Fire-fighting foam linkage supply control method based on liquid level dynamic feedback

By acquiring multiple feedback signals and using dynamic control methods, the problem of insufficient and unstable supply of fire-fighting foam liquid in the fire-fighting foam liquid supply system under changing fire-fighting conditions was solved, achieving a stable and efficient supply of fire-fighting foam liquid.

CN123127637APending Publication Date: 2026-11-20HUBEI ZHONGCHENG CENTURY ELECTRIC POWER TECHNOLOGY CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611300531.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-26
Publication Date
2026-11-20

AI Technical Summary

Technical Problem

Existing fire-fighting foam liquid supply systems are unable to adapt to changes in fire-fighting conditions, resulting in insufficient supply, unstable replenishment, or large fluctuations in liquid level in the target foam liquid tank. Existing control methods, which rely on fixed liquid level thresholds, are unable to meet actual consumption needs.

Method used

By acquiring multiple feedback signals, including liquid level, flow rate, valve position, and differential pressure, and combining them with the predicted supply duration and expected setup time, a dynamic control method is constructed. This method generates a tank entry permit and initiates replenishment after multiple signal verifications are met, dynamically adjusting the start and stop timing to ensure supply stability.

Benefits of technology

It achieves a stable supply of fire-fighting foam liquid during fire extinguishing, avoids supply interruption and repeated start-stop, improves the system's adaptability and response speed, and reduces the risk of liquid level overshoot and insufficient supply.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123127637A_ABST
    Figure CN123127637A_ABST
Patent Text Reader

Abstract

The application relates to the technical field of fire-fighting foam liquid linkage supply control, in particular to a fire-fighting foam liquid linkage supply control method based on liquid level dynamic feedback, which comprises the following steps: acquiring a first liquid level, a second liquid level, a first flow rate, a second flow rate, valve position feedback and supply branch inlet and outlet pressure; calculating a current volume, combining the first and second flow rates to determine a net consumption speed and a predicted available supply time length, determining a predicted establishment time according to the response time of an electric valve, the pressure building time of a supply pump and the branch liquid filling time, and forming a supply start criterion; when the valve position, the verification flow rate and the pressure difference continuously meet the preset verification time length, and the difference value between the conveying volume and the liquid level conversion incremental volume is not greater than the preset deviation, a tank filling permission is generated; after the permission is generated, the start boundary is corrected according to the first flow rate change rate, and the volume difference value is compared at a preset checking period; when the continuous deviation is greater than the preset deviation, the permission is cancelled and the valve is stopped; when the target tank volume reaches the dynamic stop volume, the valve is normally stopped.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of fire-fighting foam liquid linkage supply control technology, specifically a fire-fighting foam liquid linkage supply control method based on dynamic liquid level feedback. Background Technology

[0002] Firefighting foam extinguishing systems typically include components such as foam concentrate storage tanks, foam concentrate delivery pipelines, replenishment pumps, control valves, and controllers. To meet the foam concentrate consumption requirements during continuous firefighting, some systems are equipped with external foam concentrate sources or expanded foam concentrate tanks, with replenishment pumps supplying foam concentrate to the foam concentrate tanks within the system.

[0003] Existing automatic replenishment methods typically use the liquid level in the foam tank as the control basis. For example, the replenishment pump is activated when the liquid level is below a preset lower limit and stopped when the liquid level reaches a preset upper limit. Some systems also include flow rate, pressure, or valve status detection components to monitor the operating status of the liquid supply equipment.

[0004] However, the actual consumption of foam concentrate during firefighting varies with the firefighting conditions, and there may be a response delay between the start of the replenishment device and the arrival of the foam concentrate in the target foam concentrate tank. Relying solely on a fixed liquid level threshold for start-stop control is insufficient to adapt to changes in the foam concentrate consumption rate and the state of the supply process, which may lead to problems such as insufficient supply to the target foam concentrate tank, unstable replenishment, or large fluctuations in liquid level.

[0005] Therefore, a fire-fighting foam liquid linkage supply control method based on dynamic liquid level feedback is proposed. Summary of the Invention

[0006] The purpose of this invention is to provide a fire-fighting foam liquid linkage supply control method based on dynamic liquid level feedback. This method acquires a first liquid level, a second liquid level, a first flow rate, a second flow rate, valve position feedback, and inlet and outlet pressures of the supply branch. It calculates the current volume, determines the net consumption rate and predicted supply duration based on the first and second flow rates, and determines the expected establishment time based on the electric valve response time, the supply pump pressure building time, and the branch filling time, thus forming the supply start-up criterion. When the valve position, verification flow rate, and differential pressure continuously meet the preset verification duration, and the difference between the delivery volume and the incremental volume converted from the liquid level is not greater than a preset deviation, a tank entry permit is generated. After the permit is generated, the start-up boundary is corrected based on the first flow rate change rate, and the volume difference is compared according to a preset verification cycle. If the difference exceeds the limit continuously, the permit is revoked and the valve is shut down. The valve is shut down normally when the target tank volume reaches the dynamic stop volume.

[0007] To achieve the above objectives, the present invention provides the following technical solution: A fire-fighting foam liquid linkage supply control method based on dynamic liquid level feedback includes: Acquire the first liquid level of the target foam liquid tank, the second liquid level of the source foam liquid tank, the first output flow rate of the target foam liquid tank, the second output flow rate of the supply branch, valve position feedback, and the inlet and outlet pressures of the supply branch; The target foam liquid tank's current volume is determined based on the first liquid level, the source foam liquid tank's current volume is determined based on the second liquid level, and the predicted supply duration is determined based on the target foam liquid tank's current volume, the first flow rate, and the second flow rate; the estimated establishment time is determined based on the electric valve response time, the replenishment pump's pressure build-up time, and the replenishment branch's liquid filling time. When the predicted supply duration is not greater than the sum of the expected establishment time and the preset guarantee time, and the remaining available volume of the source foam liquid tank is not less than zero, the electric valve is opened and the replenishment pump is operated. When the electric valve reaches the target opening degree, the second flow rate reaches the preset verification flow rate, and the pressure difference between the inlet pressure and the outlet pressure is within the preset pressure difference range, a tank entry permit is generated. After generating the tank entry permit, maintain the supply and update the supply branch start boundary for the next supply cycle according to the first flow rate change rate of the adjacent sampling cycle; when the current volume of the target foam liquid tank reaches the dynamic stop volume, control the supply pump to stop and close the electric valve; After the tank entry permit is granted, the incremental volume is calculated by comparing the conveying volume with the liquid level according to the preset verification cycle. If the volume difference is greater than the preset volume deviation for a preset number of consecutive preset cycles, the tank entry permit is revoked.

[0008] Preferably, the predicted supply duration is determined based on the volume difference between the current volume of the target foam liquid tank and the preset supply lower limit volume, as well as the net consumption rate, wherein the net consumption rate is determined by the first flow rate and the second flow rate.

[0009] Preferably, the remaining available volume of the source foam liquid tank is determined based on the difference between the current volume of the source foam liquid tank and the preset reserve amount, the filling volume required for the replenishment branch to complete the pre-filling, and the expected consumption of the target foam liquid tank during the expected establishment time and the preset guarantee time.

[0010] Preferably, when the first flow rate change rate is greater than the preset growth rate, the target foam liquid consumption before the supply path reaches an effective supply state is predicted based on the first flow rate change rate, and the start-up boundary of the supply branch is corrected.

[0011] Preferably, for each supply process, the first time interval from the electric valve opening command to the valve position feedback reaching the target opening degree, the second time interval from the valve position feedback reaching the target opening degree to the differential pressure reaching the preset lower limit, and the third time interval from the differential pressure reaching the preset lower limit to the second flow reaching the preset verification flow are recorded, and the estimated setup time is updated according to the first time interval, the second time interval, and the third time interval.

[0012] Preferably, the longest actual setup time in the most recent preset number of effective supply processes is used as the expected setup time for the next supply cycle.

[0013] Preferably, the dynamic stop volume is determined based on the second flow rate, the stop response time of the replenishment pump, the closing response time of the electric valve, and the residual volume of the replenishment branch.

[0014] Preferably, after the conditions of the electric valve reaching the target opening degree, the second flow rate reaching the preset verification flow rate, and the pressure difference being within the preset pressure difference range are continuously met for a preset verification time, the conveying volume corresponding to the second flow rate within the preset verification time and the liquid level conversion incremental volume of the target foam liquid tank within the preset verification time are determined, and the tank entry permit is generated only when the difference between the two is not greater than the preset volume deviation.

[0015] Preferably, after generating the tank entry permit, the conveying volume and liquid level conversion incremental volume are repeatedly determined according to a preset verification cycle. When the volume difference for a preset number of consecutive times is greater than the preset volume deviation, the tank entry permit is revoked, and the replenishment pump is stopped and the electric valve is closed.

[0016] Compared with the prior art, the beneficial effects of the present invention are as follows: 1. This invention uses a two-way constraint of "predicted supply duration" and "estimated establishment time" and simultaneously introduces the calculation of "source tank available volume". The replenishment start no longer depends solely on the liquid level of the target tank, but comprehensively considers the current tank inventory, net consumption rate, actual pressure build-up delay of electric valve and replenishment pump, and the available volume of the source tank in this process. Thus, replenishment can be started in advance before possible liquid supply interruption, provided that there is sufficient reserve in the source tank, avoiding liquid supply interruption and repeated start-stop due to response lag or insufficient estimation of source tank capacity.

[0017] 2. In the tank entry permit determination stage, this invention takes three conditions as parallel prerequisites: valve position feedback reaching the set opening degree, the second flow rate reaching the verification flow rate, and the inlet and outlet pressure difference being within the set range. These conditions are required to be met continuously within a certain verification period. The delivery volume obtained by integrating the second flow rate during this period is then compared with the incremental volume calculated from the liquid level change and the first flow rate compensation. Only when the difference between the two is within the allowable range is a tank entry permit issued. Thus, through cross-verification of multiple signals such as valve position, pressure difference, flow rate, and liquid level, misjudgments caused by abnormal single sensor values ​​or short-term fluctuations are eliminated, making the tank entry permit closer to the actual effective replenishment state of the target tank.

[0018] 3. In the operational phase after permit generation, this invention combines "historical window update of actual establishment time", "start-up boundary correction based on the first flow rate change rate", "dynamic stop volume calculated according to the second flow rate and pump / valve response time and branch residual volume", and "consistency verification of periodic delivery volume and liquid level conversion incremental volume and continuous over-tolerance revocation of permit" to form a closed-loop control link from start-up criteria, replenishment establishment, stable maintenance to stop command: On the one hand, the historical establishment time and flow rate growth trend will directly affect the start point and lead time of the next cycle; on the other hand, the dynamic stop volume and periodic volume verification constrain the replenishment end time and permit maintenance state, so that the entire replenishment process can automatically adjust the start and stop timing according to the operating conditions, and promptly revoke the permit and shut down the valve when metering deviation or pipeline abnormality occurs, reducing the risk of liquid level overshoot, insufficient supply or mis-replenishment. Attached Figure Description

[0019] Figure 1 A flowchart illustrating a fire-fighting foam liquid linkage supply control method based on dynamic liquid level feedback, provided in an embodiment of the present invention; Figure 2 A schematic diagram illustrating the process for determining the actual setup time, provided as an embodiment of the present invention; Figure 3 This is a schematic diagram of a tank entry permit generation process provided by an embodiment of the present invention; Figure 4 This is a schematic diagram of a process for performing periodic volume consistency verification, continuous deviation counting, and license revocation after generating a tank entry permit, provided by an embodiment of the present invention. Figure 5 This is a schematic diagram illustrating the process of determining a dynamic stopping volume according to an embodiment of the present invention. Detailed Implementation

[0020] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0021] Example 1: Please see Figures 1 to 5 This invention provides a method for controlling the coordinated supply of fire-fighting foam liquid based on dynamic liquid level feedback. The technical solution is as follows: The target foam liquid tank in this embodiment is a vertical tank with a uniform cross-section and an effective cross-sectional area of ​​2.50m³. 2 The effective volume is 0 to 5.00 m³. 3The effective cross-sectional area of ​​the source foam liquid tank is 5.00m². 2 The first liquid level, second liquid level, first flow rate, second flow rate, valve position feedback, inlet pressure, and outlet pressure are all sampled with a 1-second sampling period and the same clock reference, with a maximum allowable time difference of 0.2 seconds. The first and second flow rates are collected in L / min and then converted to m. 3 / s is used for volume calculation, pressure is expressed in MPa, and valve position is expressed as a percentage of full opening.

[0022] Figure 1 A flowchart illustrating a fire-fighting foam liquid linkage supply control method based on dynamic liquid level feedback, provided in an embodiment of the present invention, includes: Acquire the first liquid level of the target foam liquid tank, the second liquid level of the source foam liquid tank, the first output flow rate of the target foam liquid tank, the second output flow rate of the supply branch, valve position feedback, and the inlet and outlet pressures of the supply branch; The target foam liquid tank's current volume is determined based on the first liquid level, the source foam liquid tank's current volume is determined based on the second liquid level, and the predicted supply duration is determined based on the target foam liquid tank's current volume, the first flow rate, and the second flow rate; the estimated establishment time is determined based on the electric valve response time, the replenishment pump's pressure build-up time, and the replenishment branch's liquid filling time. When the predicted supply duration is not greater than the sum of the expected establishment time and the preset guarantee time, and the remaining available volume of the source foam liquid tank is not less than zero, the electric valve is opened and the replenishment pump is operated. When the electric valve reaches the target opening degree, the second flow rate reaches the preset verification flow rate, and the pressure difference between the inlet pressure and the outlet pressure is within the preset pressure difference range, a tank entry permit is generated. After generating the tank entry permit, maintain the supply and update the supply branch start boundary for the next supply cycle according to the first flow rate change rate of the adjacent sampling cycle; when the current volume of the target foam liquid tank reaches the dynamic stop volume, control the supply pump to stop and close the electric valve; After the tank entry permit is granted, the incremental volume is calculated by comparing the conveying volume with the liquid level according to the preset verification cycle. If the volume difference is greater than the preset volume deviation for a preset number of consecutive preset cycles, the tank entry permit is revoked.

[0023] Specifically, refer to Figure 1 First, the system simultaneously collects data on the first liquid level, second liquid level, first flow rate, second flow rate, valve position feedback, inlet pressure, and outlet pressure. Initially, the first liquid level is 0.348 m, the second liquid level is 2.400 m, the first flow rate is 60 L / min, and the second flow rate is 0. Based on this, the current volume of the target tank is calculated to be 0.870 m³. 3 The current volume of the Heyuan tank is 12,000 m³. 3 The target tank can supply a minimum volume of 0.800 m³. 3The predicted supply duration is 70 seconds; the electric valve response time (3.2 seconds), the replenishment pump pressure build-up time (5.0 seconds), and the branch filling time (4.8 seconds) constitute a total estimated setup time of 13.0 seconds. Adding a 60-second preset backup time brings the total to 73 seconds. After deducting the source tank's remaining capacity, filling volume, and estimated consumption, there is still 9.897 m³ of liquid remaining. 3 The available volume triggers commands to open the electric valve and operate the feed pump.

[0024] Continue to refer to Figure 1 When the valve position reaches 85%, the second flow rate reaches 130 L / min, and the pressure difference between the inlet pressure of 0.42 MPa and the outlet pressure of 0.31 MPa is 0.11 MPa, the pre-entry permit verification shall be performed. Figure 2 Track three consecutive time intervals and obtain the actual setup time; Figure 3 Track 5-second continuous verification and volume consistency judgment; Figure 4 Track the 10-second cycle verification and continuous out-of-tolerance handling after permission is granted; Figure 5 The expected inflow and dynamic stop volume are tracked during the pump valve response. The five figures above sequentially cover the complete process of startup, establishment, authorization, maintenance replenishment, abnormal cancellation, and shutdown.

[0025] Furthermore, the predicted supply duration is determined based on the volume difference between the current volume of the target foam liquid tank and the preset supply lower limit volume, as well as the net consumption rate, which is determined by the first flow rate and the second flow rate.

[0026] Specifically, refer to Figure 1 The current volume conversion and prediction steps in the process indicate that the initial flow rate of 60L / min before startup equals 0.001m³. 3 / s, the second flow rate is 0, therefore the net consumption rate is 0.001m. 3 / s. Target tank current volume 0.870m³. 3 Subtract the minimum available volume of 0.800m³ 3 The remaining usable volume is 0.070 m³. 3 ; using 0.070m 3 Divide by 0.001m 3 / s, yielding a predicted supply duration of 70s. After generating the tank entry permit, the second flow rate uses the actual permitted flow rate entering the target tank, and the net consumption rate is recalculated for each sampling period; when the net consumption rate is not greater than 0, the predicted supply duration is recorded as positive infinity, and a new start is not triggered in this period due to the supply duration.

[0027] ; In the formula, For the first The first flow rate of each sampling period For the first The actual second flow rate entering the target tank in each sampling period, both of which are converted to m 3 / s; This represents the net consumption rate.

[0028] ; In the formula, The unit for predicting available supply duration is seconds (s). Given the current volume of the target tank, The preset minimum supply volume is shown in m². 3 .

[0029] Furthermore, the remaining available volume of the source foam liquid tank is determined based on the difference between the current volume of the source foam liquid tank and the preset reserve amount, the filling volume required for the replenishment branch to complete the pre-filling, and the expected consumption of the target foam liquid tank during the expected establishment time and the preset guarantee time.

[0030] Specifically, refer to Figure 1 The steps for calculating the available volume of the source tank are as follows: the second liquid level of the source tank is 2.400m, calculated as 5.00m. 2 The effective cross-sectional area is converted to 12.000m². 3 First deduct the 2,000m that are not included in this supply replenishment. 3 The preset reserve amount is then reduced by 0.030m, which is required to fully refill the supply branch in an empty state. 3 Filling volume. Estimated setup time 13.0s and backup time 60s, totaling 73s. Initial flow rate 0.001m³. 3 / s corresponds to an estimated consumption of 0.073m. 3 The final value was 9.897m. 3 Available volume. If the calculation result is less than 0, sampling is maintained and no start command is issued.

[0031] ; In the formula, The available volume of the source tank; This represents the current volume of the source tank. This is the preset retention amount; l represents the liquid-filled volume of the branch; For estimated establishment time; This is a preset guarantee time.

[0032] Furthermore, when the first flow rate change rate is greater than the preset growth rate, the target foam liquid consumption before the supply path reaches an effective supply state is predicted based on the first flow rate change rate, and the start-up boundary of the supply branch is corrected.

[0033] Specifically, refer to Figure 1In the final startup boundary update step, the sampling period for the first flow is 1 second. The corresponding first flow change rate is determined based on the difference in first flow between adjacent sampling periods. The average first flow change rate within this 5-second time window is then calculated to obtain the current average first flow change rate. The basic startup boundary of the supply branch is determined based on the sum of the preset supplyable lower limit volume and the expected consumption volume corresponding to the current net consumption rate within the expected setup time and preset guarantee time. That is: Basic startup boundary = Preset supplyable lower limit volume + Net consumption rate × (Expected setup time + Preset guarantee time). In this embodiment, the basic startup boundary = 0.800 + 0.001 × (13.0 + 60) = 0.873m 3 .

[0034] In this embodiment, the first flow rate increases from 60 L / min to 90 L / min within a 5-second time window. The average rate of change of the first flow rate within this 5-second time window is (90-60) ÷ 5 = 6 L / (min·s), which is greater than the preset growth rate of 1 L / (min·s). The converted rate of change is 0.0001 m. 3 / s 2 The calculation of the additional consumption is based on the premise that the first flow rate increases approximately linearly at the currently determined rate of change within the expected setup time. The additional consumption is equal to half the product of the rate of change of the first flow rate and the square of the expected setup time. Therefore, based on an expected setup time of 13.0 s, the additional consumption is 0.00845 m³. 3 Each time a new first rate of change in flow is obtained, the additional consumption is recalculated, and the current rate of change is continuously extrapolated without spanning multiple rate of change update cycles.

[0035] At the basic start-up boundary of 0.873m 3 Additional consumption of 0.00845m³ 3 The corrected start boundary was obtained as 0.88145m. 3 The revised start-up boundary is used for the next replenishment cycle. When the current volume of the target foam liquid tank is less than or equal to the revised start-up boundary, and the remaining available volume of the source foam liquid tank is not less than zero, the electric valve is opened and the replenishment pump is operated. When the rate of change is not greater than the preset growth rate, the additional consumption is zero, and the basic start-up boundary is adopted. The basic start-up boundary is the volume expression of the predicted supply duration start-up criterion at the current net consumption rate. The revised start-up boundary is used to compensate for the additional consumption caused by the continued increase of the first flow rate. The additional consumption is: ; In the formula, The first flow rate is the rate of change, in meters. 3 / s 2 ; The additional consumption resulting from the continued increase in the initial flow rate before reaching an effective supply state, expressed in m³. 3 .

[0036] ; In the formula, The revised supply branch starts at the boundary; during the first flow increase. Since the value is greater than 0, the starting boundary only increases and does not decrease.

[0037] Furthermore, for each supply process, the first time interval from the electric valve opening command to the valve position feedback reaching the target opening degree, the second time interval from the valve position feedback reaching the target opening degree to the differential pressure reaching the preset differential pressure lower limit, and the third time interval from the differential pressure reaching the preset differential pressure lower limit to the second flow reaching the preset verification flow, are recorded, and the estimated setup time is updated according to the first time interval, the second time interval, and the third time interval.

[0038] Specifically, such as Figure 2 As shown, the start time is recorded when the commands to open the electric valve and start the replenishment pump are issued. The first time interval is 3.1 seconds after the valve position feedback first reaches 85%; the second time interval is 4.6 seconds after the valve position reaches 85% until the differential pressure first reaches the lower limit of 0.08 MPa; the third time interval is 4.2 seconds after the differential pressure reaches the lower limit until the second flow rate first reaches 120 L / min. The sum of these three consecutive time intervals gives the actual setup time of 11.9 seconds. Only the process of finally generating the tank inlet permit without any volume deviation cancellation is written into the valid historical record.

[0039] ; In the formula, For the first The actual time it takes to establish an effective supply process; In order Figure 2 The first, second, and third time intervals are shown.

[0040] Furthermore, the longest actual setup time in the most recent preset number of effective supply processes is used as the expected setup time for the next supply cycle.

[0041] Specifically, continue to refer to Figure 2 The five most recent effective supply processes are used as a fixed-length historical window. The actual establishment times of the five most recent processes are 12.2s, 13.0s, 12.6s, 13.4s, and 11.9s, respectively. The maximum value of 13.4s is taken as the estimated establishment time for the next supply cycle. After a new effective process is completed, the earliest record is deleted and the latest record is added, and the maximum value is taken again. If there are fewer than five historical records, the larger value between the maximum value of the existing effective records and the initial estimated establishment time of 13.0s is taken.

[0042] ; The fixed-length maximum value update does not perform unbounded iterations, and the history window always retains only the five most recent valid records.

[0043] Furthermore, the dynamic stop volume is determined based on the second flow rate, the stop response time of the replenishment pump, the closing response time of the electric valve, and the residual volume of the replenishment branch.

[0044] Specifically, such as Figure 5 As shown, the average flow rate of the second flow after the supply stabilized over the last 5 seconds was 140 L / min, or 2.333 L / s. To estimate the maximum volume that might continue to flow into the target foam tank after the stop command is issued, this embodiment conservatively calculates the supply pump shutdown response time and the electric valve closing response time by adding them together. The supply pump shutdown response time of 2.0 s and the electric valve closing response time of 3.0 s total 5.0 s, during which an estimated 11.667 L will continue to flow in. The remaining volume in the supply branch is 30 L, and the total volume that might continue to enter the target tank after the stop command is issued is 41.667 L, or 0.041667 m³. 3 From 4,500m 3 Preset upper limit volume minus 0.041667m³ 3 The dynamic stopping volume is 4.458333 m³. 3 When the target tank's current volume first reaches or exceeds this value, a shutdown and valve closure command is issued within the same sampling period.

[0045] ; In the formula, To dynamically stop the volume; The preset maximum volume; The second highest average flow rate in the last 5 seconds; and These are the shutdown and valve closing response times, respectively. To replenish the residual volume of the branch.

[0046] Furthermore, when the conditions of the electric valve reaching the target opening degree, the second flow rate reaching the preset verification flow rate, and the pressure difference being within the preset pressure difference range are continuously met for a preset verification time, the conveying volume corresponding to the second flow rate within the preset verification time and the liquid level conversion incremental volume of the target foam liquid tank within the preset verification time are determined, and the tank entry permit is generated only when the difference between the two is not greater than the preset volume deviation.

[0047] Specifically, such as Figure 3As shown, continuous timing begins when the valve position reaches 85%, the second flow rate is not less than 120 L / min, and the pressure difference is between 0.08 and 0.16 MPa. If any condition fails within 5 seconds, the timing is immediately reset to zero. After maintaining these three conditions continuously for 5 seconds, the second flow rate is integrated over five 1-second sampling intervals. When the average second flow rate is 130 L / min, the delivery volume is 10.833 L. The original net increment corresponding to the target tank level during the same period is 5.833 L. The target tank continues to output at 60 L / min, with an output volume of 5.000 L over 5 seconds. After adding this back, the level-converted increment volume is 10.833 L. If the difference between the two volumes is 0 L or less than 5 L, a tank entry permit is generated; if the difference is greater than 5 L, no permit is generated, and a shutdown and valve closing command is issued.

[0048] ; In the formula, To verify the delivery volume corresponding to the second flow rate within the window, Use m 3 / s, Use s.

[0049] ; In the formula, The incremental volume is calculated based on the liquid level after compensation by the first flow rate output during the same period; and To verify the start and end sampling points of the window.

[0050] ; In the formula, This represents the volume difference; in this embodiment, the preset volume deviation is 5L.

[0051] Furthermore, after generating the tank entry permit, the conveying volume and liquid level conversion increment volume are repeatedly determined according to a preset verification cycle. When the volume difference for a preset number of consecutive times is greater than the preset volume deviation, the tank entry permit is revoked, and the replenishment pump is stopped and the electric valve is closed.

[0052] Specifically, such as Figure 4 As shown, after generating the tank entry permit, a verification window is set at 10 seconds. The delivery volume is obtained by integrating the second flow rate, and the incremental volume is calculated by adding the volume difference between the start and end liquid levels of the window to the integral value of the first flow rate during the same period. The differences between the three consecutive windows during normal operation are 0.6L, 0.9L, and 0.8L, respectively, and the consecutive out-of-tolerance count remains at 0. When the difference in a window exceeds 5L, the count is incremented once; when the next window returns to within 5L, the count is immediately reset to zero. During fault verification, the differences between the three consecutive windows are 6.4L, 7.0L, and 6.6L, respectively. When the count reaches three at the end of the third window, the tank entry permit is immediately revoked, and commands to stop the replenishment pump and close the electric valve are issued in the same sampling cycle.

[0053] Anomaly and boundary handling: When the available volume of the source tank is less than 0, no start command is issued and sampling is maintained; if the target opening degree, verification flow rate and differential pressure range are not reached simultaneously within 30 seconds after the start command is issued, the supply pump is stopped and the electric valve is closed. This process is not included in the valid history.

[0054] If the time difference of the required data exceeds 0.2s, the start or permission judgment for this cycle will not be executed; if any required data is missing for more than 2s consecutively, the generation or maintenance of tank entry permission will be prohibited, and if the tank is already in a replenishment state, the shutdown and valve closure will be executed immediately.

[0055] The sampling sources, conversion relationships, variable units, judgment thresholds, historical windows, conditions for clearing consecutive out-of-tolerance counts, and dynamic stopping lead amounts have all been clearly defined, and those skilled in the art can use them accordingly. Figures 1 to 5 The startup, licensing, replenishment, verification and shutdown results of this embodiment are recalculated periodically by equations (1) to (11).

[0056] Example 2: A fire-fighting foam liquid linkage supply control method based on dynamic liquid level feedback includes: Acquire the first liquid level of the target foam liquid tank, the second liquid level of the source foam liquid tank, the first output flow rate of the target foam liquid tank, the second output flow rate of the supply branch, valve position feedback, and the inlet and outlet pressures of the supply branch; The target foam liquid tank's current volume is determined based on the first liquid level, the source foam liquid tank's current volume is determined based on the second liquid level, and the predicted supply duration is determined based on the target foam liquid tank's current volume, the first flow rate, and the second flow rate; the estimated establishment time is determined based on the electric valve response time, the replenishment pump's pressure build-up time, and the replenishment branch's liquid filling time. When the predicted supply duration is not greater than the sum of the expected establishment time and the preset guarantee time, and the remaining available volume of the source foam liquid tank is not less than zero, the electric valve is opened and the replenishment pump is operated. When the electric valve reaches the target opening degree, the second flow rate reaches the preset verification flow rate, and the pressure difference between the inlet pressure and the outlet pressure is within the preset pressure difference range, a tank entry permit is generated. After generating the tank entry permit, maintain the supply and update the supply branch start boundary for the next supply cycle according to the first flow rate change rate of the adjacent sampling cycle; when the current volume of the target foam liquid tank reaches the dynamic stop volume, control the supply pump to stop and close the electric valve; After the tank entry permit is granted, the incremental volume is calculated by comparing the conveying volume with the liquid level according to the preset verification cycle. If the volume difference is greater than the preset volume deviation for a preset number of consecutive preset cycles, the tank entry permit is revoked.

[0057] Furthermore, the predicted supply duration is determined based on the volume difference between the current volume of the target foam liquid tank and the preset supply lower limit volume, as well as the net consumption rate, which is determined by the first flow rate and the second flow rate.

[0058] Furthermore, the remaining available volume of the source foam liquid tank is determined based on the difference between the current volume of the source foam liquid tank and the preset reserve amount, the filling volume required for the replenishment branch to complete the pre-filling, and the expected consumption of the target foam liquid tank during the expected establishment time and the preset guarantee time.

[0059] Furthermore, when the first flow rate change rate is greater than the preset growth rate, the target foam liquid consumption before the supply path reaches an effective supply state is predicted based on the first flow rate change rate, and the start-up boundary of the supply branch is corrected.

[0060] Furthermore, for each supply process, the first time interval from the electric valve opening command to the valve position feedback reaching the target opening degree, the second time interval from the valve position feedback reaching the target opening degree to the differential pressure reaching the preset differential pressure lower limit, and the third time interval from the differential pressure reaching the preset differential pressure lower limit to the second flow reaching the preset verification flow, are recorded, and the estimated setup time is updated according to the first time interval, the second time interval, and the third time interval.

[0061] Furthermore, the longest actual setup time in the most recent preset number of effective supply processes is used as the expected setup time for the next supply cycle.

[0062] Furthermore, the dynamic stop volume is determined based on the second flow rate, the stop response time of the replenishment pump, the closing response time of the electric valve, and the residual volume of the replenishment branch.

[0063] Furthermore, when the conditions of the electric valve reaching the target opening degree, the second flow rate reaching the preset verification flow rate, and the pressure difference being within the preset pressure difference range are continuously met for a preset verification time, the conveying volume corresponding to the second flow rate within the preset verification time and the liquid level conversion incremental volume of the target foam liquid tank within the preset verification time are determined, and the tank entry permit is generated only when the difference between the two is not greater than the preset volume deviation.

[0064] Furthermore, after generating the tank entry permit, the conveying volume and liquid level conversion increment volume are repeatedly determined according to a preset verification cycle. When the volume difference for a preset number of consecutive times is greater than the preset volume deviation, the tank entry permit is revoked, and the replenishment pump is stopped and the electric valve is closed.

[0065] Although embodiments of the invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of the invention, the scope of which is defined by the appended claims and their equivalents.

Claims

1. A method for controlling the coordinated supply of fire-fighting foam liquid based on dynamic liquid level feedback, characterized in that, include: Acquire the first liquid level of the target foam liquid tank, the second liquid level of the source foam liquid tank, the first output flow rate of the target foam liquid tank, the second output flow rate of the supply branch, valve position feedback, and the inlet and outlet pressures of the supply branch; The target foam liquid tank's current volume is determined based on the first liquid level, the source foam liquid tank's current volume is determined based on the second liquid level, and the predicted supply duration is determined based on the target foam liquid tank's current volume, the first flow rate, and the second flow rate; the estimated establishment time is determined based on the electric valve response time, the replenishment pump's pressure build-up time, and the replenishment branch's liquid filling time. When the predicted supply duration is not greater than the sum of the expected establishment time and the preset guarantee time, and the remaining available volume of the source foam liquid tank is not less than zero, the electric valve is opened and the replenishment pump is operated. When the electric valve reaches the target opening degree, the second flow rate reaches the preset verification flow rate, and the pressure difference between the inlet pressure and the outlet pressure is within the preset pressure difference range, a tank entry permit is generated. After generating the tank entry permit, maintain the supply and update the supply branch start boundary for the next supply cycle according to the first flow rate change rate of the adjacent sampling cycle; when the current volume of the target foam liquid tank reaches the dynamic stop volume, control the supply pump to stop and close the electric valve; After the tank entry permit is granted, the incremental volume is calculated by comparing the conveying volume with the liquid level according to the preset verification cycle. If the volume difference is greater than the preset volume deviation for a preset number of consecutive preset cycles, the tank entry permit is revoked.

2. The fire-fighting foam liquid linkage supply control method based on dynamic liquid level feedback according to claim 1, characterized in that: The predicted supply duration is determined based on the volume difference between the current volume of the target foam liquid tank and the preset supply lower limit volume, as well as the net consumption rate, which is determined by the first flow rate and the second flow rate.

3. The fire-fighting foam liquid linkage supply control method based on dynamic liquid level feedback according to claim 1, characterized in that, The remaining available volume of the source foam liquid tank is determined based on the difference between the current volume of the source foam liquid tank and the preset reserve amount, the filling volume required for the replenishment branch to complete the pre-filling, and the expected consumption of the target foam liquid tank during the expected establishment time and the preset guarantee time.

4. The fire-fighting foam liquid linkage supply control method based on dynamic liquid level feedback according to claim 1, characterized in that: When the first flow rate change rate is greater than the preset growth rate, the target foam liquid consumption before the supply path reaches an effective supply state is predicted based on the first flow rate change rate, and the start-up boundary of the supply branch is corrected.

5. The fire-fighting foam liquid linkage supply control method based on dynamic liquid level feedback according to claim 1, characterized in that: For each supply process, the first time interval from the electric valve opening command to the valve position feedback reaching the target opening degree, the second time interval from the valve position feedback reaching the target opening degree to the differential pressure reaching the preset lower limit, and the third time interval from the differential pressure reaching the preset lower limit to the second flow reaching the preset verification flow are recorded, and the estimated setup time is updated based on the first time interval, the second time interval, and the third time interval.

6. The fire-fighting foam liquid linkage supply control method based on dynamic liquid level feedback according to claim 5, characterized in that: The longest actual setup time in the most recent preset number of effective supply processes is used as the estimated setup time for the next supply cycle.

7. The fire-fighting foam liquid linkage supply control method based on dynamic liquid level feedback according to claim 1, characterized in that: The dynamic stop volume is determined based on the second flow rate, the stop response time of the replenishment pump, the closing response time of the electric valve, and the residual volume of the replenishment branch.

8. The fire-fighting foam liquid linkage supply control method based on dynamic liquid level feedback according to claim 1, characterized in that: When the conditions of the electric valve reaching the target opening degree, the second flow rate reaching the preset verification flow rate, and the pressure difference being within the preset pressure difference range are continuously met for the preset verification time, the conveying volume corresponding to the second flow rate within the preset verification time and the liquid level conversion increment volume of the target foam liquid tank within the preset verification time are determined, and the tank entry permit is generated only when the difference between the two is not greater than the preset volume deviation.

9. The fire-fighting foam liquid linkage supply control method based on dynamic liquid level feedback according to claim 8, characterized in that: After generating the tank entry permit, the conveying volume and liquid level conversion increment volume are repeatedly determined according to a preset verification cycle. When the volume difference for a preset number of consecutive times is greater than the preset volume deviation, the tank entry permit is revoked, and the replenishment pump is stopped and the electric valve is closed.