Railway continuous segmental beam construction structure and method
By integrating the construction process and adopting the "beam-on-beam" mode, the problems of prefabrication accuracy and safety in the construction of continuous segmental beams for railways have been solved, enabling efficient and green construction across restricted sites, and making it suitable for complex environments such as crossing rivers and roads.
Patent Information
- Application Number
- CN202611063640.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-07-17
- Publication Date
- 2026-11-20
AI Technical Summary
The construction of continuous segmental beams for railways faces challenges such as difficulty in controlling the precision of segmental prefabrication, high safety risks in hoisting and transportation, complex alignment control, and complex construction when crossing restricted sites. In particular, construction efficiency is low and safety hazards are significant in scenarios such as crossing rivers and roads.
An integrated construction process was adopted, including pier support structure, pier top segment anchoring and sliding structure, bridge deck beam transportation and erection structure, and closure and system conversion constraint structure. Combining the comprehensive long-line method and short-line method, segment prefabrication was achieved. The "beam transportation on beam" mode was adopted, and the bridge foundation was constructed simultaneously. Flow operation and reliable temporary anchoring measures were adopted.
It improves prefabrication accuracy and construction efficiency, reduces the requirements for site conditions under the bridge, reduces construction risks and investment in large temporary facilities, conforms to the concept of green construction, and is suitable for scenarios such as crossing highways and rivers.
Smart Images

Figure CN123133261A_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of bridge construction technology, specifically relating to a construction structure and method for continuous segmental beams for railways. Background Technology
[0002] Segmental construction technology for continuous railway beams has been a significant development direction in bridge engineering in recent decades, combining the characteristics of prefabrication and on-site integrated construction. The high precision requirements of segmental beam prefabrication and assembly led to early bridges failing to achieve ideal results, causing a period of stagnation in technological development.
[0003] In recent years, my country has constructed a large number of precast segmental beams using wet joints, opening up new possibilities for the application of segmental assembly technology in continuous beams. The use of post-cast wet joints between bridge segments addresses the accuracy requirements for precast segment matching, but also increases the number of construction procedures.
[0004] In terms of segmental precasting, there are currently two main technical approaches: the long-line method and the short-line method. The long-line method involves casting all beam segments within movable formwork on a fixed platform, with adjacent segments fitting together. Its advantages include reliable platform fixation and easy control of the beam's alignment after completion. However, it has disadvantages such as large land area requirements, stringent foundation requirements, and low formwork utilization. The short-line method involves casting beam segments within longitudinally movable molds on fixed platforms. A fixed formwork is installed at one end of the segment to be cast, while the other end uses a previously cast segment as a matching section. Its advantages include smaller site requirements and adaptability to precast horizontal and vertical curved beam segments. However, it demands extremely high precision control and has a relatively longer construction period.
[0005] Significant progress has been made in bridge-building machine technology in segmental assembly. Intelligent construction technology has further promoted the development of this field. For example, the new cantilever intelligent bridge-building machine integrates technologies such as the Internet of Things, big data and 5G, realizing remote control of movement, precise template positioning and visualization of construction parameters, which greatly improves construction efficiency and safety performance.
[0006] Despite significant advancements in existing technologies, railway continuous segmental beam construction still faces a series of challenges: (1) For large-span continuous beams, controlling the precision of segmental prefabrication is difficult, especially the matching prefabrication of variable cross-section beam segments; (2) The hoisting and transportation of large-tonnage 0# block segments require high-quality equipment and pose significant safety risks; (3) The alignment control during segmental assembly is complex, requiring consideration of the coordination between prefabrication and erection pre-camber; (4) Under conditions of crossing multiple highways, rivers, and other restricted sites, traditional hanging basket construction suffers from problems such as complex structure, cumbersome assembly and disassembly, and significant safety hazards.
[0007] Therefore, developing a construction method for railway continuous segmental beams that can balance prefabrication accuracy, construction efficiency, and safety performance, and is particularly suitable for restricted sites such as river crossings and road crossings, has significant engineering application value. Summary of the Invention
[0008] To address some shortcomings in existing technologies, this invention provides a construction structure and method for continuous segmental beams in railways that balances prefabrication accuracy, construction efficiency, and safety performance through an integrated construction process design. This invention employs a segmental factory-based integrated long-line prefabrication method, effectively controlling prefabrication accuracy, ensuring the bridge's alignment, allowing for extended beam curing time, later loading age, and minimizing creep camber and long-term prestress loss after bridge completion. The segmental prefabrication described in this invention can be carried out simultaneously with the bridge foundation and substructure, using a streamlined operation that avoids interference and significantly shortens the construction period. The innovative "beam-on-beam transport" mode greatly reduces the requirements for the site conditions under the bridge, making it particularly suitable for scenarios crossing highways and rivers. The method described in this invention reduces the investment in large-scale temporary facilities, aligns with green construction principles, and has excellent practicality.
[0009] To achieve the above-mentioned technical objectives, the present invention employs the following technical means: This invention first provides a construction structure for a continuous railway beam stage, the construction structure including a pier support structure, a pier top segment anchoring and sliding structure, a bridge deck beam transport and erection structure, and a closure and system conversion constraint structure; The pier support structure includes side piers and middle piers. The top of the side pier is provided with a side pier support for supporting the side span segments. The top of the middle pier is provided with a middle pier support. The middle pier support is provided with a sliding beam and a slider for sliding positioning and temporary support of segment #1. The anchoring and sliding structure of the pier top segment includes pier top segment 0, temporary anchor, and segment 1; pier top segment 0 is fixed to the top of the middle pier through temporary anchor; segment 1 is supported on the slider of the sliding beam and is connected to pier top segment 0; The bridge deck beam transport and erection structure includes a bridge deck crane, the segment to be erected, and the side span segment; the bridge deck crane is installed on the top surface of segment 1 and is used to lift the segment to be erected to achieve symmetrical cantilever erection, and to lift the side span segment to the side pier support; The closure and system transformation constraint structure includes the stiffening frame of the side span closure section, the stiffening frame of the middle span closure section, the closure hanger, and the horizontal constraint device at the middle support point.
[0010] Preferably, the pier top segment 0#, segment 1#, segment to be erected, and side span segment are prefabricated by matching prefabricated structures; The prefabricated structure includes a beam-making platform arranged along the longitudinal axis, with gantry crane foundations symmetrically arranged on both sides of the beam-making platform, and a gantry crane capable of longitudinal movement mounted on the gantry crane foundation. The beam fabrication platform is divided into two T-shaped prefabrication sections, with the mid-span closure section as the boundary.
[0011] Preferably, the No. 1 segment and the No. 0 segment at the top of the pier are connected by applying adhesive, adjusting the alignment, and tensioning temporary prestressed steel bars, and the slide beam and the slider are welded and fixed together.
[0012] Preferably, the rigid frame of the side span closure section is connected to the template of the side span closure section at the end of the side span side segment; the rigid frame of the middle span closure section is connected to the closure hanger at the ends of the cantilever segments on both sides of the middle span. The horizontal constraint device at the central fulcrum acts on the temporary anchoring position and is used for temporary constraint and unlocking during system conversion.
[0013] This invention also provides a method for constructing a continuous railway beam in stages, the method being carried out according to the above-described construction structure, the method comprising: (1) The 0# segment, 1# segment, segment to be erected and side span segment of the pier top are prefabricated using the comprehensive long-line method and stored in the beam yard after prefabrication; (2) Simultaneously construct the bridge foundation and the substructure of the side piers and middle piers, install the side pier supports and middle pier supports, use a crane to hoist the 0# segment of the pier top onto the middle pier and accurately position it, and temporarily anchor the pier top through the beam top anchoring device; (3) Hoist segment 1 onto the slide beam slider on the upper part of the middle pier support, and weld the slide beam and slider firmly to complete the connection and fixation of segment 1 and segment 0; (4) Install a bridge deck crane on the top surface of segment 1. The bridge deck crane lifts the segment to be erected on the middle span side and transports the segment to the side span side for temporary suspension. Then, it lifts the symmetrical segments to be erected on the middle span side to install the cantilever segment beam. Repeat the operation to achieve symmetrical erection of all cantilever segments on both sides of the middle pier. (5) The side span side segment is lifted onto the bridge by the bridge deck crane of the middle pier and transported to the cantilever side span of the main pier by the bridge beam transport system. It is then lifted onto the side pier support by the side span side bridge deck crane. The operation is repeated to complete the erection of all side span side segments on the side pier support. (6) Install the stiffening frame and bottom and side formwork of the side span closure section, release the temporary locking of the side pier, pour the concrete of the side span closure section in place, and complete the prestressing tensioning and grouting operation; remove the side pier support, middle pier support and middle pier temporary fixation, lower the beam, and temporarily constrain the horizontal direction of the middle support. (7) Install the mid-span closure stiffening frame and mid-span closure hanger, release the temporary horizontal constraint of the mid-support point, tension the temporary steel strands, cast the mid-span closure section in place and grout in time, temporarily store and transport the bridge beams, and finally construct the second phase of dead load to complete the bridge construction.
[0014] Preferably, in step (3), after segment 1 is hoisted onto the slide beam slider on the upper part of the pier support, the segment is positioned accurately and temporarily stabilized by applying adhesive, adjusting the line shape and temporary prestressing tension. The slide beam and slider are welded and fixed to achieve efficient positioning and temporary support of the pier top segment.
[0015] Preferably, in step (4), after the symmetrical sections to be erected are hoisted on the middle span side, the joint surface is coated with adhesive, the beam alignment is precisely adjusted, and temporary prestressed steel bars are tensioned to temporarily consolidate the sections. Then, grouting is performed on the relevant prestressed ducts.
[0016] Compared with the prior art, the beneficial effects of the present invention are as follows: (1) High precision and excellent quality: The method described in this invention is a segmental factory-based integrated long-line prefabrication method, which effectively controls the prefabrication precision and ensures the bridge alignment. The beam has a long curing time and a late loading age, resulting in less creep camber and long-term prestress loss after the bridge is completed.
[0017] (2) Short construction period and high efficiency: The method described in this invention allows for the simultaneous construction of segmental prefabrication, bridge foundation, and substructure, adopting a continuous operation that does not interfere with each other, thus significantly shortening the construction period.
[0018] (3) High adaptability and environmental protection: The present invention adopts an innovative "beam-on-beam transport" mode, which greatly reduces the requirements for the site conditions under the bridge, and is particularly suitable for scenarios such as crossing highways and rivers. The method described in the present invention requires less construction area, less concrete work, and reduces sewage, waste and noise pollution, which is in line with the concept of green construction.
[0019] (4) Good safety and economy: The present invention reduces construction risks and minimizes interference with existing traffic lines through symmetrical cantilever assembly process and reliable temporary anchoring measures. At the same time, it reduces the investment in large temporary facilities, resulting in significant technical and economic benefits.
[0020] (5) The method described in this invention effectively solves the problems existing in the prior art, such as the inconvenience of transporting segmental beams under restricted site conditions such as crossing multiple highways and rivers, the high requirements for the alignment of railway segmental beam assembly and the need to coordinate the prefabrication camber and erection camber, the difficulty in controlling the prefabrication accuracy of railway continuous beam segments, and the high requirements for hoisting and transporting equipment for large-tonnage segmental beams and the high safety risks. Attached Figure Description
[0021] Figure 1 This is a plan view of the prefabrication and storage of segmental beams.
[0022] Figure 2 This is a cross-sectional layout diagram for the prefabrication and storage of segmental beams.
[0023] Figure 3 Elevation layout of the pier top segment for the erection of continuous segmental beams for railways.
[0024] Figure 4 Elevation layout of the cantilever segment of the pier for the erection of continuous segmental beams for railways.
[0025] Figure 5 Elevation layout of the side segments for the erection of continuous segmental beams for railways.
[0026] Figure 6 This is an elevation layout diagram of a railway continuous segmental beam bridge after its erection.
[0027] In the diagram: 1-Beam fabrication platform, 2-Gantry crane foundation, 3-Gantry crane, 4-Side pier, 5-Middle pier, 6-Side pier support, 7-Middle pier support, 8-Pier top 0# segment, 9-Temporary anchorage, 10-Bridge deck crane, 11-1# segment, 12-Segment to be erected, 13-Side span side segment. Detailed Implementation
[0028] The present invention will be further described below with reference to the accompanying drawings and specific embodiments, but the scope of protection of the present invention is not limited thereto.
[0029] Example 1: like Figures 1-6 As shown, the present invention provides a construction structure for a continuous railway beam stage, the construction structure including a pier support structure, a pier top segment anchoring and sliding structure, a bridge deck beam transport and erection structure, and a closure and system conversion constraint structure; The pier support structure includes side piers 4 and middle piers 5. The top of the side piers 4 is provided with side pier supports 6 for supporting the side span segments 13. The top of the middle piers 5 is provided with middle pier supports 7. The middle pier supports 7 are provided with sliding beams and sliders for sliding positioning and temporary support of segment 11. The anchoring and sliding structure of the pier top segment includes pier top segment 0# 8, temporary anchor 9, and segment 1# 11; pier top segment 0# 8 is fixed to the top of the middle pier 5 through temporary anchor 9; segment 1# 11 is supported on the slider of the sliding beam and is connected to pier top segment 0# 8; The bridge deck beam transport and erection structure includes a bridge deck crane 10, a segment to be erected 12, and a side span segment 13; the bridge deck crane 10 is installed on the top surface of segment 11 and is used to lift the segment to be erected to achieve symmetrical cantilever erection, and to lift the side span segment 13 onto the side pier support 6. The closure and system transformation constraint structure includes the stiffening frame of the side span closure section, the stiffening frame of the middle span closure section, the closure hanger, and the horizontal constraint device at the middle support point.
[0030] In the specific implementation process, the pier top segment 0# (8), segment 1# (11), segment to be erected (12), and side span segment 13 are prefabricated through matching prefabricated structures. The prefabricated structure includes a beam-making platform 1 arranged along the longitudinal axis, with gantry crane foundations 2 symmetrically arranged on both sides of the beam-making platform 1, and a gantry crane 3 capable of longitudinal movement spanning the gantry crane foundations 2. The beam-making platform 1 is divided into two T-shaped prefabricated segments with the mid-span closure section as the boundary. The segmental beam prefabrication method of this invention combines the advantages of both the long-line and short-line methods, employing a combined long-line and short-line prefabrication approach. This method divides the continuous beam into two T-shaped prefabricated segments with the mid-span closure section as the boundary. By optimizing the construction sequence, it maintains the controllable alignment advantage of the long-line method while reducing site occupation. Specifically, this method first prefabricates the shared 0# segment, and then sequentially matches and prefabricates other segments towards the side span and mid-span directions. The matching position is adjusted by a beam-adjusting trolley, effectively improving prefabrication efficiency. Segment prefabrication and bridge foundation construction are carried out simultaneously, shortening the construction period.
[0031] In the specific implementation process, the No. 1 segment 11 and the No. 0 segment 8 on the pier top are connected by applying adhesive, adjusting the alignment and tensioning temporary prestressed steel bars, and the slide beam and the slider are welded and fixed.
[0032] In the specific implementation process, the stiffened frame of the side span closure section is connected to the template of the side span closure section at the end of the side span side segment 13; the stiffened frame of the middle span closure section is connected to the closure hanger at the ends of the cantilever segments on both sides of the middle span. The horizontal constraint device at the central support point acts on the temporary anchorage position of the central pier and is used for temporary constraint and unlocking during the system conversion process.
[0033] Example 2: The present invention also provides a method for the staged construction of a railway continuous beam, wherein the construction method is carried out according to the construction structure described in Example 1, and the construction method includes: (1) The 0# segment 8, 1# segment 11, segment 12 to be erected, and side segment 13 of the pier top are prefabricated using the comprehensive long-line method and stored in the beam yard after prefabrication.
[0034] (2) Simultaneously construct the bridge foundation and the substructure of the side piers 4 and the middle pier 5, install the side pier support 6 and the middle pier support 7, use a crane to hoist the pier top 0# segment 8 onto the middle pier and accurately position it, and temporarily anchor the pier top 9 through the beam top anchoring device.
[0035] (3) Hoist segment 11 to the slide beam slider on the upper part of the middle pier support. Ensure accurate segment positioning and temporary stability by applying glue, adjusting the line shape and temporary prestressing tension. Weld the slide beam and slider to achieve efficient positioning and temporary support of the pier top segment, and complete the connection and fixation of segment 1 and segment 0.
[0036] (4) Install a bridge deck crane on the top surface of segment 1. The bridge deck crane lifts the segment to be erected from the mid-span side and transports the segment to the side span for temporary suspension. Then, it lifts the symmetrical segments to be erected from the mid-span side to install the cantilever segment beam. After that, it applies adhesive to the joint surface, precisely adjusts the beam alignment, and tensions temporary prestressed steel bars to temporarily fix the segment. Then, it performs grouting operations on the relevant prestressed ducts. Repeat the above operations to achieve symmetrical erection of all cantilever segments on both sides of the pier.
[0037] (5) The side span segment is lifted onto the bridge by the bridge deck crane on the middle span of the middle pier, and transported to the cantilever side span of the main pier by the bridge beam transport system. It is then lifted onto the side pier support by the side span side bridge deck crane. Then, the adhesive is applied, the alignment is adjusted, and the prestressed steel bars are tensioned. The side span segment 13 is connected into a whole. The operation is repeated to complete the erection of all side span segments on the side pier support.
[0038] (6) Install the stiffening frame, bottom formwork, and side formwork of the side span closure section, release the temporary locking of the side pier, pour the concrete of the side span closure section in place, and complete the prestressing tensioning and grouting operations. Remove the side pier support 6, the middle pier support 7, and the temporary fixation 9, lower the beam, and temporarily restrain the horizontal direction of the middle support point. (7) Install the mid-span closure stiffening frame and mid-span closure hanger, release the temporary horizontal constraint of the mid-support point, tension the temporary steel strands, cast the mid-span closure section in place and grout in time, temporarily store and transport the bridge beams, and finally construct the second phase of dead load to complete the bridge construction.
[0039] In summary, this invention employs a segmental, factory-based, integrated long-line prefabrication method, effectively controlling prefabrication accuracy, ensuring the bridge's alignment, allowing for extended beam curing time and later loading age, resulting in minimal creep camber and long-term prestress loss after bridge completion. The segmental prefabrication described in this invention can be carried out simultaneously with the bridge foundation and substructure, employing a continuous flow operation that avoids interference and significantly shortens the construction period. The innovative "beam-on-beam transport" mode of this invention greatly reduces the requirements for the site conditions under the bridge, making it particularly suitable for scenarios crossing highways and rivers. The method described in this invention can reduce the investment in large-scale temporary facilities, aligns with the concept of green construction, and has excellent practicality.
[0040] The embodiments described above are preferred embodiments of the present invention, but the present invention is not limited to the above embodiments. Any obvious improvements, substitutions or modifications that can be made by those skilled in the art without departing from the essence of the present invention shall fall within the protection scope of the present invention.
Claims
1. A staged construction structure for a continuous railway beam, characterized in that, The construction structure includes a pier support structure, a pier top segment anchorage and sliding structure, a bridge deck beam transport and erection structure, and a closure and system conversion constraint structure. The pier support structure includes side piers (4) and middle piers (5). The top of the side piers (4) is provided with side pier supports (6) for supporting the side span segments (13). The top of the middle piers (5) is provided with middle pier supports (7). The middle pier supports (7) are provided with sliding beams and sliders for sliding positioning and temporary support of segment 1 (11). The pier top segment anchoring and sliding structure includes pier top 0# segment (8), temporary anchor (9), and 1# segment (11); pier top 0# segment (8) is fixed to the top of the middle pier (5) through temporary anchor (9); 1# segment (11) is supported on the slider of the sliding beam and connected to pier top 0# segment (8); The bridge deck beam transport and erection structure includes a bridge deck crane (10), a segment to be erected (12), and a side span segment (13). The bridge deck crane (10) is installed on the top surface of segment 1 (11) and is used to lift the segment to be erected (12) to achieve symmetrical cantilever erection and to lift the side span segment (13) onto the side pier support (6). The closure and system transformation constraint structure includes the stiffening frame of the side span closure section, the stiffening frame of the middle span closure section, the closure hanger, and the horizontal constraint device at the middle support point.
2. The railway continuous beam stage construction structure according to claim 1, characterized in that, The pier top 0# segment (8), 1# segment (11), segment to be erected (12), and side span segment (13) are obtained by prefabrication through matching prefabrication structures; The prefabricated structure includes a beam-making platform (1) arranged along the longitudinal axis, and gantry crane foundations (2) symmetrically arranged on both sides of the beam-making platform (1). A gantry crane (3) that can travel longitudinally is installed on the gantry crane foundations (2). The beam fabrication platform (1) is divided into two T-shaped prefabrication sections by the mid-span closure section.
3. The railway continuous beam stage construction structure according to claim 1, characterized in that, The No. 1 segment (11) and the No. 0 segment (8) on the pier top are connected by applying adhesive, adjusting the line shape and tensioning temporary prestressed steel bars, and the slide beam and the slider are welded and fixed.
4. The railway continuous beam stage construction structure according to claim 1, characterized in that, The rigid frame of the side span closure section is connected to the template of the side span closure section at the end of the side span side segment; the rigid frame of the middle span closure section is connected to the closure hanger at the end of the cantilever segments on both sides of the middle span. The horizontal constraint device at the central fulcrum acts on the temporary anchorage (9) position for temporary constraint and unlocking during system conversion.
5. A method for staged construction of a railway continuous beam, characterized in that, The construction method is carried out according to the construction structure described in any one of claims 1 to 4, and the construction method includes: (1) The 0# segment, 1# segment, segment to be erected and side span segment of the pier top are prefabricated using the comprehensive long-line method and stored in the beam yard after prefabrication; (2) Simultaneously construct the bridge foundation and the substructure of the side piers and middle piers, install the side pier supports and middle pier supports, use a crane to hoist the 0# segment of the pier top onto the middle pier and accurately position it, and temporarily anchor the pier top through the beam top anchoring device; (3) Hoist segment 1 onto the slide beam slider on the upper part of the middle pier support, and weld the slide beam and slider firmly to complete the connection and fixation of segment 1 and segment 0; (4) Install a bridge deck crane on the top surface of segment 1. The bridge deck crane lifts the segment to be erected on the middle span side and transports the segment to the side span side for temporary suspension. Then, it lifts the symmetrical segments to be erected on the middle span side to install the cantilever segment beam. Repeat the operation to achieve symmetrical erection of all cantilever segments on both sides of the middle pier. (5) The side span side segment is lifted onto the bridge by the bridge deck crane of the middle pier and transported to the cantilever side span of the main pier by the bridge beam transport system. It is then lifted onto the side pier support by the side span side bridge deck crane. The operation is repeated to complete the erection of all side span side segments on the side pier support. (6) Install the stiffened frame and bottom and side formwork of the side span closure section, release the temporary locking of the side pier, pour the concrete of the side span closure section in place, and complete the prestressing tensioning and grouting operations; remove the support and the temporary fixation of the middle pier, lower the beam, and temporarily constrain the horizontal direction of the middle support. (7) Install the mid-span closure stiffening frame and mid-span closure hanger, release the temporary horizontal constraint of the mid-support point, tension the temporary steel strands, cast the mid-span closure section in place and grout in time, temporarily store and transport the bridge beams, and finally construct the second phase of dead load to complete the bridge construction.
6. The construction method according to claim 5, characterized in that, In step (3), after segment 1 is hoisted onto the slide beam slider on the upper part of the pier support, the segment is positioned accurately and temporarily stabilized by applying adhesive, adjusting the line shape and temporary prestressing tension. The slide beam and slider are welded and fixed to achieve efficient positioning and temporary support of the pier top segment.
7. The construction method according to claim 5, characterized in that, In step (4), after the symmetrical sections to be erected are hoisted on the middle span side, the joint surface is coated with adhesive, the beam alignment is precisely adjusted, and temporary prestressed steel bars are tensioned to temporarily consolidate the sections. Then, grouting is carried out on the relevant prestressed ducts.