High durability assembled pavement structure and construction method thereof

By optimizing the prefabricated pavement structure and joint design, the problems of loose base layer, voids at the bottom of the slab, and interlayer slippage have been solved, resulting in a prefabricated pavement with high durability and good drainage performance, which is suitable for the field of road structure.

CN123133243APending Publication Date: 2026-11-20FIRST METALLURGICAL IND (YICHANG) CONSTRUCTION INVESTMENT CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611521715.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-29
Publication Date
2026-11-20

AI Technical Summary

Technical Problem

Traditional prefabricated pavements suffer from problems such as loose base layers, voids at the bottom of slabs, slippage between layers, and poor drainage, resulting in insufficient structural durability.

Method used

The structure consists of a cement-stabilized crushed stone subbase, slurry seal, crushed stone upper base, concrete pavement, rubber-modified synchronous crushed stone seal, and asphalt layer. Combined with limiting hard shoulders, anti-skid piles, and transverse drainage pipes, the joint design is optimized to enhance load-bearing capacity and drainage performance.

Benefits of technology

It improves the anti-skid ability and drainage performance of the pavement structure, prevents loosening and voiding, extends the service life of the pavement, and reduces the total life cycle cost.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123133243A_ABST
    Figure CN123133243A_ABST
Patent Text Reader

Abstract

The application relates to a high-durability assembled pavement structure and a construction method thereof, and relates to the field of road structures. The high-durability assembled pavement structure comprises, from bottom to top, a roadbed, a cement stabilized macadam lower base layer, a slurry seal layer, a macadam upper base layer, a concrete pavement slab, a rubber modified synchronous macadam seal layer and an asphalt layer; the top of the cement stabilized macadam lower base layer is provided with limiting hard road shoulders located on the two sides of the slurry seal layer, the macadam upper base layer, the concrete pavement slab, the rubber modified synchronous macadam seal layer and the asphalt layer; a plurality of anti-skid piles and a transverse drainage pipe are embedded in the limiting hard road shoulders; the bottom of the anti-skid piles penetrates through the cement stabilized macadam lower base layer and is inserted into the roadbed; one end of the transverse drainage pipe extends to the macadam upper base layer, and the other end extends out of the limiting hard road shoulder. The high-durability assembled pavement structure and the construction method thereof solve the problems that the traditional assembled pavement base layer is easy to be damaged by water, the bottom of the slab is easy to be empty, and the layers are easy to slide; and the high-durability assembled pavement structure and the construction method thereof have the advantages of good drainage performance and strong anti-sliding capacity.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This application relates to the field of road structures, and more specifically, to a highly durable prefabricated pavement structure and its construction method. Background Technology

[0002] Prefabricated pavement, as a pavement structure that can be prefabricated in a factory and quickly installed on site, conforms to the development trend of modern pavement structures. Compared with traditional cast-in-place cement concrete pavement, prefabricated pavement has advantages such as good quality stability, high precision of formwork installation, controllable maintenance conditions, reusable production equipment, good environmental performance, low requirements for construction environment, and rapid opening to traffic.

[0003] However, existing prefabricated pavements mostly adopt a single cement concrete panel prefabrication scheme without targeted innovative design for the overall pavement structure and joint construction. The following problems exist in the application process: First, the base layer mostly adopts the traditional cement-stabilized crushed stone structure, which is prone to loosening and pumping under the action of dynamic water pressure, causing the pavement panel bottom to detach and misalign. Second, the interlayer bonding between the pavement panel and the base layer and surface layer is insufficient, which easily leads to surface layer displacement, pavement panel slippage and other defects. Third, the internal drainage system of the pavement is imperfect, and seepage water cannot be discharged in time, which accelerates the process of structural water damage. Summary of the Invention

[0004] The purpose of this application is to provide a highly durable prefabricated pavement structure and its construction method, which solves the problems of easy water damage to the base layer, easy voiding at the bottom of the slab, and easy slippage between layers in traditional prefabricated pavement, and has the advantages of good drainage performance and strong anti-slip ability.

[0005] This application is implemented as follows: This application provides a highly durable prefabricated pavement structure, which includes, from bottom to top, a roadbed, a cement-stabilized crushed stone subbase, a slurry seal, a crushed stone upper base, a concrete pavement slab, a rubber-modified synchronous crushed stone seal, and an asphalt layer. The cement-stabilized crushed stone subbase is topped with limiting hard shoulders located on both sides of the slurry seal, crushed stone upper base, concrete pavement slab, rubber-modified synchronous crushed stone seal, and asphalt layer. Multiple anti-skid piles and transverse drainage pipes are embedded within the limiting hard shoulders, arranged at intervals along the length of the pavement. The transverse drainage pipes are arranged along the width of the pavement, with one end extending to the crushed stone upper base and the other end extending out of the limiting hard shoulder. The bottom of the anti-skid piles penetrates the cement-stabilized crushed stone subbase and inserts into the roadbed.

[0006] In some alternative implementations, two adjacent concrete pavement slabs are connected along the length of the pavement by a transverse joint structure. The transverse joint structure includes multiple plain round bearing steels with one end embedded inside one end of the concrete pavement slab, and a boss protruding from the bottom of the other end face of the concrete pavement slab. Each plain round bearing steel is fitted with a bearing steel sleeve. The boss has embedded installation grooves for accommodating each bearing steel sleeve. Multiple U-shaped anchoring steel bars are pre-embedded on the upper bottom and side surfaces of the other end of the concrete pavement slab. The top surface of the boss is filled with a first ultra-high performance early strength concrete layer that wraps the anchoring steel bars and the bearing steel sleeves.

[0007] In some alternative implementations, the transverse joint structure includes a joint filler plate at one end of the concrete pavement slab and a joint filler layer on top of the joint filler plate. The joint filler plate is disposed between two adjacent concrete pavement slab end faces, and the two sides of the joint filler layer are respectively connected to a first ultra-high performance early strength concrete layer and the concrete pavement slab end face.

[0008] In some alternative implementations, the top surface of the transverse joint structure is covered with a road-specific waterproof membrane layer.

[0009] In some alternative implementations, two adjacent concrete pavement slabs are connected by a longitudinal construction joint structure along the width of the pavement. The longitudinal construction joint structure includes multiple U-shaped threaded steel bars respectively located on both sides of the concrete pavement slabs and a second ultra-high performance early strength concrete layer filling the space between the two adjacent concrete pavement slabs along the width of the pavement. The second ultra-high performance early strength concrete layer wraps around the threaded steel bars.

[0010] In some alternative implementations, the top surface of the longitudinal construction joint structure is covered with a road-specific waterproof membrane layer.

[0011] In some alternative implementations, the asphalt layer includes an asphalt base layer, a tack coat, and an asphalt top layer arranged sequentially from bottom to top.

[0012] In some alternative implementations, the upper and lower surfaces of the concrete pavement slab have concave and convex structures, respectively.

[0013] This application also provides a construction method for the aforementioned high-durability prefabricated pavement structure, including the following steps: Subgrade treatment; layered filling, leveling and compaction of the subgrade to the design compaction degree; Construct a cement-stabilized crushed stone subbase on the roadbed; Construct anti-slide piles at set intervals on the cement-stabilized crushed stone subbase, install transverse drainage pipes, and pour limiting hard shoulders. Apply a slurry seal layer on a cement-stabilized crushed stone subbase. Apply the crushed stone upper base course over the slurry seal layer; Concrete pavement slabs are installed on the crushed stone base course; Use a road roller to compact the concrete pavement slab, embedding the crushed stone upper base layer into the lower surface of the concrete pavement slab; Apply rubber-modified synchronous chip seal to concrete pavement slabs; Apply an asphalt layer over a rubber-modified synchronous chip seal.

[0014] In some alternative implementations, when assembling concrete pavement slabs on a crushed stone subbase, a transverse joint structure and / or a longitudinal construction joint structure are constructed between two pre-designed adjacent concrete pavement slabs, and a road-specific waterproof membrane layer is laid on the transverse joint structure and / or the longitudinal construction joint structure.

[0015] The beneficial effects of this application are as follows: The high-durability prefabricated pavement structure provided by this application includes, from bottom to top, a subgrade, a cement-stabilized crushed stone subbase, a slurry seal, a crushed stone upper base, a concrete pavement slab, a rubber-modified synchronous crushed stone seal, and an asphalt layer; the top of the cement-stabilized crushed stone subbase is provided with limiting hard shoulders located on both sides of the slurry seal, the crushed stone upper base, the concrete pavement slab, the rubber-modified synchronous crushed stone seal, and the asphalt layer; the limiting hard shoulders are embedded with multiple anti-skid piles and transverse drainage pipes arranged at intervals along the length of the pavement; the bottom of the anti-skid piles penetrates the cement-stabilized crushed stone subbase and inserts into the subgrade; one end of the transverse drainage pipe extends to the crushed stone upper base, and the other end extends out of the limiting hard shoulder. The high-durability prefabricated pavement structure and its construction method provided in this application can fully utilize the good interlocking and drainage effects between large-diameter particles by setting a crushed stone upper base course. This provides good load-bearing capacity for the concrete pavement slab and can quickly remove water seepage inside the pavement structure, avoiding defects such as loosening, pumping, and structural failure caused by fine particles under dynamic water pressure. Furthermore, the lateral displacement of the crushed stone upper base course is effectively restricted by the limiting hard shoulders set on the side of the pavement structure, which improves the anti-skid stability of the limiting hard shoulders and prevents the crushed stone upper base course from penetrating defects and the concrete pavement slab from becoming detached from the bottom, thus providing a solid and stable load-bearing surface for the concrete pavement slab. Attached Figure Description

[0016] To more clearly illustrate the technical solutions of the embodiments of this application, the accompanying drawings used in the embodiments will be briefly introduced below. It should be understood that the following drawings only show some embodiments of this application and should not be regarded as a limitation of the scope. For those skilled in the art, other related drawings can be obtained based on these drawings without creative effort.

[0017] Figure 1 A partial cross-sectional view of the prefabricated pavement structure provided in the embodiments of this application; Figure 2 A schematic diagram of the structure when the ends of two adjacent concrete pavement panels are spliced ​​together in a high-durability prefabricated pavement structure provided in the embodiments of this application; Figure 3 A partial cross-sectional view of the ends of two adjacent concrete pavement slabs connected by a transverse joint structure in a high-durability prefabricated pavement structure provided in this application embodiment. Figure 4 A schematic diagram of the connection between the smooth round bearing steel and the bearing steel sleeve in the high-durability prefabricated pavement structure provided in the embodiments of this application; Figure 5 A schematic diagram of the structure when the sides of two adjacent concrete pavement panels are spliced ​​together in a high-durability prefabricated pavement structure provided in the embodiments of this application; Figure 6 This is a partial cross-sectional view of the high-durability prefabricated pavement structure provided in this application embodiment, showing the sides of two adjacent concrete pavement panels connected by a longitudinal construction joint structure.

[0018] In the diagram: 100, Subgrade; 110, Cement-stabilized crushed stone lower base course; 120, Slurry seal; 130, Crushed stone upper base course; 140, Concrete pavement slab; 150, Rubber-modified synchronous crushed stone seal; 160, Asphalt layer; 161, Asphalt lower layer; 162, Tack coat; 163, Asphalt upper layer; 170, Restricted hard shoulder; 180, Anti-skid pile; 190, Transverse drainage pipe; 200, Plain round bearing steel; 210, Boss; 220, Bearing steel sleeve; 230, Embedded installation groove; 240, Anchoring steel bar; 250, First ultra-high performance early strength concrete layer; 260, Joint filler board; 270, Joint filler layer; 280, Road-specific waterproof membrane layer; 290, Threaded steel bar; 300, Second ultra-high performance early strength concrete layer. Detailed Implementation

[0019] To make the objectives, technical solutions, and advantages of the embodiments of this application clearer, the technical solutions of the embodiments of this application will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of this application, and not all embodiments. The components of the embodiments of this application described and shown in the accompanying drawings can generally be arranged and designed in various different configurations.

[0020] Therefore, the following detailed description of the embodiments of this application provided in the accompanying drawings is not intended to limit the scope of the claimed application, but merely to illustrate selected embodiments of the application. All other embodiments obtained by those skilled in the art based on the embodiments of this application without inventive effort are within the scope of protection of this application.

[0021] It should be noted that similar labels and letters in the following figures indicate similar items. Therefore, once an item is defined in one figure, it does not need to be further defined and explained in subsequent figures.

[0022] In the description of this application, it should be noted that the terms "center," "upper," "lower," "left," "right," "vertical," "horizontal," "inner," and "outer," etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings, or the orientation or positional relationship commonly used when the product of this application is in use. They are only for the convenience of describing this application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation, and therefore should not be construed as a limitation on this application. In addition, the terms "first," "second," and "third," etc., are only used to distinguish descriptions and should not be construed as indicating or implying relative importance.

[0023] Furthermore, terms such as "horizontal," "vertical," and "sag" do not imply that components must be absolutely horizontal or suspended, but rather that they can be slightly tilted. For example, "horizontal" simply means that its direction is more horizontal relative to "vertical," and does not mean that the structure must be completely horizontal, but can be slightly tilted.

[0024] In the description of this application, it should also be noted that, unless otherwise expressly specified and limited, the terms "set up," "install," "connect," and "link" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; and they can refer to the internal connection of two components. Those skilled in the art can understand the specific meaning of the above terms in this application based on the specific circumstances.

[0025] In this application, unless otherwise expressly specified and limited, "above" or "below" the second feature can include direct contact between the first and second features, or contact between the first and second features through another feature between them. Furthermore, "above," "over," and "on top" of the second feature includes the first feature being directly above or diagonally above the second feature, or simply indicates that the first feature is at a higher horizontal level than the second feature. "Below," "below," and "under" the second feature includes the first feature being directly below or diagonally below the second feature, or simply indicates that the first feature is at a lower horizontal level than the second feature.

[0026] The following detailed description of the features and performance of the high-durability prefabricated pavement structure and its construction method of this application, in conjunction with embodiments, provides further insight into their characteristics and performance.

[0027] like Figure 1 , Figure 2 , Figure 3 , Figure 4 , Figure 5 and Figure 6As shown in the embodiment of this application, a highly durable prefabricated pavement structure is provided, which includes, from bottom to top, a roadbed 100, a cement-stabilized crushed stone lower base course 110, a slurry seal 120, a crushed stone upper base course 130, a concrete pavement slab 140, a rubber-modified synchronous crushed stone seal 150, and an asphalt layer 160; the cement-stabilized crushed stone lower base course 110 is provided with limiting hard shoulders 170 on both sides of the slurry seal 120, the crushed stone upper base course 130, the concrete pavement slab 140, the rubber-modified synchronous crushed stone seal 150, and the asphalt layer 160; two adjacent concrete pavement slabs 140 are connected along the length of the pavement by a transverse joint structure, and two adjacent concrete pavement slabs 140 are connected along the width of the pavement by a longitudinal construction joint structure.

[0028] Among them, such as Figure 1 As shown, the subgrade 100 is the bottom layer of the prefabricated pavement structure, playing a crucial role in transferring the load from the superstructure to the foundation. Subgrade 100 undergoes layered earthwork filling, leveling, and compaction to achieve the required compaction degree, providing a uniform and stable support foundation for the superstructure. The cement-stabilized crushed stone subbase 110 is laid on top of subgrade 100, constructed by spreading and compacting cement-stabilized crushed stone material. After being covered and cured for 7 days, it forms a stable bearing layer. The cement-stabilized crushed stone subbase 110, on the one hand, increases the top modulus and bearing capacity of subgrade 100, providing a stable working surface for the construction of the crushed stone upper base 130; on the other hand, it prevents large-diameter crushed stones in the crushed stone upper base 130 from embedding into subgrade 100, thus reducing the deformation resistance of the top surface of subgrade 100.

[0029] The slurry seal 120 is applied to the cement-stabilized crushed stone subbase 110 and is an ES-2 type slurry seal applied using an asphalt distributor. The slurry seal 120 is used to block rainwater infiltration from the upper part of the pavement structure into the cement-stabilized crushed stone subbase 110, preventing water damage to the subbase and thus avoiding defects such as pumping, slab breakage, and misalignment in the concrete pavement slab 140.

[0030] The crushed stone upper base course 130 is set on the slurry seal layer 120, with a thickness of 20-30cm. It is formed by spreading and vibrating large-diameter crushed stone. The particle size distribution range of the crushed stone should meet the following requirements: 0% passing rate of a 13.2mm square hole sieve, 0-5% passing rate of a 19mm square hole sieve, 2-25% passing rate of a 31.5mm square hole sieve, 28-63% passing rate of a 37.5mm square hole sieve, 72-99% passing rate of a 53mm square hole sieve, and 100% passing rate of a 63mm square hole sieve. Among them, the mass of crushed stone passing through the 31.5-53mm square hole sieve should not be less than 50%. Other physical and mechanical properties refer to the "Technical Specifications for Construction of Highway Pavement Base Course" (JTG / TF20-2015). After compaction, the porosity of the crushed stone upper base course 130 is no more than 20%. It makes full use of the good interlocking and drainage effect between large-diameter particles, which not only provides good load-bearing capacity for the concrete pavement slab 140, but also can quickly remove water seepage inside the pavement structure. This avoids the loosening, pumping and structural failure of fine particles in traditional graded crushed stone or cement-stabilized crushed stone base courses under the action of dynamic water pressure.

[0031] The concrete pavement slab 140 is prefabricated in the factory and then assembled on site. The preferred thickness is 25cm, and the slab length and width are 2.5-3.5m and 2-3.5m respectively (the specific length and width are determined based on actual site conditions). The concrete pavement slab 140 has an upper surface and a lower surface. The upper surface is milled during prefabrication to create an uneven structure with an average texture depth of not less than 2mm, enhancing the shear strength between it and the asphalt layer 160. The lower surface is prefabricated using a template with a macroscopic structure on the bottom, creating an uneven surface that increases its contact area with the crushed stone upper base layer 130 and facilitates embedding into the crushed stone upper base layer 130. This enhances the shear strength between the concrete pavement slab 140 and the crushed stone upper base layer 130 and prevents horizontal slippage of the pavement slab. Rubber-modified synchronous chip seal 150 is applied to the concrete pavement slab 140 using a synchronous chip seal sprayer. The rubber-modified synchronous chip seal 150 enhances the shear strength between the asphalt layer 160 and the concrete pavement slab 140, reducing asphalt surface shoving, rutting, and other defects. The asphalt layer 160 is laid on the rubber-modified synchronous chip seal 150 and includes, from bottom to top, an asphalt base layer 161, a tack coat 162, and an asphalt top layer 163. The asphalt base layer 161 is preferably a 6cm thick ATB-20 asphalt-stabilized chip stone. The tack coat 162, made of PC-3 type emulsified asphalt tack coat oil, enhances the bond between asphalt layers, improves interlayer shear strength, and allows the asphalt top and bottom layers to work together. The asphalt top layer 163 is preferably a 4cm thick AC-13C modified asphalt concrete, serving as the direct driving layer of the pavement structure, providing good skid resistance and driving comfort.

[0032] The limiting hard shoulder 170 is embedded with anti-skid piles 180 and transverse drainage pipes 190 arranged at intervals along the length of the road surface. The anti-skid piles 180 are reinforced concrete or steel pipe structures; optionally, the anti-skid piles 180 are drilled at 3m intervals along the longitudinal direction of the road surface and driven into the cement-stabilized crushed stone subbase 110 and the roadbed 100 by at least 50cm, with the top of the pile protruding 10-15cm above the top surface of the cement-stabilized crushed stone subbase 110, to improve the anti-skid stability of the hard shoulder. The bottom of the anti-skid piles 180 penetrates the cement-stabilized crushed stone subbase 110 and inserts into the roadbed 100, further improving the anti-skid stability of the hard shoulder. The transverse drainage pipes 190 are located on the top surface of the cement-stabilized crushed stone subbase 110 and arranged along the width of the road surface, with one end extending to the crushed stone upper subbase 130 and the other end extending out of the limiting hard shoulder 170, to drain seepage water from inside the road surface.

[0033] The limiting hard shoulder 170 is a cast-in-place concrete structure with a concrete strength grade of not less than C20. It is poured outside the anti-slide pile 180 and completely encloses the anti-slide pile 180. Together with the anti-slide pile 180, it restrains the lateral displacement of the crushed stone upper base course 130, prevents the crushed stone upper base course 130 from developing lateral penetration defects, and prevents the bottom of the concrete pavement slab 140 from becoming void, thus providing a solid and stable bearing boundary for the concrete pavement slab 140. The transverse drainage pipe 190 is set between the limiting hard shoulder 170 and the upper part of the cement-stabilized crushed stone lower base course 110. It is arranged transversely along the road surface and together with the slurry seal 120, it forms an internal drainage system for the road surface to promptly remove rainwater that seeps into the upper part of the road structure and reduce water damage to the road structure.

[0034] like Figure 2 and Figure 3 As shown, the transverse joint structure includes plain round bearing steel 200 arranged at intervals and embedded at one end inside one end of the concrete pavement slab 140, and a boss 210 protruding from the bottom of the other end face of the concrete pavement slab 140, as shown. Figure 4As shown, each round bearing steel 200 is fitted with a bearing steel sleeve 220, and the boss 210 has embedded mounting grooves 230 for accommodating each bearing steel sleeve 220. One end (A end) of the concrete pavement slab 140 has round bearing steel 200s arranged at intervals along its width embedded in its end face. The other end (B end) of the concrete pavement slab 140 is L-shaped, with a boss 210 protruding from its lower part. U-shaped anchoring steel bars 240 are embedded at intervals on the top of the other end (B end) and the top surface of the boss 210. A first ultra-high performance early strength concrete layer 250 is poured onto the top surface of the boss 210, encasing the anchoring steel bars 240 and the bearing steel sleeves 220. After the first ultra-high performance early strength concrete layer 250 and the anchoring steel bars 240 form a whole, it is covered and cured to seal and fix the joint between adjacent concrete pavement slabs 140. The first ultra-high performance early strength concrete layer 250 has rapid strength development and excellent durability, which can significantly shorten the time to open to traffic while ensuring the load transfer capacity and flatness of the joints.

[0035] The transverse joint structure also includes a joint filler plate 260 at one end of the concrete pavement slab 140 and a joint filler layer 270 on top of the joint filler plate 260. The joint filler plate 260 is located between ends A and B, from the bottom of the pavement to a height of 3-4 cm above the pavement, and is used to fill the lower gap of the joint and provide deformation space for the thermal expansion and contraction of the slab. The two sides of the joint filler layer 270 are respectively connected to the first ultra-high performance early strength concrete layer 250 and the end face of the concrete pavement slab 140, and are used to fill the upper gap of the joint and ensure a smooth surface. The top surface of the transverse joint structure is covered with a road-specific waterproof membrane layer 280.

[0036] like Figure 5 and Figure 6 As shown, the longitudinal construction joint structure includes U-shaped threaded steel bars 290 embedded at intervals on both sides of the concrete pavement slab 140, and a second ultra-high performance early strength concrete layer 300 filling the space between two adjacent concrete pavement slabs 140 along the width of the pavement. The second ultra-high performance early strength concrete layer 300 wraps around the threaded steel bars 290. The threaded steel bars 290 are U-shaped and are pre-embedded in the side of the concrete pavement slab 140 during factory prefabrication to form a reliable anchoring connection with the second ultra-high performance early strength concrete layer 300. The second ultra-high performance early strength concrete layer 300 is poured at the construction joint location, and after forming an integral whole with the threaded steel bars 290, it seals the construction joint to form a reliable connection. The top surface of the longitudinal construction joint structure is covered with a road-specific waterproof membrane layer 280 to prevent surface water infiltration.

[0037] This application also provides a construction method for the above-mentioned high-durability prefabricated pavement structure, including the following steps: Step 1: Subgrade 100 Treatment; First, subgrade 100 is filled in layers, each approximately 30-50cm thick, ensuring uniform filling. After filling, fine leveling is performed, followed by compaction using a vibratory roller, following the principles of light to heavy, slow to fast, and edge to center compaction until the designed compaction degree is achieved. Areas failing the compaction test are re-compacted; for weak subgrades, reinforcement is carried out using replacement or dynamic compaction methods. After the top elevation of subgrade 100 is constructed to the design elevation, a small amount of water is sprayed on the surface to retain moisture and prevent drying and cracking.

[0038] Step 2: Construction of the cement-stabilized crushed stone subbase (110mm): The cement-stabilized crushed stone mixture is transported to the site and spread using a paver. The spreading thickness is in accordance with the design requirements, and a vibratory roller is used to compact it in multiple passes to the designed compaction degree. After compaction, immediately cover with geotextile or plastic film for moisture retention and curing. The curing time is not less than 7 days, during which the surface is kept moist.

[0039] Step 3: Construction of anti-slide piles 180 and limiting hard shoulder 170; Using drilling machinery, drill holes at 3m intervals along the designed position of anti-slide piles 180, and drive in anti-slide piles 180 with a diameter of 10cm steel pipes or precast reinforced concrete. The anti-slide piles 180 should penetrate the cement-stabilized crushed stone subbase 110 and extend into the roadbed 100 by no less than 50cm. The top of the pile should be 10-15cm higher than the top surface of the cement-stabilized crushed stone subbase 110. Then, pre-install transverse drainage pipes 190 below the limiting hard shoulder 170, install the formwork, and pour the limiting hard shoulder 170. The concrete strength grade is C20, and cover and cure until the design strength.

[0040] Step 4: Apply 120 slurry seal layer; Use an asphalt sprayer to apply ES-2 type slurry seal layer 120 to the cement-stabilized crushed stone base course 110. The slurry seal layer 120 should seal the upper surface of the cement-stabilized crushed stone base course 110, with uniform thickness, no missed areas or excessive overlap. After curing to the point where it can be opened for construction, proceed to the next step.

[0041] Step 5: Construction of the 130mm crushed stone upper base course; Large-diameter crushed stone meeting the design particle size distribution requirements is transported to the site and spread using a bulldozer or grader. The spreading thickness is controlled at 20-30cm to ensure uniform thickness. After spreading, fine leveling is performed, followed by compaction using a vibratory roller in multiple passes. The crushed stone particle size distribution should meet the following requirements: 0% passing rate on a 13.2mm square-hole sieve, 0-5% passing rate on a 19mm square-hole sieve, 2-25% passing rate on a 31.5mm square-hole sieve, 28-63% passing rate on a 37.5mm square-hole sieve, 72-99% passing rate on a 53mm square-hole sieve, and 100% passing rate on a 63mm square-hole sieve; the mass percentage of crushed stone passing through the 31.5-53mm square-hole sieve should not be less than 50%. Other physical and mechanical properties should refer to the "Technical Specifications for Construction of Highway Pavement Base Course" (JTG / T F20-2015). The porosity after compaction should not exceed 20%.

[0042] Step Six: Factory Prefabrication of Concrete Pavement Slab 140; Concrete pavement slab 140 is prefabricated in the factory, preferably with a thickness of 25cm, a length of 2.5-3.5m, and a width of 2-3.5m (the specific length and width are determined according to the actual site conditions). During prefabrication, the upper surface of the concrete pavement slab 140 is milled, and the average texture depth of the milled surface is not less than 2mm; the lower surface of the concrete pavement slab 140 uses a template with a macroscopic structure on the bottom surface to create an uneven surface. The concrete pavement slab 140 includes end A and end B, both perpendicular to the road centerline: End A has 25mm diameter plain round bearing steel 200 pre-embedded at intervals in the middle of the slab thickness; End B has 12mm diameter anchor steel 240 pre-embedded at intervals on the upper bottom and sides, and a semi-cylindrical embedded installation groove 230 is reserved on the bottom surface of End B. During prefabrication, threaded steel 290 is pre-embedded on both sides of the concrete pavement slab 140, and after prefabrication, it is covered and cured to the design strength.

[0043] Step 7: On-site assembly of concrete pavement slab 140; After the concrete pavement slab 140 is transported to the site, before hoisting, the bearing steel sleeve 220 is pre-fitted into one end of the smooth round bearing steel 200. Hoist the concrete pavement slab 140 sequentially according to the designed joint positions: first, position the first pavement slab A end, then lower the adjacent pavement slab B end along the direction of the smooth round bearing steel 200 into the bearing steel sleeve 220 and the corresponding position of the embedded installation groove 230, so that the gap between the A end and the B end is controlled within 2cm, and the surfaces of adjacent pavement slabs are flat and the joints are straight.

[0044] Expansion joint: Two adjacent concrete pavement slabs 140 are connected along the length of the pavement by an expansion joint structure: After the A and B ends of the two adjacent concrete pavement slabs 140 are hoisted into place, the joint gap between the A and B ends from the bottom of the pavement to a height of 3-4 cm above the pavement is filled with a joint filler board 260; after inspection and confirmation, the first ultra-high performance early strength concrete layer 250 is poured at the reserved position above the B end, and after forming an integral whole with the anchoring steel bars 240, it is covered and cured with moisture; after curing, the joint gap between the A and B ends from the pavement to 3-4 cm below the pavement is filled with joint filler to meet the expansion and contraction deformation requirements of the concrete pavement slab 140, and then a road-specific waterproof membrane layer 280 is laid at the joint to prevent rainwater from seeping down along the joint.

[0045] Longitudinal construction joints: When the designed width of the road surface is greater than the width of the concrete pavement 140, multiple concrete pavement 140s need to be laid along the width of the road surface. Longitudinal construction joints with a width of 10-20cm are set at the connection between the concrete pavement 140s. That is, after the concrete pavement 140s are hoisted into place, the threaded steel bars 290 pre-embedded on the sides of two adjacent concrete pavement 140s are connected. Then, a second ultra-high performance early strength concrete layer 300 is poured at the connection position to form an integral whole with the threaded steel bars 290. After covering and curing, a road-specific waterproof membrane layer 280 is laid at the joint to prevent rainwater from seeping down along the joint.

[0046] Step 8: Lightly press and embed; After all concrete pavement panels 140 are assembled, a light rubber-tired roller should be used to slowly compact the pavement panels, so that the uneven structure on the lower surface of the concrete pavement panels 140 can be better embedded into the crushed stone upper base course 130, further enhancing the integrity and shear strength between the concrete pavement panels 140 and the crushed stone upper base course 130.

[0047] Step 9: Apply rubber-modified synchronous chip seal 150; clean the upper surface of the concrete pavement slab 140 to ensure it is clean and free of dust. Apply the rubber-modified synchronous chip seal 150 using a synchronous chip seal spreader. The seal should evenly cover the upper surface of the concrete pavement slab 140. After curing until conditions are suitable for the next process, apply the asphalt base course 161.

[0048] Step 10: Asphalt surface layer construction; construct a 6cm thick ATB-20 asphalt lower layer 161 and compact it to the designed compaction degree; after the surface temperature meets the requirements, use an asphalt distributor to construct a PC-3 type emulsified asphalt tack coat 162; finally, construct a 4cm thick AC-13C modified asphalt upper layer 163 and compact it in multiple passes to the designed compaction degree. After the road surface is formed, promptly install traffic safety facilities and open it to traffic.

[0049] The beneficial effects of the high-durability prefabricated pavement structure and its construction method provided in this application are: I. This application innovatively adopts a large-diameter crushed stone structure in the crushed stone upper base course 130 to replace the existing cement-stabilized crushed stone base course or graded crushed stone base course, optimizes the gradation of the crushed stone upper base course 130, and eliminates the medium and fine-grained crushed stone below 13.5mm in the traditional graded crushed stone base course or cement-stabilized crushed stone base course. It makes full use of the good interlocking and drainage effect between the large-diameter particles, which can not only provide good load-bearing capacity for the concrete pavement slab 140, but also quickly remove water seepage inside the pavement structure. At the same time, it avoids the problems such as loosening, pumping, and structural failure that are easily caused by fine particles in the traditional graded crushed stone base course and cement-stabilized crushed stone base course under the action of dynamic water pressure.

[0050] Second, by setting the limiting hard shoulder 170 and anti-skid pile 180 on the side of the road structure, this application can effectively limit the lateral displacement of the crushed stone upper base course 130, improve the anti-skid stability of the hard shoulder, avoid the crushed stone upper base course 130 from being punctured and the concrete pavement slab 140 from being delaminated at the bottom, and provide a sufficiently solid and stable bearing surface for the concrete pavement slab 140.

[0051] Third, this application replaces the plain round steel bars and plastic film in the traditional pavement structure with a high-durability and high-precision cylindrical plain round bearing steel 200 and bearing steel sleeve 220 set in the middle of the 140mm thick concrete pavement slab. This solves the problems of gaps, poor contact, poor load transfer capacity, easy deformation of dowel bars, and easy damage to concrete at dowel bars in traditional pavement joints, and significantly improves the force transfer coefficient and durability at the joints.

[0052] Fourth, this application enhances the shear strength between the concrete pavement 140 and the asphalt layer 160 by milling the upper part of the concrete pavement 140. By setting an uneven surface on the lower part of the concrete pavement 140, the lower part of the concrete pavement 140 is firmly embedded in the crushed stone upper base layer 130, which enhances the shear strength between the concrete pavement 140 and the crushed stone upper base layer 130 and prevents the concrete pavement 140 from slipping.

[0053] V. This application provides 240mm anchoring steel bars at the joint and casts in place the first ultra-high performance early strength concrete layer 250mm and the second ultra-high performance early strength concrete layer 300mm, which can effectively improve the durability of concrete joints and solve the problem that the concrete pavement slab 140 joint and the concrete at the joint are easily damaged under the action of vehicle dynamic load.

[0054] VI. By setting a cement-stabilized crushed stone lower base course 110 on the upper part of the roadbed 100, this application improves the modulus and bearing capacity of the top of the roadbed 100, provides a stable working surface for the construction of the crushed stone upper base course 130, and prevents the crushed stone in the crushed stone upper base course 130 from embedding into the soil of the roadbed 100, thereby reducing the deformation resistance of the top of the roadbed 100.

[0055] VII. This application utilizes a modern factory to carry out large-scale and precise prefabrication of concrete pavement slabs 140 and their embedded components, with only assembly and a small amount of on-site casting work. The construction operation is simple, it is highly adaptable to adverse weather conditions such as low temperature, rain, and strong wind, and it can open to traffic quickly. It has the advantages of good durability, low life cycle cost, and significant economic and environmental benefits.

[0056] The embodiments described above are some, but not all, of the embodiments of this application. The detailed description of the embodiments of this application is not intended to limit the scope of the claimed application, but merely to illustrate selected embodiments. All other embodiments obtained by those skilled in the art based on the embodiments of this application without inventive effort are within the scope of protection of this application.

Claims

1. A highly durable prefabricated pavement structure, characterized in that, It includes, from bottom to top, a roadbed, a cement-stabilized crushed stone subbase, a slurry seal, a crushed stone upper base, a concrete pavement slab, a rubber-modified synchronous crushed stone seal, and an asphalt layer. The cement-stabilized crushed stone subbase is topped with limiting shoulders located on both sides of the slurry seal, the crushed stone upper base, the concrete pavement slab, the rubber-modified synchronous crushed stone seal, and the asphalt layer. Multiple anti-skid piles and transverse drainage pipes are embedded within the limiting shoulders, arranged at intervals along the length of the road surface. The transverse drainage pipes are arranged along the width of the road surface, with one end extending to the crushed stone upper base and the other end extending out of the limiting shoulders. The bottom of the anti-skid piles penetrates the cement-stabilized crushed stone subbase and inserts into the roadbed.

2. The high-durability prefabricated pavement structure according to claim 1, characterized in that, Two adjacent concrete pavement slabs are connected along the length of the pavement by a transverse joint structure. The transverse joint structure includes multiple plain round bearing steels with one end embedded inside one end of the concrete pavement slab, and a boss protruding from the bottom of the other end face of the concrete pavement slab. Each plain round bearing steel is fitted with a bearing steel sleeve. The boss has embedded installation grooves for accommodating each bearing steel sleeve. Multiple U-shaped anchoring steel bars are pre-embedded on the upper bottom and side of the other end of the concrete pavement slab. The top surface of the boss is filled with a first ultra-high performance early strength concrete layer that wraps the anchoring steel bars and the bearing steel sleeves.

3. The high-durability prefabricated pavement structure according to claim 2, characterized in that, The transverse joint structure includes a joint filler plate at one end of the concrete pavement slab and a joint filler layer on top of the joint filler plate. The joint filler plate is disposed between two adjacent end faces of the concrete pavement slabs. The two sides of the joint filler layer are respectively connected to the first ultra-high performance early strength concrete layer and the end face of the concrete pavement slab.

4. The high-durability prefabricated pavement structure according to claim 3, characterized in that, The top surface of the transverse joint structure is covered with a road-specific waterproof membrane layer.

5. The high-durability prefabricated pavement structure according to claim 1, characterized in that, Two adjacent concrete pavement slabs are connected by a longitudinal construction joint structure along the width of the pavement. The longitudinal construction joint structure includes a plurality of U-shaped threaded steel bars respectively provided on both sides of the concrete pavement slabs and a second ultra-high performance early strength concrete layer filled between the two adjacent concrete pavement slabs along the width of the pavement. The second ultra-high performance early strength concrete layer wraps the threaded steel bars.

6. The high-durability prefabricated pavement structure according to claim 5, characterized in that, The top surface of the longitudinal construction joint structure is covered with a road-specific waterproof membrane layer.

7. The high-durability prefabricated pavement structure according to claim 1, characterized in that, The asphalt layer comprises, from bottom to top, an asphalt base layer, a tack coat, and an asphalt top layer.

8. The high-durability prefabricated pavement structure according to claim 1, characterized in that, The upper and lower surfaces of the concrete pavement slab have concave and convex structures, respectively.

9. The construction method of the high-durability prefabricated pavement structure according to any one of claims 1 to 8, characterized in that, Includes the following steps: Subgrade treatment; layered filling, leveling and compaction of the subgrade to the design compaction degree; Construct a cement-stabilized crushed stone subbase on the aforementioned roadbed; On the cement-stabilized crushed stone subbase, anti-slide piles are constructed at set intervals, transverse drainage pipes are installed, and limiting hard shoulders are poured. A slurry seal layer is applied to the cement-stabilized crushed stone subbase. A crushed stone upper base layer is constructed on the slurry seal layer; Concrete pavement panels are assembled on the crushed stone base course; The concrete pavement slab is compacted using a road roller so that the lower surface of the concrete pavement slab is embedded into the crushed stone upper base layer; Apply a rubber-modified synchronous chip seal layer to the concrete pavement slab; An asphalt layer is applied to the rubber-modified synchronous chip seal.

10. The construction method for the high-durability prefabricated pavement structure according to claim 9, characterized in that, When assembling concrete pavement slabs on the crushed stone base course, a transverse joint structure and / or a longitudinal construction joint structure are constructed between two pre-set adjacent concrete pavement slabs, and a road-specific waterproof membrane layer is laid on the transverse joint structure and / or the longitudinal construction joint structure.