A method of installing a bow thruster and its nozzle for a ship
By independently dividing the guide pipe and some segmented structural components into intermediate components and constructing them in parallel on a normal jig, the construction stoppage problem caused by equipment delivery delays during the installation of the bow thruster and guide pipe in the existing technology is solved, thereby improving installation accuracy and resource utilization efficiency.
Patent Information
- Application Number
- CN202611356753.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-03
- Publication Date
- 2026-11-20
AI Technical Summary
The existing bow thruster and guide pipe installation process relies heavily on equipment delivery and turning procedures due to segmented construction, which makes it difficult to control the positioning and installation accuracy, and also results in low utilization efficiency of construction site and crane resources.
The flow guide pipe and some segmented structural components are independently divided into intermediate components, which are constructed in parallel on normal jigs. This includes constructing the bow thruster segment on the segmented jig and the flow guide pipe intermediate component on the intermediate component jig. Precise positioning and closure are achieved through lateral translation hoisting and fine-tuning tools.
This shortened the overall construction cycle of the sections, improved the utilization efficiency of construction site and crane resources, reduced the sensitivity of equipment delivery time, and ensured the installation accuracy and construction efficiency of the diversion pipe and the bow thruster.
Smart Images

Figure CN123130180A_ABST
Abstract
Description
Technical Field
[0001] This application relates to the field of shipbuilding technology, and in particular to a method for installing a bow thruster and its guide pipe. Background Technology
[0002] Bow thrusters are typically located below the design waterline at the bow of a vessel and are used to provide lateral thrust during berthing, unberthing, and maneuvering. The mechanical components of a bow thruster include the thruster cylinder and its connection to the guide tube, the outer end of which connects to the hull hull plating. Because the bow thruster, guide tube, and hull sections have positioning, assembly, and welding relationships, the installation accuracy directly affects the quality of section construction and subsequent equipment installation.
[0003] The installation of existing bow thrusters and guide tubes typically requires coordination of equipment delivery, jig occupancy, segment turning and assembly operations during the segmented construction process. If the bow thrusters and guide tubes are manufactured and installed using the same work path, segmented construction is easily constrained by equipment delivery time and construction site conditions, and the difficulty of positioning measurement and post-welding accuracy control increases.
[0004] One existing method involves dividing the bow thruster into multiple segments for separate construction, and then completing the bow thruster installation on some segments before turning over and assembling it. This method requires the configuration of large jigs and hoisting conditions, and the segmented construction occupancy time is relatively long; when the bow thruster or diverter pipe is delayed in arrival, the segmented assembly process is also easily affected.
[0005] Another existing method involves installing the bow thruster and deflector under inverted conditions, then flipping the section back to normal conditions to continue construction. This method places high demands on jig avoidance, support, and inverted measurement; after the section is flipped, the level and benchmark need to be readjusted, which involves many procedures and is not conducive to improving the positioning efficiency and installation accuracy between the bow thruster, deflector, and the section structure. Summary of the Invention
[0006] Therefore, it is necessary to provide a method for installing a ship's bow thruster and its guide pipe that can reduce the dependence of segmented construction on equipment delivery and turning procedures, and improve the positioning and installation accuracy of the guide pipe and bow thruster.
[0007] To solve the above-mentioned technical problems, this application provides the following technical solution: A method for installing a ship's bow thruster and its guide pipe includes the following steps: S1: Delineate the installation area of the components in the guide tube based on the structural characteristics of the bow thruster, guide tube, and bow thruster segment; S2: Fabricate segmented jigs for the segmented normal construction of the bow thruster and intermediate component jigs for the construction of the intermediate components in the guide tube; S3: Construct the bow thruster segments normally on the segmented jig and position and install the bow thruster, while constructing the guide tube assembly on the mid-assembly jig; S4: Hoist the completed components of the diversion pipe to the bow thruster section and assemble them with the bow thruster and the bow thruster section; S5: Weld the joined bow thruster sections and perform a final accuracy check.
[0008] Understandably, by independently classifying the guide tube and some segmented structural components as intermediate components, parallel operations were achieved for the normal construction of the bow thruster segment and the construction of the guide tube intermediate components. The positioning and installation of the bow thruster and the fabrication and construction of the guide tube were carried out simultaneously on two independent jigs, without mutual constraints, effectively shortening the overall construction cycle of the segment and improving the utilization efficiency of shipyard space and crane resources. Simultaneously, because the guide tube intermediate components are constructed as independent modules, their installation timing can be flexibly adjusted according to the arrival of the bow thruster and the segment construction progress. They can be assembled before or after the segment deck installation, or even while the segment is flipped over, thus significantly reducing sensitivity to the bow thruster's delivery date and avoiding the problem of segment construction halts due to equipment delivery delays.
[0009] In one embodiment, the components in the guide tube include the guide tube and a partially segmented structural member connected to the guide tube, the partially segmented structural member including at least one of an outer plate, ribs, and longitudinal ribs.
[0010] In one embodiment, when defining the installation area of the components in the guide tube, the range of the outer plate of the components is determined according to the connection position between the outer port of the guide tube and the outer plate of the hull, and the arrangement of the segmented structural components connected to the guide tube is determined according to the assembly convenience of the segmented structural components.
[0011] In one embodiment, the segmented jig is a normal jig adapted to the profile of the bow thruster segment outer plate, and construction space is reserved at the location corresponding to the component installation area in the guide pipe.
[0012] In one embodiment, the intermediate component jig is a normal jig adapted to the outer plate profile of the component in the guide tube, and a jig plate is provided to ensure the edge accuracy of the component in the guide tube.
[0013] In one embodiment, the normal construction of the bow thruster segment, the positioning and installation of the bow thruster, and the construction of components in the guide tube are carried out simultaneously.
[0014] In one embodiment, a margin is reserved for the outer plate of the middle component and the components connected to the outer plate of the middle component to compensate for deviations in construction accuracy, and the margin is removed according to measurement data before the middle component in the guide tube and the bow thruster section are joined.
[0015] In one embodiment, a conformal reinforcing rib is provided on the inner side of the outer plate edge of the component in the guide tube to maintain the linear accuracy of the closing opening of the outer plate of the component in the guide tube, and the conformal reinforcing rib is removed after the component in the guide tube is closed.
[0016] In one embodiment, the component in the flow guide tube is slidably hoisted in from the side of the bow thruster section, and the position of the component in the flow guide tube is adjusted by means of temporary lifting lugs and fine-tuning tools provided inside the bow thruster section.
[0017] In one embodiment, the components in the guide tube are positioned using positioning references set on the bow thruster body and the guide tube body, and the straightness and levelness of the tube body are checked after they are closed; welding is performed after the checks are passed.
[0018] Compared with existing technologies, a method for installing a bow thruster and its guide tube allows for the parallel construction of the bow thruster section and the guide tube component by independently dividing the guide tube and some segmented structural components into intermediate modules. The positioning and installation of the bow thruster and the fabrication of the guide tube are carried out simultaneously on two independent jigs, without mutual constraints, effectively shortening the overall construction cycle of the section and improving the utilization efficiency of shipyard space and crane resources. Furthermore, because the guide tube component is constructed as an independent module, its installation timing can be flexibly adjusted according to the arrival of the bow thruster and the progress of section construction. It can be assembled before or after the deck section is installed, or even while the section is flipped over, significantly reducing the sensitivity to the bow thruster's delivery date and avoiding the problem of section construction halts due to equipment delivery delays. Attached Figure Description
[0019] To more clearly illustrate the technical solutions in the embodiments of this application or the conventional technology, the drawings used in the description of the embodiments or the conventional technology will be briefly introduced below. Obviously, the drawings described below are only some embodiments of this application. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.
[0020] Figure 1 A diagram showing the component area division in the guide pipe of a method for installing a bow thruster and its guide pipe provided in this application; Figure 2 A transverse view of the center of the bow thruster, which is provided in this application for the installation method of the bow thruster and its guide pipe. Figure 3 A top view of the bow thruster center, which is provided in this application for the installation method of a ship's bow thruster and its guide pipe; Figure 4A schematic diagram of a segmented jig for the installation method of a ship's bow thruster and its guide pipe provided in this application; Figure 5 A schematic diagram of the segmented jig in the position of the bow thruster, which is part of the installation method of the bow thruster and its guide pipe provided in this application; Figure 6 A schematic diagram of the guide pipe for the installation method of a ship's bow thruster and its guide pipe provided in this application; Figure 7 This is a schematic diagram of the normal installation of components in the guide pipe of a ship's bow thruster and its guide pipe, which is provided in this application.
[0021] The component labels are as follows: 1. Components in the flow guide tube; 2. Flow guide tube; 3. Bow thruster section; 4. Outer plate; 5. Ribs; 6. Bulk components; 7. Longitudinal ribs; 8. Frame; 9. Bow thruster. Detailed Implementation
[0022] To make the above-mentioned objectives, features, and advantages of this application more apparent and understandable, the specific embodiments of this application are described in detail below with reference to the accompanying drawings. Many specific details are set forth in the following description to provide a thorough understanding of this application. However, this application can be implemented in many other ways different from those described herein, and those skilled in the art can make similar modifications without departing from the spirit of this application. Therefore, this application is not limited to the specific embodiments disclosed below.
[0023] It should be noted that when a component is referred to as being "fixed to" or "set on" another component, it can be directly on the other component or there may be an intermediate component. When a component is considered to be "connected to" another component, it can be directly connected to the other component or there may be an intermediate component present. The terms "vertical," "horizontal," "upper," "lower," "left," "right," and similar expressions used in this application's specification are for illustrative purposes only and do not represent the only possible implementation.
[0024] Furthermore, the terms "first" and "second" are used for descriptive purposes only and should not be construed as indicating or implying relative importance or implicitly specifying the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include at least one of that feature. In the description of this application, "multiple" means at least two, such as two, three, etc., unless otherwise explicitly specified.
[0025] In this application, unless otherwise expressly specified and limited, "above" or "below" the second feature can mean that the first feature is in direct contact with the second feature, or that the first feature and the second feature are in indirect contact through an intermediate medium. Furthermore, "above," "over," and "on top" the second feature can mean that the first feature is directly above or diagonally above the second feature, or simply indicates that the first feature is at a higher horizontal level than the second feature. "Below," "below," and "under" the second feature can mean that the first feature is directly below or diagonally below the second feature, or simply indicates that the first feature is at a lower horizontal level than the second feature.
[0026] Unless otherwise defined, all technical and scientific terms used in this application have the same meaning as commonly understood by one of ordinary skill in the art to which this application belongs. The terminology used in this application is for the purpose of describing particular embodiments only and is not intended to be limiting of the application. The term "and / or" as used in this application includes any and all combinations of one or more of the associated listed items.
[0027] Please see Figures 1 to 7 This application provides a method for installing a ship's bow thruster and its guide pipe, comprising the following steps: Example 1: S1. Based on the structural characteristics of the bow thruster 9, the guide pipe 2, and the bow thruster section 3, the installation area of component 1 in the guide pipe is determined. Specifically, when determining the installation area of component 1 in the guide pipe, firstly, based on the model and size of the bow thruster 9 and its location below the design waterline at the bow of the ship, combined with the hull's hull shape variation trend in this area, the axial length of the guide pipe 2 and the spatial positions of its inner and outer ports in the ship's coordinate system are determined. The inner port of the guide pipe 2 is connected to the bow thruster 9 cylinder, and the joint position is determined according to the interface requirements of the bow thruster 9 equipment manufacturer; the outer port of the guide pipe 2 is corner-jointed with the hull outer plate 4, and its connection position is determined by the opening size and plate seam distribution of the hull outer plate 4 in this area.
[0028] The middle component 1 of the guide pipe includes a guide pipe 2 and segmented structural components connected to the guide pipe 2. The segmented structural components may include an outer plate 4, ribs 5, and longitudinal ribs 7. When determining the range of the outer plate 4 of the middle component, the corner joint position between the outer port of the guide pipe 2 and the outer plate 4 of the hull is used as a reference. Extending outward along the surface of the outer plate 4, the plate seam corresponding to the opening area of the guide pipe 2 is preferentially used as the boundary of the outer plate 4 of the middle component. If the range of the thickened plate is too large, an additional plate seam is set at a distance of about two ribs outside the opening to define the boundary of the middle component of the outer plate 4, ensuring that the overall size of the middle component is appropriate and facilitates subsequent hoisting and assembly operations.
[0029] For the segmented structural components connected to the guide pipe 2, the relevant components are designed to be extended, retracted, or assembled in a modular manner based on the ease of assembly. Specifically, for longitudinal ribs 7 and ribs 5 that intersect or are adjacent to the guide pipe 2, if their extension into the middle component area does not affect the positioning and welding operations of the guide pipe 2, they are constructed together with the middle component in an extended manner; if the placement of the component interferes with the installation operation of the guide pipe 2, the component is retracted to outside the boundary of the middle component and installed after the middle component is closed; for parts with complex structures or limited installation space, these components are reserved as modular parts 6 and assembled on-site on the segment after the middle component is closed and positioned, in order to improve the ease of construction and closure of the middle component.
[0030] Furthermore, allowances are reserved at the corresponding ends of the outer plate 4 of the middle component and its connected longitudinal ribs 7, ribs 5, etc., to compensate for construction accuracy deviations. These allowances are precisely removed based on actual on-site measurements after the middle component is constructed and before it is joined with the bow thruster section 3, ensuring the docking accuracy and weld quality between the middle component and the bow thruster section 3. This area delineation method enables modular construction of the middle component 1 in the guide tube, improving construction efficiency and facilitating its smooth subsequent joining with the bow thruster section 3.
[0031] S2, based on the line shape of the outer plate 4 of the bow side thruster segment 3, a segmented normal construction jig 8 is made, and construction space is reserved in the installation area of component 1 in the guide pipe.
[0032] Specifically, the fabrication of the segmented jig 8 is based on the hull outer plating 4 profile data of the hull region where the bow thruster segment 3 is located. Since the bow profile of a ship typically exhibits significant curvature changes, to ensure the accuracy of the outer plating 4 laying and the reliability of structural component positioning during segmented construction, the segmented jig 8 adopts a normal construction method. That is, the posture of the segment on the jig 8 is consistent with the posture of the ship in sailing condition, with the inner surface of the segmented outer plating 4 facing upwards to facilitate the laying of the outer plating 4 and the installation and welding of components such as the longitudinal ribs 7 and ribs 5. During the fabrication of the jig 8, multiple jig plates are set along the transverse rib direction of the segment. The upper edge profile of each jig plate matches the profile of the outer plating 4 at the corresponding rib position, thereby forming a multi-point support system that fits against the inner surface of the outer plating 4.
[0033] The spacing of the formwork plates is determined based on the curvature variation of the outer plate 4. In areas with drastic changes in the linear shape, the number of formwork plate intervals is appropriately increased to improve the linear accuracy of the outer plate 4 after installation and prevent deformation of the outer plate 4 due to insufficient support. At the same time, the height and angle of each formwork plate must be precisely processed after being laid out on a template or after data is extracted from a 3D digital model to ensure that the overall rigidity and positioning accuracy of the formwork frame 8 meet the requirements of segmented normal construction.
[0034] In the installation area of component 1 in the guide tube, the segmented jig 8 reserves construction space at the corresponding position. Specifically, since component 1 in the guide tube is independently constructed outside the segmented jig 8 and then moved and hoisted into the bow side to push the segment 3 for closure, when making the segmented jig 8, the jig plate or support structure that overlaps with the installation area of component 1 in the guide tube is avoided or set as a detachable temporary support. Thus, after the outer plate 4 of the segment is laid, sufficient operating space is formed below this area, which is convenient for subsequent position adjustment, measurement and welding operations when component 1 in the guide tube is moved in from the side of the segment.
[0035] The size of the reserved space is determined comprehensively based on the outline dimensions of component 1 in the diversion pipe, the hoisting path, and the operating range of the fine-tuning tools, so as to ensure the convenience and safety of the closure construction.
[0036] Simultaneously, the intermediate component jig 8 is fabricated based on the linear shape of the outer plate 4 of the intermediate component 1 in the guide tube. The intermediate component jig 8 also adopts a normal construction method, which is used to independently bear and support the outer plate 4 and internal structural components of the intermediate component 1 in the guide tube outside the segment jig 8, so that the construction of the intermediate component 1 in the guide tube is not constrained by the construction progress of the bow thruster segment 3.
[0037] The size of the intermediate component jig 8 is much smaller than that of the segmented jig 8, and it only needs to cover the area of the outer plate 4 of the intermediate component 1 in the guide pipe. Therefore, the jig 8 uses less material, occupies less space, and has a shorter production cycle. Several jig plates are set in both the transverse and longitudinal directions of the intermediate component jig 8. The line shape of each jig plate corresponds to the line shape of the outer plate 4 of the intermediate component 1 in the guide pipe at that position, so as to ensure that the outer plate 4 is consistent with the design line shape after being laid.
[0038] The mid-component jig 8 is also equipped with jig plates to ensure the edge accuracy of the mid-component 1 in the guide tube. These jig plates are arranged on the upper end face of the edge area of the mid-component outer plate 4, that is, at the closing position where the mid-component and the bow thruster segment 3 meet. Their upper edges are consistent with the theoretical line shape at the closing position, and are used to constrain the shape and position of the free edge of the mid-component outer plate 4, preventing edge misalignment due to shrinkage deformation or gravity during construction and welding. The setting of the conformal jig plates effectively ensures the geometric accuracy of the mid-component closing position, providing a reliable foundation for subsequent high-precision docking with the bow thruster segment 3.
[0039] Both the segmental jig 8 and the intermediate component jig 8 are normal jigs 8, meaning that both ensure the constructed components are in an upward-facing state consistent with the ship's sailing attitude. The advantages of the normal jig 8 are: during the laying of the outer plates 4, the plates naturally conform to the jig line under their own weight, facilitating positioning and fixing; during structural component assembly, the component installation direction is consistent with the design state, eliminating the need for coordinate transformation during baseline marking and measurement, reducing construction difficulty and measurement errors; and during subsequent closure operations, the closure joint is located on the side or below the component, facilitating access and operation for construction personnel. Through the combined use of these two normal jigs 8, the parallel and independent construction of the bow thruster segment 3 and the intermediate component 1 in the guide pipe is achieved, shortening the overall construction cycle and effectively ensuring the structural accuracy of each component, laying a solid foundation for subsequent precise closure.
[0040] S3, the bow thruster segment 3 is constructed normally on the segmented jig 8, and the bow thruster 9 is installed after the bottom structural components of the bow thruster 9 are positioned; Specifically, during the normal construction of the bow thruster segment 3 on the segmented jig 8, the laying of the segmented outer plates 4 is carried out first. According to the line markings on each jig plate on the segmented jig 8, the operators hoist the pre-treated outer plates 4 sequentially to the top of the jig 8, position them one by one according to the pre-marked laying reference lines on the jig 8, and temporarily fix the outer plates 4 to the jig plates through a clamping device and locating welding, so that the inner surface of the outer plate 4 is tightly attached to the upper edge of the jig plate.
[0041] After the outer plate 4 is laid, structural assembly reference lines, such as the installation lines for the longitudinal stiffeners 7 and the positioning lines for the ribs 5, are marked on the inner surface of the outer plate 4. Subsequently, the longitudinal stiffeners 7, ribs 5, longitudinal girder, and rib plates of the outer plate 4 are installed sequentially. The installation sequence of each structural component proceeds layer by layer from the bottom towards the deck. First, the longitudinal and transverse reinforcing members close to the outer plate 4 are installed, then the internal support structure is installed, and finally the deck components are installed, ensuring good structural stability and sufficient operating space during construction. During the installation of structural components, the positioning of each component is referenced to the reference lines marked on the outer plate 4, and a laser theodolite is used to check the levelness and position to ensure that the assembly accuracy of each component meets the design requirements.
[0042] The installation of the bow thruster 9 is scheduled to take place after the bottom structural components of the bow thruster 9 have been positioned. Once the bottom longitudinal ribs 7, ribs 5, and rib plates around the installation area of the bow thruster 9 have been positioned and preliminarily welded, the bow thruster 9 can be hoisted into its predetermined position within the section. The hoisting of the bow thruster 9 can be carried out using temporary lifting points set above the section or by using a workshop crane in conjunction with specialized lifting equipment, slowly lowering it to the cylinder installation position. During installation, the horizontality, height, and positioning dimensions in the front-to-back and left-to-right directions of the bow thruster 9 cylinder are first measured using the theoretical centerline and waterline height benchmark of the bow thruster 9 on the section as references.
[0043] By setting up a precision level and a laser rangefinder on the flange face of the bow thruster 9 cylinder or on a preset measurement reference surface, the posture of the cylinder is repeatedly adjusted until the deviations in all directions are controlled within the design allowable range. Then, tack welding is performed to temporarily fix the bow thruster 9 cylinder to the bottom structural component, and then continuous welding is carried out between the bow thruster 9 cylinder and the segmented structure.
[0044] While the normal construction of the bow thruster segment 3 is underway, the middle component 1 of the guide tube is constructed on the middle component jig 8. The construction of the middle component 1 of the guide tube first involves the processing and welding of the guide tube 2. The cylindrical body of the guide tube 2 is usually made of rolled and welded steel plate. Its processing includes steel plate blanking, rolling, longitudinal seam welding and rounding. After the cylindrical body is formed, bevels are processed at both ends of the cylindrical body, and relevant accessories are installed on the outer wall of the cylindrical body.
[0045] After the guide pipe 2 is processed, the guide pipe middle component 1 is assembled on the middle component jig 8. The construction sequence is as follows: first, lay the middle component outer plate 4, position the outer plate 4 according to the jig 8 line and temporarily fix it; then, hoist the processed guide pipe 2 into the opening area of the outer plate 4, and complete the positioning of the guide pipe 2 on the outer plate 4 with the corner joint position of the outer port of the guide pipe 2 and the outer plate 4 as the reference, and ensure that the center line of the inner port of the guide pipe 2 and the flange face are consistent with the subsequent docking requirements of the bow thruster 9 cylinder.
[0046] After the guide tube 2 is positioned, other structural components connected to it are installed, including ribs 5, longitudinal ribs 7, and various support seats and connectors attached to the guide tube 2. Welding is then carried out after all components are in place. To further maintain the linear accuracy of the closure joint of the outer plate 4 of component 1 in the guide tube, conformal reinforcing ribs are provided on the inner side of the edge of the outer plate 4. These conformal reinforcing ribs are welded near the inner edge of the closure joint of the outer plate 4, extending along the contour of the closure joint, effectively constraining the deformation of the free edge of the outer plate 4 during construction and welding, ensuring that the shape of the closure joint is consistent with the design line. After component 1 in the guide tube is hoisted to the bow thruster section 3 and the closure positioning and welding are completed, the conformal reinforcing ribs are removed to restore the final shape of the structure at the closure joint of the outer plate 4. Through the above parallel construction method, the overall construction efficiency is significantly improved, and the manufacturing accuracy of the bow thruster 9 and the guide tube 2 is guaranteed.
[0047] S4. After the bow thruster section 3 is assembled normally, the component 1 in the guide tube is moved and hoisted into the bow thruster section 3 from the side. Specifically, after the bow thruster section 3 is assembled normally and passes the preliminary welding inspection, the assembly and installation of the component 1 in the guide tube is carried out.
[0048] Since the middle component 1 of the diversion pipe has been constructed on the independent middle component jig 8, and the shape of its outer plate 4 and the accuracy of the closing joint have been maintained by the shape-preserving reinforcing ribs, before hoisting, the actual dimensions of the middle component must be checked, the length, width and diagonal data of the closing joint must be measured, and compared with the corresponding closing joint measurement data on the bow side thrust section 3. Only after confirming that the matching relationship between the two meets the closing requirements can hoisting be carried out.
[0049] The component 1 in the guide tube is hoisted by sliding it into the side of the section 3 from the bow side. Since the outer port of component 1 in the guide tube needs to be connected with the opening of the outer plate 4 of the section, and its installation direction is roughly perpendicular to the side of the section, the side sliding method can effectively utilize the open space on the side of the section and avoid interference from the section deck or upper structure when hoisting from above.
[0050] Before the hoisting operation, several temporary lifting lugs are first installed in the area inside the bow thruster section 3 corresponding to the installation position of component 1 in the guide tube. These temporary lifting lugs are arranged in locations with high structural strength inside the section, such as the intersection of rib 5 and longitudinal rib 7, to ensure reasonable stress distribution and structural safety during hoisting. The number and distribution of temporary lifting lugs are determined comprehensively based on the weight, center of gravity position, and translation path of component 1 in the guide tube. Lifting lugs are usually installed above and on the side of the entry path of the middle component to facilitate multi-directional adjustment of the attitude of the middle component during hoisting.
[0051] During hoisting, a workshop overhead crane or crawler crane is used to move component 1 of the guide pipe from the side of the segment into the segment's interior. Once the component has basically reached its predetermined position, a hand-operated hoist or chain hoist, or other traction tool, pre-installed on temporary lifting lugs, is used to initially position the component. Because component 1 may experience positional deviations during the translation process due to hoisting deformation or space constraints, further fine-tuning tools are needed to precisely adjust its position. These fine-tuning tools can be hydraulic jacks or screw jacks, positioned at appropriate gaps between the outer plate 4 of the component and the internal structure of the segment. By gradually applying pressure or rotating the screw, the position of the component in the front-back, left-right, and up-down directions is precisely adjusted.
[0052] During the positioning adjustment process, the positioning references set on the bow thruster 9 cylinder and the guide tube 2 cylinder are used to accurately position component 1 in the guide tube. Specifically, sample gun points are set at the upper, lower, left, and right positions at the port of the bow thruster 9 cylinder as positioning references, and the same sample gun points are also set at the corresponding positions at the inner port of the guide tube 2 cylinder. During adjustment, the operator visually inspects or uses a laser alignment instrument to align the sample gun points at the corresponding positions of the two cylinders, thereby ensuring the consistency of the circumferential orientation and the collinearity of the axial centerline between the guide tube 2 cylinder and the bow thruster 9 cylinder. At the same time, the overall position of component 1 in the guide tube is checked against the hull centerline and waterline height references on the section to verify whether it meets the design requirements.
[0053] After component 1 in the guide tube is positioned and initially fixed, the straightness and levelness of the joined cylinder are immediately checked. The straightness check can be performed using a wire drawing method or a laser collimator, measuring the center deviation at multiple cross-sections along the cylinder's axial direction to ensure the straightness of the entire cylinder meets accuracy standards in the axial direction. The levelness check uses a precision level to measure the height difference between the preset horizontal reference planes on the bow thruster 9 cylinder and the guide tube 2 cylinder, ensuring they are on the same horizontal plane. After passing the checks, the reserved joining allowance at the outer plate 4 of the middle component and the cylinder port is precisely scribed and cut off based on the measured data. Then, a welding bevel is opened at the joining joint, and the formal welding of the joining weld is carried out. Through the above comprehensive process measures of lateral translation, fine-tuning positioning, and reference alignment, the docking accuracy and joining quality between the bow thruster 9 cylinder and the guide tube 2 cylinder are effectively guaranteed.
[0054] S5, after the component 1 in the guide tube and the bow thruster section 3 are joined together, the bow thruster section 3 is normally welded, and then turned over to be welded.
[0055] Specifically, the formal welding of the closure weld is carried out immediately after the inspection is passed, the excess material is removed, and the beveling is done. Since the weld at the closure joint includes the butt ring weld between the guide tube 2 cylinder and the bow thruster 9 cylinder, and the fillet weld between the outer plate 4 of component 1 in the guide tube and the outer plate 4 of the bow thruster segment 3, the welding quality of these two types of welds is directly related to the sealing performance and structural strength of the bow thruster 9 device.
[0056] Therefore, before welding, the joint area must be cleaned and preheated to remove oil, rust, and moisture. Appropriate welding process parameters should be selected based on the base material and plate thickness. During welding, symmetrical welding and segmented back-welding are used to control welding deformation and avoid deviations in cylinder roundness or misalignment of the outer plate's four-line profile due to localized overheating. Simultaneously, a dedicated person should continuously monitor the shrinkage of the joint area during welding. If deformation exceeds the allowable range, the welding sequence should be adjusted promptly or temporary reinforcement measures should be taken to correct it.
[0057] The normal welding refers to welding performed on the bow thruster section 3 while it is on the jig 8 in the same attitude as the ship's navigation. This mainly involves welding the joint and any unwelded areas inside the section left over from the installation of the intermediate components. After normal welding is completed, the section is lifted off the jig 8 and turned over. The turning operation requires a specialized turning lifting tool and lifting point arrangement plan designed according to the section's weight and center of gravity to ensure the section structure is not damaged during the turning process. After the section is turned over, areas that were previously located at the bottom or lower side and could not be welded in the normal state are repaired, including the reinforcing welds on the bottom outer plate 4 of the section and a portion of the lower side of the bow thruster 9 cylinder. By completing all welding work in both the normal and turned states, the accessibility and welding quality of the welds at each part of the section are ensured, avoiding defects such as incomplete penetration or slag inclusions caused by limitations in welding posture.
[0058] After welding, a comprehensive precision inspection is conducted on the bow thruster section 3. This precision inspection includes two aspects: firstly, the overall dimensions of the bow thruster section 3 are checked, including the overall length, width, height, and diagonal deviation, to ensure that the geometric dimensions meet the assembly precision requirements during hull assembly; secondly, the installation precision of the bow thruster 9 cylinder and the guide pipe 2 is specifically inspected, including the straightness of the cylinder axis, the parallelism and coaxiality of the flange faces or ports at both ends of the cylinder, the linear fit between the outer port of the guide pipe 2 and the four corner joints of the outer plate, and the relative positional dimensions of the centerline of the bow thruster 9 cylinder and the hull baseline. All the above inspection data are recorded as a basis for quality traceability in subsequent processes. After passing the inspection, the bow thruster section 3 can proceed to the subsequent painting process. Before painting, the surfaces of the sections were cleaned and polished to remove weld slag, spatter, and residue from temporary lifting lugs. Rust removal and primer application were then performed on each area of the section according to the painting process requirements, ultimately completing the section's protective coating. This complete process of welding, turning over, and precision inspection ensured the final quality of the bow thruster section 3 and guide pipe 2 installation, providing a reliable guarantee for the smooth assembly of the hull.
[0059] Example 2 presents an installation method for a bow thruster 9 and its guide pipe 2, which is basically the same as Example 1. The specific difference is that after the bow thruster section 3 and the bow thruster 9 are installed and welded in a normal position, they are flipped over and placed in a reverse position. After leveling the sections, the component 1 in the guide pipe is hoisted in and installed. This example is particularly suitable for cases where the guide pipe 2 is delivered late, greatly reducing the impact on the section construction cycle. Other specific implementation methods are the same as in Example 1, and will not be described in detail here.
[0060] Example 3 presents an installation method for a ship's bow thruster 9 and its guide pipe 2, which is basically the same as Example 1. The specific difference is that when the delivery time of the bow thruster 9 is affected, the components can be installed and welded in sections first. After the bow thruster 9 arrives, it can be moved into the section through the opening of the side outer plate 4 for installation, and then the component 1 in the guide pipe can be installed. It should be noted in this example that when dividing the component 1 in the guide pipe, the position of the plate seam of the outer plate 4 should take into account the feasibility of the bow thruster 9 entering, that is, the size of the component area in the outer plate 4 can accommodate the entry of the bow thruster 9.
[0061] The technical features of the above embodiments can be combined in any way. For the sake of brevity, not all possible combinations of the technical features in the above embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.
[0062] The embodiments described above are merely illustrative of several implementation methods of this application, and while the descriptions are relatively specific and detailed, they should not be construed as limiting the scope of the patent application. It should be noted that those skilled in the art can make various modifications and improvements without departing from the concept of this application, and these all fall within the scope of protection of this application. Therefore, the patent protection scope of this application should be determined by the appended claims.
Claims
1. A method for installing a ship's bow thruster and its guide pipe, characterized in that, Includes the following steps: S1: Determine the installation area of component (1) in the guide tube according to the structural characteristics of the bow thruster (9), the guide tube (2) and the bow thruster segment (3); S2: Fabricate a segment jig (8) for normal construction of the bow thruster segment (3) and a mid-component jig (8) for construction of the mid-component (1) in the diversion tube. S3: The bow thruster segment (3) is constructed normally on the segmented jig (8) and the bow thruster (9) is positioned and installed. At the same time, the flow guide tube middle component (1) is constructed on the middle component jig (8). S4: Hoist the completed diversion tube component (1) to the bow thruster section (3) and join it with the bow thruster (9) and the bow thruster section (3); S5: Weld the bow thruster section (3) after it is joined together, and check the accuracy of the finished product.
2. The method for installing the bow thruster and its guide pipe of a ship according to claim 1, characterized in that, The component (1) in the guide tube includes a guide tube (2) and a partially segmented structural member connected to the guide tube (2), wherein the partially segmented structural member includes at least one of an outer plate (4), a rib (5) and a longitudinal bone (7).
3. The method for installing the bow thruster and its guide pipe of a ship according to claim 2, characterized in that, When defining the installation area of the component (1) in the guide pipe, the range of the outer plate (4) of the component is determined according to the connection position between the outer port of the guide pipe (2) and the outer plate (4) of the ship body, and the setting method of the segment structure connected to the guide pipe (2) is determined according to the assembly convenience of the segment structure.
4. The method for installing the bow thruster and its guide pipe of a ship according to claim 1, characterized in that, The segmented frame (8) is a normal frame (8) adapted to the line shape of the bow side thrust segmented outer plate (4), and construction space is reserved at the position of the corresponding component (1) installation area in the guide pipe.
5. The method for installing the bow thruster and its guide pipe of a ship according to claim 1, characterized in that, The intermediate component frame (8) is a normal frame (8) that is adapted to the line shape of the outer plate (4) of the intermediate component (1) in the guide tube, and a frame plate is provided to ensure the edge accuracy of the intermediate component (1).
6. The method for installing the bow thruster and its guide pipe of a ship according to claim 1, characterized in that, The normal construction of the bow thruster segment (3), the positioning and installation of the bow thruster (9), and the construction of the component (1) in the guide tube were carried out simultaneously.
7. The method for installing the bow thruster and its guide pipe of a ship according to claim 3, characterized in that, The outer plate (4) of the middle component and the components connected to the outer plate (4) of the middle component are reserved for compensation of construction accuracy deviation, and the reserved amount is removed according to the measurement data before the middle component (1) of the guide tube and the bow thrust section (3) are closed.
8. The method for installing the bow thruster and its guide pipe of a ship according to claim 1, characterized in that, A conformal reinforcing rib is provided on the inner side of the edge of the outer plate (4) of the component (1) in the guide tube to maintain the linear accuracy of the closing opening of the outer plate (4) of the component (1) in the guide tube, and the conformal reinforcing rib is cut off after the component (1) in the guide tube is closed.
9. The method for installing a ship's bow thruster and its guide pipe according to claim 1, characterized in that, The component (1) in the guide tube is moved into the side of the bow thrust section (3) and the position of the component (1) in the guide tube is adjusted by means of temporary lifting lugs and fine-tuning tools set inside the bow thrust section (3).
10. The method for installing a ship's bow thruster and its guide pipe according to claim 9, characterized in that, The component (1) in the guide pipe is positioned using the positioning reference set on the bow thruster (9) cylinder and the guide pipe (2) cylinder, and the straightness and levelness of the cylinder are checked after closing; welding is carried out after the inspection is qualified.