A centralized electric vehicle charging and battery swapping station intelligent operation system
By integrating a three-dimensional temperature field digital twin module, a demand forecasting module, and an impedance risk assessment module, combined with a software-defined physical power matrix and a robotic arm, the problems of battery thermal imbalance, efficiency loss, and safety hazards in centralized charging and battery swapping stations have been solved. This has enabled efficient and safe physical repositioning of batteries and battery status detection, thereby improving the overall operational efficiency and safety of charging and battery swapping stations.
Patent Information
- Application Number
- CN202611354755.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-03
- Publication Date
- 2026-11-20
AI Technical Summary
The existing centralized charging and battery swapping station operation system fails to deeply couple the physical heat dissipation structure, charging power channel topology, and mechanical transport trajectory, resulting in a mismatch between the heat generation of heterogeneous batteries and the heat dissipation capacity of the storage compartments. This leads to local thermal imbalance, efficiency loss due to batteries sharing fixed charging channels on multiple voltage platforms, and safety hazards due to a mismatch between the battery status detection cycle and the physical cycle of battery swapping.
By employing a three-dimensional temperature field digital twin module, a demand forecasting module, and an impedance risk assessment module, combined with temperature, current, and voltage sensors, and through a software-defined physical power matrix (SDPM) and a battery swapping robotic arm, the system integrates battery heat generation calculation, warehouse scheduling priority scoring, dynamic reconfiguration of charging module and warehouse connection, impedance spectrum detection, and mechanical transfer. This enables efficient physical relocation of batteries, topology reconstruction of the switch matrix, and high-risk interception of batteries with latent faults.
It achieves local thermal equilibrium without increasing the energy consumption of cooling equipment, reduces the probability of thermal runaway, improves the utilization efficiency of charging resources, ensures safe battery sharing and scheduling, avoids the placement of batteries with hidden faults on the rack, and improves the overall operational efficiency and safety of battery swapping stations.
Smart Images

Figure CN123129763A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of electric vehicle charging and battery swapping services, specifically to an intelligent operation system for a centralized electric vehicle charging and battery swapping station. Background Technology
[0002] With the rapid growth of electric vehicle ownership, centralized charging and battery swapping stations, due to their large-scale energy storage attributes, are gradually becoming important nodes for participating in grid-vehicle-grid interaction and virtual power plant scheduling. These battery swapping stations are typically equipped with dozens to hundreds of battery compartments, with automated robotic arms completing the grabbing, transfer, and racking of batteries. Ventilation or cooling systems within the station maintain the ambient temperature, and different compartments have different heat dissipation capabilities due to their different locations in the airflow channels.
[0003] Currently, publicly available or commercially available charging and battery swapping station operating systems consist of an upper layer of queuing billing and demand response scheduling algorithms that calculate the target power of each charging module based on grid dispatch instructions; a middle layer of energy management system that allocates power proportionally within fixed physical charging channels; and a bottom layer of fixed topology for the correspondence between charging modules and battery compartments, as well as robotic arms operating according to preset standard procedures. These systems do not accept dynamic intervention from the operating system based on real-time battery status. Battery status detection mainly relies on asynchronous cloud-based diagnostics using conventional parameters uploaded by the battery management system, and the detection cycle is typically longer than the physical cycle time required for a single battery swap at the station.
[0004] The above scheme has at least the following shortcomings: First, power scheduling only considers electrical parameters and does not take into account the differences in heat dissipation capacity of each compartment. Heterogeneous batteries are randomly assigned to any compartment, which can easily lead to local thermal imbalance within the station. Second, the charging module and the battery compartment are fixedly connected. When batteries from multiple voltage platforms share a fixed physical channel, there will be power cut-off, switching losses, and charging efficiency losses. Third, the battery status detection process and the mechanical transfer action are independent of each other. Batteries with hidden faults may be received into the warehouse through the normal battery swapping process before the detection alarm is triggered, which poses a safety hazard. Summary of the Invention
[0005] The technical problem this invention aims to solve is that existing centralized charging and battery swapping station operation systems only focus on billing and scheduling at the software level, failing to deeply couple with the station's physical heat dissipation structure, charging power channel topology, and mechanical transport trajectory. This results in problems such as a mismatch between the heat generation of heterogeneous batteries and the heat dissipation capacity of the battery compartments, leading to local thermal imbalance; multiple voltage platform batteries sharing fixed charging channels, resulting in efficiency loss; and a mismatch between the battery status detection cycle and the physical cycle of battery swapping, leading to the placement of batteries with hidden faults.
[0006] To address the aforementioned technical problems, this invention provides an intelligent operation system for centralized electric vehicle charging and battery swapping stations. This system comprises a decision-making layer, a station control and coordination layer, and a bottom-level physical execution layer. The decision-making layer is equipped with a three-dimensional temperature field digital twin module, a demand forecasting module, and an impedance risk assessment module. The station control and coordination layer converts the decision-making results of the decision-making layer into bay scheduling instructions, power matrix topology configuration instructions, and robotic arm trajectory instructions. The bottom-level physical execution layer includes temperature sensors, current sensors, and voltage sensors distributed across each battery bay in the battery swapping station; a software-defined physical power matrix (SDPM) composed of a solid-state switch array positioned between the charging module array and the battery bay array; an impedance spectrum excitation and acquisition module integrated into the running track of the battery swapping robotic arm; and a battery swapping robotic arm that receives instructions from the station control and coordination layer and executes actions.
[0007] Firstly, the three-dimensional temperature field digital twin module calculates the heat generation of the corresponding battery in each battery compartment based on data collected by temperature, current, and voltage sensors. The calculation method for heat generation is as follows:
[0008] ;
[0009] in, For the first The heat generated by the battery during the sampling period. For the first The effective value of the charging and discharging current of the battery. For the first The equivalent internal resistance of a battery cell. This is the duration of the sampling period.
[0010] Substituting the heat generation into the thermodynamic model yields the predicted temperature for each storage location in the future:
[0011] ;
[0012] in, For the first The compartment where the battery is located is Predicted temperature at any time This is the measured temperature of the warehouse at the current moment. For the first The convective heat transfer coefficient of the storage compartment. This provides an effective heat dissipation area for the battery and the storage environment. The ambient temperature inside the battery swapping station. For battery quality, This refers to the specific heat capacity of the battery.
[0013] Based on this, the priority score for warehouse scheduling is calculated by comprehensively considering heat production rate, health decay rate, and physical transport distance.
[0014] ;
[0015] in, For the first Battery cell storage allocation priority scoring. This serves as the baseline value for heat production used in normalization. For the first The rate of health degradation of a block battery. The preset health decay reference threshold, This refers to the physical transport distance between the current battery storage location and the candidate target storage location. The reference value for the transfer distance used for normalization, , , These are the heat production weight coefficient, the health weight coefficient, and the transportation cost weight coefficient, respectively, and the sum of the three is 1.
[0016] The station control coordination layer uses the scoring to drive the battery swapping robotic arm to physically transfer the battery between the first and second compartments, which are divided according to heat dissipation capacity. The heat dissipation capacity of the first compartment is higher than that of the second compartment.
[0017] Secondly, the demand forecasting module outputs a predicted charging power demand vector for the next scheduling cycle based on historical battery swapping demand data, time-related weather characteristics, and grid dispatching event characteristics:
[0018] ;
[0019] in, To predict the charging power demand vector, For the mapping function of the pre-trained time series prediction model, This is a historical battery swapping demand data sequence. For time, weather and external characteristics, Based on the characteristics of power grid dispatch events, the station control coordination layer solves for the closed state of each switching unit in SDPM with the optimization objective of reducing the total switching and conversion losses:
[0020] ;
[0021] in, Let be the switch state matrix to be solved, and have elements , This represents the total number of physical storage units within the station. The total number of charging modules, For the first The charging module is connected to the first The loss coefficient generated by each warehouse is determined under the following constraints:
[0022] ;
[0023] ;
[0024] in, For the first The rated output power of each charging module, For the first Forecast power demand for each warehouse For the first The maximum number of compartments that can be connected in parallel by a single charging module.
[0025] Third, the impedance spectrum excitation and acquisition module injects a broadband AC excitation current and acquires the response within the physical cycle of the battery swapping robotic arm transporting the battery, thus obtaining the electrochemical impedance spectrum:
[0026] ;
[0027] in, Angular frequency The complex impedance of the battery. For voltage response phasors, For the excitation current phasor, The impedance amplitude, The impedance phase angle is used to obtain the normalized impedance deviation index by comparing the measured impedance spectrum with the impedance spectrum of a health reference.
[0028] ;
[0029] in, The normalized impedance deviation index. The total number of frequency sampling points participating in the comparison. The measured complex impedance at the k-th frequency point is... For the corresponding health reference complex impedance, when When the preset risk threshold is exceeded, the impedance risk determination module sends a trajectory rewrite instruction to the programmable logic controller corresponding to the battery swapping robot arm, so that the robot arm can transfer the battery to the explosion-proof isolation compartment outside the station along the isolated track branch. When the threshold is not exceeded, the robot arm enters the rack according to the original trajectory, and the detection data is fed back to the three-dimensional temperature field digital twin module.
[0030] Compared with the prior art, the beneficial effects of the present invention by adopting the above technical solution are as follows:
[0031] Firstly, by quantitatively matching the battery heat generation rate with the heat dissipation capacity of the storage area and directly driving the robotic arm to complete the dynamic rearrangement of physical positions, local thermal equilibrium within the station can be achieved without increasing the energy consumption of the refrigeration equipment, thereby reducing the probability of thermal runaway.
[0032] Secondly, by dynamically reconstructing the topology of the switching matrix based on prediction, the fixed connection boundary between the charging module and the compartment is broken, reducing switching and conversion losses and improving the utilization efficiency of charging resources.
[0033] Third, by physically integrating impedance spectrum detection with mechanical transfer actions, high-risk interception and physical isolation of batteries with latent faults can be achieved without interrupting the physical cycle of battery swapping, thereby enabling efficient sharing and scheduling of heterogeneous batteries while ensuring safety. Attached Figure Description
[0034] Figure 1 This is a schematic diagram of the overall system architecture of the present invention;
[0035] Figure 2 This is a flowchart of the thermo-electric-mechanical coordinated physical scheduling process of the present invention;
[0036] Figure 3 This is a flowchart of the integrated detection-isolation physical blocking process of the present invention. Detailed Implementation
[0037] The following is in conjunction with the appendix Figure 1-3 The specific embodiments of the present invention will be further described below. It should be noted that the description of these embodiments is for the purpose of helping to understand the present invention, but does not constitute a limitation of the present invention.
[0038] Furthermore, the technical features involved in the various embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other.
[0039] In this embodiment, the intelligent operation system of the centralized electric vehicle charging and swapping station is structurally divided into three levels: decision-making layer, station control coordination layer, and bottom physical execution layer. The decision-making layer can be deployed on edge computing nodes or cloud servers, and integrates a three-dimensional temperature field digital twin module, a demand prediction module, and an impedance risk assessment module. The three interact with each other through a data bus. The station control coordination layer is set in the control cabinet inside the station, including a bay scheduling instruction generation unit, an SDPM topology configuration unit, and a robotic arm trajectory rewriting unit. It receives the outputs of the three modules of the decision-making layer and sends control instructions to the bottom layer. The bottom physical execution layer includes temperature sensors, current sensors, and voltage sensors distributed in each battery bay, SDPM power matrix hardware composed of a solid-state switch array, an impedance spectrum excitation and acquisition module integrated in the battery swapping base and robotic arm guide rail, a battery swapping robotic arm that receives instructions from a programmable logic controller (hereinafter referred to as PLC) to execute actions, and an explosion-proof isolation bay independently set on the outside of the station.
[0040] Regarding the first part of the implementation method, namely the thermo-electric-mechanical coordinated physical scheduling process, firstly, by using current sensors, voltage sensors, and temperature sensors deployed in each battery compartment, the charging and discharging current of each battery, the equivalent internal resistance obtained from online identification within the station or uploaded by the battery management system, and the current measured temperature of the compartment are collected in real time. Simultaneously, the internal air duct structure parameters of the battery swapping station, the convective heat transfer coefficient of each compartment, and the ambient temperature within the station are also collected. Secondly, based on the collected current and internal resistance data, according to... The heat generation of each battery within one sampling period is calculated. Then, the heat generation is substituted into the digital twin thermodynamic model, according to... The predicted temperature of each storage location at the end of a future period is projected, and a three-dimensional temperature field distribution within the station is generated using edge computing nodes. Then, considering factors such as battery heat generation rate, health degradation rate, and physical transport distance, the temperature is calculated according to... Calculate the storage priority score for each battery pack. A higher score indicates that it should be prioritized for transfer to a storage area with higher heat dissipation capacity. For example, if a battery pack has a normalized heat generation rate of 0.8, a normalized health degradation rate of 0.6, and a normalized transfer distance of 0.3, then the weighting coefficients are used. It is 0.5. It is 0.3. If the score is 0.2, then the scheduling priority score of this battery is calculated as 0.5 multiplied by 0.8 plus 0.3 multiplied by 0.6 minus 0.2 multiplied by 0.3, which is 0.52. This score is used to rank and compare with the scores of other batteries on the rack in the station.
[0041] Next, all physical bays within the station are divided into a first bay area and a second bay area based on their historically calibrated heat dissipation capabilities. The heat dissipation capability of the first bay area is higher than that of the second bay area. Batteries are sorted from highest to lowest score, and batteries with scores above a preset range are matched to currently idle bays in the first bay area. Batteries with scores below the preset range are matched to the second bay area. Subsequently, the operation system converts the matching results into physical bay transfer instructions, which are then sent to the underlying PLC through the station control coordination layer. The PLC rewrites the running trajectory and grasping coordinates of the battery swapping robotic arm, driving the robotic arm to complete the physical transfer of the batteries. After the transfer is completed, the system continuously collects temperature data of each bay and updates the digital twin model, entering the next round of rolling scheduling to form a closed-loop control.
[0042] Regarding the second part of the implementation method, namely the SDPM dynamic reconfiguration process, firstly, the system continuously collects battery swapping demand data for each time period within several past battery swapping cycles, including the number of batteries arriving at each voltage platform, their state of charge, and target charging power. Simultaneously, it collects time, external weather characteristics, and grid dispatch event characteristics. Secondly, the above characteristics are input into a pre-trained time-series prediction model, according to... Output the predicted charging power demand vector for each bay in the next scheduling cycle. Then, construct a loss coefficient matrix based on the number of switching operations, conduction losses, and voltage conversion losses between the charging module and the bay under different voltage platform adaptations. Finally, with the optimization objective of reducing the total sum of overall switching and conversion losses, according to... The solution process involves determining the values of each switch state variable, which is subject to two sets of constraints. The first set of constraints is... The second set of constraints is used to ensure that the available charging power obtained by each unit is not less than its predicted demand. To prevent overloading caused by excessive allocation of a single charging module, the solution-obtained switch state matrix is then converted into closing and opening control signals for a solid-state switch array. These signals are sent in real time through the underlying drive circuit to dynamically reconstruct the electrical connection between the charging module and the battery compartment. When an actual battery swapping request arrives, the system feeds back the deviation between the measured power demand and the predicted value to the prediction model for online correction. The above process is repeated in the next scheduling cycle to achieve dynamic rolling reconstruction. For example, when a battery from a 400V voltage platform arrives at the station, the system can optimize the solution to reconnect the charging module that was originally connected to the 800V battery to the battery compartment of the 400V battery through the switch array. This allows for flexible sharing of charging resources before the end of the next scheduling cycle, avoiding efficiency losses caused by derating power supply through a fixed channel.
[0043] Regarding the third implementation method, namely the integrated detection-isolation physical blocking process, firstly, when the battery swapping robotic arm performs a grabbing action on the incoming battery and enters the initial stage of the physical transfer cycle, the operation system synchronously triggers the high-frequency signal generation module integrated on the battery swapping base and the robotic arm guide rail to inject a wideband AC small-signal excitation current into the battery charging contacts. Secondly, the impedance spectrum excitation and acquisition module synchronously acquires the battery's voltage response and phase delay data under this excitation. Then, based on the excitation and response signals, according to... The complex impedance at each frequency point was calculated to obtain the electrochemical impedance spectroscopy (EIS) data set of the battery. Then, the measured impedance spectra were compared point by point with the health reference impedance spectra of the same model, the same state of charge range, and the same temperature conditions in the station's database. The normalized impedance deviation index is calculated, and then compared with a preset risk threshold. If the deviation index exceeds the threshold, the battery is determined to be in a high-risk state, such as a hidden micro-short circuit in the chassis. The operation system immediately sends a trajectory rewrite command to the PLC to rewrite the current running trajectory and target coordinates of the robotic arm in real time. The original racking path is canceled, and the robotic arm is driven to send the battery into an independent explosion-proof isolation compartment outside the station along a dedicated isolation track. At the same time, the fire extinguishing device is triggered to enter standby mode and the isolation compartment door is locked. If the deviation index does not exceed the threshold, the battery is determined to be normal. The robotic arm completes the racking action according to the original path, and the detection data of the battery and the target compartment information are synchronously fed back to the aforementioned three-dimensional temperature field scheduling module as one of the input data for subsequent compartment scheduling, forming a data closed loop between the detection and scheduling links.
[0044] Regarding the implementation of the physical structure layout of the battery swapping station, the battery compartments within the station are divided into a first compartment area and a second compartment area according to the historically calibrated heat dissipation capacity. The SDPM power matrix hardware is set in the electrical connection layer between the charging module array and the compartment array. In addition to connecting each compartment within the station, the robotic arm running track has an independent branch track that directly connects to the explosion-proof isolation compartment located outside the main structure of the station, equipped with explosion-proof walls and automatic fire extinguishing devices. This ensures that the main battery swapping path and the isolation path are physically independent of each other, avoiding interference between the high-risk battery transfer process and the normal battery swapping process.
[0045] In another embodiment of the present invention, the three-dimensional temperature field scheduling part may not use a complete digital twin simulation model based on the principle of computational fluid dynamics, but a simplified regression or lookup table model trained based on historical temperature and current data to quickly estimate the heat dissipation capacity and target temperature of each compartment, so as to reduce the computing power and modeling cost of edge computing nodes, while still achieving the purpose of physical transfer scheduling of high-heat batteries to compartments with higher heat dissipation capacity.
[0046] In another embodiment of the present invention, the excitation injection action of the integrated detection-isolation mechanism does not need to be completely synchronized with the gripping and transporting action of the robotic arm. Instead, the excitation injection and response acquisition are completed during the short pause period between mechanical actions such as battery locking and unlocking. This can also achieve non-destructive detection of hidden fault batteries and subsequent mechanical trajectory linkage isolation without significantly extending the overall battery swapping physical cycle.
[0047] Although the present invention has been disclosed above with reference to preferred embodiments, it is not intended to limit the present invention. Any person skilled in the art can make possible changes and modifications without departing from the spirit and scope of the present invention. Therefore, any modifications, equivalent changes and alterations made to the above embodiments based on the technical essence of the present invention without departing from the content of the technical solution of the present invention shall fall within the protection scope defined by the claims of the present invention.
Claims
1. An intelligent operation system for a centralized electric vehicle charging and battery swapping station, characterized in that, include: At the decision-making level, a three-dimensional temperature field digital twin module, a demand forecasting module, and an impedance risk assessment module are deployed; The station control and coordination layer is used to convert the decision results of the decision-making layer into warehouse scheduling instructions, power matrix topology configuration instructions, and robotic arm trajectory instructions. The underlying physical execution layer includes temperature sensors, current sensors, and voltage sensors distributed in each battery compartment of the battery swapping station; a software-defined physical power matrix composed of a solid-state switch array and set between the charging module array and the battery compartment array; an impedance spectrum excitation and acquisition module integrated into the running track of the battery swapping robotic arm; and a battery swapping robotic arm that receives instructions from the station control coordination layer to execute actions. The three-dimensional temperature field digital twin module is used to calculate the heat generation of the battery corresponding to each battery compartment based on the data collected by the temperature sensor, current sensor and voltage sensor, and to deduce the predicted temperature of each battery compartment by combining the convective heat transfer coefficient of each battery compartment. Based on the heat generation of the battery, the battery health decay rate and the physical transfer distance between the current battery compartment and the candidate compartment, the module calculates the compartment scheduling priority score of each battery. The station control coordination layer generates a physical compartment transfer command based on the compartment scheduling priority score, and drives the battery swapping robotic arm to physically transfer the battery between the first compartment area and the second compartment area, which are pre-divided according to the heat dissipation capacity. The heat dissipation capacity of the first compartment area is higher than that of the second compartment area. The demand forecasting module is used to predict the charging power demand of each battery compartment in the next scheduling cycle based on historical battery swapping demand data. The station control coordination layer solves the closing state of each switch unit in the software-defined physical power matrix based on the predicted charging power demand and the preset switching loss coefficient matrix, generates a power matrix topology configuration instruction, and realizes the dynamic reconstruction of the electrical connection relationship between the charging module and the battery compartment. The impedance spectrum excitation and acquisition module is used to inject a wideband AC excitation current into the battery and acquire voltage response data during the physical cycle of the battery swapping robotic arm performing the grabbing and transfer action on the battery entering the station, thereby obtaining the battery's electrochemical impedance spectrum. The impedance risk determination module is used to compare the electrochemical impedance spectrum with a preset health benchmark impedance spectrum to obtain a normalized impedance deviation index. If the normalized impedance deviation index exceeds a preset risk threshold, the module issues a trajectory rewrite instruction to the programmable logic controller corresponding to the battery swapping robotic arm, so that the battery swapping robotic arm transfers the corresponding battery to the explosion-proof isolation chamber set outside the battery swapping station.
2. The system according to claim 1, characterized in that, The warehouse scheduling priority score is calculated as follows: the ratio of battery heat generation to a preset heat generation benchmark value is used as the heat generation rate normalization term; the ratio of battery health decay rate to a preset health decay reference threshold is used as the health normalization term; and the ratio of the physical transfer distance between the current battery warehouse and the candidate warehouse to a preset transfer distance benchmark value is used as the transfer cost normalization term. The heat generation rate normalization term and the health normalization term are multiplied by their corresponding weight coefficients and then added together. Finally, the transfer cost normalization term multiplied by its corresponding weight coefficient is subtracted to obtain the warehouse scheduling priority score. The sum of the weight coefficients of the heat generation rate normalization term, the health normalization term, and the transfer cost normalization term is 1.
3. The system according to claim 1, characterized in that, The station control coordination layer is also used to continuously acquire temperature data of each battery compartment after the battery transfer is completed and update the simulation results of the three-dimensional temperature field digital twin module for the next round of compartment scheduling.
4. The system according to claim 1, characterized in that, In the software-defined physical power matrix, each switching unit is set at an electrical connection node between a charging module and a battery compartment. When the station control coordination layer solves the closed state of each switching unit, it takes reducing the total switching loss as the optimization objective and satisfies the following constraints: the charging power obtained by each battery compartment is not less than its predicted charging power demand, and the number of battery compartments connected in parallel by each charging module does not exceed the preset upper limit.
5. The system according to claim 1, characterized in that, The demand forecasting module is used to output the predicted charging power demand vector for each battery compartment in the next scheduling cycle based on historical battery swapping demand data, time and weather characteristics, and grid scheduling event characteristics, using a pre-trained time series forecasting model.
6. The system according to claim 1, characterized in that, The operating track of the battery swapping robotic arm includes a main operating track connecting each battery compartment within the battery swapping station and an isolation track branch set independently of the main operating track. The isolation track branch extends to the explosion-proof isolation compartment located outside the battery swapping station body, equipped with an explosion-proof wall and an automatic fire extinguishing device. When the normalized impedance deviation index exceeds a preset risk threshold, the battery swapping robotic arm transfers the corresponding battery to the explosion-proof isolation compartment along the isolation track branch and triggers the automatic fire extinguishing device to enter a standby state.
7. The system according to claim 1, characterized in that, If the normalized impedance deviation index does not exceed the preset risk threshold, the battery swapping robotic arm completes the battery placement action according to the original running trajectory, and feeds back the electrochemical impedance spectroscopy detection data of the corresponding battery and the target storage location information to the three-dimensional temperature field digital twin module as input data for the next round of storage location scheduling.
8. The system according to claim 1, characterized in that, The first compartment area and the second compartment area are divided according to the pre-calibrated convective heat transfer coefficient of each battery compartment. The convective heat transfer coefficient of each battery compartment in the first compartment area is higher than that of each battery compartment in the second compartment area.
9. The system according to claim 1, characterized in that, The impedance spectrum excitation and acquisition module is integrated into the robotic arm guide rail of the battery swapping robotic arm. It is used to simultaneously complete the injection of broadband AC excitation current and the acquisition of voltage response data when the battery swapping robotic arm enters the initial stage of the physical transfer cycle after performing a gripping action on the battery entering the station.