding to different construction measures in each construction stage; the construction stage includes the drilling stage, the foundation pit excavation stage, and the support stage.

[0025] In some implementations, the target tower site engineering information set includes geological condition parameters, hydrological condition parameters, pile foundation parameters, pile cap pit parameters, and surrounding load parameters; the step of extracting the construction condition characteristics of each construction stage during the construction of the transmission tower pile foundation from the target tower site engineering information set includes: The design pile diameter, design pile length, stratum lithology parameters, and groundwater level parameters are extracted from the geological condition parameters, hydrological condition parameters, and pile foundation parameters of the target tower site engineering information set to form the construction condition characteristics of the drilling stage. Among them, the stratum lithology parameters include the thickness of the soft soil layer, the burial depth of the top boundary of the weak layer, the burial depth of the bottom boundary of the weak layer, the burial depth of the top boundary of the high permeability layer, the thickness of the high permeability layer, and the permeability coefficient of the high permeability layer; the groundwater level parameters include the groundwater level, the head difference, and the mud equivalent head. From the pile foundation parameters, pile cap pit parameters, and geological condition parameters of the target tower site project information set, the pile diameter, pile length, pile spacing, pit width, pit length, pit excavation depth, soft soil layer thickness, and soil strength and stiffness parameters are extracted to form the construction condition characteristics of the pit excavation stage. From the pile foundation parameters, foundation pit parameters, and surrounding load parameters of the target tower site project information set, the excavation depth of the foundation pit, the additional load of the building, the distance between the building and the foundation pit, the direction of the building's action relative to the foundation pit, the additional traffic load, the distance between the road and the foundation pit, and the direction of the traffic load are extracted to form the construction condition characteristics of the support stage.

[0026] After constructing the target tower site engineering information set, this embodiment extracts parameter fields related to each construction stage from the target tower site engineering information set according to the pile foundation construction sequence. It constructs construction condition characteristics for the drilling stage, the pile cap excavation stage, and the support stage. This ensures that the condition characteristics for each construction stage only include influencing parameters closely related to the engineering response at that stage, avoiding the problem of insufficient matching specificity caused by using uniform input for indiscriminate matching of all engineering parameters. Specifically, this embodiment extracts the design pile diameter and design pile length from the pile foundation parameters, and extracts soft soil parameters from the geological condition parameters. The thickness of the layer, the burial depth of the top and bottom interfaces of the main weak layers, the burial depth of the top interface of the high-permeability layer, the thickness of the high-permeability layer, and the permeability coefficient of the high-permeability layer are extracted from the hydrological condition parameters. Groundwater level characterization parameters, water head difference and mud equivalent water head used to characterize the hydraulic conditions inside and outside the borehole or external recharge conditions are extracted from the hydrological condition parameters. These parameters are arranged and combined according to the preset field order to form the construction condition characteristics of the borehole formation stage. The construction condition characteristics of the borehole formation stage cover the main geological and hydrological factors that affect borehole wall deformation and seepage anomalies during the borehole formation process, and are used for subsequent matching of target conditions in the borehole formation response sub-library.

[0027] When the current foundation layout of the tower site is a pile group foundation, this embodiment extracts parameters related to the displacement of the soil on the side of the pit and the heave response of the pit bottom during the excavation stage of the pile group cap foundation pit from the target tower site engineering information set. Specifically, it extracts the identified foundation layout, design pile diameter, design pile length, and center distance between adjacent piles from the pile foundation parameters; it extracts the planned excavation width, planned excavation length, and planned excavation depth of the foundation pit from the cap foundation pit parameters; and it extracts the thickness of the soft soil layer that affects the excavation response and the strata used to characterize the mechanical properties of the strata from the geological condition parameters. The feature parameter group, in which the stratum feature parameter group is determined according to the soil constitutive model used when constructing the construction response database, specifically includes soil strength parameters and soil stiffness parameters related to the calculation of the foundation pit excavation response. In this embodiment, these parameters are arranged and combined according to a preset field order to form the construction condition characteristics of the pile group foundation pit excavation stage. The construction condition characteristics of the pile group foundation pit excavation stage cover the main controlling factors affecting the degree of lateral displacement of the pit wall and the heave response of the pit bottom during the foundation pit excavation process. They are used for subsequent matching of target conditions in the pile group foundation pit excavation response sub-library.

[0028] Meanwhile, this embodiment extracts parameters related to the impact of surrounding additional loads on the stability of the foundation pit from the target tower site engineering information set. Specifically, it extracts the foundation layout form from the pile foundation parameters, the planned excavation depth of the foundation pit from the pile cap foundation pit parameters, and the building additional load and its distance from its position to the edge of the foundation pit and its direction of action relative to the foundation pit, as well as the traffic additional load and its distance from its position to the edge of the foundation pit and its direction of action relative to the foundation pit, from the surrounding load parameters. This embodiment arranges and combines these parameters according to a preset field order to form the construction condition characteristics of the surrounding load verification and support stage. The construction condition characteristics of the support stage cover the main controlling factors of additional loads that affect the surface settlement and lateral displacement of the pit wall around the foundation pit, which are used for subsequent matching of target conditions in the surrounding load and support response sub-library.

[0029] In some implementations, the step of calling a pre-established construction response database to match the construction condition characteristics of each construction stage and determine the engineering response corresponding to different construction measures in each construction stage includes: The pre-established construction response database is invoked; the construction response database stores multiple standard construction condition characteristics and reference engineering responses corresponding to different construction measures under each standard construction condition characteristic. The construction conditions of the current construction stage are matched with the standard construction conditions to determine the target standard conditions that match the construction conditions of each construction stage. The reference engineering response under the construction measures corresponding to the target standard working condition characteristics is read from the construction response database and used as the engineering response corresponding to the construction measures under the current construction stage.

[0030] The step of matching the construction condition characteristics of the current construction stage with the standard construction condition characteristics to determine the target standard construction condition characteristics that match the construction condition characteristics of each construction stage includes: If the construction condition characteristics of the current construction stage are continuous construction condition parameters, then the standard construction condition characteristics whose absolute value of the difference with the construction condition characteristics of the current construction stage does not exceed the preset allowable deviation will be used as candidate standard construction condition characteristics. If the construction condition characteristics of the current construction stage are discrete construction condition parameters, then the standard construction condition characteristics with the same category will be used as candidate standard construction condition characteristics. When multiple candidate standard working condition features exist, the working condition distance between the current construction stage working condition feature and the candidate standard working condition feature is calculated, and the candidate standard working condition feature with the smallest working condition distance is taken as the target standard working condition feature.

[0031] In a specific embodiment, such as Figure 2 As shown, this embodiment calls a pre-established construction response database for transmission tower pile foundations to match the construction conditions of each construction stage, determining the engineering response corresponding to different construction measures in each stage. Based on the geometric characteristics, main influencing factors, and differences in engineering response at different construction stages of the transmission tower pile foundation, the construction response database establishes corresponding parametric geotechnical numerical analysis models. The calculation results under different construction conditions and measures are then structured and organized to form the database. The construction response database includes at least a drilling response sub-database, a pile cap excavation response sub-database, and sub-databases for surrounding loads and supports. Each response sub-library sets construction condition feature fields for its working condition response units based on the response matching requirements of the corresponding construction stage. These fields consist of the corresponding stage's construction condition feature vector and valid parameter fields from the target foundation pit evaluation condition or support discrimination index, arranged in a preset field order. This allows the construction condition features of the target tower location at the corresponding stage, as well as the target foundation pit evaluation condition or support discrimination index, to be compared with the working condition response units in the corresponding response sub-library. In this embodiment, each response sub-library consists of multiple working condition response units, each including the corresponding construction condition features. And the multi-measure response group for the same construction condition associated with the characteristics of this construction condition. The multi-measure response group for the same working condition includes the benchmark construction measures for the current construction stage. and their corresponding engineering responses and various candidate construction measures set in order of preset measure levels. and the corresponding engineering response under the same construction conditions. The purpose is to associate multiple construction measures and their corresponding engineering responses under the same construction conditions, so that the control effects of different measures can be compared on the same basis when judging subsequent measures, and to avoid inconsistent benchmarks for comparing measures due to inconsistent conditions.

[0032] In this embodiment, the engineering responses in the borehole formation response sub-library include at least the maximum horizontal displacement of the borehole wall, the depth of maximum borehole wall deformation, and the state of abnormal seepage or mud loss; the engineering responses in the pile cap foundation pit excavation response sub-library include at least the maximum horizontal displacement of the pit side and the maximum heave displacement of the pit bottom; the engineering responses in the surrounding load and support response sub-library include at least the maximum horizontal displacement of the pit side, the maximum heave displacement of the pit bottom, and the maximum surface settlement. This embodiment establishes a phased construction response database, and structures the existing parametric numerical calculation results according to the relationship between construction condition characteristics, construction measures, and their corresponding engineering responses. This allows target tower locations within the database's applicable range to directly call the engineering responses corresponding to existing construction measures, reducing redundant modeling and calculation workload and improving the reuse efficiency of existing parametric calculation results. Next, this embodiment uses the construction condition feature vector of the construction stage corresponding to the target tower location, the target foundation pit evaluation condition, or the support discrimination index to filter the condition response units in the corresponding response sub-library according to preset parameter matching conditions, and determines the engineering responses corresponding to different construction measures in each construction stage. The specific matching process is as follows: This embodiment first determines the type of construction condition parameters in the current construction stage. For continuous construction condition parameters, such as soil thickness, burial depth, permeability coefficient, groundwater level, pile diameter, pile length, foundation pit size, and load strength, if the absolute value of the difference between the j-th parameter of the target condition and the corresponding parameter of the i-th condition response unit in the database does not exceed the preset allowable deviation of the j-th construction condition parameter, the continuous construction condition parameter is determined to meet the preset parameter matching condition; if it exceeds the preset allowable deviation, the parameter is determined not to meet the matching condition. The preset allowable deviation is based on the reasonable variation range of each parameter in engineering practice and the parameter's... The sensitivity of the parameters to the engineering response is set separately, and this embodiment does not impose any restrictions. For discrete construction condition parameters such as stratum type, foundation layout, external load type, and load direction category, this embodiment filters them according to the complete consistency of the category or according to the pre-established correspondence of engineering attributes. For example, stratum types with similar physical and mechanical properties are grouped into the same matching category. Through the above-mentioned categorized matching method of continuous parameters and discrete parameters, the quantitative comparability of numerical parameters is ensured, and the consistency of qualitative characteristics of categorical parameters is also ensured, avoiding the problem of incorrectly calling irrelevant condition responses due to parameter type mismatch.

[0033] When multiple candidate working condition response units satisfy the above-mentioned preset parameter matching conditions exist, this embodiment needs to select the one closest to the target working condition from the multiple candidates as the target working condition response unit. The specific calculation process is as follows: For each continuous construction working condition parameter, this embodiment first calculates the difference between the j-th parameter of the target working condition and the corresponding parameter of the i-th working condition response unit in the database, divided by the preset allowable deviation of the j-th parameter, to obtain the dimensionless deviation value of the parameter. Then, the dimensionless deviation value is multiplied by the matching weight of the j-th construction working condition parameter. Finally, all the parameter items involved in the calculation are added together to obtain the comprehensive working condition distance between the target working condition and the i-th candidate working condition response unit. Among them, the sum of the matching weights of all the continuous construction working condition parameters involved in the calculation is equal to 1. The specific calculation formula is as follows: In the formula, is the comprehensive working condition distance of the i-th candidate working condition response unit. The smaller the comprehensive working condition distance, the closer the working condition of the target working condition is to that of the candidate working condition response unit. m is the total number of continuous construction working condition parameters involved in the comprehensive working condition distance calculation. It should be noted that discrete construction working condition parameters (such as stratum type, foundation layout, etc.) are not involved in the distance numerical calculation and are only used for qualitative screening of candidate working conditions. The matching weight is the j-th construction condition parameter. This weight is used to reflect the difference in the degree of influence of different parameters on the project response. The sum of the matching weights of all construction condition parameters involved in the calculation is equal to 1. This refers to the specific value of the j-th continuous parameter in the construction condition characteristics of the i-th candidate working condition response unit in the construction response database; This refers to the specific value of the j-th continuous parameter in the characteristic vector of the construction conditions of the target tower site at the current construction stage. is the preset allowable deviation of the j-th construction condition parameter. This value is used to perform dimensionless processing on the parameter differences of different dimensions, so that parameters of different physical units can be compared in distance on the same scale; i is the number of the i-th candidate condition response unit in the construction response database that meets the preset parameter matching conditions; j is the j-th parameter in the continuous construction condition parameter sequence that participates in the comprehensive condition distance calculation.

[0034] After calculating the comprehensive working condition distance between the target working condition and each candidate working condition response unit, this embodiment selects the candidate working condition response unit with the smallest comprehensive working condition distance as the target working condition response unit. This embodiment uses comprehensive working condition distance calculation to quantitatively evaluate the overall similarity between the target working condition and each candidate working condition among multiple candidate working conditions, making the matching results more consistent with the characteristics of multi-parameter coupling influence in actual engineering, avoiding the problem of local optima and overall deviation caused by single-parameter matching. When multiple working condition response units have the same and smallest comprehensive working condition distance, an equidistant matching working condition set is formed, and units with the same comprehensive working condition distance are selected from the equidistant matching working condition set. For each engineering response identified by the construction measures, a conservative response value is selected in the unfavorable direction relative to the corresponding response control limit. The conservative response value forms the conservative response vector of the corresponding construction measure. For example, for the horizontal displacement of the borehole wall, if the response control limit is the upper limit, the largest displacement value among multiple equidistant working conditions is selected as the conservative response value. The opposite is true for parameters that need to meet the lower limit requirement. In this embodiment, by selecting conservative response values ​​under equidistant conditions, a safer value selection strategy is adopted when there is uncertainty in the working condition matching. This ensures that the subsequent measure judgment is carried out under the premise of being safer, thereby improving the reliability of the final determined construction plan.

[0035] When the target working condition exceeds the preset applicable range of the corresponding response sub-library, for example, if the value of a continuous parameter of the target working condition exceeds the range from the minimum to the maximum value of that parameter in the database, or if there is no corresponding entry for a discrete parameter category in the database, an out-of-domain identifier is generated, and supplementary numerical calculation or engineering review process is triggered. This ensures that working conditions outside the database coverage can also obtain the required engineering response data through supplementary calculation, avoiding interruption of scheme generation due to database limitations. After matching the response units of the target working condition, the benchmark construction measures and their corresponding engineering responses corresponding to the characteristics of the target standard working condition, as well as various candidate construction measures and their corresponding engineering responses, are read from the construction response database and used as the engineering responses corresponding to each construction measure in the current construction stage. For example, for the drilling stage, based on the drilling... The phased construction condition feature vector is matched with the target condition response unit in the borehole formation response sub-library. The engineering response corresponding to the benchmark borehole formation measure in the target condition response unit is read, and the construction condition features of the borehole formation stage and the matched engineering response are written into the borehole formation stage status node. For the pile group foundation pit excavation stage, the target condition response unit is matched with the pile group foundation pit excavation response sub-library according to the target foundation pit evaluation condition, and the engineering response under the corresponding excavation measure is read. For the surrounding load check and support stage, the target condition response unit is matched with the surrounding load and support response sub-library according to the support discrimination index, and the engineering response under the corresponding support measure is read. This embodiment calls the engineering responses in the corresponding response sub-library in stages, so that the response analysis of each construction stage focuses on the engineering response type unique to that stage, and improves the pertinence of construction measure discrimination.

[0036] This embodiment, through the aforementioned working condition matching method, enables existing parametric numerical calculation results to be uniformly organized and quickly retrieved according to the structured relationship between construction working condition characteristics, construction measures, and their corresponding engineering responses. For target tower site construction working conditions within the applicable scope of the database, it is not necessary to rebuild a complete numerical calculation model for each tower site and calculate the engineering responses corresponding to the benchmark construction measures and multiple candidate construction measures separately. Instead, the existing calculation results in the database are directly called for subsequent discrimination, thereby significantly reducing the workload of repetitive modeling and calculation and improving the efficiency of construction scheme generation. At the same time, through mechanisms such as comprehensive working condition distance calculation and conservative response value selection, the accuracy of working condition matching and engineering safety are guaranteed.

[0037] S3. Under the current layout of the pile foundation at the tower site, the engineering response corresponding to different construction measures is judged, and the target tower site construction measures for each construction stage are determined.

[0038] In some implementations, when the current tower location pile foundation layout is a single pile foundation, only the drilling construction measures for the drilling stage are determined; when the current tower location pile foundation layout is a pile group foundation, the drilling construction measures for the drilling stage, the foundation pit construction measures for the excavation stage, and the foundation pit support measures for the support stage are determined sequentially. Specifically, when the current construction stage is the drilling stage and the current tower location pile foundation layout is a single pile foundation or a pile group foundation, the step of judging the engineering responses corresponding to different construction measures and determining the target tower location construction measures for each construction stage includes: comparing the engineering response corresponding to the benchmark drilling measure under the drilling stage in the construction response database with a preset drilling response control limit; if the engineering response is within the preset drilling response control limit, the benchmark drilling measure is determined as the drilling construction measure; when the current construction stage is the foundation pit excavation stage and the current tower location pile foundation layout is a pile group foundation, the step of judging the engineering responses corresponding to different construction measures and determining the target tower location construction measures for each construction stage includes: The target construction measures of the drilling stage are transferred to the foundation pit excavation stage, and the surrounding load status of the current tower site in the foundation pit excavation stage is determined according to the surrounding load parameters. The surrounding load conditions and the construction conditions of the foundation pit excavation stage are combined into the target foundation pit evaluation conditions, and the engineering responses corresponding to unsupported vertical excavation and slope excavation measures are matched in the construction response database according to the target foundation pit evaluation conditions. The engineering response corresponding to the unsupported vertical excavation measure is compared with the preset response control limits, and the first unsupported vertical excavation measure that meets all response control limits is determined as the foundation pit construction measure.

[0039] When the current construction phase is the support phase and the current tower site pile foundation layout is a pile group foundation, the steps for judging the engineering response corresponding to different construction measures and determining the target tower site construction measures for each construction phase include: When neither the unsupported vertical excavation measure nor the slope excavation measure meets all response control limits, the engineering response corresponding to different support measures is read sequentially according to the preset support measure level, and compared with the preset response control limits. The support measure that meets all response control limits for the first time is determined as the foundation pit support measure.

[0040] In a specific embodiment, when the current tower location's pile foundation layout is a single pile foundation, since the single pile foundation only involves the drilling and hole-forming stage and does not require subsequent foundation pit excavation, it is only necessary to determine the drilling and hole-forming construction measures to terminate the activation of the state nodes in subsequent stages. The foundation pit excavation and support stages are no longer required for differentiation, thus avoiding unnecessary analysis and calculations for the single pile foundation and simplifying the construction plan generation process. When the current tower location's pile foundation layout is a pile group foundation, since the pile group foundation requires pile cap construction after the drilling and hole-forming stage,... The excavation of the foundation pit and the determination of necessary support measures require sequential determination of the drilling construction measures, the foundation pit construction measures, and the foundation pit support measures according to the construction sequence. This embodiment divides the construction process based on the pile foundation layout, allowing single pile foundations to directly complete the drilling stage determination and proceed to scheme generation, while group pile foundations continue with the pile cap foundation pit-related determinations. When the current construction stage is the drilling stage and the current tower location pile foundation layout is a single pile foundation or a group pile foundation, the determination process for the drilling stage construction measures is as follows: Figure 4 This is a schematic diagram of the target tower site construction measure discrimination process provided by an embodiment of the present invention. In this embodiment, the target working condition response unit is matched in the drilling response sub-library based on the construction working condition feature vector of the drilling stage. The engineering response corresponding to the benchmark drilling measure is read, and the ratio of the maximum horizontal displacement of the borehole wall to the designed pile diameter is used as the drilling deformation evaluation index. The drilling deformation evaluation index is compared with the corresponding response control limit. The drilling response control state is determined according to whether abnormal seepage, mud loss or slurry leakage occurs. If the drilling deformation evaluation index does not exceed the corresponding response control limit, it means that all engineering responses corresponding to the benchmark drilling measure meet the corresponding preset response control limit. At this time, if the drilling deformation evaluation index is detected to not exceed the control limit and no abnormal seepage, mud loss or slurry leakage occurs, the benchmark drilling measure is directly determined as the drilling construction measure for the target tower site. This allows the benchmark construction measure with the lowest degree of engineering intervention to be used first in the drilling stage. Only when the benchmark measure cannot meet the response control requirements is the progressive discrimination of candidate measures initiated, thereby avoiding unnecessary engineering measure upgrades and achieving the economy of the construction plan.

[0041] If at least one engineering response corresponding to the benchmark borehole drilling measure fails to meet the corresponding preset response control limit, such as the borehole deformation evaluation index exceeding the control limit, or abnormal seepage, mud loss, or slurry runoff occurring, then it is necessary to further determine the main control response index. In this embodiment, the main control response index is determined based on the spatial correspondence between the depth of maximum borehole wall deformation and the burial depth range of the main weak layer, as well as the spatial correspondence between the location of abnormal seepage, mud loss, or slurry runoff and the burial depth range of the high permeability layer. The main control response index is a risk type label variable, which includes at least one of borehole wall deformation control label and seepage control label. Specifically, when the depth of maximum borehole wall deformation is located in the main weak layer... When the distance between the borehole wall deformation control label and the boundary of the burial depth is less than the preset spatial proximity judgment threshold, the borehole wall deformation control label is used as the main control response indicator. When the location of abnormal seepage, mud loss, or slurry leakage is located within the burial depth of the high permeability layer or the distance between the location and the boundary of the burial depth is less than the preset spatial proximity judgment threshold, the seepage control label is used as the main control response indicator. This label variable does not contain any numerical data and only indicates the type of risk identified under the current target working condition. This is to determine the direction of invocation of candidate measures when the baseline measures do not meet the control requirements, so that the selection of subsequent candidate measures matches the actual construction risks existing at the target tower location, and avoids calling measures unrelated to the main control risks, which would reduce the judgment efficiency.

[0042] It should be noted that during the construction response database construction phase, each candidate borehole drilling measure in the multi-measure response group under the same working condition is pre-set with a function type identifier field. This field is also marked using a classification label system. For example, in this embodiment, measures to adjust mud wall parameters can be pre-marked as borehole wall deformation control; measures to set up steel casing covering the main borehole wall deformation control zone can be pre-marked as borehole wall deformation control; measures to adjust mud equivalent head or mud performance parameters can be pre-marked as seepage control; and measures to set up steel casing that penetrates high-permeability risk layers and enters relatively stable strata can be pre-marked as seepage control. The measures pre-labeled as seepage control, and the integrated measures that simultaneously adjust mud parameters and install steel casing, are pre-labeled as borehole wall deformation control and seepage control, respectively. After the risk type labels of the main control response indicators are assigned, this embodiment reads all candidate measures and their pre-labeled function type identifiers in the multi-measure response group under the same working condition. The risk type labels of the main control response indicators are matched and filtered with the function type identifiers of each candidate measure. If the main control response indicator only contains the borehole wall deformation control label, then all candidates with the function type identifier of seepage control are filtered out in the multi-measure response group under the same working condition. For subsequent comparisons, only candidate measures categorized as "borehole deformation control" will be retained. These candidate measures related to borehole deformation control must include at least measures to adjust mud wall protection parameters and measures to install steel casings covering the main borehole deformation control zone. If the main control response index only includes the seepage control tag, all candidate measures categorized as "borehole deformation control" will be removed from the multi-measure response group under the same working condition. Only candidate measures categorized as "seepage control" will be retained for subsequent comparisons. Other measures related to abnormal seepage, mud loss, or mud runoff control will also be considered. The selected borehole formation measures should include at least measures to adjust the equivalent hydraulic head or performance parameters of the drilling mud, and measures to install steel casings to penetrate high-permeability risk layers and enter relatively stable formations. If the main control response index includes both borehole wall deformation control and seepage control labels, all candidate measures in the multi-measure response group under the same working condition should be retained without screening. This way, by using the main control response index to selectively call candidate measures, the subsequent progressive judgment process will only compare candidate measures related to the current risk type, avoiding the unreasonable judgment results caused by mixing borehole wall deformation control measures and seepage control measures.

[0043] In the selected subset of candidate measures, this embodiment sequentially reads the engineering responses corresponding to each candidate measure according to the preset measure level order, and compares the read engineering responses corresponding to each candidate measure with the preset response control limits. The candidate measure that first satisfies all preset response control limits is determined as the construction measure for the target tower site at this stage. The preset measure level order is set from low to high according to the degree of intervention of each candidate measure on the construction conditions, ensuring that the selection of construction measures follows a progressive relationship from low to high intervention, avoiding the waste of engineering economy caused by directly adopting high-cost measures. It should be noted that when the engineering responses corresponding to all candidate drilling measures do not satisfy all preset response control limits... A special drilling design trigger identifier is generated. This special drilling design trigger identifier indicates that none of the existing candidate measures in the current construction response database can meet the drilling control requirements of this tower site. Special design and calculation are required for the special working conditions of this tower site. In this embodiment, the special design trigger identifier is passed to the final construction plan generation process to remind the engineering designers that there are drilling control requirements for this tower site that exceed the scope of conventional measures. In this embodiment, the construction working condition characteristics of the drilling stage, the matched engineering response, the drilling response control status, the main control response index, and the determined drilling construction measures are written into the drilling stage status node. When generating the special drilling design trigger identifier, the identifier is also written into the drilling stage status node.

[0044] After determining the drilling and hole-forming construction measures for the borehole-forming stage, this embodiment divides the construction process according to the current pile foundation layout of the tower location. When the current pile foundation layout of the tower location is a 1*1 single pile foundation, the activation of subsequent stage status nodes is terminated, and the process directly proceeds to the construction plan generation step. When the current pile foundation layout of the tower location is a pile group foundation with the requirement of pile group cap foundation pit construction, the drilling and hole-forming construction measures and response discrimination status of the drilling and hole-forming stage are passed as the preceding construction status fields to the foundation pit excavation stage status node, and the foundation pit excavation stage status node is activated to discriminate the construction measures for the foundation pit excavation stage. The discrimination process of the construction measures for the foundation pit excavation stage in this embodiment is as follows: This embodiment identifies the surrounding load state of the current tower location based on the surrounding load parameters of the target tower location. It forms a corresponding surrounding load state based on the load type, load magnitude, load distance, and load direction. The surrounding load state includes at least four states: no additional load, building load, traffic load, and combined load. Specifically, when there are no additional building or traffic loads, it is identified as a no-additional-load state; when only additional building loads exist, it is identified as a building load state; when only additional traffic loads exist, it is identified as a traffic load state; and when both additional building and traffic loads exist, it is identified as a combined load state, enabling subsequent... The working condition identification can take into account the actual impact of surrounding additional loads on the stability of the foundation pit, avoiding the use of the same construction measures in the presence of surrounding loads as in the absence of loads, which would lead to foundation pit safety risks. Then, in this embodiment, the identified surrounding load state is merged with the feature vector of the construction working condition during the excavation stage of the pile cap foundation pit to form the target foundation pit evaluation working condition. This target foundation pit evaluation working condition includes not only the foundation pit's own stratum conditions, geometric conditions, and foundation layout conditions, but also the additional load conditions around the foundation pit, so that it can comprehensively reflect the stress and deformation conditions of the target foundation pit in the actual construction environment, thereby ensuring the accuracy and pertinence of subsequent engineering response identification.

[0045] In this embodiment, the corresponding target condition response unit is matched in the pile cap foundation pit excavation response sub-library of the construction response database based on the target foundation pit evaluation condition. The engineering response corresponding to the unsupported vertical excavation measure is read and compared with the preset response control limit. If all engineering responses corresponding to the unsupported vertical excavation measure meet the corresponding preset response control limit, the unsupported vertical excavation measure is determined as the foundation pit construction measure. The target foundation pit evaluation condition, the matched engineering response, the response discrimination status, and the foundation pit construction measure status are written into the foundation pit excavation stage status node. Then, the activation of subsequent stage status nodes is terminated, and the construction plan generation step is directly entered. This is to ensure that this embodiment prioritizes the unsupported vertical excavation measure, which is the simplest and lowest cost to construct, and only considers excavation or support measures with a higher degree of intervention when the control requirements cannot be met.

[0046] If at least one engineering response corresponding to the unsupported vertical excavation measure does not meet the corresponding preset response control limit, the site is further judged based on the site construction space parameters to determine whether the site has the conditions for slope excavation. Specifically, in this embodiment, the feasibility status of slope excavation is comprehensively determined based on factors such as whether the available construction width around the foundation pit is sufficient to meet the horizontal expansion distance required for slope excavation, whether the distance from the edge of the foundation pit to the site boundary or adjacent obstacles meets the safety distance requirements for slope excavation, and whether the site slope is favorable or unfavorable for slope excavation. If the site construction space parameters meet the above-mentioned preset slope excavation conditions, the engineering response corresponding to the slope excavation measure under the target foundation pit evaluation condition is read, and the engineering response is compared with the preset response control limit. If all engineering responses corresponding to the slope excavation measure meet the corresponding preset response control limit, the slope excavation measure is determined as the foundation pit construction measure, and the target foundation pit evaluation condition, the matched engineering response, the response discrimination status, and the foundation pit construction measure status are written into the foundation pit excavation stage status node. Then, the activation of the subsequent stage status nodes is terminated, and the construction plan generation step is directly entered.

[0047] If the site construction space parameters do not meet the preset slope conditions, or if the site has slope conditions but at least one engineering response corresponding to the slope excavation measures does not meet the corresponding preset response control limit, then the response discrimination status of the foundation pit excavation stage is marked as requiring support measures discrimination, and the foundation pit excavation stage response discrimination status and foundation pit construction measures status are written into the foundation pit excavation stage status node. At the same time, the surrounding load check and support stage status nodes are activated, and the discrimination of support stage construction measures is entered. Among them, when the foundation pit construction measures have not yet been determined, the foundation pit construction measures status is set to the undetermined measures status. This process uses slope excavation as a transitional discrimination link between unsupported vertical excavation and support measures, so that slope excavation is given priority when site conditions permit and slope can meet control requirements, avoiding directly jumping to support measures with a high degree of engineering intervention.

[0048] When the response judgment state during the foundation pit excavation stage indicates a need for support measures, this embodiment uses the target foundation pit evaluation condition and the response judgment state during the foundation pit excavation stage to construct a support judgment index. This index integrates the determined geometric conditions, soil conditions, surrounding load conditions, and the judgment state requiring support that have been established during the foundation pit excavation stage, forming a complete index for matching the support stage conditions. This ensures that the response unit matched during the support stage is consistent with the target foundation pit evaluation condition during the excavation stage in terms of engineering conditions, avoiding mismatches between support measures and actual foundation pit conditions due to inconsistent conditions. Then, this embodiment uses this support judgment index... In the perimeter load and support response sub-library of the construction response database, the corresponding target working condition response unit is matched, and the corresponding multi-measure response group of the same working condition is called according to the matched target working condition response unit. The multi-measure response group of the same working condition stores a variety of candidate support measures and their corresponding engineering responses in the order of preset support measure levels. The preset support measure level order is determined according to the support measure type and its degree of intervention in the engineering environment. For example, when steel sheet piles of different lengths are used as candidate support measures, this embodiment can set the measure level in the order of steel sheet pile support length from shortest to longest, that is, shorter steel sheet piles correspond to lower measure levels, and longer steel sheet piles correspond to higher measure levels.

[0049] In this embodiment, following the preset support measure levels, starting from the lowest level, the engineering responses corresponding to the current candidate support measures are read sequentially. These responses are then compared with preset response control limits. If all engineering responses corresponding to the current candidate support measures meet the corresponding preset response control limits, the current candidate support measure is determined as the foundation pit support measure for the target pile group foundation. The surrounding load and support condition characteristics, the matched engineering responses, the response discrimination status, and the finally determined foundation pit support measure status are written into the surrounding load verification and support stage status node. If at least one engineering response corresponding to the current candidate support measure does not meet the corresponding preset response control limit and there are still candidate support measures at the next lower level, the next lower level candidate support measures and their corresponding engineering responses are called, and the response control limit discrimination is performed again. This embodiment performs progressive discrimination in the above manner until a candidate support measure that first meets all preset response control limits is found.

[0050] When the target tower is simultaneously affected by building loads and traffic loads, if a corresponding combined load condition response unit exists in the surrounding load and support response sub-database, the support measures are progressively judged based on the combined load condition response unit. If no corresponding combined load condition response unit exists, a combined load over-domain identifier is generated and a supplementary numerical calculation or engineering review process is triggered. When the engineering responses corresponding to all candidate support measures in the preset measure level sequence do not meet all response control requirements, a special support design trigger identifier is generated. This special support design trigger identifier indicates that none of the existing candidate support measures in the current construction response database can meet the support control requirements of the tower under the surrounding additional load conditions. The surrounding load and support condition characteristics, matching engineering responses, response judgment status, and the finally determined foundation pit support measure status are written into the surrounding load verification and support stage status node. When a special support design trigger identifier is formed, the identifier and its triggering reason are written into the surrounding load verification and support stage status node.

[0051] This embodiment employs a phased, progressive discrimination process. The drilling, excavation, and support stages are each judged in order of increasing intervention levels. The construction measure that first meets all response control requirements is identified as the target tower site construction measure for that stage. This achieves gradual optimization of construction measures at each stage. Simultaneously, by recording special design trigger markers in the stage status nodes, it ensures that special design requirements can be output in a timely manner when existing database measures cannot meet control requirements. This avoids generating construction schemes lacking safety guarantees, thus ensuring both the economic rationality and the safety and reliability of the construction scheme.

[0052] S4. Combine the construction measures for the target tower sites at each construction stage according to the construction sequence to generate a multi-stage construction plan for the target tower sites.

[0053] After determining the construction measures for the target tower location at each construction stage, this embodiment reads the response judgment status and construction measure status in the status nodes of each activated stage according to the construction sequence. The construction measures determined at each stage are combined according to the construction sequence to generate a multi-stage construction plan for the target tower location. Specifically, since the construction process of a single pile foundation only involves the drilling stage and there is no need for excavation and support of the pile cap pit, this embodiment only reads the drilling response control status, main control response indicators, and determined drilling construction measures in the status nodes of the drilling stage to generate a tower-level construction plan for the single pile foundation. This plan includes the drilling construction measures and their corresponding response judgment criteria.

[0054] Since the construction process of pile group foundation involves the drilling stage, the excavation stage, and the activated peripheral load check and support stage, this embodiment needs to read the response judgment status and construction measure status recorded in the state nodes of the drilling stage, the excavation stage, and the peripheral load check and support stage in sequence according to the construction order of the multi-stage construction response state chain. The construction measures determined in each stage are then combined in an orderly manner according to the construction order of drilling, excavation, and support to generate a multi-stage construction plan for pile group foundation. The pile group foundation tower level construction plan consists of two parts: drilling construction measures and pile cap pit construction measures. When the excavation stage enters the progressive judgment process of support measures, the pile cap pit construction measures further include the finally determined pit support measures.

[0055] During the above construction scheme generation process, when any stage status node contains a special design trigger identifier, the special design requirements and triggering reasons for that construction stage are output in the multi-stage construction scheme. For example, when the hole-forming stage status node contains a special hole-forming design trigger identifier, the special design requirements for the hole-forming stage are output in the final scheme, along with the reasons for the engineering response exceeding the limits that triggers the requirements and information on candidate measures that have been tried but cannot meet the requirements. When the support stage status node contains a special support design trigger identifier, the special design requirements for the support stage are output in the final scheme, along with the surrounding load conditions that trigger the requirements and information on candidate support measures that have been tried but cannot meet the requirements. This embodiment provides a clear triggering basis for subsequent supplementary numerical calculations or engineering verification by clearly marking special design requirements that exceed the scope of the database in the construction scheme, avoiding unreliable extrapolation matching of out-of-domain conditions, and ensuring the safety and reliability of the construction scheme.

[0056] This embodiment achieves complete consistency between the generated construction plan and the actual construction sequence of drilling, excavation, and support stages by reading the status nodes of each activated stage in the order of the multi-stage construction response state chain and combining the construction measures of each stage. At the same time, the construction measures determined in each stage are accompanied by corresponding response discrimination status and engineering response data as the basis for their selection, so that each target tower location obtains a personalized construction plan that matches its specific engineering conditions.

[0057] It should be noted that, based on the geometric characteristics, main influencing factors, and differences in engineering response at different construction stages of transmission tower pile foundations, this embodiment establishes corresponding parametric geotechnical numerical analysis models. The calculation results under different construction conditions and measures are then structured and organized into sub-libraries for borehole formation response, pile group cap foundation pit excavation response, and surrounding load and support response. For single-pile borehole formation, this embodiment employs a two-dimensional axisymmetric finite element model based on its axisymmetric geometric characteristics to analyze borehole wall deformation and abnormal seepage response under different geological structures, hydrological conditions, and borehole control measures. For pile group cap foundation pit excavation and surrounding load and support response... For the problem of asymmetric load action, this embodiment uses a three-dimensional finite element model based on the spatial arrangement of pile groups, the geometry of the foundation pit, and the characteristics of load action. It analyzes the horizontal displacement of the pit side, the heave of the pit bottom, and the surface settlement under different foundation pit excavation measures, surrounding load conditions, and support measures. The above numerical calculations are completed using finite element calculation software. The numerical models of different construction stages are used to generate engineering response data under different construction conditions and different construction measures at the corresponding stages. The response judgment state and construction measure state of the previous stage are passed between different construction stages through a multi-stage construction response state chain, so that the response matching and measure judgment of different stages are continuously executed according to the actual construction sequence.

[0058] After numerical calculations are completed, this embodiment extracts the main engineering responses corresponding to each calculation condition and organizes them using a structured data table. The recorded fields include at least the foundation layout form, pile foundation geometric parameters, pile cap pit geometric parameters, soil parameters, hydrological conditions, surrounding load parameters, construction measure identifiers, measure parameters, and engineering responses. For calculation results with the same construction condition but different construction measures, this embodiment organizes them according to their construction stage and response sub-library to form a multi-measure response group for the same condition. Each response sub-library consists of multiple condition response units. The i-th condition response unit contains the construction condition feature corresponding to that unit and the multi-measures for the same condition associated with that construction condition feature. The response group; the multi-measure response group under the same working condition includes the benchmark construction measures and their corresponding engineering responses for the current construction stage, as well as various candidate construction measures and their corresponding engineering responses under the same construction condition characteristics, set according to the preset measure level order. After the target tower enters the corresponding construction stage, this embodiment matches the target working condition response unit according to the construction condition characteristics of that stage or the corresponding discrimination index, and reads the engineering response corresponding to the corresponding construction measures. When the current measures cannot meet all response control requirements, the subsequent candidate measures and their corresponding engineering responses are read in sequence according to the preset measure level order, and the construction measures that first meet all response control requirements are determined as the construction measures for the current construction stage.

[0059] To facilitate understanding, the following detailed descriptions of the drilling and pile group foundation construction examples are provided. Specifically, this example uses a two-dimensional axisymmetric finite element model to analyze the drilling and grouting pile formation process. The typical analysis model has a designed pile diameter of 2.0 meters and a pile length of 40 meters. The computational domain depth and radial width are both 60 meters. The model sets up strata stratification, groundwater conditions, drilling excavation, and mud wall protection conditions. By changing the thickness of the soft soil layer, the burial depth of the weak layer, the location of the high permeability layer, and hydraulic conditions, multiple parameterized construction conditions are formed. Drilling excavation and mud wall protection are simulated according to the drilling and grouting construction process. After the calculation is completed, the horizontal displacement along the borehole wall is extracted as a function of depth, and the maximum horizontal displacement of the borehole wall, the depth of the maximum borehole wall deformation, and the abnormal seepage, mud loss, or mud runoff are recorded. The calculation results of the maximum horizontal displacement of the borehole wall under different soft soil thickness conditions are shown in Table 1. Table 1 In this embodiment, the geological conditions, hydrological conditions, pile foundation parameters, construction measure identifiers, and engineering responses corresponding to the different working conditions mentioned above are respectively written into the borehole formation response sub-library. After the target tower site enters the borehole formation stage, this embodiment matches the target working condition response unit in the borehole formation response sub-library according to the construction working condition characteristics of the borehole formation stage. For example, when the construction working condition of the target tower site's borehole formation stage is the same as or similar to the existing calculated working condition with a soft soil thickness of 25 meters, it is matched to the corresponding working condition response unit, and the maximum horizontal displacement of the borehole wall under the benchmark borehole formation measures is read as 45.78 mm. According to the borehole deformation evaluation index, its ratio is 2.289%. This embodiment uses 1% of the design pile diameter as the borehole deformation early warning reference value and 3% of the design pile diameter as the trigger reference value for further control measures progressive judgment. The above working condition reaches the borehole deformation early warning state, but has not yet reached the further control measures. The trigger reference value for progressive discrimination is written into the state node of the borehole stage, corresponding to the matching engineering response and response discrimination status. Furthermore, this embodiment conducts hydrogeological response analysis for the working condition where there is a high permeability layer within a range of 17 to 20 meters underground. When the high permeability layer forms a hydraulic connection with the external hydraulic recharge conditions, the calculated maximum horizontal displacement of the borehole wall is approximately 44.19 mm. When the mud head in the borehole decreases and abnormal mud loss occurs, obvious deformation concentration occurs near the high permeability layer, and the local horizontal displacement of the borehole wall reaches approximately 72 mm, corresponding to a borehole deformation ratio of 3.6%, which exceeds the further discrimination trigger reference value of 3% of the design pile diameter adopted in this embodiment. Based on the spatial correspondence between the location of the maximum borehole wall deformation concentration, the location of abnormal mud loss, and the burial depth range of the high permeability layer, this embodiment determines the main control response index of this working condition as two types: borehole wall deformation control and seepage control.

[0060] To address the aforementioned unfavorable hydrogeological conditions, this embodiment employs a steel casing control measure while maintaining the same geological structure, pile foundation parameters, and hydraulic conditions. In the specific calculation case, the steel casing thickness is 8 mm, and the bottom depth of the casing is 17 meters. Calculation results show that after installing the steel casing, the horizontal displacement of the borehole wall is reduced to less than 1 mm. The response relationship of different measures under the same construction conditions is shown in Table 2. Table 2 After the target tower location is matched to the above-mentioned working condition response unit, this embodiment first reads the engineering response corresponding to the benchmark drilling measure, since 72mm The reference hole-forming measure of 60mm does not meet the response control requirements of this embodiment. The system further calls the steel casing measure response from the multi-measure response group under the same working condition. Since the horizontal displacement of the hole wall after setting the steel casing is less than 1mm, it meets all the response control requirements set in this embodiment. Therefore, the steel casing measure is determined as the hole-forming construction measure for this working condition. This process does not calculate the steel casing measure parameters backward based on a certain target hole wall displacement value. Instead, after the target tower location is matched with the corresponding working condition response unit, the response is calculated based on the numerical values ​​already obtained by different construction measures under the same construction condition. After sequential comparison and response discrimination, this embodiment writes the drilling and hole-forming stage construction condition characteristics, matching engineering response, hole-forming response control status, main control response index, and determined hole-forming construction measure status into the hole-forming stage status node. When the target foundation is a single pile foundation, the hole-forming stage status node is used as the termination node of the multi-stage construction response status chain, and the tower-level construction scheme generation process begins. When the target foundation is a pile group foundation with pile cap foundation pit construction requirements, the response discrimination status and construction measure status of the hole-forming stage are transferred to the foundation pit excavation stage. Figure 3 This is a schematic diagram illustrating the state transmission relationship at different construction stages provided in an embodiment of the present invention.

[0061] The following is an example of the progressive discrimination of construction response and generation of tower-level construction schemes for a 3x3 pile group foundation. In this example, the target foundation uses a 3x3 pile group arrangement, with key parameters including a design pile diameter of 1000 mm, a pile length of 36 meters, a foundation pit width of 8.0 meters, and a pit excavation depth of 2.0 meters. Based on the number of target tower piles and the plane coordinates of each pile's center, three different pile coordinate positions are identified in two mutually orthogonal arrangement directions. Therefore, this example identifies the target foundation as a 3x3 pile group foundation. After completing the hole-forming stage response matching and determining the hole-forming construction measures, this example writes the hole-forming stage response discrimination status and the hole-forming construction measure status into the preceding construction status field of the foundation pit excavation stage status node, and activates the foundation pit excavation stage status node. Then, this example further... The load parameters around the target tower location are read, the load status around the target tower location is identified, and the surrounding load status is combined with the construction condition characteristics of the pile cap foundation pit excavation stage to form the target foundation pit evaluation condition. It should be noted that the basic condition in this embodiment does not have additional loads from surrounding buildings or traffic, so its surrounding load status is set to a no-addition-load state. Under this target foundation pit evaluation condition, the response to unsupported vertical excavation and slope excavation measures is judged. For the 3x3 pile foundation in this embodiment, under the same foundation layout, pile diameter, pile length, foundation pit size, stratum conditions, and no-addition-load state, the engineering response under the conditions of unsupported vertical excavation, 1:1 slope excavation, and 4-meter steel sheet pile support is calculated respectively. The response of the 3*3 pile foundation under different construction measures is shown in Table 3: Table 3 Among them, the engineering responses corresponding to unsupported vertical excavation measures and 1:1 slope excavation measures are associated and organized according to the same target foundation pit evaluation conditions, and are used for measure response judgment during the foundation pit excavation stage; the engineering response corresponding to the 4-meter steel sheet pile support measures is written into the surrounding load and support response sub-library as the support response under the state of no additional load, and is used for the support measure response call after the foundation pit excavation stage forms a state that requires support measure judgment. The relevant conditions in different response sub-libraries establish corresponding relationships through common fields such as foundation layout form, foundation pit geometry, stratum conditions and surrounding load state.

[0062] To illustrate the response determination process, this embodiment uses a horizontal displacement ratio of 3‰ as the reference value for controlling horizontal deformation on the pit side. Since the excavation depth is 2.0 meters, the corresponding reference value for horizontal displacement control is 6.0 mm. A bottom heave ratio of 6‰ is used as the reference value for controlling bottom heave. Since the pit width is 8 meters, the corresponding reference value for bottom heave control is 48 mm. This embodiment first reads the engineering response corresponding to unsupported vertical excavation measures, where the maximum horizontal displacement on the pit side is 8.82 mm. The maximum horizontal displacement on the pit side is 6.0mm, therefore, the unsupported vertical excavation method does not meet the horizontal displacement control requirements adopted in this embodiment. Since the target tower location has sufficient space for slope construction, this embodiment further reads the engineering response corresponding to the 1:1 slope excavation method, and the maximum horizontal displacement on the pit side is 6.29mm. Although the slope excavation reduces the maximum horizontal displacement of the pit side by about 28.7% compared to unsupported vertical excavation, it is still slightly higher than the control reference value. Therefore, in this embodiment, the response judgment state of the foundation pit excavation stage is set to the need for support measures. Since no foundation pit construction measures that can be directly adopted have been determined at present, the foundation pit construction measures state is set to the undetermined measures state, thereby forming the preceding construction state field and activating the surrounding load check and support stage state node.

[0063] This embodiment constructs a support discrimination index based on the target foundation pit evaluation conditions and the response discrimination status during the foundation pit excavation stage. The support discrimination index includes the target foundation pit evaluation conditions and the response discrimination status during the foundation pit excavation stage. At the same time, it matches the corresponding target condition response units in the surrounding load and support response sub-library and reads the lowest level candidate support measure, namely the engineering response corresponding to the 4m steel sheet pile support measure, whose maximum horizontal displacement on the pit side is 1.07mm. 6.0mm; the maximum bulge at the bottom of the pit is 14mm. 48mm, therefore, the 4-meter steel sheet pile support measure simultaneously meets all the main response control requirements set in this embodiment. Since the 4-meter steel sheet pile support measure is the first support measure in the preset support measure level sequence to meet all response control requirements, it is determined as the foundation pit support measure.

[0064] To illustrate the identification of surrounding load conditions, formation of target foundation pit evaluation conditions, and engineering response matching process when the target tower location is subject to adjacent building loads or traffic loads, this embodiment sets up two types of asymmetric load conditions for 2*2 and 3*3 pile foundations: building eccentricity and traffic overload. The net distance from the load application location to the edge of the foundation pit is taken as 3 meters, 6 meters, and 9 meters, respectively; the building height for the building eccentricity condition is taken as 9 meters, 18 meters, and 27 meters, respectively; and the additional load for the traffic overload condition is taken as 20 kPa and 40 kPa, respectively. For loads of 60 kPa and 20 kPa, 36 sets of parametric calculation cases are formed by combining 2 foundation layouts, 2 types of peripheral loads, 3 application distances, and 3 load intensities. After each calculation case is completed, this embodiment extracts the maximum surface settlement, the maximum horizontal displacement of the pit wall near the load, the maximum horizontal displacement of the pit wall far from the load, and the maximum pit bottom heave. These are then written into the peripheral load and support response sub-library along with the corresponding foundation layout, pit conditions, soil conditions, load type, load magnitude, load application distance, and load application direction. When the target parameter is within the existing parameterized calculation range but does not completely coincide with a discrete calculation point, after completing the screening of discrete working condition parameters such as foundation layout, load type, and load direction, and confirming that the target continuous parameter is within the existing calculation grid range, this embodiment can read adjacent discrete calculation points and obtain the engineering response corresponding to the target parameter location through interpolation. For example, for a 3*3 pile group foundation, the target tower is subjected to building bias, the net distance between the building and the edge of the foundation pit is 5 meters, and the building height is 24 meters. This embodiment performs bilinear interpolation based on the adjacent working conditions of 3 meters and 6 meters in the distance direction and the adjacent working conditions of 18 meters and 27 meters in the building height direction, obtaining a maximum surface settlement of 9.586 mm, a maximum horizontal displacement of the pit wall on the near-load side of 14.518 mm, a maximum horizontal displacement of the pit wall on the far-load side of 10.222 mm, and a maximum pit bottom heave of 28.243 mm. This matching result serves as the engineering response under the target foundation pit evaluation working condition, which is used for subsequent foundation pit excavation and support measures.

[0065] For target conditions with surrounding additional loads and site conditions suitable for slope protection, this embodiment can set corresponding slope excavation calculation conditions while keeping the foundation layout, pit geometry, stratum conditions, and surrounding load parameters unchanged. The engineering responses corresponding to unsupported vertical excavation and slope excavation are associated and stored according to the same target pit evaluation condition. When the target condition response unit does not yet have a corresponding slope excavation response, a missing response data flag is generated, triggering supplementary numerical calculations or engineering verification. The unsupported vertical excavation response is not directly substituted for the slope excavation response for judgment. To further illustrate the progressive process of support measures after the pit excavation stage has reached a state requiring support measure judgment, this embodiment selects extreme conditions of building eccentricity and traffic overload for 3*3 pile foundations, calculating the engineering responses under unsupported, 4-meter, 6-meter, and 8-meter sheet pile conditions respectively. The responses to different measures under the extreme building eccentricity condition are shown in Table 4. Table 4 Table 5 shows the different response measures for extreme traffic overload conditions: Table 5 The above-mentioned different measures responses are associated and organized according to the same basic conditions and the same external load conditions to form a multi-measure response group under the same target condition response unit. In this embodiment, taking the building eccentric extreme condition as an example, its support measure response group includes unsupported state, 4-meter steel sheet pile, 6-meter steel sheet pile and 8-meter steel sheet pile support measures and their corresponding engineering response vectors. When the foundation pit excavation stage has formed a response judgment state that requires support measure judgment, the system reads the engineering responses corresponding to different steel sheet pile support measures in the order of 4-meter, 6-meter and 8-meter measure levels. When all the engineering responses corresponding to the current support measure have met the response control limits set by the specific project, the system stops calling subsequent level support measures and determines the current support measure as the foundation pit support measure. When at least one engineering response of the current support measure does not meet the corresponding control limit and there is still a next level support measure, this embodiment calls the engineering response corresponding to the next level support measure. When all the support measures in the preset measure level order cannot meet all response control requirements, a special support design trigger identifier is generated.

[0066] Finally, following the construction sequence of the multi-stage construction response state chain, the response judgment state and construction measure state of each activated stage state node are read to generate a tower-level construction plan. This plan consists of the drilling construction measures and the foundation pit construction measures determined in the drilling stage. When the foundation pit excavation stage enters the progressive judgment of support measures, the foundation pit construction measures include the finally determined foundation pit support measures, thus forming a tower-level combined construction plan consisting of drilling construction measures and pile foundation pit construction measures.

[0067] This invention provides a method for generating a multi-stage construction scheme for transmission tower pile foundations. The method involves acquiring a target tower location engineering information set for the target transmission tower pile foundation, identifying the current tower location pile foundation layout based on the number of piles and the plane coordinates of each pile's center in the target tower location engineering information set; extracting construction condition characteristics of each construction stage from the target tower location engineering information set, and matching these characteristics with a pre-established construction response database to determine the engineering responses corresponding to different construction measures in each construction stage; the construction stages include drilling, excavation, and support; under the current tower location pile foundation layout, judging the engineering responses corresponding to different construction measures to determine the target tower location construction measures for each construction stage; and combining the target tower location construction measures for each construction stage according to the construction sequence to generate a multi-stage construction scheme for the target tower location. Compared with existing technologies, this method performs phased working condition matching and progressive judgment on the drilling, excavation and support stages of the transmission tower pile foundation construction process according to the construction sequence. It also realizes the diversion of construction process for different foundation layout forms according to the pile foundation layout form, thereby generating a multi-stage combined construction scheme adapted to the engineering conditions of the target tower site. This improves the reuse efficiency of existing parametric calculation results and reduces the workload of repeated modeling and calculation, while ensuring the safety of the construction scheme.

[0068] It should be noted that the sequence number of each process does not imply the order of execution. The execution order of each process should be determined by its function and internal logic, and should not constitute any limitation on the implementation process of the embodiments of this application.

[0069] In one embodiment, such as Figure 5 As shown in the figure, this invention provides a multi-stage construction scheme generation system for power transmission tower pile foundations, the system comprising: The data acquisition module 101 is used to acquire the target tower site engineering information set of the target transmission tower pile foundation, and to identify the current tower site pile foundation layout form according to the number of piles and the plane coordinates of the center of each pile in the target tower site engineering information set. The working condition matching module 102 is used to extract the construction working condition characteristics of each construction stage in the construction process of the transmission tower pile foundation from the target tower site engineering information set, and call the pre-established construction response database to perform working condition matching on the construction working condition characteristics of each construction stage to determine the engineering response corresponding to different construction measures in each construction stage; the construction stages include the drilling stage, the foundation pit excavation stage, and the support stage. The scheme generation module 103 is used to identify the engineering response corresponding to different construction measures under the current pile foundation layout of the tower site, and to determine the target tower site construction measures for each construction stage. The scheme combination module 104 is used to combine the construction measures of the target tower site in each construction stage according to the construction sequence to generate a multi-stage construction scheme for the target tower site.

[0070] Specific limitations regarding the system for generating multi-stage construction schemes for transmission tower pile foundations can be found in the aforementioned limitations regarding the method for generating multi-stage construction schemes for transmission tower pile foundations, and will not be repeated here. Those skilled in the art will recognize that the various modules and steps described in conjunction with the embodiments disclosed in this application can be implemented in hardware, software, or a combination of both. Whether these functions are implemented in hardware or software depends on the specific application and design constraints of the technical solution. Those skilled in the art can use different methods to implement the described functions for each specific application, but such implementation should not be considered beyond the scope of this application.

[0071] This invention provides a multi-stage construction scheme generation system for transmission tower pile foundations. The system acquires a target tower location engineering information set through a data acquisition module, and identifies the current tower location pile foundation layout based on the number of piles and the plane coordinates of each pile's center in the target tower location engineering information set. A working condition matching module extracts the construction working condition characteristics of each construction stage from the target tower location engineering information set, and calls a pre-established construction response database to match the working condition characteristics of each construction stage, determining the engineering response corresponding to different construction measures in each construction stage. The construction stages include drilling, excavation, and support. A scheme generation module, under the current tower location pile foundation layout, discriminates the engineering responses corresponding to different construction measures, determining the target tower location construction measures for each construction stage. A scheme combination module combines the target tower location construction measures of each construction stage according to the construction sequence, generating a multi-stage construction scheme for the target tower location. Compared with existing technologies, this system performs phased working condition matching and progressive judgment for the drilling, excavation and support stages of transmission tower pile foundation construction according to the construction sequence. It also realizes the diversion of construction process for different foundation layout forms according to the pile foundation layout form, thereby generating a multi-stage combined construction plan adapted to the engineering conditions of the target tower site. This improves the reuse efficiency of existing parametric calculation results and reduces the workload of repeated modeling and calculation, while ensuring the safety of the construction plan.

[0072] The embodiments described above are merely preferred embodiments of this application, and while the descriptions are specific and detailed, they should not be construed as limiting the scope of the invention patent. It should be noted that those skilled in the art can make various improvements and substitutions without departing from the technical principles of this invention, and these improvements and substitutions should also be considered within the scope of protection of this application. Therefore, the scope of protection of this patent application should be determined by the scope of the claims.

Claims

1. A method for generating a multi-stage construction scheme for transmission tower pile foundations, characterized in that, Includes the following steps: Obtain the target tower location engineering information set for the target transmission tower pile foundation, and identify the current tower location pile foundation layout form based on the number of piles and the plane coordinates of the center of each pile in the target tower location engineering information set; Construction condition characteristics of each construction stage during the construction of the transmission tower pile foundation are extracted from the target tower site engineering information set, and the construction condition characteristics of each construction stage are matched by calling the pre-established construction response database to determine the engineering response corresponding to different construction measures in each construction stage; the construction stages include the drilling stage, the foundation pit excavation stage, and the support stage. Under the current layout of the pile foundation at the tower site, the engineering response corresponding to different construction measures is judged, and the target tower site construction measures for each construction stage are determined. The construction measures for the target tower sites at each construction stage are combined according to the construction sequence to generate a multi-stage construction plan for the target tower sites.

2. The method for generating a multi-stage construction scheme for transmission tower pile foundations as described in claim 1, characterized in that, The step of identifying the pile foundation layout of the current tower site based on the number of piles and the plane coordinates of the center of each pile in the target tower site engineering information set includes: The number of piles and the plane coordinates of the center of each pile are read from the target tower site engineering information set; When the number of piles is one, the current pile foundation layout of the tower site will be identified as a single pile foundation; When the number of piles is greater than one and multiple pile foundations share a pile cap and there is a need for pile cap pit excavation, the current pile foundation layout of the tower location will be identified as a pile group foundation. When the current pile foundation layout is a group pile foundation and adopts a matrix arrangement, the row and column layout of the group pile foundation is determined according to the number of different coordinate positions of the center plane coordinates of each pile in two mutually orthogonal arrangement directions. The number of different coordinate positions in the two mutually orthogonal arrangement directions are respectively taken as the number of rows and the number of columns, and the product of the number of rows and the number of columns is the row and column layout of the group pile foundation.

3. The method for generating a multi-stage construction scheme for transmission tower pile foundations as described in claim 2, characterized in that, The target tower site engineering information set includes geological condition parameters, hydrological condition parameters, pile foundation parameters, pile cap pit parameters, and surrounding load parameters; the steps of extracting the construction condition characteristics of each construction stage during the construction of the transmission tower pile foundation from the target tower site engineering information set include: The design pile diameter, design pile length, stratum lithology parameters, and groundwater level parameters are extracted from the geological condition parameters, hydrological condition parameters, and pile foundation parameters of the target tower site project information set to form the construction condition characteristics of the drilling stage. Among them, the stratum lithology parameters include the thickness of the soft soil layer, the burial depth of the top boundary of the weak layer, the burial depth of the bottom boundary of the weak layer, the burial depth of the top boundary of the high permeability layer, the thickness of the high permeability layer, and the permeability coefficient of the high permeability layer; the groundwater level parameters include the groundwater level, the head difference, and the mud equivalent head. From the pile foundation parameters, pile cap pit parameters, and geological condition parameters of the target tower site project information set, the pile diameter, pile length, pile spacing, pit width, pit length, pit excavation depth, soft soil layer thickness, and soil strength and stiffness parameters are extracted to form the construction condition characteristics of the pit excavation stage. From the pile foundation parameters, foundation pit parameters, and surrounding load parameters of the target tower site project information set, the excavation depth of the foundation pit, the additional load of the building, the distance between the building and the foundation pit, the direction of the building's action relative to the foundation pit, the additional traffic load, the distance between the road and the foundation pit, and the direction of the traffic load are extracted to form the construction condition characteristics of the support stage.

4. The method for generating a multi-stage construction scheme for transmission tower pile foundations as described in claim 1, characterized in that, The steps of calling the pre-established construction response database to match the construction condition characteristics of each construction stage and determine the engineering response corresponding to different construction measures in each construction stage include: The pre-established construction response database is invoked; the construction response database stores multiple standard construction condition characteristics and reference engineering responses corresponding to different construction measures under each standard construction condition characteristic. The construction conditions of the current construction stage are matched with the standard construction conditions to determine the target standard conditions that match the construction conditions of each construction stage. The reference engineering response under the construction measures corresponding to the target standard working condition characteristics is read from the construction response database and used as the engineering response corresponding to the construction measures under the current construction stage.

5. The method for generating a multi-stage construction scheme for transmission tower pile foundations as described in claim 4, characterized in that, The step of matching the construction condition characteristics of the current construction stage with the standard construction condition characteristics to determine the target standard construction condition characteristics that match the construction condition characteristics of each construction stage includes: If the construction condition characteristics of the current construction stage are continuous construction condition parameters, then the standard construction condition characteristics whose absolute value of the difference with the construction condition characteristics of the current construction stage does not exceed the preset allowable deviation will be used as candidate standard construction condition characteristics. If the construction condition characteristics of the current construction stage are discrete construction condition parameters, then the standard construction condition characteristics with the same category will be used as candidate standard construction condition characteristics. When multiple candidate standard working condition features exist, the working condition distance between the current construction stage working condition feature and the candidate standard working condition feature is calculated, and the candidate standard working condition feature with the smallest working condition distance is taken as the target standard working condition feature.

6. The method for generating a multi-stage construction scheme for transmission tower pile foundations as described in claim 3, characterized in that: When the current tower location pile foundation layout is a single pile foundation, only the drilling construction measures for the drilling stage are determined. When the current tower location pile foundation layout is a pile group foundation, the drilling construction measures, the excavation construction measures, and the support measures are determined sequentially.

7. The method for generating a multi-stage construction scheme for transmission tower pile foundations as described in claim 6, characterized in that, When the current construction phase is the drilling and hole-forming phase and the current tower site pile foundation layout is a single pile foundation or a group pile foundation, the steps for judging the engineering response corresponding to different construction measures and determining the target tower site construction measures for each construction phase include: The engineering response corresponding to the benchmark drilling measure in the drilling stage of the construction response database is compared with the preset drilling response control limit. If the engineering response is within the preset drilling response control limit, the benchmark drilling measure is determined as the drilling construction measure.

8. The method for generating a multi-stage construction scheme for transmission tower pile foundations as described in claim 6, characterized in that, When the current construction phase is the foundation pit excavation phase and the current tower location pile foundation layout is a group pile foundation, the steps for judging the engineering response corresponding to different construction measures and determining the target tower location construction measures for each construction phase include: The target construction measures of the drilling stage are transferred to the foundation pit excavation stage, and the surrounding load status of the current tower site in the foundation pit excavation stage is determined according to the surrounding load parameters. The surrounding load conditions and the construction conditions of the foundation pit excavation stage are combined into the target foundation pit evaluation conditions, and the engineering responses corresponding to unsupported vertical excavation and slope excavation measures are matched in the construction response database according to the target foundation pit evaluation conditions. The engineering response corresponding to the unsupported vertical excavation measure is compared with the preset response control limits, and the first unsupported vertical excavation measure that meets all response control limits is determined as the foundation pit construction measure.

9. The method for generating a multi-stage construction scheme for transmission tower pile foundations as described in claim 1, characterized in that, When the current construction phase is the support phase and the current tower site pile foundation layout is a pile group foundation, the steps for judging the engineering response corresponding to different construction measures and determining the target tower site construction measures for each construction phase include: When neither the unsupported vertical excavation measure nor the slope excavation measure meets all response control limits, the engineering response corresponding to different support measures is read sequentially according to the preset support measure level, and compared with the preset response control limits. The support measure that meets all response control limits for the first time is determined as the foundation pit support measure.

10. A system for generating multi-stage construction schemes for transmission tower pile foundations, characterized in that, The system includes: The data acquisition module is used to acquire the target tower site engineering information set of the target transmission tower pile foundation, and to identify the current tower site pile foundation layout form based on the number of piles and the plane coordinates of the center of each pile in the target tower site engineering information set. The working condition matching module is used to extract the construction working condition characteristics of each construction stage in the construction of the transmission tower pile foundation from the target tower site engineering information set, and call the pre-established construction response database to perform working condition matching on the construction working condition characteristics of each construction stage to determine the engineering response corresponding to different construction measures in each construction stage; the construction stages include the drilling stage, the foundation pit excavation stage, and the support stage. The scheme generation module is used to identify the engineering response corresponding to different construction measures under the current pile foundation layout of the tower site, and to determine the target tower site construction measures for each construction stage. The scheme combination module is used to combine the construction measures of the target tower site in each construction stage according to the construction sequence to generate a multi-stage construction scheme for the target tower site.