Anti-collision retaining wall true joint forming member and construction method thereof
By designing the true-joint molding components for the crash barrier, and utilizing the interlocking structure of the splicing panels and partitions, as well as the sealing strips, the problems of poor molding quality and high cost caused by the softness of the extruded polystyrene board are solved, achieving efficient and low-cost true-joint molding and simplified construction.
Patent Information
- Application Number
- CN202611447909.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-17
- Publication Date
- 2026-11-20
AI Technical Summary
In the current construction of crash barriers, the extruded polystyrene board material is soft and has low rigidity, making it easy to slip and tilt. This results in poor quality of the joint forming, high cost, complicated construction procedures, serious material waste, and easy water seepage problems.
The anti-collision barrier adopts a true-joint molded component, including spliced plate assemblies and partitions. The conduit is installed through a snap-fit structure, combined with sealing strips and lubricating oil to ensure the stability of the component and easy disassembly. Steel plates are used to improve rigidity, and the structure can be recycled after construction.
It improves the quality of the true seam forming, reduces construction costs, simplifies procedures, reduces material waste, avoids leakage and aging problems, and improves construction efficiency.
Smart Images

Figure CN123133274A_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of anti-collision barrier construction technology, and specifically relates to an anti-collision barrier true joint forming component and its construction method. Background Technology
[0002] To compensate for structural cracks caused by the thermal shrinkage and drying shrinkage of concrete, vertical continuous joints need to be set at intervals along the longitudinal direction for the crash barrier of municipal bridges. At present, the industry's conventional construction process is to pre-embed extruded polystyrene (XPS) boards as joint separators. However, XPS boards are soft and have very low rigidity. During concrete pouring and vibration, they are prone to slippage, tilting, and bending deformation under lateral pressure, resulting in uneven joint widths, distorted lines, and difficulty in controlling the appearance quality.
[0003] To avoid the problem of extruded polystyrene (XPS) board displacement and deformation, on-site construction can only adopt a segmented, skip-pour pouring method between joints. This limits the length of each pouring section, necessitates the repeated erection and dismantling of temporary boundary barriers, and results in fragmented and disjointed work processes, significantly extending the overall construction period and hindering the overlapping of multiple work procedures. After pouring, the XPS board is permanently embedded in the concrete, making it a disposable material; each joint requires a continuous supply of new board, leading to high material costs. Furthermore, the XPS board embedded in the concrete is subject to long-term erosion from rainwater and wet-dry cycles, causing aging and shrinkage. Without treatment, the joints are prone to defects and water seepage, increasing maintenance workload. Therefore, we propose a true-joint molding component for crash barriers and its construction method to solve the above problems. Summary of the Invention
[0004] To address the aforementioned problems, this invention provides a true-joint molding component for crash barriers and its construction method, which solves the problems of high cost and poor molding quality associated with traditional construction methods.
[0005] This invention is achieved through the following solution: a true-joint molding component for a crash barrier, comprising two adjacent barrier template groups, wherein a conduit for threading is pre-embedded within the barrier, and the molding component further includes: Two sets of interlocking plates are disposed between the two sets of retaining wall templates. They are used to tightly adhere to and seal the opposite sides of the two adjacent sets of retaining wall templates. Each set of interlocking plates includes two interlocking plates, and each of the two interlocking plates has a notch on its opposite side. When the opposite sides of the two interlocking plates are fitted together, the two notches combine to form a snap-fit, which is used to fit onto the conduit. A partition is placed between two sets of panels and abuts against the panels in the two sets of panels.
[0006] A further improvement of the anti-collision barrier true joint forming component of the present invention is that a sealing strip is fixedly connected to the inner wall of the recess to prevent leakage between the threaded pipe and the clamp.
[0007] A further improvement of the present invention is that each of the said splicing plates is coated with a release agent on the side facing the retaining wall template assembly.
[0008] A further improvement of the anti-collision barrier true joint molding component of the present invention is that lubricating oil is applied between the partition and the splicing plate.
[0009] A further improvement of the present invention is that the anti-collision retaining wall true joint forming component includes a bottom foundation and a steel reinforcement skeleton erected on the bottom foundation and located within the retaining wall template assembly; The splicing plate abuts against the steel reinforcement frame.
[0010] A further improvement of the anti-collision barrier true joint forming component of the present invention is that the lower end of the splicing plate is provided with a first overlapping part for sitting on the base.
[0011] A further improvement of the anti-collision barrier true joint forming component of the present invention is that the middle part of the partition is provided with an opening for the passage of the wire conduit, and the opening of the opening faces downward. The lower end of the partition is provided with a second overlapping part for sitting on the foundation.
[0012] A further improvement of the anti-collision barrier true joint forming component of the present invention is that the outer edges of the partition and each of the splicing plates are fixedly connected with an outer pull ring.
[0013] A further improvement of the anti-collision barrier true joint forming component of the present invention is that the partition and all the splicing plates are made of steel plates.
[0014] A method for constructing a true joint in a crash barrier wall, using the molding components described above, includes the following steps: S1. After the two adjacent retaining wall template groups are installed, two splicing plate groups are placed between the two retaining wall template groups, and are respectively attached to and sealed on the opposite side of the two adjacent retaining wall template groups. At the same time, the opposite sides of the two splicing plates in the splicing plate group are attached, so that the two notches are combined to form a snap-fit on the conduit. S2. Place the partition between the two sets of panels, and make the partition abut against the panels in the two sets of panels; S3. Pour concrete into the two retaining wall formwork groups, and the retaining wall will be formed after curing. S4. First, remove the two retaining wall formwork groups, then remove the partitions, and then remove all the splicing panels to form a true joint between the adjacent retaining walls.
[0015] Compared with the prior art, the beneficial effects of the present invention are as follows: This invention involves placing two sets of interlocking panels between two sets of retaining wall templates, tightly abutting and sealing them against the opposite sides of the two adjacent sets. Then, a partition is placed between the two sets of interlocking panels, with the partition abutting against the interlocking panels in the two sets, thereby forming a true joint between the two sets of retaining wall templates. After the concrete retaining wall is formed, the partition and all the interlocking panels can be directly removed, leaving no components inside the true joint. This allows for recycling and reuse, reducing construction costs and improving the forming quality of the true joint. Attached Figure Description
[0016] Figure 1 The diagram shows the installation positions of the panels and partitions according to the present invention.
[0017] Figure 2 The diagram shows a schematic of the installation of the panels and partitions according to the present invention.
[0018] Figure 3 A schematic diagram of the partition structure of the present invention is shown.
[0019] Figure 4 A schematic diagram of the panel assembly structure of the present invention is shown.
[0020] Figure 5 A schematic diagram of the location of the reinforcing steel skeleton of the present invention is shown.
[0021] Figure 6 This diagram illustrates the formation of a concrete wall after concrete is poured into the retaining wall template assembly according to the present invention.
[0022] In the diagram: 1. Retaining wall formwork assembly; 2. Butt joint plate; 201. Clamp; 202. Notch; 203. First erection section; 3. Partition plate; 301. Through opening; 302. Second erection section; 4. Wiring pipe; 5. Retaining wall; 501. Foundation; 502. Reinforcing steel cage; 503. Concrete wall; 6. External tie ring. Detailed Implementation
[0023] To address the problems of high cost and poor forming quality of traditional construction methods, this invention provides a true-joint molded component for crash barriers and its construction method. The following detailed description, in conjunction with specific embodiments and accompanying drawings, further illustrates this true-joint molded component for crash barriers and its construction method.
[0024] See Figures 1-6 As shown, a true-joint molding component for a crash barrier includes two adjacent barrier template groups 1, a conduit 4 pre-embedded within the barrier 5, and the molding component further includes: Two sets of interlocking plates 2 are set between two retaining wall template sets 1, and are used to tightly adhere to and seal the opposite side of the two adjacent retaining wall template sets 1 respectively. Each set of interlocking plates 2 includes two interlocking plates 2, and each of the two interlocking plates 2 has a notch 202 on the opposite side. When the opposite sides of the two interlocking plates 2 are attached, the two notches 202 combine to form a snap 201, which is used to fit onto the conduit 4. The partition 3 is positioned between the two sets of paired panels 2 and abuts against the paired panels 2 in the two sets of paired panels 2.
[0025] By placing two sets of interlocking plates 2 between two sets of retaining wall templates 1, and tightly abutting and sealing them on opposite sides of the two adjacent sets of retaining wall templates 1, and then placing a partition 3 between the two sets of interlocking plates 2, so that the partition 3 abuts against the interlocking plates 2 in the two sets of interlocking plates 2, a true joint is formed between the two sets of retaining wall templates 1. After the concrete retaining wall 5 is formed, the partition 3 and all the interlocking plates 2 can be directly removed, leaving no components inside the true joint. This allows for recycling and reuse, reducing construction costs and improving the forming quality of the true joint.
[0026] Further, see Figure 2 As shown, in this embodiment, there are multiple conduits 4. The number of notches 202 on each pair of panels 2 is the same as the number of conduits 4, and the size of the formed slot 201 is adapted to the size of the corresponding conduit 4. By cooperating with the conduit 4 through the set slot 201, the retaining wall template group 1 is blocked, and the multiple conduits 4 are not hindered from being laid out, thus avoiding leakage.
[0027] A sealing strip is fixedly connected to the inner wall of the notch 202 to prevent leakage between the conduit 4 and the bayonet 201.
[0028] Furthermore, the sealing strip is made of rubber.
[0029] By adopting the above design, the gap between the conduit 4 and the clamp 201 can be sealed with a sealing strip to prevent grout leakage during concrete pouring and improve the forming quality.
[0030] Each of the two panels 2 is coated with a release agent on the side facing the retaining wall template group 1.
[0031] The release agent applied can greatly reduce the bonding resistance between the splice plate 2 and the concrete, making it easy to remove the splice plate 2 after construction.
[0032] Lubricating oil is applied between the partition 3 and the splicing plate 2.
[0033] The application of lubricating oil can greatly reduce the bonding resistance between the splice plate 2 and the partition plate 3, making it easier to remove the partition plate 3 after construction.
[0034] Among them, see Figure 5 As shown, the retaining wall 5 includes a foundation 501 and a steel reinforcement frame 502 erected on the foundation 501 and located within the retaining wall formwork assembly 1; The splice plate 2 abuts against the steel reinforcement cage 502.
[0035] Further, see Figure 6 As shown, the retaining wall 5 also includes a concrete wall 503, which is formed by pouring concrete into the retaining wall template group 1 and curing it. The concrete wall 503 encloses the steel reinforcement skeleton 502 and is anchored to the steel reinforcement skeleton 502 and the foundation 501 as a whole. When the conduit 4 is pre-embedded, it is fixed to the steel reinforcement skeleton 502 to improve the stability of the conduit 4 when pouring concrete.
[0036] By abutting the middle areas of the two assembled plates 2 on both sides with the steel reinforcement skeleton 502 inside the retaining wall formwork group 1, and the edge areas with the two retaining wall formwork groups 1 on both sides, and then using the partition plate 3 to abut between the two assembled plates 2, the clamping stability of the assembled plates 2 and the partition plate 3 can be improved, and the force on the assembled plates 2 can be balanced, avoiding deformation during concrete pouring and improving the forming quality.
[0037] Among them, see Figure 2 and Figure 4 As shown, a first stacking part 203 is provided at the lower end of the panel 2 for sitting on the foundation 501.
[0038] By using the first mounting part 203 to sit on the foundation 501, and using the foundation 501 to bear the weight of the splicing plate 2, the stability of the splicing plate 2 installation can be improved; when disassembly is required, the splicing plates 2 on both sides can be pulled outward to the left and right to detach from the cured concrete wall 503 to complete the disassembly.
[0039] Among them, see Figure 2 and Figure 3 As shown, the partition 3 has a through-hole 301 in the middle for the conduit 4 to pass through, and the opening of the through-hole 301 faces downward. The lower end of the partition 3 has a second mounting part 302 for sitting on the foundation 501.
[0040] By using the second mounting part 302 to sit on the base 501, the weight of the partition 3 can be borne by the base 501, which can improve the stability of the partition 3 installation. Furthermore, by setting the downward-facing opening 301, it is convenient to directly insert the partition 3 between the two sets of panels 2 during installation. When it needs to be removed, the partition 3 can be pulled up to detach it from the two sets of panels 2, which is convenient for disassembly and assembly. After the partition 3 is removed, there is a gap of not less than 1cm between the two sets of panels 2, which facilitates the subsequent removal of the panels 2.
[0041] Among them, see Figure 3 and Figure 4 As shown, the outer edges of the partition 3 and each pair of panels 2 are fixedly connected with an outer pull ring 6.
[0042] With the outer pull ring 6, when it is necessary to remove the splicing plate 2 and the partition plate 3 after construction, the force can be applied to the partition plate 3 and the splicing plate 2 by pulling the outer pull ring 6, which is conducive to the quick removal of the partition plate 3 and the splicing plate 2.
[0043] Among them, partition 3 and all the splicing plates 2 are made of steel plates.
[0044] By using steel plates, the strength of partition 3 and splicing plate 2 can be greatly improved, and the rigidity of the plates can be used to resist the lateral extrusion force of concrete pouring, thereby improving the forming quality.
[0045] A construction method for creating true joints in a crash barrier wall, using the aforementioned molded components, includes the following steps: S1. After the two adjacent retaining wall template groups 1 are installed, two sets of interlocking plates 2 are placed between the two retaining wall template groups 1, and are respectively attached to and sealed on the opposite side of the two adjacent retaining wall template groups 1. At the same time, the opposite sides of the two interlocking plates 2 in the interlocking plate group 2 are attached, so that the two notches 202 are combined to form a snap 201 and are fitted onto the conduit 4. S2. Place the partition 3 between the two sets of paired panels 2, and make the partition 3 abut against the paired panels 2 in the two sets of paired panels 2; S3. Pour concrete into the two retaining wall template groups 1, and after curing, form retaining wall 5; S4. First, remove the two retaining wall template groups 1, then remove the partition 3, and then remove all the splicing panels 2 to form a true joint between the adjacent retaining walls 5.
[0046] Furthermore, before construction step S1, the foundation 501 is constructed first. After the foundation 501 has solidified and formed, the steel reinforcement frame 502 is erected on the foundation 501, and then the retaining wall formwork assembly 1 is constructed. During construction step S1, release agent is applied to the side of the splicing plate 2 facing the retaining wall template group 1, and lubricating oil is applied between the partition plate 3 and the splicing plate 2.
[0047] It should be noted that, in this document, relational terms such as "first" and "second" are used only to distinguish one entity or operation from another, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Furthermore, the terms "comprising," "including," or any other variations thereof are intended to cover non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements includes not only those elements but also other elements not expressly listed, or elements inherent to such process, method, article, or apparatus.
[0048] The present invention has been described in detail above with reference to the accompanying drawings and embodiments. Those skilled in the art can make various modifications to the present invention based on the above description. Therefore, certain details in the embodiments should not be construed as limiting the present invention, and the scope of protection of the present invention shall be defined by the appended claims.
Claims
1. A true-joint molding component for a crash barrier, comprising two adjacent barrier template groups, wherein a conduit for wiring is pre-embedded within the barrier, characterized in that, The molded component further includes: Two sets of interlocking plates are disposed between the two sets of retaining wall templates. They are used to tightly adhere to and seal the opposite sides of the two adjacent sets of retaining wall templates. Each set of interlocking plates includes two interlocking plates, and each of the two interlocking plates has a notch on its opposite side. When the opposite sides of the two interlocking plates are fitted together, the two notches combine to form a snap-fit, which is used to fit onto the conduit. A partition is placed between two sets of panels and abuts against the panels in the two sets of panels.
2. The anti-collision barrier wall with true joint molding component as described in claim 1, characterized in that, A sealing strip is fixedly connected to the inner wall of the notch to prevent leakage between the threaded conduit and the bayonet.
3. The anti-collision barrier wall with true joint molding component as described in claim 1, characterized in that, Each of the said panels is coated with a release agent on the side facing the retaining wall template assembly.
4. The anti-collision barrier wall with true joint molding component as described in claim 1, characterized in that, Lubricating oil is applied between the partition and the splicing plate.
5. The anti-collision barrier wall with true joint molding component as described in claim 1, characterized in that, The retaining wall includes a foundation and a steel reinforcement cage erected on the foundation and located within the retaining wall formwork assembly; The splicing plate abuts against the steel reinforcement frame.
6. The anti-collision barrier wall with true joint molding component as described in claim 5, characterized in that, The lower end of the panel is provided with a first overlapping part for sitting on the foundation.
7. The anti-collision barrier wall with true joint molding component as described in claim 5, characterized in that, The partition has an opening in the middle for threading pipes to pass through, with the opening facing downwards. The lower end of the partition has a second support section for sitting on the foundation.
8. The anti-collision barrier wall with true joint molding component as described in claim 1, characterized in that, Each partition and each of the paired panels is fixedly connected to an outer pull ring along its outer edge.
9. The anti-collision barrier wall with true joint molding component as described in claim 1, characterized in that, The partition and all the panels are made of steel plates.
10. A construction method for a true joint in a crash barrier, implemented using the molding component as described in claim 1, characterized in that, Includes the following steps: S1. After the two adjacent retaining wall template groups are installed, two splicing plate groups are placed between the two retaining wall template groups, and are respectively attached to and sealed on the opposite side of the two adjacent retaining wall template groups. At the same time, the opposite sides of the two splicing plates in the splicing plate group are attached, so that the two notches are combined to form a snap-fit on the conduit. S2. Place the partition between the two sets of panels, and make the partition abut against the panels in the two sets of panels; S3. Pour concrete into the two retaining wall formwork groups, and the retaining wall will be formed after curing. S4. First, remove the two retaining wall formwork groups, then remove the partitions, and then remove all the splicing panels to form a true joint between the adjacent retaining walls.