A marine elevator installation and method thereof
By pre-assembling the cantilever beam and flat structure of the elevator at the dock, utilizing the support frame and multi-point coordinated turning technology, combined with guy rope anchoring and hydraulic cylinder stop mechanical limit, and using dual-machine tandem hoisting for whole-machine installation, the problems of high-altitude operation safety risks and assembly precision that are difficult to guarantee in existing technologies have been solved, achieving efficient and safe elevator installation.
Patent Information
- Application Number
- CN202611534298.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-30
- Publication Date
- 2026-11-20
AI Technical Summary
The existing elevator installation process involves completing many critical steps at high altitudes in the dock, making it difficult to consistently guarantee assembly accuracy and posing significant safety risks. Furthermore, it lacks standardized and quantifiable process methods, with aspects such as component turning, hook unhooking judgment, crane selection, wind resistance constraints, and site organization relying on experience-based judgment.
Pre-assembly of cantilever beams and flat structures is carried out at the dock. Using the support frame and multi-point coordinated turning technology, combined with guy rope anchoring and hydraulic cylinder stop mechanical limit, the whole machine is installed by dual-machine tandem lifting. The crane model and weld completion rate are selected by quantitative calculation as the conditions for unhooking.
Reduce the frequency of high-risk, high-altitude operations, improve assembly accuracy and safety, shorten the construction period, reduce crane shift costs, adapt to multi-component site organization, and achieve quantifiable quality control.
Smart Images

Figure CN123130184A_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of marine equipment technology, and more specifically, relates to a method for installing a ship elevator. Background Technology
[0002] Large ship elevators are key heavy-duty supporting equipment for special engineering vessels, used for the transfer of heavy equipment and vehicles. These elevators are very heavy, weighing hundreds of tons. Taking a typical 350-ton large ship elevator as an example, this article provides the installation method for large ship elevators. The cantilever assembly of a 350T elevator includes four cantilever beams (plus telescopic box beams, cylinders, and accessories), two flat structures (plus a pump station and operating platform); a single cantilever beam weighs 145.6 tons, and a single flat structure assembly weighs 146.5 tons. The total weight of a single assembled unit is 510 tons (the overall dimensions are approximately 39.4 × 20.6 × 21.5 m), classifying it as a high-risk lifting operation. Due to water and land transport restrictions and weight limits, the entire unit cannot be shipped from the factory as a whole; it must be disassembled into heavy components and transported to the shipyard dock for installation on board.
[0003] Existing shipyards mainly employ two implementation processes for this type of large marine elevator: The first method involves sequentially hoisting individual components onto the ship and assembling them in situ on the hull deck in the dock. All assembly, turning, pin assembly, and welding are completed at high altitude in the dock. The dock work area has a maximum elevation difference of 15m, involves multiple disciplines working simultaneously, and the maximum hoisting and docking height is 20m from the hull bottom. High-altitude work space is limited, wind disturbance is significant, and the cantilever beam installation accuracy requirements are: perpendicularity to the deck surface ≤5mm, parallelism to the hull centerline ≤2mm, and hull stiffener misalignment controlled to no more than 1 / 3 of the plate thickness. High-altitude assembly in this loose-piece assembly mode is difficult to control in terms of accuracy, and is highly prone to misalignment, exceeding tolerances, and rework. High-altitude primary hoisting operations are frequent, posing significant safety risks, and the crane's occupation period is long, making the project schedule uncontrollable. The second method involves unloading and transferring individual components at the dock, then directly hoisting them onto the ship and docking them with the hull. Components are not pre-assembled at the dock, and the connection and assembly of the cantilever beam and flat plate are all carried out at high altitude on the ship. While this method reduces some ground work, it still cannot avoid the challenges of high-altitude pin insertion and assembly; the configuration of lifting points and slings relies on the experience of construction personnel and lacks standardized collaborative turning processes; after the components are in place, the hooking is completely based on the experience of on-site personnel to judge the welding completion status. If the weld is not strong enough to bear the load, the hooking will be done in advance, and the component's own weight will cause displacement and deformation, which may lead to safety accidents in severe cases; if the hooking is done after the weld is 100% completed, the large crane will occupy the position for a long time, which is extremely costly.
[0004] Furthermore, when space is limited in the dockyard and multiple sets of elevator components coexist, there is a lack of sequential constraints for the transfer, pre-assembly, and hoisting of complete sets of components onto the ship. In dual-crane lifting operations, the selection of crawler cranes only considers the maximum lifting capacity without comprehensively taking into account lifting reduction factors and safety reserve factors, which can easily lead to safety hazards due to insufficient rated capacity of the cranes. Existing technology also lacks a temporary wind-resistant anchoring process for heavy cantilever beams after they have been turned over and positioned. Under gusts of wind in the dock, the cantilever beams are prone to swaying, making alignment and assembly difficult.
[0005] The shortcomings of existing technologies are: current shipboard installation processes involve completing many critical steps high up in the dock, making it difficult to consistently guarantee assembly accuracy and posing significant safety risks; at the same time, steps such as component turning, pin assembly, hook unhooking judgment, crane selection, wind resistance constraints, and site organization generally rely on experience-based judgment and lack standardized, quantifiable process methods. Specific shortcomings are as follows: 1. High-altitude operations are frequent, making it difficult to balance assembly precision and safety: The in-situ assembly process requires the assembly of cantilever beams and flat plates, pin assembly, and adjustment measurements to be carried out at a height of 20 meters in the dock. Due to the elevation difference, cross-operations, and wind load interference within the dock, it is difficult to consistently achieve high-precision indicators such as the verticality and parallelism of the cantilever beams. The high frequency of first-level high-risk hoisting operations places significant pressure on the safety management of personnel and equipment at height. 2. Lack of standardized multi-point collaborative technology for turning heavy components: Current construction lacks a gantry crane-assisted turning process for 145t cantilever beams; there is a lack of anti-slip restraint measures for hydraulic cylinders and telescopic box girders; the stress on lifting points and the configuration of slings during the turning process rely on experience, posing a risk of component slippage and overturning. 3. Lack of objective and quantifiable judgment standards for unhooking the entire machine: The industry generally relies on the subjective experience of welders and supervisors to determine whether unhooking is possible, lacking a hard indicator of weld completion; premature unhooking poses a risk of component deformation and instability; unhooking after all welds are completed results in large cranes being idle, leading to high economic costs. 4. Lack of quantitative calculation logic in the selection of dual-crane lifting equipment: When operating with two cranes simultaneously, the load reduction factor and lifting safety reserve factor for dual-crane lifting are not considered; the selection of crane boom length, working radius, and rated lifting capacity is based solely on experience, posing a risk of overloading. 5. Lack of reliable temporary wind-resistant constraints on components after turning and positioning: Before the cantilever beam is turned, the pin is locked, and it is connected to the hull, there are no standardized cable-stayed anchoring measures; in open-air dock operations, gusts of wind can cause components to sway and shift, increasing the difficulty of alignment. 6. Lack of clear grouping logic when the dock-dock space is limited: With four cantilever beams and two flat structure components present simultaneously, there is no clear pre-assembly or lifting sequence for loading onto the ship, easily leading to spatial interference between components and chaotic site layout.
[0006] Existing technology includes a device titled "A Cantilever Beam Device for Shipbuilding," with publication number "122725163A." This technology comprises a base assembly, a slewing bearing, a column, a cantilever beam body, a pitch drive mechanism, a counterweight balancing mechanism, a working platform, a platform leveling mechanism, and a safety locking mechanism. The column is mounted above the base assembly via the slewing bearing. The cantilever beam body consists of a sleeve-type outer beam and an inner beam. The inner end of the outer beam is hinged to a hinged lug on the upper end of the column, and the inner beam slides within the inner cavity of the outer beam and is driven to extend and retract by a telescopic cylinder. The pitch cylinder is hinged at both ends to the middle of the column and the lower side of the outer beam to drive the cantilever pitch. The counterweight balancing mechanism balances the cantilever load by driving a counterweight block to reciprocate along the extension beam. This invention has a reasonable structure, strong load-bearing capacity, flexible adjustment of the cantilever length and angle, automatic balancing and leveling, and is safe and reliable. It is suitable for various high-altitude operations such as welding, painting, and inspection in shipbuilding.
[0007] However, this technology does not address the technical issues and solutions of this application. Summary of the Invention
[0008] The technical problem to be solved by this invention is to provide a ship elevator installation method that addresses the shortcomings of existing technologies by placing many key processes at high altitudes in the dock, making it difficult to guarantee stable assembly accuracy and posing significant safety risks. Furthermore, the existing elevator installation process relies heavily on experience-based judgment in areas such as component turning, unhooking determination, crane selection, wind resistance constraints, and site organization, lacking standardized and quantifiable process methods.
[0009] To solve the above-mentioned technical problems, the technical solution adopted by the present invention is as follows: This invention relates to a method for installing a ship elevator, the installation steps of which are as follows: S1. The whole machine includes a cantilever beam and a flat plate mechanism. The support components are arranged at the dock, including multiple support frames one and multiple support frames two. The cantilever beam positioning part is set on the support frame one. The difference between the bottom height of the cantilever beam positioning part and the height of the support frame two is equal to the difference between the bottom of the cantilever beam and the height of the flat plate structure. S2. Hoist the flat plate structure onto the second support frame, then hoist the cantilever beam, control the cantilever beam 5 to rotate and place it in the cantilever beam positioning position, align the cantilever beam and the flat plate structure, and connect the cantilever beam and the flat plate structure. S3. The cantilever beam and flat plate structure form the complete elevator. The complete elevator is hoisted close to the ship's hull. The multiple alignment and connection parts of the cantilever beam are respectively brought into contact with the corresponding positions on the ship's hull. Each alignment and connection part is respectively connected to the corresponding position on the ship's hull to complete the installation of the complete elevator on the ship's hull.
[0010] Repeat steps S1 to S3 to complete the hoisting and connection of the cantilever beams and flat plate structures of the other complete machines, and to connect each alignment connection part to the corresponding position of the ship hull.
[0011] Multiple cantilever frames are installed on each flat plate structure. When arranging the support components at the dock, the flat plate structure is located on support frame two. The number and arrangement of support frame one correspond to the number and arrangement of cantilever frames.
[0012] When the cantilever beam positioning part is set on the shelf, the center line of the cantilever beam positioning part is parallel to the center line of the cantilever beam. When the cantilever beam is placed on the cantilever beam positioning part, the cantilever beam is set to be able to overlap the flat plate structure, and the positioning part of the cantilever beam and the positioning part of the flat plate structure are docked and positioned.
[0013] When hoisting the flat plate structure, the two sides of the flat plate structure are connected by the traction ropes of the gantry crane trolley. Before the flat plate structure is lowered, a ground-lift inspection is performed. The flat plate structure is lifted off the ground and held statically for a set time. After the inspection is passed, it is placed on the second support frame.
[0014] When hoisting the cantilever beam, the hook of the connecting rope of the upper trolley of the gantry crane is hooked to the top of the cantilever beam; the hook of the connecting rope of the lower trolley of the gantry crane is hooked to the lower part of the cantilever beam; one or more upper and lower trolleys of the gantry crane are provided, and the flat plate structure placed on the second support frame is in a horizontal state.
[0015] Before the cantilever beam is lowered, a ground-lift inspection is performed. The cantilever beam is lifted off the ground and held statically for a set time. After the inspection is passed, the upper trolley of the gantry crane continues to lift, while the lower trolley of the gantry crane slowly lowers simultaneously to complete the cantilever beam's flipping. The cantilever beam is kept in a vertical flat plate state until it is flipped into place. After the cantilever beam is in place, the connecting rope of the lower trolley of the gantry crane is removed.
[0016] When hoisting the entire machine, a dual-machine hoisting system is used, consisting of a gantry crane trolley and a crawler crane. The crane selection calculation logic is as follows: maximum lifting weight of the entire machine XT (tons); the load reduction factor A for dual-machine hoisting is 0.7-0.9, and the hoisting safety reserve factor B is 1.0-1.3; minimum rated lifting capacity C = XT ÷ A × B = CT; the rated lifting capacity of the crawler crane 11 must be ≥ CT.
[0017] When hoisting a flat structure, the hook at the lower end of the connecting rope of the upper trolley of the gantry crane is hooked onto the lifting lug on the flat structure. When hoisting a cantilever beam, the hook at the lower end of the connecting rope of the upper and lower trolleys of the gantry crane is hooked onto the lifting lug on the cantilever beam.
[0018] This invention also relates to a ship elevator installation device that can improve installation quality by addressing the challenges of existing elevator installation processes where many critical steps are completed high above the dock, making it difficult to guarantee stable assembly accuracy and posing significant safety risks. Furthermore, processes such as component turning, unhooking judgment, crane selection, wind resistance constraints, and site organization generally rely on experience-based judgment, lacking standardized and quantifiable process methods. The elevator assembly comprises a cantilever beam and a flatbed structure. The support components of the ship elevator installation device are arranged on the dock. Each support component includes multiple support frames (first and second). A cantilever beam positioning part is installed on support frame one. The difference between the bottom height of the cantilever beam positioning part and the height of support frame two is equal to the difference between the bottom height of the cantilever beam and the height of the flatbed structure. When the cantilever beam positioning part is installed on support frame one, the centerline of the cantilever beam positioning part is parallel to the centerline of the cantilever beam, and the positioning parts of the cantilever beam and the flatbed structure are docked and positioned. The device also includes a gantry crane and a crawler crane.
[0019] The working principle and beneficial effects of the technical solution adopted in this invention are as follows: The ship elevator installation method described in this invention offers the following benefits: 1. Safety benefits: Significantly reduces high-risk high-altitude operations: The cantilever beam turning and cantilever beam-flat plate structure assembly are transferred to the dock surface; reducing high-altitude operations due to dock height restrictions and decreasing the frequency of first-level high-risk hoisting operations; guy rope anchoring and hydraulic cylinder stop mechanical limit avoid the risk of component slippage and overturning during the turning and positioning stages; the dual-machine hoisting adopts quantitative selection calculations to avoid the risk of overloading during lifting. 2. Assembly quality benefits: Stably meets high-precision installation indicators: The ground pre-assembly operation environment is open, and the measurement and adjustment conditions are better than at high altitudes; it can stably achieve the perpendicularity of the cantilever beam to the deck surface, the parallelism with the ship's centerline, and the control of stiffener misalignment; symmetrical welding process suppresses welding deformation. 3. Process control benefits: Establishes objective and reproducible quantitative criteria: Abandoning on-site personnel's experience-based unhooking, the percentage completion of all three butt welds is used as a hard condition for unhooking; this indicator takes into account both structural load-bearing safety and crane shift costs, and is recordable, inspectable, and reproducible, facilitating process quality control. 4. In terms of economic benefits, this process shortens the construction period and saves on large crane shifts: Compared to the original hull assembly method, this process can reduce high-altitude assembly time, shortening the overall installation period by approximately [percentage missing]. Under the premise of ensuring structural safety, it eliminates the need to wait for 100% completion of welds before unhooking, reducing the ineffective standby time of large gantry cranes and crawler cranes, and significantly lowering the cost of heavy crane shifts. 5. Strong site adaptability and replicable and scalable process: It clarifies the sequential construction logic of the two sets of complete machines when dock space is limited, solving the interference problem of multiple components being placed on the same site. The entire process can be extended to other segmented, large-tonnage marine deck heavy-duty equipment dock pre-assembly-dual-crane lifting and installation scenarios. This effectively improves the applicability of the method and equipment. Attached Figure Description
[0020] The following is a brief explanation of the contents depicted in the accompanying drawings and the markings therein: Figure 1 This is a front view schematic diagram of the support frame arrangement in the ship elevator installation method described in this invention. Figure 2 This is a top view of the support frame arrangement in the ship elevator installation method of the present invention. Figure 3 This is a schematic diagram of the cantilever beam hoisting structure of the ship elevator installation method described in this invention; Figure 4 This is a schematic diagram of the cantilever beam hoisting structure of the ship elevator installation method described in this invention; Figure 5 This is a schematic diagram of the flat plate structure hoisting method for the ship elevator installation method described in this invention; Figure 6 This is a schematic diagram of the flat plate structure hoisting method for the ship elevator installation method described in this invention; Figure 7 This is a schematic diagram of the cantilever beam turning structure in the ship elevator installation method described in this invention; Figure 8 This is a schematic diagram of the cantilever beam hoisting structure of the ship elevator installation method described in this invention; Figure 9 This is a schematic diagram of the cantilever beam turning over in the ship elevator installation method described in this invention. Figure 10 This is a schematic diagram of the arrangement structure of the cantilever beam on the support frame in the ship elevator installation method described in this invention; Figure 11 This is a schematic diagram of the cable and guy rope system layout structure after the cantilever beam is in place in the ship elevator installation method of the present invention. Figure 12 This is a schematic diagram of the flat plate structure of the ship elevator installation method described in this invention, arranged on the support frame. Figure 13 This is a schematic diagram of the overall hoisting structure of the ship elevator installation method described in this invention; Figure 14 This is a schematic diagram of the overall hoisting structure of the ship elevator installation method described in this invention; Figure 15 This is a schematic diagram of the structure of the dual-machine tandem hoisting system and its docking with the ship hull in the ship elevator installation method described in this invention; Figure 16 This is a structural schematic diagram of the three alignment connections between the cantilever beam and the hull in the ship elevator installation method described in this invention. Figure 17This is a schematic diagram of the gantry crane and crawler crane used in the ship elevator installation method described in this invention; Figure 18 This is a schematic diagram of the gantry crane and crawler crane used in the ship elevator installation method described in this invention; Figure 19 This is a schematic diagram of the structure when the entire elevator and the ship hull are properly connected in the installation method of the ship elevator described in this invention; Figure 20 This is a schematic diagram of the structure when the entire elevator and the ship hull are properly connected in the installation method of the ship elevator described in this invention; Figure 21 This is a schematic diagram of the structure when the entire elevator and the ship hull are properly connected in the installation method of the ship elevator described in this invention; The labels in the attached diagram are as follows: 1. Shelving frame one; 2. Shelving frame two; 3. Wharf; 4. Cantilever beam positioning part; 5. Cantilever beam; 6. Flat plate mechanism; 7. Alignment connection part; 8. Gantry crane upper trolley; 9. Connecting rope; 10. Gantry crane lower trolley; 11. Crawler crane; 12. Ship hull; 13. Guy rope. Detailed Implementation
[0021] The following description, with reference to the accompanying drawings, provides a more detailed explanation of the specific embodiments of the present invention, including the shape and structure of each component, the relative positions and connections between the parts, the functions and working principles of each part: As attached Figure 1 - Appendix Figure 21 As shown, the present invention is a method for installing a ship elevator.
[0022] The installation steps of the aforementioned ship elevator installation method are as follows: S1. The complete machine includes a cantilever beam 5 and a flat plate structure 6. Support components are arranged on the dock 3, including multiple support frames 1 and multiple support frames 2. A cantilever beam positioning part 4 is installed on the support frame 1. The difference between the bottom height of the cantilever beam positioning part 4 and the height of the support frame 2 is equal to the difference between the bottom height of the cantilever beam 5 and the height of the flat plate structure 6. S2. The flat plate structure 6 is hoisted and placed on the support frame 2, and then the cantilever beam 5 is hoisted. The cantilever beam 5 is controlled to rotate and placed in the position of the cantilever beam positioning part 4. The cantilever beam 5 and the flat plate structure 6 are aligned and connected. S3. The cantilever beam 5 and the flat plate structure 6 form the complete elevator. The complete elevator is hoisted close to the ship hull 12. Multiple alignment connection parts 7 of the cantilever beam 5 are respectively brought into contact with corresponding positions on the ship hull 12. Each alignment connection part 7 is connected to its corresponding position on the ship hull 12, completing the installation of the complete elevator on the ship hull 12. The above steps address the shortcomings of existing technologies and propose improved technical solutions. The overall process of the ship elevator installation method of this invention is as follows: all processes such as the assembly, alignment, and cantilever beam flipping of the elevator's cantilever beam-flat structure are completed on the dock surface. After the entire machine is pre-assembled to form the elevator assembly, it is then hoisted onto the ship and connected to the ship's hull using a dual-crane gantry crane. When hoisting the flat structure, it can be done using a gantry crane trolley 8. The gantry crane trolley 8 connects to both sides of the flat structure 6 via traction ropes 9 on each side, allowing for reliable hoisting and placement onto the support frame 2. When hoisting the cantilever beam, multiple lifting points of the gantry crane's upper and lower trolleys are coordinated to lift the 100-ton cantilever beam horizontally and place it into the cantilever beam positioning part 4 of the support frame. After turning it to a vertical position and positioning the cantilever beam, guy ropes are installed on the upper part of the cantilever beam at an angle of 45-60°. After the guy ropes are installed, the lifting points of the gantry crane's upper and lower trolleys are removed. Then, the cantilever beam and the flat structure are reliably aligned and welded together to form the complete elevator. The complete elevator is then hoisted, and each alignment connection 7 of the cantilever beam is connected to its corresponding position on the ship's hull 12 to complete the installation of the complete elevator on the ship's hull 12. When connecting each alignment connection 7 to its corresponding position on the ship's hull 12, welding is used, and the completion rate of each weld must reach more than 60% before the elevator can be released from hoisting. The ship elevator installation method described in this invention allows the assembly of the entire elevator to be unaffected by the dock space and eliminates the need to weld individual parts onto the ship. Instead, the cantilever beam and flat structure are first assembled on the support frame assembly on the dock, and then hoisted onto the ship hull for welding. This achieves the goals of improving assembly accuracy, reducing high-altitude risks, shortening the construction period, and controlling crane costs.
[0023] Repeat steps S1-S3 to complete the hoisting and connection of the cantilever beams 5 and flat plate structures 6 of the other complete machines, and to complete the connection of each alignment connection 7 to the corresponding position of the ship hull 12. The lifting frame of the present invention requires multiple complete lifting machines. Therefore, multiple complete lifting machines can be assembled sequentially on the support frame assembly arranged on the dock, and then each complete lifting machine can be hoisted to the corresponding position of the ship hull in sequence, followed by alignment and welding.
[0024] Multiple cantilever frames 5 are installed on each flat plate structure 6. When the supporting components are arranged on the dock 3, the flat plate structure 6 is located on the second supporting frame 2. The number and arrangement of the first supporting frame 1 correspond to the number and arrangement of the cantilever frames 5. Based on the actual needs of different complete elevator systems, the above steps involve setting a corresponding number of cantilever frames on a corresponding flat plate structure 6. The cantilever frames need to be installed perpendicular to the flat plate structure. Therefore, when connecting the cantilever frames and the flat plate structure, they are first connected on the first and second supporting frames arranged on the dock. The first supporting frame not only supports the cantilever frames but also positions them. Through the positioning of the cantilever frames and the flat plate structure, their alignment is achieved, and then they are welded together to achieve a fixed connection.
[0025] When the cantilever beam positioning part 4 is installed on the first support frame 1, the center line of the cantilever beam positioning part 4 is parallel to the center line of the cantilever beam 5. When the cantilever beam 5 is placed on the cantilever beam positioning part 4, the cantilever beam 5 is configured to overlap the flat plate structure 5, and the positioning parts of the cantilever beam 5 and the positioning parts of the flat plate structure 6 are docked and positioned. When hoisting the flat plate structure 6, the two sides of the flat plate structure 6 are connected by the traction ropes 9 of the gantry crane trolley 8. Before the flat plate structure 6 is lowered, a lifting inspection is performed. The flat plate structure 6 is lifted off the ground and held statically for a set time. After passing the lifting inspection, it is placed on the second support frame 2. In the above structure, the lifting of the flat plate structure is completed by a crane, so that the flat plate structure 6 is arranged on the second support frame, parallel to the wharf. When hoisting the cantilever beam 5, the hooks of the connecting ropes 9 of the upper trolley 8 of the gantry crane are attached to the top of the cantilever beam 5; the hooks of the connecting ropes 9 of the lower trolley 10 of the gantry crane are attached to the lower part of the cantilever beam 5; one or more upper trolleys 8 and lower trolleys 10 are provided, and the flat plate structure 6 placed on the support frame 2 is in a horizontal state. The hoisting of the cantilever beam 5 is accomplished by two sets of gantry cranes, namely the upper trolley 8 and the lower trolley 10, which not only achieves hoisting but also turning over.
[0026] Before the cantilever beam 5 is lowered, a ground-lift inspection is performed. The cantilever beam 5 is lifted off the ground and held statically for a set time. After the inspection is passed, the upper trolley 8 of the gantry crane continues to lift, and the lower trolley 10 of the gantry crane is lowered slowly at the same time to complete the flipping of the cantilever beam 5 until the cantilever beam 5 is in a vertical flat plate structure 6 state. After the flipping is in place, the connecting rope 10 of the lower trolley 10 of the gantry crane is removed.
[0027] During the hoisting of the entire machine, a dual-crane system is used, consisting of a gantry crane trolley 8 and a crawler crane 11. The crane selection calculation logic is as follows: maximum lifting weight XT (T is the unit of weight: tons); the dual-crane lifting load reduction factor A is taken as 0.7-0.9, and the hoisting safety reserve factor B is taken as 1.0-1.3; the minimum rated lifting capacity C = XT ÷ A × B = CT; the rated lifting capacity of crawler crane 11 must be ≥ CT. The above steps require two sets of cranes to move the entire elevator closer to the ship's hull for welding connection.
[0028] When hoisting the flat plate structure 6, the hook at the lower end of the connecting rope 9 of the upper trolley 8 of the gantry crane hooks onto the lifting lug on the flat plate structure 6. When hoisting the cantilever beam 5, the hook at the lower end of the connecting rope 9 of the upper trolley 8 and the lower trolley 10 of the gantry crane hooks onto the lifting lug on the cantilever beam 5.
[0029] This invention also relates to a ship elevator installation device that can improve installation quality by addressing the problems of existing elevator installation processes where many critical steps are completed high above the dock, making it difficult to guarantee stable assembly accuracy and posing significant safety risks. Furthermore, the device relies heavily on experience for component turning, unhooking judgment, crane selection, wind resistance constraints, and site organization, lacking standardized and quantifiable process methods. The elevator assembly includes a cantilever beam 5 and a flat structure 6. The support components of the ship elevator installation device are arranged on the dock 3. These support components include multiple support frames 1 and multiple support frames 2. A cantilever beam positioning part 4 is provided on support frame 1. The difference between the bottom height of the cantilever beam positioning part 4 and the height of support frame 2 is equal to the difference between the bottom height of the cantilever beam 5 and the height of the flat structure 6. When the cantilever beam positioning part 4 is provided on support frame 1, the centerline of the cantilever beam positioning part 4 is parallel to the centerline of the cantilever beam 5, and the positioning parts of the cantilever beam 5 and the flat structure 6 are docked and positioned. The device also includes a gantry crane and a crawler crane 11.
[0030] The following describes the installation method of the ship elevator according to the present invention using the installation of a specific model of ship elevator as an example. The method of the present invention is used for the installation of large ship elevators, as follows: The aforementioned elevator comprises four cantilever beams and two flat plate structure components, with the two cantilever beams and one flat plate structure forming a complete unit; the installation method includes the following steps: The cantilever beam components arrived at the dock by water transport. The cantilever beam was unloaded using its own 80T and 50T lifting lugs (see Figure 3). Figure 4 The flat panel structure component utilizes its built-in 40T lifting lugs for horizontal lifting and unloading, as shown in Figure 5. Figure 6Unloading sling configuration: For both cantilever beams and flat structures, four connecting ropes (steel wire ropes) meeting safety requirements are used for unloading, along with four corresponding shackles (safety factor calculated at five times). Lifting inspection: The crane lifts the cantilever beam or flat structure 100mm off the dock ground, holds it under load for 3 minutes, and inspects the crane's condition, wire ropes, shackles, and lifting lugs. The crane's braking system is tested, and only after confirming there are no abnormalities can it be lowered to the designated placement area on the dock. Following the order of Group 1: Cantilever Beam 3, Cantilever Beam 4 and corresponding flat structures; Group 2: Cantilever Beam 1, Cantilever Beam 2 and corresponding flat structures, they are sequentially transferred to the dock pre-assembly area. The corresponding group of cantilever beams and flat structures will be combined to form the complete machine.
[0031] When designing Shelf 1 and Shelf 2 of the shelving assembly, corresponding heights need to be set. The heights must be greater than a certain value to ensure that the cantilever beam and flat plate structure will not touch the ground after being placed on the shelving. Furthermore, the height difference between Shelf 1 and Shelf 2 needs to be strictly controlled, and the height difference should be the theoretical height difference between the cantilever beam and the flat plate structure. Thin wooden boards or burlap pads should be laid at the contact points between the flat plate and the shelving to prevent the components from slipping or bumping.
[0032] The top lifting lugs of the flat plate structure are attached by a double hook on the trolley of the gantry crane (Figure 4). Figure 5 A connecting rope is installed on each side of the flat plate structure for lifting and attitude control; a 100mm lift inspection is performed, and the load is maintained for 3 minutes; the flat plate structure is smoothly lowered onto the assembly fixture and support frame 2 (Figure 2); the crane is slowly unloaded, and the flat plate is observed for 3 minutes to confirm that there is no risk of slippage or overturning. Then, the hook is released, that is, the connecting rope for lifting the flat plate structure is separated from the flat plate structure.
[0033] The upper trolley of the gantry crane uses double hooks to attach to the four 80T lifting lugs at the top of the cantilever beam; the lower trolley of the gantry crane uses a single hook to attach to the 50T lifting lug at the bottom of the cantilever beam. See the lifting point arrangement for details. Figure 7 , Figure 8 Traction ropes are installed on both sides of the cantilever beam; the breaking strength and safety factor of each sling are checked at five times; ground lifting test: lift 100mm off the ground, hold the load for 3 minutes, and test the braking performance of the upper and lower trolleys; lift the cantilever beam to a height of about 10m off the ground and wait for the component to stabilize; through coordinated control: the upper trolley of the gantry crane continues to lift, and the lower trolley of the gantry crane slowly lowers synchronously, completing a 90° turn of the cantilever beam, changing the cantilever beam from a near-horizontal state to a near-vertical state. The change in the turning posture is shown in [the diagram]. Figure 9 After the crane is turned into position, remove all the slings corresponding to the hooks of the gantry crane's lower trolley.
[0034] After adjusting the cantilever beam's posture, move it to the assembly position to achieve precise alignment between the cantilever beam and the flat structure; slowly unload the crane, observe for 3 minutes to confirm component stability, then release the crane hook; immediately deploy the temporary guy rope anchoring system, see [link to relevant documentation]. Figure 11 The cantilever beam is reliably positioned by connecting the upper lifting lugs of the cantilever beam to the pre-embedded ground anchors using six 10m 10T slings, six 17T shackles, and four turnbuckle tensioners. The angle between the guy ropes and the main body of the cantilever beam is controlled between 45° and 60°. The laying sequence is to pull the outer side first, then the inner side. The operation sequence is strictly as follows: first lay one guy rope, then remove one lifting point, and work alternately point by point. It is forbidden for the component to be suspended in the air without restraint.
[0035] The method of this invention requires repeating the corresponding steps to connect different sets of cantilever beam components and to the ship's hull. Different cantilever beams need to be connected using connecting fixtures (four fixtures in total, each weighing 15t) to reliably and rigidly connect and fix two cantilever beams, forming a complete elevator structure consisting of a flat plate structure and cantilever beams. After confirming that all bolts on the connecting fixtures are tightened in place, all guy ropes are removed, completing the ground pre-assembly of a single elevator unit. The total weight of a single unit is 510t. See Figure 12 for the lifting points of the entire unit.
[0036] The gantry crane's trolley is hooked onto the 100T lifting lugs on the inner side of the main beam of the entire machine via double hooks, as shown in Figure 12. Figure 13 The sling configuration consists of eight 20m / 100T slings and eight matching 100T shackles; traction ropes are arranged on both sides of the machine; a 100mm lift inspection is performed, and the machine is held in place for 3 minutes; the machine is then raised to approximately 35m off the ground (the lowest point of the machine is ≥1m higher than the ship's hull structure along the transfer path) to avoid interference during transfer; the gantry crane is moved to transfer the machine to the side of the ship; the machine is then placed on a temporary support fixture set on the bow of the ship, and after static observation to confirm stability, the hook is released.
[0037] Crane selection calculation logic: Maximum lifting weight of the whole machine is 309.6T; the load reduction factor for dual-crane lifting is 0.8; the lifting safety reserve factor is 1.25; Minimum rated lifting capacity = 309.6T ÷ 0.8 × 1.25 = 483.75T; the rated lifting capacity of the crawler crane must be ≥ 483.75T; In this embodiment, an 800T crawler crane is selected, with a main boom length of 78m and a working radius of 24m. The rated lifting capacity under this working condition is 494T, which meets the calculation requirements. See Figure 16 for the crawler crane's position and operating parameters; The gantry crane's trolley and the crawler crane are respectively attached to the 100T lifting lugs on the inner side of the main beam of the whole machine. The sling configuration uses 8 x 20m / 100T slings with 8 matching 100T shackles; traction ropes are arranged on both sides of the whole machine. See Figure 14 for the assembly diagram of dual-crane lifting. The two cranes simultaneously lift the load 100mm off the ground and hold it at rest for 3 minutes. The braking systems, slings, and lifting lugs of both the gantry crane and crawler crane are then inspected to confirm no abnormalities. The two cranes work in tandem, with the gantry crane slowly lifting approximately 21m to align the entire machine with the three docking points on the hull. The locations of the docking welds are shown in Figure 11. Welders on both sides simultaneously and symmetrically weld to suppress welding deformation. The mandatory condition for unhooking is that the weld completion rate at each of the three docking points between the cantilever beam and the hull must reach 67% before unhooking can proceed. Unhooking operation: The gantry crane and crawler crane simultaneously and slowly unload the load, gradually releasing the load through the slings. The crane is held at rest for 3 minutes to confirm no displacement or deformation of the entire machine before releasing the slings sequentially.
[0038] Due to space constraints at the dock, the work sequence is as follows: complete the ground pre-assembly of the first group (cantilever beams three and four + corresponding flat structures) and the docking of the two cranes onto the ship; then carry out the second group (cantilever beams one and two + corresponding flat structures) to complete the installation of the entire elevator system.
[0039] The installation method described in this invention transfers the connection between the cantilever beam and the flat structure from high altitude to the dock ground, significantly reducing high-altitude operations; the height difference of the support frame matches the assembly posture of the components; the upper and lower trolleys coordinate multiple lifting points, and with the mechanical limit of the hydraulic cylinder stop plate, the heavy cantilever beam can be safely turned over; when the cantilever beam is horizontally lifted before turning over, the upper trolley's double hooks are single lifting points with no diagonal tension, while the lower trolley's single hook is a double lifting point with diagonal tension, and the force on the lifting lug on the top side away from the hydraulic cylinder is negligible; after turning over 90°, only the four lifting lugs on the upper side are subjected to force, the angle between the upper trolley's double hooks is small, and the diagonal tension is negligible; the guy rope system and the operation sequence of "pulling the guy rope first, then removing the lifting points" solve the risk of component swaying and instability under gusts of wind in open docks; the three alignment connection parts 7 (connection positions) all achieve 67%. Weld completion rate serves as an objective indicator for unhooking, replacing subjective human experience; it ensures the load-bearing capacity of the weld while avoiding prolonged crane standby; it establishes a quantitative calculation formula for dual-machine lifting to determine the minimum rated lifting capacity of the crawler crane and avoid the risk of overloading during lifting; it clarifies the construction sequence of the two sets of machines under site constraints to avoid spatial interference between components.
[0040] The beneficial effects of the method and apparatus of this invention are as follows: 1. Safety benefits: Significantly reduces high-risk high-altitude operations: The cantilever beam turning and cantilever beam-flat plate structure assembly are transferred to the dock ground for implementation; reducing high-altitude operations at a height of 20m in the dock and reducing the frequency of first-level high-risk hoisting operations; guy rope anchoring and hydraulic cylinder stop mechanical limit avoid the risk of component slippage and overturning during the turning and positioning stages; the dual-machine hoisting adopts quantitative selection calculation to avoid the risk of overloading during lifting. 2. Assembly quality benefits: Stably meets high-precision installation indicators: The ground pre-assembly operation environment is open, and the measurement and adjustment conditions are better than those at high altitudes; it can stably achieve a cantilever beam perpendicularity to the deck surface ≤5mm, parallelism to the ship's centerline ≤2mm, and stiffener misalignment control ≤1 / 3 of the plate thickness; symmetrical welding process suppresses welding deformation. 3. Process Control Benefits: Establishing objective and reproducible quantitative criteria: Abandoning on-site personnel's experience-based unhooking, adopting the requirement that all three butt welds be 67% complete as a mandatory condition for unhooking; this indicator balances structural load-bearing safety and crane operating costs, is recordable, inspectable, and reproducible, facilitating process quality control. 4. Economic Benefits: Shortening the construction period and saving on large crane operating costs: Compared to the in-situ bulk assembly method, this process can reduce high-altitude assembly time by more than 40%, shortening the overall installation period by approximately 30%; under the premise of ensuring structural safety, unhooking can be performed without waiting for 100% completion of welds, reducing the ineffective standby time of large gantry cranes and crawler cranes, and significantly reducing heavy crane operating costs. 5. Strong site adaptability and replicable and scalable process: Clearly defines the sequential construction logic of the two sets of complete machines when dock space is limited, resolving interference issues caused by placing multiple components on the same site; the entire process is not only applicable to 350T large marine elevators, but can also be extended to other segmented, large-tonnage marine deck heavy-duty equipment dock pre-assembly-dual-machine lifting and installation scenarios. This effectively improves the applicability of the method and equipment.
[0041] The present invention has been described above by way of example with reference to the accompanying drawings. Obviously, the specific implementation of the present invention is not limited to the above-described manner. Any improvements made by adopting the inventive concept and technical solution of the present invention, or the direct application of the inventive concept and technical solution of the present invention to other occasions without modification, are all within the protection scope of the present invention.
Claims
1. A method for installing a ship elevator, characterized in that: The installation steps of the aforementioned ship elevator installation method are as follows: S1. The whole machine includes a cantilever beam (5) and a flat plate mechanism (6). The support components are arranged on the dock (3), including multiple support frames one (1) and multiple support frames two (2). The cantilever beam positioning part (4) is set on the support frame one (1). The difference between the bottom height of the cantilever beam positioning part (4) and the height of the support frame two (2) is equal to the difference between the bottom of the cantilever beam (5) and the height of the flat plate structure (6). S2. Hoist the flat plate structure (6) onto the second shelf (2), then hoist the cantilever beam (5), control the cantilever beam (5) to flip and place it in the position of the cantilever beam positioning part (4), align the cantilever beam (5) and the flat plate structure (6), and connect the cantilever beam (5) and the flat plate structure (6). S3. The cantilever beam (5) and the flat plate structure (6) form the complete elevator. The complete elevator is hoisted close to the ship hull (12). The multiple alignment connection parts (7) of the cantilever beam (5) are respectively contacted with the corresponding positions of the ship hull (12). Each alignment connection part (7) is respectively connected to the corresponding position of the ship hull (12) to complete the installation of the complete elevator on the ship hull (12).
2. The method for installing a ship elevator according to claim 1, characterized in that: Repeat steps S1 to S3 to complete the hoisting and connection of the cantilever beams (5) and flat plate structures (6) of the other complete machines, and to complete the connection of each alignment connection part (7) to the corresponding position of the ship hull (12).
3. The method for installing a ship elevator according to claim 1 or 2, characterized in that: Multiple cantilever frames (5) are set on each flat structure (6). When the mounting components are arranged at the dock (3), the flat structure (6) is located on the second mounting frame (2). The number and arrangement position of the first mounting frame (1) correspond to the number and arrangement position of the cantilever frames (6).
4. The method for installing a ship elevator according to claim 1 or 2, characterized in that: When the cantilever beam positioning part (4) is set on the shelf (1), the center line of the cantilever beam positioning part (4) is parallel to the center line of the cantilever beam (5). When the cantilever beam (5) is placed on the cantilever beam positioning part (4), the cantilever beam (5) is set to be able to overlap the flat plate structure (5), and the positioning part of the cantilever beam (5) and the positioning part of the flat plate structure (6) are docked and positioned.
5. The method for installing a ship elevator according to claim 1 or 2, characterized in that: When hoisting the flat plate structure (6), the two sides of the flat plate structure (6) are connected by the traction rope (9) of the gantry crane trolley (8). Before the flat plate structure (6) is lowered, a ground-lifting inspection is performed. The flat plate structure (6) is lifted off the ground and left to stand for a set time. After the inspection is passed, it is placed on the second shelf (2).
6. The method for installing a ship elevator according to claim 1 or 2, characterized in that: When hoisting the cantilever beam (5), the hook of the connecting rope (9) of the upper trolley (8) of the gantry crane is hooked to the top position of the cantilever beam (5); the connecting rope (9) of the lower trolley (10) of the gantry crane is hooked to the lower position of the cantilever beam (5); one or more upper trolleys (8) and lower trolleys (10) of the gantry crane are provided, and the flat plate structure (6) placed on the second shelf (2) is in a horizontal state.
7. The method for installing a ship elevator according to claim 6, characterized in that: Before the cantilever beam (5) is lowered, a lifting inspection is performed. The cantilever beam (5) is lifted off the ground and left to stand for a set time. After the lifting inspection is qualified, the upper trolley (8) of the gantry crane continues to lift, and the lower trolley (10) of the gantry crane is lowered slowly at the same time to complete the turning of the cantilever beam (5) until the cantilever beam (5) is in the state of a vertical flat plate structure (6). After turning into place, the connecting rope (10) of the lower trolley (10) of the gantry crane is removed.
8. The method for installing a ship elevator according to claim 1 or 2, characterized in that: When hoisting the entire machine, a dual-machine hoisting crane is used, namely a gantry crane trolley (8) and a crawler crane (11). The crane selection calculation logic is as follows: the maximum lifting weight of the entire machine is XT (tons); the load reduction factor A for dual-machine hoisting is 0.7-0.9, and the hoisting safety reserve factor B is 1.0-1.3; the minimum rated lifting capacity C = XT ÷ A × B = CT; the rated lifting capacity of the crawler crane (11) must be ≥ CT.
9. The method for installing a ship elevator according to claim 5, characterized in that: When hoisting the flat plate structure (6), the hook at the lower end of the connecting rope (9) of the gantry crane trolley (8) hooks onto the lifting lug on the flat plate structure (6). When hoisting the cantilever beam (5), the hook at the lower end of the connecting rope (9) of the gantry crane trolley (8) and the gantry crane lower trolley (10) hooks onto the lifting lug on the cantilever beam (5).
10. The ship elevator installation device according to any one of claims 1 to 9, characterized in that: The elevator assembly includes a cantilever beam (5) and a flat plate structure (6). The mounting components of the ship elevator installation device are arranged on the dock (3). The mounting components include multiple mounting frames one (1) and multiple mounting frames two (2). A cantilever beam positioning part (4) is set on the mounting frame one (1). The difference between the bottom height of the cantilever beam positioning part (4) and the height of the mounting frame two (2) is equal to the difference between the bottom height of the cantilever beam (5) and the height of the flat plate structure (6). When the cantilever beam positioning part (4) is set on the mounting frame one (1), the center line of the cantilever beam positioning part (4) is parallel to the center line of the cantilever beam (5), and the positioning parts of the cantilever beam (5) and the positioning parts of the flat plate structure (6) are docked and positioned. It also includes a gantry crane and a crawler crane (11).